I want to search for...
Permit #2022050574
Permit Details
Status: COED
| Parcel Id: 41-11-31-4975-00000-0010 |
| Total Square Footage: 3500 sqft |
| Block: 00000 |
| Subdivision: 1155 - PALM HARBOR SHOPPING VILLAGE |
| Job Phone: 321-723-5661 |
| Location Address: 250 PALM COAST PKWY NE |
| Type: CIA - COMMERCIAL INTERIOR EXTERIOR ALTERATION |
| Issue Date: 08/24/2022 |
| NOC: RECORDED |
| Applicant name: GARY HOWELL II NEAL |
| Owner: BRANCH ISLAND WALK ASSOCIATES LP |
|
Address SUITE 600 ATLANTA, GA 30326 |
|
Address 3340 PEACHTREE ROAD NE ATLANTA, GA 30326 |
| Lot: 0010 |
| Contracted Stated Job Value: ¤900,000.00 |
| Job Description: UNIT 1302 - HEARTLAND DENTAL |
| Type: CN |
Contractor
M E CONSTRUCTION INC
| Status | Location Address | State License Number | Phone |
| ACTIVE |
445 PINEDA CT MELBOURNE, FL 32940 |
CGC1525425 (Exp: 08/31/2026) | 321-723-5661 |
Sub Contractors
LEONARD G MARX
| Status | Location Address | Mailing Address | State License Number | Phone | Fax |
| ACTIVE |
750 OAK HEIGHTS CT PORT ORANGE, FL 32127 |
# 310 PORT ORANGE, FL 32127 |
CAC032453 (Exp: 08/31/2026) | (386) 252-1222 | (386)756-2931 |
DERRICK SCOTT HARGER
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
975 SUNSHINE LANE ALTAMONTE SPRINGS, FL 32714 |
CFC1425861 (Exp: 08/31/2026) | (407)295-1000 | (407)295-0000 |
JOHN GAIL REGER
| Status | Location Address | State License Number | Phone |
| INACTIVE |
1312 ROSEWOOD AVE ST. CLOUD , FL 34771 |
EC0003021 (Exp: 08/31/2024) | 407-873-4665 |
Inspection History
| Type | Request Date | Result | Inspector |
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | 07/28/2023 | APPROVED | LFITZGERALD |
| Note: 2/6/2023 - PREVIOUS INSPECTION NOTES installed 1.5 inch poly service to building from new 2inch Back flow Preventor/installed 2inch gate valve for wet tap on existing DI water main/installed 2inch meter/backflow Ok per inspector fitzgerald | |||
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | 07/27/2023 | APPROVED | LFITZGERALD |
| BUILDING FINAL | 07/26/2023 | FINAL APPROVED | JWALKER |
| FIRE FINAL | 07/26/2023 | APPROVED | RMARTIN |
| FIREWALL FINAL | 07/26/2023 | FINAL APPROVED | JWALKER |
| Note: 7/24/2023 - PREVIOUS INSPECTION NOTES 7/24/23 CPVC plumbings lines pentrating need to be sleeved as per the UL listing or need changed to copper. 7/18/2023 - PREVIOUS INSPECTION NOTES 1. Acoustical ceiling support wire need to be sealed at the ceiling where ther sheet rock was dug out. 2. The plumbing box and the 2" drian pipe need to be removed from the fire wall as these membrane penetrations are not UL listed. 3. Dryer duct missing fire damper at the roof penetration. 4. Dryer duct box at the fire wall needs to be seal where it meets the sheetrock. | |||
| PLUMBING FINAL | 07/26/2023 | FINAL APPROVED | JWALKER |
| Note: 7/18/2023 - PREVIOUS INSPECTION NOTES 1. No hot water to the lavs in the staff restroom and the Treatment room suite 1. 2. Missing floor clean out in the office 104. 3. Missing wall cleanouts in the equipment room and at the drinking fountians. 4. Women rest room sink has been installed above the 34" maximum distance off the finish floor. 5. Please have roof access available at the reinspection. Previous inspection notes below. Check Vaccum line connection and roof vent at final. | |||
| ELECTRIC FINAL | 07/25/2023 | APPROVED | RMARTIN |
| Note: 7/24/2023 - PREVIOUS INSPECTION NOTES 7/24/23 lobby area needs tamper proof outlets per nec 406.12 and mini split calls for 15a breaker and a 20a is installed 7/21/2023 - PREVIOUS INSPECTION NOTES 7/18/2023 - PREVIOUS INSPECTION NOTES need access to the roof for inspection, interior is good 7/6/2023 - PREVIOUS INSPECTION NOTES Not ready, outlets missing, blanks missing, call in for re-inspection when ready for final | |||
| ELECTRIC FINAL | 07/24/2023 | Disapproved - NO FEE | RMARTIN |
| Note: 7/24/23 lobby area needs tamper proof outlets per nec 406.12 and mini split calls for 15a breaker and a 20a is installed 7/21/2023 - PREVIOUS INSPECTION NOTES 7/18/2023 - PREVIOUS INSPECTION NOTES need access to the roof for inspection, interior is good 7/6/2023 - PREVIOUS INSPECTION NOTES Not ready, outlets missing, blanks missing, call in for re-inspection when ready for final | |||
| HVAC FINAL | 07/24/2023 | FINAL APPROVED | CPISCITELLI |
| Note: 7/21/2023 - PREVIOUS INSPECTION NOTES | |||
| FIREWALL FINAL | 07/24/2023 | Disapproved - NO FEE | JWALKER |
| Note: 7/24/23 CPVC plumbings lines pentrating need to be sleeved as per the UL listing or need changed to copper. 7/18/2023 - PREVIOUS INSPECTION NOTES 1. Acoustical ceiling support wire need to be sealed at the ceiling where ther sheet rock was dug out. 2. The plumbing box and the 2" drian pipe need to be removed from the fire wall as these membrane penetrations are not UL listed. 3. Dryer duct missing fire damper at the roof penetration. 4. Dryer duct box at the fire wall needs to be seal where it meets the sheetrock. | |||
| FIRE FINAL | 07/24/2023 | APPROVED | RMARTIN |
| HVAC FINAL | 07/21/2023 | CANCELLED BY APPLICANT | CPISCITELLI |
| ELECTRIC FINAL | 07/21/2023 | CANCELLED BY APPLICANT | RMARTIN |
| Note: 7/18/2023 - PREVIOUS INSPECTION NOTES need access to the roof for inspection, interior is good 7/6/2023 - PREVIOUS INSPECTION NOTES Not ready, outlets missing, blanks missing, call in for re-inspection when ready for final | |||
| ELECTRIC FINAL | 07/18/2023 | Disapproved - NO FEE | RMARTIN |
| Note: need access to the roof for inspection, interior is good 7/6/2023 - PREVIOUS INSPECTION NOTES Not ready, outlets missing, blanks missing, call in for re-inspection when ready for final | |||
| PLUMBING FINAL | 07/18/2023 | Disapproved - NO FEE | JWALKER |
| Note: 1. No hot water to the lavs in the staff restroom and the Treatment room suite 1. 2. Missing floor clean out in the office 104. 3. Missing wall cleanouts in the equipment room and at the drinking fountians. 4. Women rest room sink has been installed above the 34" maximum distance off the finish floor. 5. Please have roof access available at the reinspection. Previous inspection notes below. Check Vaccum line connection and roof vent at final. | |||
| U - UTILITY COMMERCIAL FINAL | 07/18/2023 | FINAL APPROVED | LFITZGERALD |
| FIREWALL FINAL | 07/18/2023 | Disapproved - NO FEE | JWALKER |
| Note: 1. Acoustical ceiling support wire need to be sealed at the ceiling where ther sheet rock was dug out. 2. The plumbing box and the 2" drian pipe need to be removed from the fire wall as these membrane penetrations are not UL listed. 3. Dryer duct missing fire damper at the roof penetration. 4. Dryer duct box at the fire wall needs to be seal where it meets the sheetrock. | |||
| ELECTRIC FINAL | 07/06/2023 | Disapproved - NO FEE | MKRASKI |
| Note: Not ready, outlets missing, blanks missing, call in for re-inspection when ready for final | |||
| PLUMBING 2ND ROUGH | 06/07/2023 | APPROVED - AS NOTED | JWALKER |
| Note: 6/7/23 Check for install of water filtration and backflow preventer. Vaccum line connection at final. 5/24/2023 - PREVIOUS INSPECTION NOTES 5/24/23 1. Multiple above ceiling shut off valves have duct work up against the valves. This will not allow the valves to be open and closed. 2. Toilet room 109 Side wall clearance to the toilet is to be 16 to 18". Plumbing pipe is at 13 1/2" 3. Drawings call for 3- 3" vtr. Unable to locate. Please have plumber onsite to show locations. 4. DW calls for a water filtration and backflow preventer to be installed detail P-102 5. Water distribution lines need to be place under pressure test. 6. Revison for pipes , water hammers and sprinkler have been submitted and accepted not yet approved. See notes below. 11/3/2022 - PREVIOUS INSPECTION NOTES 1. Water hammers have non been installed. Install hammers of have engineer submitt revision noted they can be omitted. 2. Cold and hot water supply lines are specifed to be L type copper. CPVC has been installed. Have engineer submitt a revision to the building department for change of material. 3. 2 of 3 vent to roof have not been installed. 4. Hose bib line at front right of the building has not been roughed in. 5. Page 102 Shows a 3/4 " water supply into the dental gas room calling for a sprinkler head to be installed. Please clarify this detail of have omitted by the engineer. 6. Trap primer valves have not been installed. 7. Multiple shut off valves detaild have not been installed in the water supply lines above ceiling. 8. Domestic water hook up has not been installed. | |||
| FIREWALL NAILING | 06/07/2023 | APPROVED | FWILLIS |
| ABOVE CEILING | 06/01/2023 | APPROVED - AS NOTED | RMARTIN |
| Note: 6/1 Minisplit pump not connected and copper lines not supported will look at on final Plumbing: Not Ready Electrical: need to cover open 4"sq box in back room ceiling, need to connect whip to cabinet lights in hall, will check on final 10/20/2022 - PREVIOUS INSPECTION NOTES NOT COMPLETE. WORKERS STOPPED UNTIL FLOOR GRINDING AND BUFFERING IS COMPLETE. A DUST ISSUE. 10.21.22 - Portion inspected was far left rear corner of unit, this gets a secondary partition 10/26/22 - REAR ROOM ONLY. 11/18/22 - Partial Firewall North side. 1/9/23- Laundry room 1 st layer 5/8 on ceiling, walls have all been double layered. No other firewall inspection done at this inspection. | |||
| FIREWALL NAILING | 06/01/2023 | APPROVED | FWILLIS |
| Note: 5/26/2023 - PREVIOUS INSPECTION NOTES First layer approved. | |||
| ELECTRIC - EARLY POWER | 06/01/2023 | APPROVED - AS NOTED | RMARTIN |
| Note: Inspector Notes from Inspection 3210 6/1/23 wire size is corrected 5/23/23 released power up to disconnect only, keep disconnect locked out 1/11/2023 - PREVIOUS INSPECTION NOTES meter is ok to re-use | |||
| ELECTRIC 2ND ROUGH | 06/01/2023 | APPROVED | RMARTIN |
| FIREWALL FRAMING | 05/31/2023 | Disapproved - NO FEE | FWILLIS |
| Note: 5/31/23 - ELECTRICAL LINE NEEDS FIRE CAULKING. | |||
| FIREWALL NAILING | 05/26/2023 | PARTIALLY APPROVED | JWALKER |
| Note: First layer approved. | |||
| ABOVE CEILING | 05/24/2023 | Disapproved - NO FEE | RMARTIN |
| Note: 05/24/2023- Mechanical: Need to seal all flex connections with a panduit strap and mastic on connection to metal. Need to use UL181 approved tape or mastic on exhaust flex to metal. Several duct lines are laying in plumbing pipes and need to be lifted. Need to use UL181 tape on return boxes and seal connection from duct to box with mastic or Ul181 approved tape. Flex duct in front area too short and kinked. Need to support all exhaust flex. Minisplit pump not connected and copper lines not supported. Plumbing: Not Ready Electrical: need to cover open 4"sq box in back room ceiling, need to connect whip to cabinet lights in hall, will check on final 10/20/2022 - PREVIOUS INSPECTION NOTES NOT COMPLETE. WORKERS STOPPED UNTIL FLOOR GRINDING AND BUFFERING IS COMPLETE. A DUST ISSUE. 10.21.22 - Portion inspected was far left rear corner of unit, this gets a secondary partition 10/26/22 - REAR ROOM ONLY. 11/18/22 - Partial Firewall North side. 1/9/23- Laundry room 1 st layer 5/8 on ceiling, walls have all been double layered. No other firewall inspection done at this inspection. | |||
| ELECTRIC 2ND ROUGH | 05/24/2023 | APPROVED | RMARTIN |
| ELECTRIC - EARLY POWER | 05/24/2023 | Disapproved - NO FEE | RMARTIN |
| Note: plans do not match what is installed | |||
| PLUMBING 2ND ROUGH | 05/24/2023 | PARTIALLY APPROVED | JWALKER |
| Note: 5/24/23 1. Multiple above ceiling shut off valves have duct work up against the valves. This will not allow the valves to be open and closed. 2. Toilet room 109 Side wall clearance to the toilet is to be 16 to 18". Plumbing pipe is at 13 1/2" 3. Drawings call for 3- 3" vtr. Unable to locate. Please have plumber onsite to show locations. 4. DW calls for a water filtration and backflow preventer to be installed detail P-102 5. Water distribution lines need to be place under pressure test. 6. Revison for pipes , water hammers and sprinkler have been submitted and accepted not yet approved. See notes below. 11/3/2022 - PREVIOUS INSPECTION NOTES 1. Water hammers have non been installed. Install hammers of have engineer submitt revision noted they can be omitted. 2. Cold and hot water supply lines are specifed to be L type copper. CPVC has been installed. Have engineer submitt a revision to the building department for change of material. 3. 2 of 3 vent to roof have not been installed. 4. Hose bib line at front right of the building has not been roughed in. 5. Page 102 Shows a 3/4 " water supply into the dental gas room calling for a sprinkler head to be installed. Please clarify this detail of have omitted by the engineer. 6. Trap primer valves have not been installed. 7. Multiple shut off valves detaild have not been installed in the water supply lines above ceiling. 8. Domestic water hook up has not been installed. | |||
| HVAC ROUGH | 05/24/2023 | APPROVED | CPISCITELLI |
| ELECTRIC - EARLY POWER | 05/23/2023 | APPROVED - AS NOTED | RMARTIN |
| Note: 5/23/23 released power up to disconnect only, keep disconnect locked out 1/11/2023 - PREVIOUS INSPECTION NOTES meter is ok to re-use | |||
| ELECTRIC 2ND ROUGH | 05/22/2023 | APPROVED - AS NOTED | RMARTIN |
| Note: this was an power inspection will add inspection | |||
| ELECTRIC 2ND ROUGH | 05/16/2023 | APPROVED - AS NOTED | RMARTIN |
| Note: This was for conduits underground outside to transformer then to disconnect | |||
| ABOVE CEILING | 03/07/2023 | Disapproved - NO FEE | RMARTIN |
| Note: Inspector Notes from Inspection 3441 3/7/23 all MEPs need to be done for above ceiling 12/22/2022 - PREVIOUS INSPECTION NOTES 11/18/2022 - PREVIOUS INSPECTION NOTES 10/26/2022 - PREVIOUS INSPECTION NOTES 10/21/2022 - PREVIOUS INSPECTION NOTES 10/20/2022 - PREVIOUS INSPECTION NOTES NOT COMPLETE. WORKERS STOPPED UNTIL FLOOR GRINDING AND BUFFERING IS COMPLETE. A DUST ISSUE. 10.21.22 - Portion inspected was far left rear corner of unit, this gets a secondary partition 10/26/22 - REAR ROOM ONLY. 11/18/22 - Partial Firewall North side. 1/9/23- Laundry room 1 st layer 5/8 on ceiling, walls have all been double layered. No other firewall inspection done at this inspection. | |||
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | 02/06/2023 | PARTIALLY APPROVED | LFITZGERALD |
| Note: installed 1.5 inch poly service to building from new 2inch Back flow Preventor/installed 2inch gate valve for wet tap on existing DI water main/installed 2inch meter/backflow | |||
| ELECTRIC - EARLY POWER | 01/11/2023 | CANCELLED BY APPLICANT | RMARTIN |
| Note: meter is ok to re-use | |||
| FIREWALL FRAMING | 01/09/2023 | APPROVED - AS NOTED | JWALKER |
| Note: 12/22/2022 - PREVIOUS INSPECTION NOTES 11/18/2022 - PREVIOUS INSPECTION NOTES 10/26/2022 - PREVIOUS INSPECTION NOTES 10/21/2022 - PREVIOUS INSPECTION NOTES 10/20/2022 - PREVIOUS INSPECTION NOTES NOT COMPLETE. WORKERS STOPPED UNTIL FLOOR GRINDING AND BUFFERING IS COMPLETE. A DUST ISSUE. 10.21.22 - Portion inspected was far left rear corner of unit, this gets a secondary partition 10/26/22 - REAR ROOM ONLY. 11/18/22 - Partial Firewall North side. 1/9/23- Laundry room 1 st layer 5/8 on ceiling, walls have all been double layered. No other firewall inspection done at this inspection. | |||
| HVAC ROUGH | 01/04/2023 | APPROVED | CPISCITELLI |
| Note: 11/29/2022 - PREVIOUS INSPECTION NOTES inspected curb and stand attachment to roof google duo inspection | |||
| FIREWALL FRAMING | 12/22/2022 | CANCELLED BY APPLICANT | JWALKER |
| Note: 11/18/2022 - PREVIOUS INSPECTION NOTES 10/26/2022 - PREVIOUS INSPECTION NOTES 10/21/2022 - PREVIOUS INSPECTION NOTES 10/20/2022 - PREVIOUS INSPECTION NOTES NOT COMPLETE. WORKERS STOPPED UNTIL FLOOR GRINDING AND BUFFERING IS COMPLETE. A DUST ISSUE. 10.21.22 - Portion inspected was far left rear corner of unit, this gets a secondary partition 10/26/22 - REAR ROOM ONLY. 11/18/22 - Partial Firewall North side. | |||
| WINDOW NAILING | 12/19/2022 | CANCELLED BY APPLICANT | WEB |
| Note: Inspector Notes from Inspection 3447 Laundry room ceiling framing, and front entry column frame out | |||
| WINDOW NAILING | 12/19/2022 | APPROVED | JWALKER |
| Note: New inspection due to canceled inspection Inspector Notes from Inspection 3447 Laundry room ceiling framing, and front entry column frame out | |||
| HORIZONTAL ASSEMB DRYWALL | 12/14/2022 | APPROVED - AS NOTED | DCUSHING |
| Note: Laundry room ceiling framing, and front entry column frame out | |||
| FIREWALL NAILING | 11/29/2022 | APPROVED | FWILLIS |
| HVAC ROUGH | 11/29/2022 | PARTIALLY APPROVED | CPISCITELLI |
| EXTERIOR WALL SHEATHING / SHEARWALL | 11/22/2022 | APPROVED | FWILLIS |
| Note: South Elevation. | |||
| HORIZONTAL ASSEMB FRAMING | 11/21/2022 | APPROVED | FWILLIS |
| EXTERIOR WALL SHEATHING / SHEARWALL | 11/18/2022 | CANCELLED BY APPLICANT | WEB |
| FIREWALL FRAMING | 11/18/2022 | PARTIALLY APPROVED | FWILLIS |
| Note: 10/26/2022 - PREVIOUS INSPECTION NOTES 10/21/2022 - PREVIOUS INSPECTION NOTES 10/20/2022 - PREVIOUS INSPECTION NOTES NOT COMPLETE. WORKERS STOPPED UNTIL FLOOR GRINDING AND BUFFERING IS COMPLETE. A DUST ISSUE. 10.21.22 - Portion inspected was far left rear corner of unit, this gets a secondary partition 10/26/22 - REAR ROOM ONLY. 11/18/22 - Partial Firewall North side. | |||
| FRAMING | 11/15/2022 | APPROVED | DCUSHING |
| Note: Also looked at back door frames | |||
| HVAC ROUGH | 11/14/2022 | PARTIALLY APPROVED | CPISCITELLI |
| Note: Inspected duct to be able to wrap. Highlighted plans | |||
| HVAC ROUGH | 11/14/2022 | APPROVED | CPISCITELLI |
| Note: 11/14/2022 - PREVIOUS INSPECTION NOTES Inspected duct to be able to wrap. Highlighted plans | |||
| ELECTRIC 2ND ROUGH | 11/14/2022 | APPROVED | RMARTIN |
| Note: 11/1/2022 - PREVIOUS INSPECTION NOTES 10/28/2022 - PREVIOUS INSPECTION NOTES 10/26/2022 - PREVIOUS INSPECTION NOTES 9/19/2022 - PREVIOUS INSPECTION NOTES underground only 10/28/22 marked on print 11/1/22 walls marked on print | |||
| PLUMBING 2ND ROUGH | 11/03/2022 | Disapproved - NO FEE | JWALKER |
| Note: 1. Water hammers have non been installed. Install hammers of have engineer submitt revision noted they can be omitted. 2. Cold and hot water supply lines are specifed to be L type copper. CPVC has been installed. Have engineer submitt a revision to the building department for change of material. 3. 2 of 3 vent to roof have not been installed. 4. Hose bib line at front right of the building has not been roughed in. 5. Page 102 Shows a 3/4 " water supply into the dental gas room calling for a sprinkler head to be installed. Please clarify this detail of have omitted by the engineer. 6. Trap primer valves have not been installed. 7. Multiple shut off valves detaild have not been installed in the water supply lines above ceiling. 8. Domestic water hook up has not been installed. | |||
| ELECTRIC 2ND ROUGH | 11/01/2022 | PARTIALLY APPROVED | RMARTIN |
| Note: 10/28/2022 - PREVIOUS INSPECTION NOTES 10/26/2022 - PREVIOUS INSPECTION NOTES 9/19/2022 - PREVIOUS INSPECTION NOTES underground only 10/28/22 marked on print 11/1/22 walls marked on print | |||
| ELECTRIC 2ND ROUGH | 10/28/2022 | PARTIALLY APPROVED | RMARTIN |
| Note: 10/26/2022 - PREVIOUS INSPECTION NOTES 9/19/2022 - PREVIOUS INSPECTION NOTES underground only 10/28/22 marked on print | |||
| ELECTRIC 2ND ROUGH | 10/26/2022 | CANCELLED BY APPLICANT | RMARTIN |
| Note: 9/19/2022 - PREVIOUS INSPECTION NOTES underground only | |||
| FIREWALL FRAMING | 10/26/2022 | PARTIALLY APPROVED | FWILLIS |
| Note: 10/21/2022 - PREVIOUS INSPECTION NOTES 10/20/2022 - PREVIOUS INSPECTION NOTES NOT COMPLETE. WORKERS STOPPED UNTIL FLOOR GRINDING AND BUFFERING IS COMPLETE. A DUST ISSUE. 10.21.22 - Portion inspected was far left rear corner of unit, this gets a secondary partition 10/26/22 - REAR ROOM ONLY. | |||
| FIREWALL FRAMING | 10/21/2022 | PARTIALLY APPROVED | DCUSHING |
| Note: 10/20/2022 - PREVIOUS INSPECTION NOTES NOT COMPLETE. WORKERS STOPPED UNTIL FLOOR GRINDING AND BUFFERING IS COMPLETE. A DUST ISSUE. 10.21.22 - Portion inspected was far left rear corner of unit, this gets a secondary partition | |||
| FIREWALL FRAMING | 10/20/2022 | Disapproved - NO FEE | FWILLIS |
| Note: NOT COMPLETE. WORKERS STOPPED UNTIL FLOOR GRINDING AND BUFFERING IS COMPLETE. A DUST ISSUE. | |||
| MONOLITHIC SLAB | 10/05/2022 | APPROVED | DCUSHING |
| ELECTRIC 2ND ROUGH | 09/19/2022 | PARTIALLY APPROVED | RMARTIN |
| Note: underground only | |||
| PLUMBING 1ST ROUGH | 09/14/2022 | APPROVED | JWALKER |
| Note: THIS IS A REINSPECTION Please have a full set of approved prints onsite for inspections. Courtsey walk through of site. Check all piping for leaks. Ensure that all drain lines have full bedding. Check for sagging of pipes. Check drain lines for proper slopes. | |||
| PLUMBING 1ST ROUGH | 09/13/2022 | Disapproved - NO FEE | JWALKER |
| Note: Please have a full set of approved prints onsite for inspections. Courtsey walk through of site. Check all piping for leaks. Ensure that all drain lines have full bedding. Check for sagging of pipes. Check drain lines for proper slopes. |
Review History
| Department | Status | Date In | Date Out |
| PLUM | COMPLETE | 06/02/2023 | 06/07/2023 |
| Note: Released By: PATRICK BUCKLEY - (386)986-3786 - PBUCKLEY@PALMCOASTGOV.COM | |||
| FI1 | COMPLETE | 06/02/2023 | 06/07/2023 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 11/07/2022 | 11/07/2022 |
| Note: Released By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM | |||
| ELEC | COMPLETE | 11/07/2022 | 11/08/2022 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| FI1 | COMPLETE | 11/07/2022 | 11/07/2022 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 10/28/2022 | 10/31/2022 |
| Note: Released By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM | |||
| ELEC | COMPLETE | 10/28/2022 | 10/28/2022 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| FI1 | COMPLETE | 10/28/2022 | 10/31/2022 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| MECH | COMPLETE | 10/28/2022 | 10/28/2022 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| ELEC | COMPLETE | 10/06/2022 | 10/10/2022 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| FI1 | COMPLETE | 09/19/2022 | 09/20/2022 |
| Note: Released By: LEE MILLER - (386)986-3783 - WMILLER@PALMCOASTGOV.COM | |||
| BLD | INFORMATION | 09/09/2022 | 09/09/2022 |
| Note: Marked INFORMATION By: SCOTT THOMAS - - STHOMAS@PALMCOASTGOV.COM NOC MUST BE RECORDED IN FLAGLER COUNTY CLERK OF COURT | |||
| FI1 | COMPLETE | 08/24/2022 | 08/24/2022 |
| Note: Released By: LEE MILLER - (386)986-3783 - WMILLER@PALMCOASTGOV.COM | |||
| MECH | COMPLETE | 08/23/2022 | 08/23/2022 |
| Note: Released By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM | |||
| MECH | HOLD | 08/18/2022 | 08/18/2022 |
| Note: Held By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM BASED ON FIRE REVIEW COMMENTS Unable to ventilate Fire Rated Door Gas Room. Provide Details showing Fire Damper and ventilation in wall. | |||
| FI1 | HOLD | 08/09/2022 | 08/18/2022 |
| Note: Held By: LEE MILLER - (386)986-3783 - WMILLER@PALMCOASTGOV.COM Nitrous Manifold PDF. note under drawing illustration of tanks states this is for a Level III Facility, Please provide Nitrous Manifold PDF for Level II Facility (Henry Schein Dental Documents) (Per documents this is a Level II Facility). | |||
| PLUM | COMPLETE | 08/09/2022 | 08/16/2022 |
| Note: Released By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM | |||
| ELEC | COMPLETE | 08/09/2022 | 08/18/2022 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| FI1 | HOLD | 07/29/2022 | 08/04/2022 |
| Note: Held By: LEE MILLER - (386)986-3783 - WMILLER@PALMCOASTGOV.COM All comments below per the 2020 Florida Fire Prevention Code. And or 2020 FBC Please provide a written response to each comment below in a response letter and provide clouded response changes on plan sheets and add page locations for each response. Please check all plan sheets for reference to Med Gas and make sure the correct category is used (For instance… sheet P103 still lists category 3 in the note while the cover page shows the facility medial gas as category 2) (please check all sheets and ensure the category is the same throughout all plan sheets). Category 3 cannot have medical gas per NFPA99 (2018) 15.5.1.2 (This facility has Medical Gas NO2 per documents, please remove all reference to medical gas category 3 “on all documents” and revise Category where incorrect). Once the category has been correctly identified on all plan pages with no discrepancies between plan sheets, (please have provide (be sure to satisfy all the requirements of the correct category and related requirements of chapter 15, and include the needed information for the next review, additional comments are likely after resubmittal). Please perform a complete code analysis with chapter 15 of NFPA 99 (2018), It is imperative that the Facility medical gas category is the same and correct on all plan sheets. It is also imperative that all of NFPA chapter 15 is reviewed by the design professional and all requirements of the category are sufficiently identified in the documents. (For instance just to name and identify a few items, we need all the information for the warning systems in 15.4.2.10, dental air and vacuum piping systems in 15.4.3, are there manufactured assemblies for (Oxygen and Nitrous Oxide and if so we need the information required to confirm compliance with 5.2.9 and 5.1.8 per 15.4.2.10). Again this is just to name a few of the requirements, please consult with a design professional familiar with the requirements NFPA 99 Chapter 15 (2018) and resubmit for review after compliance has been revised. Additional comments are possible after a complete submittal. | |||
| BLD | COMPLETE | 07/29/2022 | 08/01/2022 |
| Note: Released By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM | |||
| FI1 | HOLD | 07/14/2022 | 07/25/2022 |
| Note: Held By: LEE MILLER - (386)986-3783 - WMILLER@PALMCOASTGOV.COM Please define category of dental piped gas per NFPA 99 (2018) chapter 15 for review (of correct category) (category 1, 2, or 3). There are three options... Category 1, Category 2, or Category 3 the review for each category is different as each category has to comply to separate sections of NFPA99. (The Category of Dental Piped Gas must be included in the Design Summery on sheet G001). | |||
| ELEC | COMPLETE | 07/14/2022 | 07/19/2022 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| BLD | HOLD | 07/14/2022 | 07/28/2022 |
| Note: Held By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM All comments below per the 2020 Florida Building Code REVIEW COMMENTS: 1. Provide units and unit classifications nest to proposed dental office. 2. OK 3. OK 4. OK | |||
| MECH | COMPLETE | 06/30/2022 | 07/01/2022 |
| Note: Released By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM | |||
| ELEC | COMPLETE | 06/30/2022 | 07/06/2022 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| FI1 | HOLD | 06/30/2022 | 07/12/2022 |
| Note: Held By: LEE MILLER - (386)986-3783 - WMILLER@PALMCOASTGOV.COM 1. Please add exit signs at the ends of the hallways such as to indicate two ways to an approved exit is readily visible from any direction of egress travel. 7th ed. FFPC 101 7.10.1.2.1. and FBC1013.1 Show the changes on PG E201, and the Life Safety Plan 2. Per review comment response letter and response to question 2, the Category of Dental Piped Gas per NFPA 99 (2018) Chapter 15 is Category 3. Category 3 cannot have medical gas per NFPA99 (2018) 15.5.1.2 (This facility has Medical Gas NO2 per documents, please remove all reference to medical gas on all documents or revise Category for review). Additional comments likely after corrections | |||
| ELEC | HOLD | 06/08/2022 | 06/09/2022 |
| Note: Held By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM Energy Calc requirements need to be 100% addressed in comcheck | |||
| MECH | HOLD | 06/08/2022 | 06/09/2022 |
| Note: Held By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM Energy Calc requirements need to be 100% addressed in comcheck | |||
| FI1 | HOLD | 06/08/2022 | 06/22/2022 |
| Note: Held By: LEE MILLER - (386)986-3783 - WMILLER@PALMCOASTGOV.COM 1. Please add exit signs at the ends of the hallways such as to indicate the way to an exit is clearly identified per Exit signs. 7th ed. FFPC 101 7.10.1.2.1. (the page that the exit signs are on E201, shows a dead end corridor at the bottom left hallway, however the floor plan shows that area as an open corner, please adjust the exit to the end of the hallway accordingly). PG E201 2. Please define category of facility dental piped gas per NFPA 99 (2018) chapter 15 for review (of correct category) (category 1, 2, or 3). | |||
| BLD | COMPLETE | 06/08/2022 | 06/09/2022 |
| Note: Released By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM | |||
| BLD | HOLD | 05/10/2022 | 05/23/2022 |
| Note: Held By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM All comments below per the 2020 Florida Building Code REVIEW COMMENTS: 1. Provide units and unit classifications nest to proposed dental office. 2. Section 303.1.2 is called-out under Occupancy Classification. The main occupancy of the proposed building is B per 304 of the Florida Building Code. Provide the correct occupancy of the and use of the tenant space. 3. Occupant Load and Egress Width on sheet G001 shows 100 sf per person. A revision is required to reference the occupant load factor per Table 1004.5 2020 Florida Building Code. 4. A revision to the Room Occupancy Summary on sheet A002. Load factors are to be from Table 1004.5 2020 Florida Building Code. Conflicts between referenced standards and the Code, the Code shall apply FBC[A]102.4.1. | |||
| DSD | COMPLETE | 05/10/2022 | 05/10/2022 |
| Note: Released By: DAMARIS RAMIREZ - (386)986-3750 - DRAMIREZ@PALMCOASTGOV.COM | |||
| ELEC | HOLD | 05/10/2022 | 05/16/2022 |
| Note: Held By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM 1. Wrong energy code on E001. 2. Submit energy calc.FBC Energy 2020C405 3. Provide emergency light in equipment room. NEC 2017 110.26 (D) | |||
| FI1 | HOLD | 05/10/2022 | 05/20/2022 |
| Note: Held By: LEE MILLER - (386)986-3783 - WMILLER@PALMCOASTGOV.COM All comments below per the 2020 Florida Fire Prevention Code. And or 2020 FBC Please provide a written response to each comment below in a response letter and provide clouded response changes on plan sheets and add page locations for each response. 1. Please show travel distance for extinguishers per NFPA 10 -6.2.1.2.2 2. Please add exit signs at the ends of the hallways such as to indicate the way to an exit is clearly identified per Exit signs. 7th ed. FFPC 101 7.10.1.2.1. 3. Please define category of facility per NFPA 99 (2018) chapter 15 for review (of correct category) (be sure to satisfy all the requirements of the correct category and related requirements of chapter 15 and include the needed information in for the next review, additional comments are likely after resubmittal). | |||
| MECH | HOLD | 05/10/2022 | 05/16/2022 |
| Note: Held By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM 1. Provide Energy Calculations per C407 FBC Energy Conservation 2020 7Th edition 2. Provide Heatload Calculation per C403.2.1 FBC Energy Conservation 2020 7Th edition | |||
| PLUM | COMPLETE | 05/10/2022 | 05/23/2022 |
| Note: Released By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM | |||
| UD1 | COMPLETE | 05/10/2022 | 05/16/2022 |
| Note: Released By: CHRIS JOHNSON - (386)986-2384 - CJOHNSON@PALMCOASTGOV.COM |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| PLAN REVIEW - REVISION | ¤32.50 | 07/27/2023 |
| PLAN REVIEW - REVISION | ¤32.50 | 07/27/2023 |
| CONTRACTOR CHANGE | ¤40.00 | 08/24/2022 |
| SURCHARGE FS 533.721 | ¤38.31 | 08/24/2022 |
| SURCHARGE - FS 468.631 | ¤57.46 | 08/24/2022 |
| SITE PLAN 30 | ¤30.00 | 08/24/2022 |
| ADJUSTMENT 50% | (¤3,705.00) | 08/24/2022 |
| ADMINISTRATIVE - COMMERCIAL | ¤75.00 | 08/24/2022 |
| INSPECTION COMMERCIAL | ¤6,300.00 | 08/24/2022 |
| PLAN REVIEW - COMMERCIAL | ¤1,035.00 | 08/24/2022 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤3,935.77 |