I want to search for...
Permit #2022030803
Permit Details
Status: COED
| Parcel Id: 07-11-31-7029-00310-0080 |
| CONDITIONED SPACE: 2062 sqft |
| GARAGE: 433 sqft |
| Total Square Footage: 2495 sqft |
| Block: 00310 |
| Subdivision: 2209 - SECTION 29-ROYAL PALMS |
| Job Phone: 904-888-6443 |
| Location Address: 51 RYDER DR |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 05/02/2022 |
| NOC: RECORDED |
| Applicant name: AMIR BENTOV |
| Owner: DS PALM COAST DEV LLC |
|
Address 820 S EDENBRIDGE WAY ST AUGUSTINE, FL 32092 |
| Lot: 0080 |
| Contracted Stated Job Value: ¤200,000.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
MAVEN HOMES LLC
| Status | Location Address | State License Number | Phone |
| ACTIVE |
2800 N 6TH ST UNIT 790 , |
CRC1333741 (Exp: 08/31/2026) | 904-667-4330 |
Sub Contractors
GARY LLOYD SHEFFIELD
| Status | Location Address | State License Number | Phone |
| ACTIVE |
48 EAGLE LAKES DRIVE FLAGLER BEACH, FL 32136 |
CAC048127 (Exp: 08/31/2026) | 386-597-3280 |
OLEG BELINSKIY
| Status | Location Address | State License Number | Phone |
| ACTIVE |
19 PINE CIRCLE DRIVE19 PALM COAST, FL 32167 |
CCC1325974 (Exp: 08/31/2026) | 386-263-7906 |
ROBERT E GRANT JR
| Status | Location Address | State License Number |
| INACTIVE |
6060 CHESTER CIRCLE JACKSONVILLE, FL 32217 |
EC13008285 (Exp: 08/31/2024) |
JAMES MCGOVERN
| Status | Location Address | Phone | Fax |
| ACTIVE |
PO BOX 354295 PALM COAST, FL 32137 |
(386)931-8940 | (386)986-4835 |
RUSSELL J CARTER
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
PO BOX 302 DELAND, FL 32721 |
CFC1425938 (Exp: 08/31/2026) | 386-736-4220 | 386-736-4219 |
Inspection History
| Type | Request Date | Result | Inspector |
| ROW - STORMWATER FINAL | 07/10/2023 | FINAL APPROVED | EMADISON |
| Note: ** 07/10/23 CORRECTIONS MADE 6/28/2023 - PREVIOUS INSPECTION NOTES 06/28/23 NEED TO FINISH REPAIRING AND RESODDING THE RIGHT SWALE AREA BEFORE ROW FINAL PASSAGE. ________________________________________________________________________________________________________________________ 6/20/2023 - PREVIOUS INSPECTION NOTES 6/20/23= NEED TO REMOVE THE HUMP ON THE PROPERTY LINE ON THE RIGHT SIDE SWALE. NEED TO READ INSPECTOR NOTES . ++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ 4/24/2023 - PREVIOUS INSPECTION NOTES 4/24/23=NEED TO MATCH EXISTING GRADE AT EACH PROPERTY LINE. WATER FLOW FROM THE RIGHT TO THE LEFT. +++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ 04/06/23 NEED TO MATCH SOD GRADE IN SWALE ON RIGHT SIDE PROPERTY SWALE TO EXISTING ADJOINING PROPERTY SWALE (TOO HIGH). TRASH AND CONSTUCTION DEBRIS NEED TO BE REMOVED FROM SITE AND CULVERT ENDS BEFORE PASSING ROW FINAL. | |||
| U -UTILITY RESIDENTIAL FINAL | 07/10/2023 | FINAL APPROVED | LFITZGERALD |
| Note: 7/5/2023 - PREVIOUS INSPECTION NOTES no corrections made?? 6/28/2023 - PREVIOUS INSPECTION NOTES this seems to be reaccurring issue-Do Not Paint over labels on the pep tank control panel of house wall-go to utility ept. ,get labels and attach to panel cover | |||
| U -UTILITY RESIDENTIAL FINAL | 07/05/2023 | Disapproved - NO FEE | LFITZGERALD |
| Note: no corrections made?? 6/28/2023 - PREVIOUS INSPECTION NOTES this seems to be reaccurring issue-Do Not Paint over labels on the pep tank control panel of house wall-go to utility ept. ,get labels and attach to panel cover | |||
| U -UTILITY RESIDENTIAL FINAL | 06/28/2023 | Disapproved - NO FEE | LFITZGERALD |
| Note: this seems to be reaccurring issue-Do Not Paint over labels on the pep tank control panel of house wall-go to utility ept. ,get labels and attach to panel cover | |||
| ROW - STORMWATER FINAL | 06/28/2023 | Disapproved -FEE REQUIRED | FSLADISH |
| Note: 06/28/23 NEED TO FINISH REPAIRING AND RESODDING THE RIGHT SWALE AREA BEFORE ROW FINAL PASSAGE. SEE PHOTO FOR REFERENCE ________________________________________________________________________________________________________________________ 6/20/2023 - PREVIOUS INSPECTION NOTES 6/20/23= NEED TO REMOVE THE HUMP ON THE PROPERTY LINE ON THE RIGHT SIDE SWALE. NEED TO READ INSPECTOR NOTES . ++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ 4/24/2023 - PREVIOUS INSPECTION NOTES 4/24/23=NEED TO MATCH EXISTING GRADE AT EACH PROPERTY LINE. WATER FLOW FROM THE RIGHT TO THE LEFT. +++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ 04/06/23 NEED TO MATCH SOD GRADE IN SWALE ON RIGHT SIDE PROPERTY SWALE TO EXISTING ADJOINING PROPERTY SWALE (TOO HIGH). TRASH AND CONSTUCTION DEBRIS NEED TO BE REMOVED FROM SITE AND CULVERT ENDS BEFORE PASSING ROW FINAL. | |||
| BLD - BUILDING FINAL | 06/28/2023 | Approval - Private Provider | PPROVIDER |
| ROW - STORMWATER FINAL | 06/20/2023 | Disapproved -FEE REQUIRED | GBERTOLA |
| Note: 6/20/23= NEED TO REMOVE THE HUMP ON THE PROPERTY LINE ON THE RIGHT SIDE SWALE. NEED TO READ INSPECTOR NOTES . ++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ 4/24/2023 - PREVIOUS INSPECTION NOTES 4/24/23=NEED TO MATCH EXISTING GRADE AT EACH PROPERTY LINE. WATER FLOW FROM THE RIGHT TO THE LEFT. +++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ 04/06/23 NEED TO MATCH SOD GRADE IN SWALE ON RIGHT SIDE PROPERTY SWALE TO EXISTING ADJOINING PROPERTY SWALE (TOO HIGH). TRASH AND CONSTUCTION DEBRIS NEED TO BE REMOVED FROM SITE AND CULVERT ENDS BEFORE PASSING ROW FINAL. | |||
| LATH/BRICK/ WATER BARRIER | 05/17/2023 | Approval - Private Provider | PPROVIDER |
| Note: 5/16/2023 12:40:30 PM- PREVIOUS INSPECTION NOTES | |||
| LATH/BRICK/ WATER BARRIER | 05/08/2023 | CANCELLED BY APPLICANT | PPROVIDER |
| U-CROSS CONNECTION | 04/24/2023 | APPROVED - AS NOTED | LFITZGERALD |
| Note: no irrigation-no cross connection | |||
| ROW - STORMWATER FINAL | 04/24/2023 | Disapproved -FEE REQUIRED | GBERTOLA |
| Note: 4/24/23=NEED TO MATCH EXISTING GRADE AT EACH PROPERTY LINE. WATER FLOW FROM THE RIGHT TO THE LEFT. +++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ 04/06/23 NEED TO MATCH SOD GRADE IN SWALE ON RIGHT SIDE PROPERTY SWALE TO EXISTING ADJOINING PROPERTY SWALE (TOO HIGH). TRASH AND CONSTUCTION DEBRIS NEED TO BE REMOVED FROM SITE AND CULVERT ENDS BEFORE PASSING ROW FINAL. | |||
| ROW FIELD SURVEY /GRADING CERTIFICATION | 04/06/2023 | APPROVED | FSLADISH |
| Note: 04/06/23 NEED TO MATCH SOD GRADE IN SWALE ON RIGHT SIDE PROPERTY SWALE TO EXISTING ADJOINING PROPERTY SWALE (TOO HIGH). TRASH AND CONSTUCTION DEBRIS NEED TO BE REMOVED FROM SITE AND CULVERT ENDS BEFORE PASSING ROW FINAL. | |||
| ROW - FINAL APRON (AFTER POUR) | 04/06/2023 | APPROVED | FSLADISH |
| ROW- FINAL SURVEY/GRADING CERTIFICATION | 03/30/2023 | APPROVED | FSLADISH |
| ELECTRIC - EARLY POWER | 03/10/2023 | Approval - Private Provider | PPROVIDER |
| ROW- PRE-APRON (PRE-POUR) | 02/22/2023 | APPROVED | GBERTOLA |
| Note: AT THE TIME OF THE INSPECTION CULVERT PIPE IS GOOD IS READY TO POUR, IF RAIN PLEASE, BUILDER SHOULD DOUBLE CHECK CULVERT ELEVATIONS BEFORE POURING. MAKE SURE IS 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE (FRC) DRAWING 300,E RESIDENTIAL CULVERT DETAIL | |||
| U - SEWER TIE IN | 01/04/2023 | APPROVED - AS NOTED | MGIBSON |
| Note: THIS WAS A VIRTUAL INSPECTION | |||
| GRAVITY SEWER TEST | 01/03/2023 | Approval - Private Provider | PPROVIDER |
| PEP TANK INSTALLATION REQUEST | 12/13/2022 | APPROVED | CSTONE |
| INSULATION | 12/07/2022 | Approval - Private Provider | PPROVIDER |
| Note: 12/06/2022 LB Code: 0510 Dakota L. Hilton | |||
| ALL ROUGH | 11/18/2022 | Approval - Private Provider | PPROVIDER |
| WALL SHEATHING | 09/20/2022 | Approval - Private Provider | PPROVIDER |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 09/20/2022 | Approval - Private Provider | PPROVIDER |
| ROOF VALLEY & METAL | 09/20/2022 | Approval - Private Provider | PPROVIDER |
| FOUND SURVEY APPROVED (OFFICE) | 08/05/2022 | APPROVED | TBAKER |
| MONOLITHIC SLAB | 07/07/2022 | Approval - Private Provider | PPROVIDER |
| PLUMBING 1ST ROUGH UNDERGROUND | 06/30/2022 | Approval - Private Provider | PPROVIDER |
| WATER METER INSTALLATION REQUEST | 06/06/2022 | APPROVED | CSTONE |
| Note: THIS IS A REINSPECTION ADDED ON 5/4/2022 2:24:56 PM lot not cleared | |||
| WATER METER INSTALLATION REQUEST | 05/03/2022 | Disapproved - NO FEE | CSTONE |
| Note: lot not cleared |
Review History
| Department | Status | Date In | Date Out |
| ENGIN1 | COMPLETE | 08/05/2022 | 08/05/2022 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 08/05/2022 | 08/05/2022 |
| Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 03/30/2022 | 03/30/2022 |
| Note: Released By: FRED REODICA - (386)986-4734 - FREODICA@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 03/22/2022 | 03/22/2022 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 03/22/2022 | 03/23/2022 |
| Note: Released By: CINDY CHIRI-GONCALVES - - CGONCALVES@PALMCOASTGOV.COM | |||
| BLD | HOLD | 03/22/2022 | 03/22/2022 |
| Note: Held By: FRED REODICA - (386)986-4734 - FREODICA@PALMCOASTGOV.COM Correction comment: The address on structural plans and roofing worksheet is still incorrect. Revise to 51 Ryder Drive - FBC 7th Ed. Sec. 107.3. | |||
| ELEC | COMPLETE | 03/22/2022 | 03/23/2022 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| MECH | COMPLETE | 03/22/2022 | 03/22/2022 |
| Note: Released By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM | |||
| LOCATE | COMPLETE | 03/22/2022 | 03/30/2022 |
| Note: Released By: CANDACE STONE - - CSTONE@PALMCOASTGOV.COM | |||
| SWALE | COMPLETE | 03/22/2022 | 05/26/2022 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| BLD | HOLD | 03/15/2022 | 03/16/2022 |
| Note: Held By: FRED REODICA - (386)986-4734 - FREODICA@PALMCOASTGOV.COM The address on architectural, structural , product approval and roofing worksheet is not coordinated - FBC 7th Ed. Sec. 107.3. | |||
| CUSVC | COMPLETE | 03/15/2022 | 03/16/2022 |
| Note: Released By: CYNTHIA SCHWEERS - - CSCHWEERS@PALMCOASSTGOV.COM | |||
| ELEC | HOLD | 03/15/2022 | 03/16/2022 |
| Note: Held By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM Need correct Outlet spacing NEC 2017 210.52 | |||
| ENGIN1 | HOLD | 03/15/2022 | 03/15/2022 |
| Note: Held By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM Wrong survey/site plan submitted. | |||
| LOCATE | HOLD | 03/15/2022 | 03/21/2022 |
| Note: Held By: CANDACE STONE - - CSTONE@PALMCOASTGOV.COM wrong plot plan | |||
| MECH | HOLD | 03/15/2022 | 03/18/2022 |
| Note: Held By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM Orientation of Energy Calcs does not match. The site plan submitted is for the wrong address. Revise calcs to correct direction | |||
| SW1 | COMPLETE | 03/15/2022 | 03/21/2022 |
| Note: Released By: PARREN FLANAGAN - - PFLANAGAN@PALMCOASTGOV.COM | |||
| ZON | HOLD | 03/15/2022 | 03/15/2022 |
| Note: Held By: CINDY CHIRI-GONCALVES - - CGONCALVES@PALMCOASTGOV.COM The site plan, landscape plan, color sheet and boundary survey are for a different address. |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| CONTRACTOR CHANGE | ¤20.00 | 07/10/2023 |
| SW ENG REINSPECTION 20 | ¤20.00 | 07/10/2023 |
| SW ENG REINSPECTION 20 | ¤20.00 | 07/10/2023 |
| SW ENG REINSPECTION 20 | ¤20.00 | 07/10/2023 |
| SW ENG - REVIEW 20 | ¤20.00 | 05/02/2022 |
| SW ENG RES REVIEW 200 | ¤200.00 | 05/02/2022 |
| 3% TRANS IMPACT FEE CREDIT | (¤52.92) | 05/02/2022 |
| SEWER CREDIT | (¤1,342.00) | 05/02/2022 |
| SEWER INSPECTION | ¤25.00 | 05/02/2022 |
| SEWER CAPITAL FACILITY | ¤4,939.76 | 05/02/2022 |
| WATER CAPITAL FACILITY FEE | ¤3,626.50 | 05/02/2022 |
| SITE PLAN 30 | ¤30.00 | 05/02/2022 |
| 3% FIRE IMPACT FEE CREDIT | (¤11.66) | 05/02/2022 |
| IMPACT FEE FIRE | ¤388.65 | 05/02/2022 |
| IMPACT FEE PARKS | ¤1,455.13 | 05/02/2022 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 05/02/2022 |
| IMPACT FEE TRANSPORTATION | ¤1,764.00 | 05/02/2022 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 05/02/2022 |
| 3% PARKS IMPACT FEE CREDIT | (¤43.65) | 05/02/2022 |
| SURCHARGE FS 533.721 | ¤9.52 | 05/02/2022 |
| SURCHARGE - FS 468.631 | ¤14.28 | 05/02/2022 |
| SW ENG - FOUNDATION SURVEY | ¤20.00 | 05/02/2022 |
| SW ENG INSPECTION 80 | ¤80.00 | 05/02/2022 |
| SW ENG PRE APRON | ¤30.00 | 05/02/2022 |
| WATER- TURN ON | ¤25.00 | 05/02/2022 |
| ADMINISTRATIVE RESIDENTIAL | ¤30.00 | 05/02/2022 |
| ADMINISTRATIVE - RESID PP | ¤225.00 | 05/02/2022 |
| PLAN REVIEW - RESIDENTIAL | ¤191.88 | 05/02/2022 |
| CONNECTION FEES | ¤1,077.88 | 05/02/2022 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤16,407.37 |