I want to search for...
Permit #2021120967
Permit Details
Status: FINAL
| Parcel Id: 07-11-31-7003-00080-0170 |
| Block: 00080 |
| Subdivision: 2190 - SECTION 3-COUNTRY CLUB COVE |
| Job Phone: 407-448-8644 |
| Location Address: 23 CLOVERDALE CT S |
| Type: SW - SEAWALL |
| Issue Date: 03/16/2022 |
| NOC: RECORDED |
| Applicant name: LARRY BRUCE SCHNAPPER |
| Owner: GORETTI JOSE L |
|
Address 23 CLOVERDALE CT S PALM COAST, FL 32137 |
| Lot: 0170 |
| Contracted Stated Job Value: ¤27,000.00 |
| Job Description: REPLACE WITH GRAY VINYL |
| Type: CN |
Contractor
LBS CONSTRUCTION SERVICES INC
| Status | Location Address | State License Number | Phone |
| INACTIVE |
410 EAST PACKWOOD AVE MAITLAND, FL 32751 |
CGCA27951 (Exp: 08/31/2026) | 407-448-8644 |
Inspection History
| Type | Request Date | Result | Inspector |
| SEAWALL FINAL | 09/06/2022 | FINAL APPROVED | AGAETANO |
| SEAWALL FINAL | 08/29/2022 | CANCELLED BY APPLICANT | AWS_IVR |
| Note: THIS IS A REINSPECTION Turbidity barrier not removed. | |||
| ROW - FINAL INSPECTION | 08/24/2022 | Disapproved -FEE REQUIRED | EMADISON |
| Note: ** 08/24/22 SOD NEED ON RIGHT SIDE IN SWALE AREAS WHERE DIRT WAS DROPPED FOR THE PROJECT ** LEFT SIDE OF DRIVEWAY SOD NEEDED IN LARGE BARE AREA / AT SEAWALL BARE AREA SOD NEEDED WHERE DIRT WAS USED TO FILL A HOLE FROM A WASH OUT | |||
| ROW - FINAL INSPECTION | 08/24/2022 | APPROVED - AS NOTED | EMADISON |
| Note: THIS IS A REINSPECTION ** 08/24/22 PER PATRICK BUCKLEY THIS INSPECTION IS BEING PASSED WITHOUT THE REQUIRED WORK BEING COMPLETED AS REQUIRED FOR THE FINAL ROW INSPECTION,AS DIRECTED BY CONRAD TROHA ** 08/24/22 SOD NEED ON RIGHT SIDE IN SWALE AREAS WHERE DIRT WAS DROPPED FOR THE PROJECT ** LEFT SIDE OF DRIVEWAY SOD NEEDED IN LARGE BARE AREA / AT SEAWALL BARE AREA SOD NEEDED WHERE DIRT WAS USED TO FILL A HOLE FROM A WASH OUT | |||
| SEAWALL FINAL | 08/24/2022 | Disapproved - NO FEE | AGAETANO |
| Note: Turbidity barrier not removed. | |||
| SEAWALL DEADMAN CAP | 06/21/2022 | APPROVED | AGAETANO |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION Not ready 6-7-22 Received call from contractor requesting me to come by 9:30 am because he had concrete set up for 10:30. I came off my route to perform the inspection, it was not ready. 1. Missing steel per plans 2. MIssing deadman per plans 3. Need to remove old asbestos panel material and broken concrete fom jobsite prior to this inspection Photo evidence uploaded to system | |||
| SEAWALL DEADMAN CAP | 06/07/2022 | Disapproved -FEE REQUIRED | LMILLER |
| Note: THIS IS A REINSPECTION Not ready 6-7-22 Received call from contractor requesting me to come by 9:30 am because he had concrete set up for 10:30. I came off my route to perform the inspection, it was not ready. 1. Missing steel per plans 2. MIssing deadman per plans 3. Need to remove old asbestos panel material and broken concrete fom jobsite prior to this inspection 4. Deadman end are directly on ground and 24x24x24 forms are missing (no holes or forms) Photo evidence uploaded to system | |||
| SEAWALL DEADMAN CAP | 06/06/2022 | Disapproved - NO FEE | MKRASKI |
| Note: Not ready | |||
| ROW -TURBIDITY BARRER | 03/18/2022 | APPROVED | KRUTH |
Review History
| Department | Status | Date In | Date Out |
| ENGIN1 | COMPLETE | 12/22/2021 | 12/27/2021 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| SW1 | COMPLETE | 12/22/2021 | 12/28/2021 |
| Note: Released By: KALEN RUTH - (386)566-1273 - KRUTH@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 12/22/2021 | 12/22/2021 |
| Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| ADMINISTRATIVE RESIDENTIAL | ¤30.00 | 03/16/2022 |
| INSPECTION - RESIDENTIAL | ¤74.25 | 03/16/2022 |
| PLAN REVIEW - MISC 32.50 | ¤32.50 | 03/16/2022 |
| SURCHARGE FS 533.721 | ¤2.00 | 03/16/2022 |
| SURCHARGE - FS 468.631 | ¤2.11 | 03/16/2022 |
| SW ENG REVIEW- 40 | ¤40.00 | 03/16/2022 |
| SW ENG - INSPECTION 20 | ¤20.00 | 03/16/2022 |
| SW ENG - REVIEW 20 | ¤20.00 | 03/16/2022 |
| SITE PLAN 15 | ¤15.00 | 03/16/2022 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤235.86 |