Permit #2022010979
Permit Details
Status: COED
| Parcel Id: 07-11-31-7033-00400-0330 |
| CONDITIONED SPACE: 1821 sqft |
| GARAGE: 478 sqft |
| OPENED PORCH (WITH ROOF) : 120 sqft |
| OPENED PORCH (WITH ROOF) : 30 sqft |
| Total Square Footage: 2449 sqft |
| Block: 00400 |
| Subdivision: 2184 - SECTION 33-ROYAL PALMS |
| Job Phone: 321-501-4617 |
| Location Address: 7 RENFRO LN |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 03/17/2022 |
| NOC: RECORDED |
| Applicant name: JAMES FUCETOLA III |
| Owner: PALM COAST COMMUNITIES LLC |
|
Address PO BOX 22547 ST SIMONS, GA 31522 |
| Lot: 0330 |
| Contracted Stated Job Value: ¤165,000.00 |
| Job Description: Single Family Residence |
| Type: CN |
Contractor
PALM COAST COMMUNITIES LLC
| Status | Location Address | State License Number | Phone |
| INACTIVE |
PO BOX 22547 PALM COAST, FL 32164 |
CBC1262878 (Exp: 08/31/2026) | 321-501-4617 |
Sub Contractors
JEFFREY TROY SABAKA
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
2191 DEERWOOD ACRES DR ST AUGUSTINE, FL 32084 |
CFC1427439 (Exp: 08/31/2026) | 904-838-2218 | 904-819-0965 |
GARY LLOYD SHEFFIELD
| Status | Location Address | State License Number | Phone |
| ACTIVE |
48 EAGLE LAKES DRIVE FLAGLER BEACH, FL 32136 |
CAC048127 (Exp: 08/31/2026) | 386-597-3280 |
WILLIAM FRANK DUDLEY JR.
| Status | Location Address | State License Number | Phone |
| ACTIVE |
P.O. BOX 978 Bunnell, FL 32110 |
EC0003177 (Exp: 08/31/2026) | (386)437-3068 |
OLEG BELINSKIY
| Status | Location Address | State License Number | Phone |
| ACTIVE |
19 PINE CIRCLE DRIVE19 PALM COAST, FL 32167 |
CCC1325974 (Exp: 08/31/2026) | 386-263-7906 |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 04/13/2023 | FINAL APPROVED | TSTAUFFACHER |
| Note: Check for AAV at final at kitchen sink and right side bath lav. | |||
| U -UTILITY RESIDENTIAL FINAL | 04/04/2023 | FINAL APPROVED | LFITZGERALD |
| Note: 3/31/2023 - PREVIOUS INSPECTION NOTES circuit breaker for pep tank required to bestand alone/dedicated 20amp-no AF/GFI | |||
| ROW - STORMWATER FINAL | 03/31/2023 | APPROVED | FSLADISH |
| Note: 03/31/23 LOOKED GOOD AT TIME OF INSPECTION | |||
| U -UTILITY RESIDENTIAL FINAL | 03/31/2023 | Disapproved -FEE REQUIRED | LFITZGERALD |
| Note: circuit breaker for pep tank required to bestand alone/dedicated 20amp-no AF/GFI | |||
| U-CROSS CONNECTION | 03/31/2023 | APPROVED - AS NOTED | LFITZGERALD |
| Note: has potable irrigation with DBL Check assembly-no cross connection | |||
| ROW - FINAL APRON (AFTER POUR) | 03/30/2023 | APPROVED | FSLADISH |
| ROW FIELD SURVEY /GRADING CERTIFICATION | 03/30/2023 | APPROVED | FSLADISH |
| Note: 03/30/23 CORRECTIONS MADE 3/28/2023 - PREVIOUS INSPECTION NOTES 03/28/23 DURING FIELD SURVEY NOTICED THAT ON LEFT SIDE OF PROPERTY LINE RUNNING DOWN THE FENCE LINE THE DRAINAGE AS IS WILL NEGATIVELY AFFECT PROPERTY ON THE LEFT. NEED TO CREATE BERM RUNNING DOWN FENCE LINE TO REDIRECT WATER FLOW TO THE FRONT OF THE PROPERTY. RELOCATE TREE IN BACK LEFT CORNER OUT OF THE DRAINAGE CONVEYANCE. | |||
| ROW- FINAL SURVEY/GRADING CERTIFICATION | 03/28/2023 | APPROVED | FSLADISH |
| ROW FIELD SURVEY /GRADING CERTIFICATION | 03/28/2023 | Disapproved - NO FEE | FSLADISH |
| Note: 03/28/23 DURING FIELD SURVEY NOTICED THAT ON LEFT SIDE OF PROPERTY LINE RUNNING DOWN THE FENCE LINE THE DRAINAGE AS IS WILL NEGATIVELY AFFECT PROPERTY ON THE LEFT. NEED TO CREATE BERM RUNNING DOWN FENCE LINE TO REDIRECT WATER FLOW TO THE FRONT OF THE PROPERTY. RELOCATE TREE IN BACK LEFT CORNER OUT OF THE DRAINAGE CONVEYANCE. | |||
| U - SEWER TIE IN | 02/27/2023 | APPROVED | MGIBSON |
| ELECTRIC - EARLY POWER | 02/21/2023 | APPROVED | JMUNSON |
| ROW- PRE-APRON (PRE-POUR) | 02/01/2023 | APPROVED | GBERTOLA |
| Note: 02/01/23=AT THE TIME OF THE INSPECTION CULVERT PIPE IS GOOD IS READY TO POUR, IF RAIN PLEASE, BUILDER SHOULD DOUBLE CHECK CULVERT ELEVATIONS BEFORE POURING. MAKE SURE IS 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE (FRC) DRAWING 300,E RESIDENTIAL CULVERT DETAIL ++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ 1/31/2023 - PREVIOUS INSPECTION NOTES CHIP CONCRETE BY THE GARAGE ENTRANCE MINIMUM IS 4" | |||
| ROW- PRE-APRON (PRE-POUR) | 01/31/2023 | Disapproved -FEE REQUIRED | GBERTOLA |
| Note: CHIP CONCRETE BY THE GARAGE ENTRANCE MINIMUM IS 4" CULVERT PIPE IS GOOD | |||
| PEP TANK INSTALLATION REQUEST | 01/12/2023 | APPROVED | CSTONE |
| Note: 1/9/2023 8:10:11 AM- PREVIOUS INSPECTION NOTES Interior-Drywall must be onsite | |||
| PEP TANK INSTALLATION REQUEST | 01/03/2023 | Disapproved - NO FEE | CSTONE |
| Note: Interior-Drywall must be onsite | |||
| INSULATION | 01/03/2023 | APPROVED | JWALKER |
| Note: 12/29/2022 - PREVIOUS INSPECTION NOTES 12/27/2022 - PREVIOUS INSPECTION NOTES HVAC return plenum seal exterior edges and corners of box. Top of box also needs to be sealed when looking inside the plenum. 12/27/22 Above listed correction has not been made. Approved sealant is to be used or approved tape. Top of box inside has not been sealed also. 12/29/22 The edges of the box have not been sealed. The fiber glass is still exposed. And as listed prior the sealeant is to be of the approved type please provide the can or the specs as to the type of foam used. | |||
| INSULATION | 12/29/2022 | Disapproved -FEE REQUIRED | JWALKER |
| Note: 12/27/2022 - PREVIOUS INSPECTION NOTES HVAC return plenum seal exterior edges and corners of box. Top of box also needs to be sealed when looking inside the plenum. 12/27/22 Above listed correction has not been made. Approved sealant is to be used or approved tape. Top of box inside has not been sealed also. 12/29/22 The edges of the box have not been sealed. The fiber glass is still exposed. And as listed prior the sealeant is to be of the approved type please provide the can or the specs as to the type of foam used. | |||
| INSULATION | 12/27/2022 | Disapproved -FEE REQUIRED | JWALKER |
| Note: HVAC return plenum seal exterior edges and corners of box. Top of box also needs to be sealed when looking inside the plenum. Check for AAV at final at kitchen sink and right side bath lav 12/27/22 Above listed correction has not been made. Approved sealant is to be used or approved tape. Top of box inside has not been sealed also. | |||
| LATH/BRICK/ WATER BARRIER | 12/09/2022 | APPROVED | JWALKER |
| Note: Inspector Notes from Inspection 2420 HVAC return plenum seal exterior edges and corners of box. Top of box also needs to be sealed when looking inside the plenum. Check for AAV at final at kitchen sink and right side bath lav. | |||
| ALL ROUGH | 12/05/2022 | APPROVED - AS NOTED | JWALKER |
| Note: HVAC return plenum seal exterior edges and corners of box. Top of box also needs to be sealed when looking inside the plenum. Check for AAV at final at kitchen sink and right side bath lav. | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 11/04/2022 | APPROVED | JWALKER |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 11/01/2022 | APPROVED - AS NOTED | JWALKER |
| Note: The Gable end bracing used is for a non structual gable from the Mitek spec sheets. Sheet MIIGE130 D-Sp has been used. Detail 8 Does not apply to stuctual gable. Have engineer submitt a revison to the building department stating the gable is non structual or have engineer submitt a bracing and blocking detail for gable. Mitek specs do show a common bracing system for structual gable ends, however the engineer will need to specify this detail can be used. Check above listed at ALL ROUGH. | |||
| ROOF VALLEY & METAL | 09/01/2022 | APPROVED | JWALKER |
| ROOF SHEATHING | 08/23/2022 | APPROVED | MKRASKI |
| WALL SHEATHING | 08/23/2022 | APPROVED | MKRASKI |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 08/23/2022 | Disapproved - NO FEE | MKRASKI |
| Note: 1. No Girder truss detail on site 2. No gable end detail on site 3. Over framing missing Simpson H2.5 per plans Stopped inspectio | |||
| FOUND SURVEY APPROVED (OFFICE) | 08/04/2022 | APPROVED | TBAKER |
| TIE BEAM / LINTEL | 07/26/2022 | APPROVED | JWALKER |
| MONOLITHIC SLAB | 07/08/2022 | APPROVED | JWALKER |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION Soil has washed out into the footings covering the rebar. Footing will need to be dug out. Ensure rebar has 3" ground clearance. 403.1 RBC. | |||
| MONOLITHIC SLAB | 07/07/2022 | CANCELLED BY APPLICANT | JWALKER |
| Note: THIS IS A REINSPECTION Soil has washed out into the footings covering the rebar. Footing will need to be dug out. Ensure rebar has 3" ground clearance. 403.1 RBC. | |||
| MONOLITHIC SLAB | 07/06/2022 | Disapproved - NO FEE | JWALKER |
| Note: Soil has washed out into the footings covering the rebar. Footing will need to be dug out. Ensure rebar has 3" ground clearance. 403.1 RBC. | |||
| MONOLITHIC SLAB | 07/05/2022 | CANCELLED BY APPLICANT | AWS_IVR |
| Note: THIS IS A REINSPECTION The footing at the garage wall is not installed as per the detail 3/F. Foundation drawing is circled for location. | |||
| MONOLITHIC SLAB | 06/30/2022 | Disapproved - NO FEE | JWALKER |
| Note: The footing at the garage wall is not installed as per the detail 3/F. Foundation drawing is circled for location. | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 06/21/2022 | APPROVED | MGIBSON |
| GRAVITY SEWER TEST | 06/21/2022 | APPROVED | MGIBSON |
| WATER METER INSTALLATION REQUEST | 05/23/2022 | APPROVED | CSTONE |
| WATER METER INSTALLATION REQUEST | 05/17/2022 | APPROVED | CSTONE |
Review History
| Department | Status | Date In | Date Out |
| ENGIN1 | COMPLETE | 08/04/2022 | 08/04/2022 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 08/04/2022 | 08/04/2022 |
| Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 03/13/2022 | 03/14/2022 |
| Note: Released By: FRED REODICA - (386)986-4734 - FREODICA@PALMCOASTGOV.COM | |||
| BADMIN | INFORMATION | 03/03/2022 | 03/03/2022 |
| Note: Marked INFORMATION By: BARBIE BEMBRY - (386)986-3780 - BUILDINGDIVISION@PALMCOASTGOV.COM The digital signature submitted on the revised plan is not verifiable. | |||
| BLD | HOLD | 02/28/2022 | 02/28/2022 |
| Note: Held By: FRED REODICA - (386)986-4734 - FREODICA@PALMCOASTGOV.COM Correction review comment: Design pressure of garage door, 16 ft x 7 ft shown as 21.7/-24.1 PSF on Sheet 3 of 6, Table R301.2(4) does not match with those shown on Sheet 1 of 6 as 17.7/19.7 PSF. Coordinate for clarity per FBC 7th Ed. Sec. 107.3. | |||
| BLD | HOLD | 02/22/2022 | 02/23/2022 |
| Note: Held By: FRED REODICA - (386)986-4734 - FREODICA@PALMCOASTGOV.COM Repeat previous comment item 2: 1. Okay. 2. Provide Components and Cladding of Pressure Zones per FBC - Residential Figure R301.2 (7). 3. Okay. | |||
| BLD | HOLD | 01/21/2022 | 01/24/2022 |
| Note: Held By: FRED REODICA - (386)986-4734 - FREODICA@PALMCOASTGOV.COM 1. Provide missing engineered truss/roof framing layout that should have been submitted during the permit application. A request on letter head should be submitted for deferred submittal as provided on Ciy's Website. Truss package may be submitted at the job site. 2. Provide Components and Cladding of Pressure Zones per FBC - Residential Figure R301.2(7). 3. Sheet 4 of 6 - Foundation Plan: a. Referenced Mark, 3/F between garage and driveway is incorrect based on footer detail shown on Sheet 5 of 6. Also, provide applicable footer details on foundation plan for clarity per FBC 7th Ed. Sec. 107.3. | |||
| CUSVC | COMPLETE | 01/21/2022 | 01/26/2022 |
| Note: Released By: HALEIGH HAND - - | |||
| ELEC | COMPLETE | 01/21/2022 | 01/24/2022 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 01/21/2022 | 01/21/2022 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| LOCATE | COMPLETE | 01/21/2022 | 01/24/2022 |
| Note: Released By: CANDACE STONE - - CSTONE@PALMCOASTGOV.COM | |||
| MECH | COMPLETE | 01/21/2022 | 01/21/2022 |
| Note: Released By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM | |||
| SW1 | COMPLETE | 01/21/2022 | 01/26/2022 |
| Note: Released By: PARREN FLANAGAN - - PFLANAGAN@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 01/21/2022 | 01/24/2022 |
| Note: Released By: CINDY CHIRI-GONCALVES - - CGONCALVES@PALMCOASTGOV.COM | |||
| SWALE | COMPLETE | 01/21/2022 | 03/23/2022 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION RESIDENTIAL | ¤40.00 | 04/13/2023 |
| REINSPECTION RESIDENTIAL | ¤40.00 | 04/13/2023 |
| REINSPECTION FEE | ¤40.00 | 04/13/2023 |
| SW ENG REINSPECTION 30 | ¤30.00 | 04/13/2023 |
| SW ENG - REVIEW 20 | ¤20.00 | 03/17/2022 |
| SW ENG RES REVIEW 200 | ¤200.00 | 03/17/2022 |
| 3% TRANS IMPACT FEE CREDIT | (¤52.92) | 03/17/2022 |
| SEWER CREDIT | (¤292.17) | 03/17/2022 |
| SEWER INSPECTION | ¤25.00 | 03/17/2022 |
| SEWER CAPITAL FACILITY | ¤4,939.76 | 03/17/2022 |
| WATER CAPITAL FACILITY FEE | ¤3,626.50 | 03/17/2022 |
| SITE PLAN 30 | ¤30.00 | 03/17/2022 |
| SURCHARGE FS 533.721 | ¤8.87 | 03/17/2022 |
| SURCHARGE - FS 468.631 | ¤13.31 | 03/17/2022 |
| SW ENG - FOUNDATION SURVEY | ¤20.00 | 03/17/2022 |
| SW ENG INSPECTION 80 | ¤80.00 | 03/17/2022 |
| SW ENG PRE APRON | ¤30.00 | 03/17/2022 |
| METER - DEPOSIT | ¤60.00 | 03/17/2022 |
| WATER- TURN ON | ¤25.00 | 03/17/2022 |
| ADMINISTRATIVE RESIDENTIAL | ¤30.00 | 03/17/2022 |
| INSPECTION - RESIDENTIAL | ¤627.00 | 03/17/2022 |
| PLAN REVIEW - RESIDENTIAL | ¤177.84 | 03/17/2022 |
| CONNECTION FEES | ¤1,077.88 | 03/17/2022 |
| 3% FIRE IMPACT FEE CREDIT | (¤11.66) | 03/17/2022 |
| IMPACT FEE FIRE | ¤388.65 | 03/17/2022 |
| IMPACT FEE PARKS | ¤1,455.13 | 03/17/2022 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 03/17/2022 |
| IMPACT FEE TRANSPORTATION | ¤1,764.00 | 03/17/2022 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 03/17/2022 |
| 3% PARKS IMPACT FEE CREDIT | (¤43.65) | 03/17/2022 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤17,973.54 |