Permit #2021120144
Permit Details
Status: COED
| Parcel Id: 07-11-31-7035-01170-0050 |
| CONDITIONED SPACE: 2062 sqft |
| GARAGE: 433 sqft |
| OPENED PORCH (WITH ROOF) : 112 sqft |
| OPENED PORCH (WITH ROOF) : 52 sqft |
| Total Square Footage: 2659 sqft |
| Block: 01170 |
| Subdivision: 2172 - SECTION 35-BELLE TERRE |
| Job Phone: 904-667-3599 |
| Location Address: 27 BISCAY LN |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 01/27/2022 |
| NOC: RECORDED |
| Applicant name: TONY S JACKSON |
| Owner: 3DRE, LLC |
|
Address 820 EDENBRIDGE WAY ST AUGUSTINE, FL 32092 |
| Lot: 0050 |
| Contracted Stated Job Value: ¤200,000.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
T-DAWG CONSTRUCTION LLC
| Status | Location Address | State License Number | Phone |
| INACTIVE |
6821 SOUTH POINT DR N NEPTUNE , FL 32266 |
CGC1523419 (Exp: 08/31/2024) | 904-667-3599 |
Sub Contractors
RUSSELL J CARTER
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
PO BOX 302 DELAND, FL 32721 |
CFC1425938 (Exp: 08/31/2026) | 386-736-4220 | 386-736-4219 |
MAXIM BUDNIK
| Status | Location Address | State License Number |
| ACTIVE |
3 WAVECREST PL PALM COAST, FL 32164 |
CAC1818445 (Exp: 08/31/2026) |
GARY LLOYD SHEFFIELD
| Status | Location Address | State License Number | Phone |
| ACTIVE |
48 EAGLE LAKES DRIVE FLAGLER BEACH, FL 32136 |
CAC048127 (Exp: 08/31/2026) | 386-597-3280 |
JAMES MCGOVERN
| Status | Location Address | Phone | Fax |
| INACTIVE |
121 BIRD OF PARADISE DR BUNNELL, FL 32110 |
386-931-8940 | 386-986-4835 |
OLEG BELINSKIY
| Status | Location Address | State License Number | Phone |
| ACTIVE |
19 PINE CIRCLE DRIVE19 PALM COAST, FL 32167 |
CCC1325974 (Exp: 08/31/2026) | 386-263-7906 |
Inspection History
| Type | Request Date | Result | Inspector |
| U -UTILITY RESIDENTIAL FINAL | 01/10/2023 | FINAL APPROVED | DHANEY |
| Note: 1/6/2023 - PREVIOUS INSPECTION NOTES 1/6/2023 not ready, have to change breaker in garage for pep system. 12/27/2022 - PREVIOUS INSPECTION NOTES 12/15/2022 - PREVIOUS INSPECTION NOTES 12/13/2022 - PREVIOUS INSPECTION NOTES PEP Panel side of house is to high - needs to be Below 5 ' and connected to electric . Also sewer clean out at pep tank is to high - needs trimmed to ground level. ALSO water meter pit full of dirt , can not see Back Flow , needs cleaned out . PEP Panel on side of house still to high and can not get to water meter pit , has culvert pipe laying on top.12-15 PEP Panel still to HIGH, electric not connected to pep tank. 12/27 [Water meter ok now] | |||
| U -UTILITY RESIDENTIAL FINAL | 01/06/2023 | CANCELLED BY APPLICANT | JHARDING |
| Note: 1/6/2023 not ready, have to change breaker in garage for pep system. 12/27/2022 - PREVIOUS INSPECTION NOTES 12/15/2022 - PREVIOUS INSPECTION NOTES 12/13/2022 - PREVIOUS INSPECTION NOTES PEP Panel side of house is to high - needs to be Below 5 ' and connected to electric . Also sewer clean out at pep tank is to high - needs trimmed to ground level. ALSO water meter pit full of dirt , can not see Back Flow , needs cleaned out . PEP Panel on side of house still to high and can not get to water meter pit , has culvert pipe laying on top.12-15 PEP Panel still to HIGH, electric not connected to pep tank. 12/27 [Water meter ok now] | |||
| ROW - STORMWATER FINAL | 12/29/2022 | APPROVED | GBERTOLA |
| Note: 12/29/22= correction were made 12/27/2022 - PREVIOUS INSPECTION NOTES 12/27/22= NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTE ________________________________________________________________________________________________________________________ 12/15/2022 - PREVIOUS INSPECTION NOTES ** 12/15/22 ** REMOVE HUMP FROM LEFT SIDE SWALE OUTLINED WITH PINK PAINT AND SOD TO MATCH EXISTING GRADE ** REMOVE OLD CULVERT THAT IS BLOCKING SWALE AND LEFT SIDE DRIVEWAY PIPE ** SEE ATTACHED PHOTOS 12/13/2022 - PREVIOUS INSPECTION NOTES ** 12/13/22 NO CORRECTIONS MADE SINCE PREVIOUS INSPECTION SEE NOTES FROM 12/01/22 ** REMOVE HUMP FROM LEFT SIDE SWALE OUTLINED WITH PINK PAINT AND SOD TO MATCH EXISTING GRADE ** CLEAN OUT CULVERT ENDS / REMOVE OLD CULVERT THAT IS BLOCKING SWALE AND LEFT SIDE DRIVEWAY PIPE ** 12/01/22 CLEAN OUT CULVERT ENDS LEFT SIDE SWALE REMOVE HUMP AT PROPERTY LINE MATCH EXISTING GRADE WITH SOD. | |||
| U -UTILITY RESIDENTIAL FINAL | 12/27/2022 | Disapproved -FEE REQUIRED | DHANEY |
| Note: 12/15/2022 - PREVIOUS INSPECTION NOTES 12/13/2022 - PREVIOUS INSPECTION NOTES PEP Panel side of house is to high - needs to be Below 5 ' and connected to electric . Also sewer clean out at pep tank is to high - needs trimmed to ground level. ALSO water meter pit full of dirt , can not see Back Flow , needs cleaned out . PEP Panel on side of house still to high and can not get to water meter pit , has culvert pipe laying on top.12-15 PEP Panel still to HIGH, electric not connected to pep tank. 12/27 [Water meter ok now] Fee Removed on 12/28/2022 per Don Haney. | |||
| ROW - STORMWATER FINAL | 12/27/2022 | Disapproved -FEE REQUIRED | GBERTOLA |
| Note: 12/27/22= NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTE ________________________________________________________________________________________________________________________ 12/15/2022 - PREVIOUS INSPECTION NOTES ** 12/15/22 ** REMOVE HUMP FROM LEFT SIDE SWALE OUTLINED WITH PINK PAINT AND SOD TO MATCH EXISTING GRADE ** REMOVE OLD CULVERT THAT IS BLOCKING SWALE AND LEFT SIDE DRIVEWAY PIPE ** SEE ATTACHED PHOTOS 12/13/2022 - PREVIOUS INSPECTION NOTES ** 12/13/22 NO CORRECTIONS MADE SINCE PREVIOUS INSPECTION SEE NOTES FROM 12/01/22 ** REMOVE HUMP FROM LEFT SIDE SWALE OUTLINED WITH PINK PAINT AND SOD TO MATCH EXISTING GRADE ** CLEAN OUT CULVERT ENDS / REMOVE OLD CULVERT THAT IS BLOCKING SWALE AND LEFT SIDE DRIVEWAY PIPE ** 12/01/22 CLEAN OUT CULVERT ENDS LEFT SIDE SWALE REMOVE HUMP AT PROPERTY LINE MATCH EXISTING GRADE WITH SOD. | |||
| BLD - BUILDING FINAL | 12/16/2022 | Approval - Private Provider | PPROVIDER |
| ROW - STORMWATER FINAL | 12/15/2022 | Disapproved -FEE REQUIRED | EMADISON |
| Note: ** 12/15/22 ** REMOVE HUMP FROM LEFT SIDE SWALE OUTLINED WITH PINK PAINT AND SOD TO MATCH EXISTING GRADE ** REMOVE OLD CULVERT THAT IS BLOCKING SWALE AND LEFT SIDE DRIVEWAY PIPE ** SEE ATTACHED PHOTOS 12/13/2022 - PREVIOUS INSPECTION NOTES ** 12/13/22 NO CORRECTIONS MADE SINCE PREVIOUS INSPECTION SEE NOTES FROM 12/01/22 ** REMOVE HUMP FROM LEFT SIDE SWALE OUTLINED WITH PINK PAINT AND SOD TO MATCH EXISTING GRADE ** CLEAN OUT CULVERT ENDS / REMOVE OLD CULVERT THAT IS BLOCKING SWALE AND LEFT SIDE DRIVEWAY PIPE ** 12/01/22 CLEAN OUT CULVERT ENDS LEFT SIDE SWALE REMOVE HUMP AT PROPERTY LINE MATCH EXISTING GRADE WITH SOD. | |||
| U -UTILITY RESIDENTIAL FINAL | 12/15/2022 | Disapproved - NO FEE | DHANEY |
| Note: 12/13/2022 - PREVIOUS INSPECTION NOTES PEP Panel side of house is to high - needs to be Below 5 ' and connected to electric . Also sewer clean out at pep tank is to high - needs trimmed to ground level. ALSO water meter pit full of dirt , can not see Back Flow , needs cleaned out . PEP Panel on side of house still to high and can not get to water meter pit , has culvert pipe laying on top.12-15 | |||
| U -UTILITY RESIDENTIAL FINAL | 12/13/2022 | Disapproved - NO FEE | DHANEY |
| Note: PEP Panel side of house is to high - needs to be Below 5 ' and connected to electric . Also sewer clean out at pep tank is to high - needs trimmed to ground level. ALSO water meter pit full of dirt , can not see Back Flow , needs cleaned out . | |||
| ROW - STORMWATER FINAL | 12/13/2022 | Disapproved -FEE REQUIRED | EMADISON |
| Note: ** 12/13/22 NO CORRECTIONS MADE SINCE PREVIOUS INSPECTION SEE NOTES FROM 12/01/22 ** REMOVE HUMP FROM LEFT SIDE SWALE OUTLINED WITH PINK PAINT AND SOD TO MATCH EXISTING GRADE ** CLEAN OUT CULVERT ENDS / REMOVE OLD CULVERT THAT IS BLOCKING SWALE AND LEFT SIDE DRIVEWAY PIPE ** 12/01/22 CLEAN OUT CULVERT ENDS LEFT SIDE SWALE REMOVE HUMP AT PROPERTY LINE MATCH EXISTING GRADE WITH SOD. | |||
| ROW - FINAL APRON (AFTER POUR) | 12/01/2022 | APPROVED | EMADISON |
| ROW- FINAL SURVEY/GRADING CERTIFICATION | 12/01/2022 | APPROVED | EMADISON |
| ROW FIELD SURVEY /GRADING CERTIFICATION | 12/01/2022 | APPROVED | EMADISON |
| Note: ** 12/01/22 CLEAN OUT CULVERT ENDS LEFT SIDE SWALE REMOVE HUMP AT PROPERTY LINE MATCH EXISTING GRADE WITH SOD. | |||
| U-CROSS CONNECTION | 11/21/2022 | FINAL APPROVED | JHARDING |
| Note: 11/21/2022- no irrigatioj, no cross connections. 11/15/2022 - PREVIOUS INSPECTION NOTES THIS IS A REINSPECTION THIS IS A REINSPECTION Water meter pit completly under Mud/dirt, can not verify if back flow device is still installed. Pit Needs cleaned out. Water meter pit still completly full of mud . 11-15-22 | |||
| U-CROSS CONNECTION | 11/15/2022 | Disapproved - NO FEE | DHANEY |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION Water meter pit completly under Mud/dirt, can not verify if back flow device is still installed. Pit Needs cleaned out. Water meter pit still completly full of mud . 11-15-22 | |||
| ROW- PRE-APRON (PRE-POUR) | 10/25/2022 | APPROVED | EMADISON |
| Note: ** 10/25/22 MAKE SURE THERE IS 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE (FRC) DRAWING 300,E RESIDENTIAL CULVERT DETAIL ** SITE IS READFY TO POUR | |||
| ROW - DRAINAGE | 10/06/2022 | APPROVED | EMADISON |
| Note: ** 10/06/22 CORRECTIONS HAVE BEEN MADE 10/5/2022 - PREVIOUS INSPECTION NOTES ** ** 10/05/22 NO CORRECTIONS HAVE BEEN MADE SICE PREVIOUS INSPECTION ** BUILDER NEEDS TO OPEN SWALE IMMEDIATE ** BUILDER ALSO NEEDS TO REMOVE THE PORTA-JOHN FROM THE SWALE AND PUT ONTO JOB SITE ** A STOP WORK ORDER WILL BE IMPOSED ON JOB SITE FOR FAILURE TO TAKE CORRECTIVE ACTION WITH ROW DRAINAGE ISSUES. ** FOLLOW UP INSPECTION ON 10/06/22 10/4/2022 - PREVIOUS INSPECTION NOTES ** ** 10/04/22 NO CORRECTIONS HAVE BEEN MADE SICE PREVIOUS INSPECTION ** BUILDER NEEDS TO OPEN SWALE IMMEDIATE ** BUILDER ALSO NEEDS TO REMOVE THE PORTA-JOHN FROM THE SWALE AND PUT ONTO JOB SITE 10/3/2022 - PREVIOUS INSPECTION NOTES ** 10/03/22 NO CORRECTIONS HAVE BEEN MADE SICE PREVIOUS INSPECTION ** BUILDER NEEDS TO OPEN SWALE IMMEDIATELY. ** 09/28/22 FOLLOW UP INSPECTION WILL BE CONDUCTED ON 10/03/22 DUE TO HURRICANE IAN 9/27/2022 - PREVIOUS INSPECTION NOTES ** 09/27/22 BUILDER NEEDS TO OPEN FRONT SWALE IMMEDIATELY TO ALLOPW FOR STORMWATER TO FLOW CULVERT IS PLUGGED PREVENTING DRAINAGE. ** REMOVE PORTA-JOHN FROM SWALE PUT ONTO PROJECT SITE ** FOLLOW UP INSPECTION ON 09/28/22 | |||
| ROW - DRAINAGE | 10/05/2022 | Disapproved -FEE REQUIRED | EMADISON |
| Note: ** ** 10/05/22 NO CORRECTIONS HAVE BEEN MADE SICE PREVIOUS INSPECTION ** BUILDER NEEDS TO OPEN SWALE IMMEDIATE ** BUILDER ALSO NEEDS TO REMOVE THE PORTA-JOHN FROM THE SWALE AND PUT ONTO JOB SITE ** A STOP WORK ORDER WILL BE IMPOSED ON JOB SITE FOR FAILURE TO TAKE CORRECTIVE ACTION WITH ROW DRAINAGE ISSUES. ** FOLLOW UP INSPECTION ON 10/06/22 10/4/2022 - PREVIOUS INSPECTION NOTES ** ** 10/04/22 NO CORRECTIONS HAVE BEEN MADE SICE PREVIOUS INSPECTION ** BUILDER NEEDS TO OPEN SWALE IMMEDIATE ** BUILDER ALSO NEEDS TO REMOVE THE PORTA-JOHN FROM THE SWALE AND PUT ONTO JOB SITE 10/3/2022 - PREVIOUS INSPECTION NOTES ** 10/03/22 NO CORRECTIONS HAVE BEEN MADE SICE PREVIOUS INSPECTION ** BUILDER NEEDS TO OPEN SWALE IMMEDIATELY. ** 09/28/22 FOLLOW UP INSPECTION WILL BE CONDUCTED ON 10/03/22 DUE TO HURRICANE IAN 9/27/2022 - PREVIOUS INSPECTION NOTES ** 09/27/22 BUILDER NEEDS TO OPEN FRONT SWALE IMMEDIATELY TO ALLOPW FOR STORMWATER TO FLOW CULVERT IS PLUGGED PREVENTING DRAINAGE. ** REMOVE PORTA-JOHN FROM SWALE PUT ONTO PROJECT SITE ** FOLLOW UP INSPECTION ON 09/28/22 | |||
| ROW - DRAINAGE | 10/04/2022 | Disapproved -FEE REQUIRED | EMADISON |
| Note: ** ** 10/04/22 NO CORRECTIONS HAVE BEEN MADE SICE PREVIOUS INSPECTION ** BUILDER NEEDS TO OPEN SWALE IMMEDIATE ** BUILDER ALSO NEEDS TO REMOVE THE PORTA-JOHN FROM THE SWALE AND PUT ONTO JOB SITE ** FOLLOW UP INSPECTION ON 10/05/22 10/3/2022 - PREVIOUS INSPECTION NOTES ** 10/03/22 NO CORRECTIONS HAVE BEEN MADE SICE PREVIOUS INSPECTION ** BUILDER NEEDS TO OPEN SWALE IMMEDIATELY. ** 09/28/22 FOLLOW UP INSPECTION WILL BE CONDUCTED ON 10/03/22 DUE TO HURRICANE IAN 9/27/2022 - PREVIOUS INSPECTION NOTES ** 09/27/22 BUILDER NEEDS TO OPEN FRONT SWALE IMMEDIATELY TO ALLOPW FOR STORMWATER TO FLOW CULVERT IS PLUGGED PREVENTING DRAINAGE. ** REMOVE PORTA-JOHN FROM SWALE PUT ONTO PROJECT SITE ** FOLLOW UP INSPECTION ON 09/28/22 | |||
| ROW - DRAINAGE | 10/03/2022 | Disapproved -FEE REQUIRED | EMADISON |
| Note: ** 10/03/22 NO CORRECTIONS HAVE BEEN MADE SICE PREVIOUS INSPECTION ** BUILDER NEEDS TO OPEN SWALE IMMEDIATELY. ** FOLLOW UP INSPECTION ON 10/04/22 ** 09/28/22 FOLLOW UP INSPECTION WILL BE CONDUCTED ON 10/03/22 DUE TO HURRICANE IAN 9/27/2022 - PREVIOUS INSPECTION NOTES ** 09/27/22 BUILDER NEEDS TO OPEN FRONT SWALE IMMEDIATELY TO ALLOPW FOR STORMWATER TO FLOW CULVERT IS PLUGGED PREVENTING DRAINAGE. ** REMOVE PORTA-JOHN FROM SWALE PUT ONTO PROJECT SITE ** FOLLOW UP INSPECTION ON 09/28/22 | |||
| ROW - DRAINAGE | 09/28/2022 | CANCELLED BY INSPECTOR | EMADISON |
| Note: ** 09/28/22 FOLLOW UP INSPECTION WILL BE CONDUCTED ON 10/03/22 DUE TO HURRICANE IAN 9/27/2022 - PREVIOUS INSPECTION NOTES ** 09/27/22 BUILDER NEEDS TO OPEN FRONT SWALE IMMEDIATELY TO ALLOPW FOR STORMWATER TO FLOW CULVERT IS PLUGGED PREVENTING DRAINAGE. ** REMOVE PORTA-JOHN FROM SWALE PUT ONTO PROJECT SITE ** FOLLOW UP INSPECTION ON 09/28/22 | |||
| ROW - DRAINAGE | 09/27/2022 | Disapproved - NO FEE | EMADISON |
| Note: ** 09/27/22 BUILDER NEEDS TO OPEN FRONT SWALE IMMEDIATELY TO ALLOPW FOR STORMWATER TO FLOW CULVERT IS PLUGGED PREVENTING DRAINAGE. ** FOLLOW UP INSPECTION ON 09/28/22 | |||
| ELECTRIC - EARLY POWER | 08/17/2022 | Approval - Private Provider | PPROVIDER |
| GRAVITY SEWER TEST | 07/29/2022 | APPROVED | MGIBSON |
| Note: THIS IS A REINSPECTION Ditch full of water and unable to see for inspection. | |||
| U-CROSS CONNECTION | 07/29/2022 | Disapproved -FEE REQUIRED | DHANEY |
| Note: THIS IS A REINSPECTION Water meter pit completly under Mud/dirt, can not verify if back flow device is still installed. Pit Needs cleaned out. | |||
| U - SEWER TIE IN | 07/29/2022 | APPROVED | MGIBSON |
| Note: THIS IS A REINSPECTION Ditch full of water and unable to see for inspection. | |||
| U - SEWER TIE IN | 07/12/2022 | Disapproved - NO FEE | MKRASKI |
| Note: Ditch full of water and unable to see for inspection. | |||
| U-CROSS CONNECTION | 07/12/2022 | Disapproved - NO FEE | DHANEY |
| Note: Water meter pit completly under Mud/dirt, can not verify if back flow device is still installed. Pit Needs cleaned out. | |||
| GRAVITY SEWER TEST | 07/12/2022 | Disapproved - NO FEE | MKRASKI |
| Note: Ditch full of water and unable to see for inspection. | |||
| PEP TANK INSTALLATION REQUEST | 05/12/2022 | APPROVED | CSTONE |
| FOUND SURVEY APPROVED (OFFICE) | 05/11/2022 | APPROVED | TBAKER |
| INSULATION | 05/03/2022 | Approval - Private Provider | PPROVIDER |
| ALL ROUGH | 04/25/2022 | Approval - Private Provider | PPROVIDER |
| ROOF VALLEY & METAL | 03/28/2022 | Approval - Private Provider | PPROVIDER |
| WALL SHEATHING | 03/25/2022 | Approval - Private Provider | PPROVIDER |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 03/25/2022 | Approval - Private Provider | PPROVIDER |
| MONOLITHIC SLAB | 02/21/2022 | Approval - Private Provider | PPROVIDER |
| Note: 02/21/2022 Monolithic Slab Inspection passed. Dakota Hilton | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 02/09/2022 | Approval - Private Provider | PPROVIDER |
| WATER METER INSTALLATION REQUEST | 02/09/2022 | APPROVED | CSTONE |
| Note: THIS IS A REINSPECTION ADDED ON 2/7/2022 8:55:26 AM No work order please contact customer service | |||
| WATER METER INSTALLATION REQUEST | 01/28/2022 | Disapproved - NO FEE | CSTONE |
| Note: No work order please contact customer service |
Review History
| Department | Status | Date In | Date Out |
| ENGIN1 | COMPLETE | 03/03/2022 | 03/03/2022 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 03/03/2022 | 03/03/2022 |
| Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 03/03/2022 | 03/03/2022 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 03/03/2022 | 03/03/2022 |
| Note: Released By: CINDY CHIRI-GONCALVES - - CGONCALVES@PALMCOASTGOV.COM | |||
| ELEC | COMPLETE | 12/09/2021 | 12/10/2021 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 12/09/2021 | 12/09/2021 |
| Note: Released By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 12/09/2021 | 12/09/2021 |
| Note: Released By: CINDY CHIRI-GONCALVES - - CGONCALVES@PALMCOASTGOV.COM | |||
| SW1 | COMPLETE | 12/09/2021 | 12/16/2021 |
| Note: Released By: KALEN RUTH - (386)566-1273 - KRUTH@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 12/09/2021 | 12/09/2021 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| ELEC | COMPLETE | 12/09/2021 | 12/10/2021 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| BLD | HOLD | 12/03/2021 | 12/03/2021 |
| Note: Held By: FRED REODICA - (386)986-4734 - FREODICA@PALMCOASTGOV.COM Additional comment on Roofing Worksheet: Provide product approval number for underlayment and identify the type to be used. | |||
| SWALE | COMPLETE | 12/03/2021 | 01/31/2022 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| ELEC | HOLD | 12/03/2021 | 12/03/2021 |
| Note: Held By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM Submit electric plans | |||
| BLD | HOLD | 12/02/2021 | 12/03/2021 |
| Note: Held By: FRED REODICA - (386)986-4734 - FREODICA@PALMCOASTGOV.COM Product approval FL 15081.1 for fixed insulated vinly window cannot be found in Product approval listing. Please verify the number and re-submit per F.S. 553.842. | |||
| CUSVC | COMPLETE | 12/02/2021 | 12/06/2021 |
| Note: Released By: HALEIGH HAND - - | |||
| ELEC | HOLD | 12/02/2021 | 12/03/2021 |
| Note: Held By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 12/02/2021 | 12/03/2021 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| LOCATE | COMPLETE | 12/02/2021 | 12/07/2021 |
| Note: Released By: CANDACE STONE - - CSTONE@PALMCOASTGOV.COM | |||
| MECH | COMPLETE | 12/02/2021 | 12/03/2021 |
| Note: Released By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM | |||
| SW1 | HOLD | 12/02/2021 | 12/08/2021 |
| Note: Held By: KALEN RUTH - (386)566-1273 - KRUTH@PALMCOASTGOV.COM There are no proposed elevations shown it shows elv | |||
| ZON | HOLD | 12/02/2021 | 12/06/2021 |
| Note: Held By: CINDY CHIRI-GONCALVES - - CGONCALVES@PALMCOASTGOV.COM Site plan survey: Map flood panel number incorrect. |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| CONTRACTOR CHANGE | ¤40.00 | 01/10/2023 |
| REINSPECTION FEE | ¤40.00 | 01/10/2023 |
| SW ENG - INSPECTION 20 | ¤20.00 | 01/10/2023 |
| SW ENG - INSPECTION 20 | ¤20.00 | 01/10/2023 |
| SW ENG - INSPECTION 20 | ¤20.00 | 01/10/2023 |
| SW ENG - INSPECTION 20 | ¤20.00 | 01/10/2023 |
| SW ENG - INSPECTION 20 | ¤20.00 | 01/10/2023 |
| SW ENG - INSPECTION 20 | ¤20.00 | 01/10/2023 |
| SW ENG REINSPECTION 20 | ¤20.00 | 01/10/2023 |
| SW ENG REINSPECTION 20 | ¤20.00 | 01/10/2023 |
| SW ENG REINSPECTION 20 | ¤20.00 | 01/10/2023 |
| SW ENG - REVIEW 20 | ¤20.00 | 01/27/2022 |
| SW ENG RES REVIEW 200 | ¤200.00 | 01/27/2022 |
| 3% TRANS IMPACT FEE CREDIT | (¤51.54) | 01/27/2022 |
| SEWER CREDIT | (¤850.00) | 01/27/2022 |
| SEWER INSPECTION | ¤25.00 | 01/27/2022 |
| SEWER CAPITAL FACILITY | ¤4,939.76 | 01/27/2022 |
| WATER CAPITAL FACILITY FEE | ¤3,626.50 | 01/27/2022 |
| SITE PLAN 30 | ¤30.00 | 01/27/2022 |
| SW ENG INSPECTION 80 | ¤80.00 | 01/27/2022 |
| SW ENG PRE APRON | ¤30.00 | 01/27/2022 |
| SURCHARGE FS 533.721 | ¤9.78 | 01/27/2022 |
| SURCHARGE - FS 468.631 | ¤14.66 | 01/27/2022 |
| SW ENG - FOUNDATION SURVEY | ¤20.00 | 01/27/2022 |
| METER - DEPOSIT | ¤60.00 | 01/27/2022 |
| WATER- TURN ON | ¤25.00 | 01/27/2022 |
| ADMINISTRATIVE RESIDENTIAL | ¤30.00 | 01/27/2022 |
| INSPECTION - RESIDENTIAL | ¤695.75 | 01/27/2022 |
| PLAN REVIEW - RESIDENTIAL | ¤197.34 | 01/27/2022 |
| CONNECTION FEES | ¤1,077.88 | 01/27/2022 |
| 3% FIRE IMPACT FEE CREDIT | (¤11.66) | 01/27/2022 |
| IMPACT FEE FIRE | ¤388.65 | 01/27/2022 |
| IMPACT FEE PARKS | ¤1,455.13 | 01/27/2022 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 01/27/2022 |
| IMPACT FEE TRANSPORTATION | ¤1,718.00 | 01/27/2022 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 01/27/2022 |
| 3% PARKS IMPACT FEE CREDIT | (¤43.65) | 01/27/2022 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤17,571.60 |