I want to search for...

Permit #2022061136

Permit Details

Status: COED

Parcel Id: 07-11-31-7016-00040-1670
CONDITIONED SPACE: 1587 sqft
OPENED PORCH (WITH ROOF) : 87 sqft
OPENED PORCH (WITH ROOF) : 250 sqft
GARAGE: 455 sqft
Total Square Footage: 2379 sqft
Block: 00040
Subdivision: 2201 - SECTION 16-COUNTRY CLUB COVE
Job Phone: 386-237-5837
Location Address: 56 COLUMBIA LN
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 08/18/2022
NOC: RECORDED
Applicant name: MARSEL GILMANSHIN
Owner: RABOVSKI MARINA

Address

140 CHELSEA AVE

LONG BRANCH, NJ 07740

Lot: 1670
Contracted Stated Job Value: ¤335,000.00
Job Description: Single Family Residence
Type: CN

Contractor

GILMANS DEVELOPMENT CORP
Status Location Address State License Number Phone
ACTIVE

4873 PALM COAST PARKWAY NW #4

PALM COAST, FL 32137

CBC1263180 (Exp: 08/31/2026) 386-237-5837

Inspection History

Type Request Date Result Inspector
BLD - BUILDING FINAL 03/24/2025 FINAL APPROVED HCAMACHO
U -UTILITY RESIDENTIAL FINAL 03/20/2025 FINAL APPROVED LFITZGERALD
Note: Inspector Notes from Inspection 9035 no irr. no cc
ROW - STORMWATER FINAL 03/18/2025 APPROVED PFLANAGAN
Note: At the time of the inspection all minimum city requirements were met. It is the builders and the homowners responsibility to ensure that nothing changes after this Inspection is approved. It will not be on the city if any changes after this inspection.
ROW FIELD SURVEY /GRADING CERTIFICATION 03/18/2025 APPROVED PFLANAGAN
Note: CORRECTIONS MADE ----------------------------------------------------- 3/17/2025 - PREVIOUS INSPECTION NOTES 1) STILL THE RIGHT SIDE OF DRIVEWAY THE ROADSIDE SWALE NEED TO RAISED UP MORE SO WATER WILL NOT SIT IN THE SWALE. 2) THERE ARE STILL AREAS THAT NEED SOD SO SOIL WILL NOT WASH AWAY INTO THE CANAL OR ROADSIDE SWALE. Sec 300.03 F4 Bare earth on the site or surrounding properties must be sodded. Bare earth and damage to any City roadside swales, drainage ditches, canals or other drainage conveyances must be graded to the proper elevation and sodded to prevent soil erosion. ----------------------------------------------------------------------------------------- 3/11/2025 - PREVIOUS INSPECTION NOTES 1) THE FRONT SIDE SWALE IS TOO LOW NEED TO RAISE SWALE TO MATCH ADJACENT PROPERTY. 2) ALL DIRT IN THE BACK NEED TO HAVE SOD.
ROW - FINAL APRON (AFTER POUR) 03/18/2025 APPROVED PFLANAGAN
Note: At the time of the inspection all minimum city requirements were met. It is the builders and the homowners responsibility to ensure that nothing changes after this Inspection is approved. It will not be on the city if any changes after this inspection.
ROW FIELD SURVEY /GRADING CERTIFICATION 03/17/2025 Disapproved -FEE REQUIRED PFLANAGAN
Note: 1) STILL THE RIGHT SIDE OF DRIVEWAY THE ROADSIDE SWALE NEED TO RAISED UP MORE SO WATER WILL NOT SIT IN THE SWALE. 2) THERE ARE STILL AREAS THAT NEED SOD SO SOIL WILL NOT WASH AWAY INTO THE CANAL OR ROADSIDE SWALE. Sec 300.03 F4 Bare earth on the site or surrounding properties must be sodded. Bare earth and damage to any City roadside swales, drainage ditches, canals or other drainage conveyances must be graded to the proper elevation and sodded to prevent soil erosion. ----------------------------------------------------------------------------------------- 3/11/2025 - PREVIOUS INSPECTION NOTES 1) THE FRONT SIDE SWALE IS TOO LOW NEED TO RAISE SWALE TO MATCH ADJACENT PROPERTY. 2) ALL DIRT IN THE BACK NEED TO HAVE SOD.
ROW FIELD SURVEY /GRADING CERTIFICATION 03/11/2025 Disapproved -FEE REQUIRED PFLANAGAN
Note: 1) THE FRONT SIDE SWALE IS TOO LOW NEED TO RAISE SWALE TO MATCH ADJACENT PROPERTY. 2) ALL DIRT IN THE BACK NEED TO HAVE SOD.
ROW FIELD SURVEY /GRADING CERTIFICATION 03/10/2025 CANCELLED BY APPLICANT EMADISON
Note: ** 03/10/25 CANCELLED VIA TEXT MESSAGE FROM CM NOT READY New inspection due to canceled inspection Inspector Notes from Inspection 9470 ** ALL CORRECTIONS HAVE BEEN MADE IN REGARD TO THIS ROW DRAINAGE ** IT IS THE BUILDERS RESPONSIBILITY TO MAINTAIN THE DRAINAGE, SEDIMENT AND EROSION CONTROL OF THE JOB SITE THROUGH OUT THE PROJECT SO AS NOT TO HAVE A NEGATIVE IMPACT ON ANY ADJACENT PROPERTIES OR THE ROADWAY ________________________________________________________________________________________________________________________ 10/20/2023 - PREVIOUS INSPECTION NOTES Pallet and trash still in the swale. Rear right and left silt fence still needs reestablished to prevent washout. 10/19/2023 - PREVIOUS INSPECTION NOTES ** 10/19/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/20/23 10/18/2023 - PREVIOUS INSPECTION NOTES ** 10/18/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/19/23 ____________________________________________________________________________________________________________________ 10/17/2023 - PREVIOUS INSPECTION NOTES ** 10/17/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/18/23 _______________________________________________________________________________________________________________________ 10/16/2023 - PREVIOUS INSPECTION NOTES ** 10/16/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/17/23 ______________________________________________________________________________________________________________________ 10/11/2023 - PREVIOUS INSPECTION NOTES ** 10/11/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/16/23 ____________________________________________________________________________________________________________________ _____________________________________________________________________________________________________________________ rjg. Caller at 58 says there is no dumpster and the builder is allowing trash and debri to fill the swale causisng a back up of storm water. Also says the silt fence to protect the canal is collapsed.
ROW FIELD SURVEY /GRADING CERTIFICATION 03/06/2025 CANCELLED BY APPLICANT WEB
Note: Inspector Notes from Inspection 9470 ** ALL CORRECTIONS HAVE BEEN MADE IN REGARD TO THIS ROW DRAINAGE ** IT IS THE BUILDERS RESPONSIBILITY TO MAINTAIN THE DRAINAGE, SEDIMENT AND EROSION CONTROL OF THE JOB SITE THROUGH OUT THE PROJECT SO AS NOT TO HAVE A NEGATIVE IMPACT ON ANY ADJACENT PROPERTIES OR THE ROADWAY ________________________________________________________________________________________________________________________ 10/20/2023 - PREVIOUS INSPECTION NOTES Pallet and trash still in the swale. Rear right and left silt fence still needs reestablished to prevent washout. 10/19/2023 - PREVIOUS INSPECTION NOTES ** 10/19/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/20/23 10/18/2023 - PREVIOUS INSPECTION NOTES ** 10/18/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/19/23 ____________________________________________________________________________________________________________________ 10/17/2023 - PREVIOUS INSPECTION NOTES ** 10/17/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/18/23 _______________________________________________________________________________________________________________________ 10/16/2023 - PREVIOUS INSPECTION NOTES ** 10/16/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/17/23 ______________________________________________________________________________________________________________________ 10/11/2023 - PREVIOUS INSPECTION NOTES ** 10/11/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/16/23 ____________________________________________________________________________________________________________________ _____________________________________________________________________________________________________________________ rjg. Caller at 58 says there is no dumpster and the builder is allowing trash and debri to fill the swale causisng a back up of storm water. Also says the silt fence to protect the canal is collapsed.
ROW FIELD SURVEY /GRADING CERTIFICATION 02/04/2025 Disapproved - NO FEE EMADISON
Note: ** 02/04/25 LEFT SIDE ALONG PROPERTY LINE NEED TO CREATE MORE OF AN INSIDE SWALE NEEDS TO BE A MINIMUM OF .30 FROM THE BOTTOM OF DRAINAGE CONVEYANCE TO TOP OF BERM THAT IS COMPACTED MATERIAL AND SODDED TO PREVENT WTER FROM NEGATIVELY IMPACTING THE ADJACENT PROPERTY ** RIGHT SIDE ALONG PROPERTY LINE NEED TO CREATE MORE OF AN INSIDE SWALE ALONG PROPERTY LINE A MINIMUM OF .03 FROM BOTTOM OF DRAINAGE CONVEYANCE TO THE TOP OF BERM ** ALONG SEAWALL RIGHT CORNER NEED TO FILL WASH OUT AND SOD ** NEED TO REPAIR WASH OUT OFF OF THE BACK PATIO ** RIGHT SIDE AT PROPERTY LINE IN ROAD SIDE SWALE NEED TO REMOVE THE HUMP WHICH WILL HOLD BACK WATER FROM FLOWING ** NEED TO CLEAN OUT THE ENTIRE CULVERT PIPE OF ALL ERODED DIRT AND SEDIMENT AND REMOVE MOUND OF DIRT THAT IS AT THE OUTLET OF THE CULVERT ON RIGHT SIDE ** RIGHT REAR CORNER OF SEAWALL NEED TO CLEAN OUT THE SEDIMENT THT WAS WASHED INTO THE CANAL LARGE HUMP ____________________________________________________________________________________________________________________ 1/14/2025 - PREVIOUS INSPECTION NOTES ** 01/14/25 BUILDER NEEDS TO SUBMIT A FINAL SURVEY AND IT MUST PASS BEFORE THE INSPECTOR WILL SCHEDULE OR CONDUCT A (ROW) FIELD SURVEY
ROW- FINAL SURVEY/GRADING CERTIFICATION 02/04/2025 APPROVED EMADISON
Note: 12/30/2024 - PREVIOUS INSPECTION NOTES YOUR DRAINAGE IS IMPACTING THE ADJACENT LOTS TO THE RIGHT AND THE LEFT NEED TO FIX SO NO WATER WILL IMPACT THOSE LOTS. Section 300.01 (A)(1)(C)(6). The subject lots drainage must not negatively impact any adjacent property.
ROW - DRAINAGE 02/04/2025 APPROVED - AS NOTED EMADISON
Note: ** ALL CORRECTIONS HAVE BEEN MADE IN REGARD TO THIS ROW DRAINAGE ** IT IS THE BUILDERS RESPONSIBILITY TO MAINTAIN THE DRAINAGE, SEDIMENT AND EROSION CONTROL OF THE JOB SITE THROUGH OUT THE PROJECT SO AS NOT TO HAVE A NEGATIVE IMPACT ON ANY ADJACENT PROPERTIES OR THE ROADWAY ________________________________________________________________________________________________________________________ 10/20/2023 - PREVIOUS INSPECTION NOTES Pallet and trash still in the swale. Rear right and left silt fence still needs reestablished to prevent washout. 10/19/2023 - PREVIOUS INSPECTION NOTES ** 10/19/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/20/23 10/18/2023 - PREVIOUS INSPECTION NOTES ** 10/18/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/19/23 ____________________________________________________________________________________________________________________ 10/17/2023 - PREVIOUS INSPECTION NOTES ** 10/17/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/18/23 _______________________________________________________________________________________________________________________ 10/16/2023 - PREVIOUS INSPECTION NOTES ** 10/16/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/17/23 ______________________________________________________________________________________________________________________ 10/11/2023 - PREVIOUS INSPECTION NOTES ** 10/11/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/16/23 ____________________________________________________________________________________________________________________ _____________________________________________________________________________________________________________________ rjg. Caller at 58 says there is no dumpster and the builder is allowing trash and debri to fill the swale causisng a back up of storm water. Also says the silt fence to protect the canal is collapsed.
ELECTRIC - EARLY POWER 01/15/2025 APPROVED - AS NOTED HCAMACHO
Note: *Note* Before Final Inspection All the Smoke Detectors need to be up to code. FBCR 314 & 315 ALL SMOKE/ CO2 DETECTORS INSTALLED, OPERATIONAL AND WITHIN 10' OF THE BEDROOM. FBCR 314.3(4) SMOKE ALARMS SHALL NOT BE INSTALLED WITHIN 3’ OF BATHROOM NFPA 72 SMOKE DETECTORS NEED TO BE 3` AWAY FROM FAN BLADES AND A/C VENTS
ELECTRIC - EARLY POWER 01/14/2025 Disapproved - NO FEE HCAMACHO
Note: 1. Generator power being used to power house. Remove ilegal wire. Service not safe. 2. Breaker panel not safe, missing cover. 3. Outlet outside front door not installed. 4. Attic light in Garage not installed. 5. No house number. *NEC 110.27(A) LIVE PARTS GUARDED AGAINTS ACCIDENTAL CONTACT*
ROW FIELD SURVEY /GRADING CERTIFICATION 01/14/2025 Disapproved - NO FEE EMADISON
Note: ** 01/14/25 BUILDER NEEDS TO SUBMIT A FINAL SURVEY AND IT MUST PASS BEFORE THE INSPECTOR WILL SCHEDULE OR CONDUCT A (ROW) FIELD SURVEY
ROW- FINAL SURVEY/GRADING CERTIFICATION 12/30/2024 Disapproved - NO FEE PFLANAGAN
Note: YOUR DRAINAGE IS IMPACTING THE ADJACENT LOTS TO THE RIGHT AND THE LEFT NEED TO FIX SO NO WATER WILL IMPACT THOSE LOTS. Section 300.01 (A)(1)(C)(6). The subject lots drainage must not negatively impact any adjacent property.
U-CROSS CONNECTION 12/26/2024 APPROVED - AS NOTED BWRIGHT
Note: no irr. no cc
ELECTRIC - EARLY POWER 12/10/2024 CANCELLED BY APPLICANT WEB
Note: Inspector Notes from Inspection 2170 01-16-2024 Please have trash removed prior to inspection.
ROW- PRE-APRON (PRE-POUR) 08/30/2024 APPROVED - AS NOTED EMADISON
Note: ** 08/30/24 READY TO POUR ** At the time of the inspection all minimum city requirements were met. It is the builders responsibility to ensure that nothing changes after this Inspection is approved. This includes but is not limited to, the Culvert Pipe Elevation from the time of the inspection approval to the concrete pour. **MAKE SURE THERE IS 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE (FRC) DRAWING 300,E RESIDENTIAL CULVERT DETAIL ________________________________________________________________________________________________________________ 8/28/2024 - PREVIOUS INSPECTION NOTES ** 08/28/24 NEED TO CHIP AWAY ALL OVER POUR CONCRETE AT GARAGE OPENING ** NEED A MINIMUM OF 4 INCHES OF CONCRETE IN DRIVEWAY POUR AREA. NOTE STRING LINE ** NEED TO EITHER BACK FILL OR EXTEND FORMS TO CONTAIN THE CONCRETE WITHIN THE POUR AREA ** SEE ATTACHED PHOTOS
ROW- PRE-APRON (PRE-POUR) 08/28/2024 Disapproved -FEE REQUIRED EMADISON
Note: ** 08/28/24 NEED TO CHIP AWAY ALL OVER POUR CONCRETE AT GARAGE OPENING ** NEED A MINIMUM OF 4 INCHES OF CONCRETE IN DRIVEWAY POUR AREA. NOTE STRING LINE ** NEED TO EITHER BACK FILL OR EXTEND FORMS TO CONTAIN THE CONCRETE WITHIN THE POUR AREA ** SEE ATTACHED PHOTOS
INSULATION 07/01/2024 APPROVED BTAYLOR
Note: Inspector Notes from Inspection 2420 *** NOTES ADDED BY LMILLER 6/28/2024 10:17:45 AM *** 1. Missing nail plates. FBCR M1308.2 (dry exaust top plate)M1502.5 (wrong Nail plates used) 2. Need 5ft head testFBC CHAPTER 25 SECTION P2503.5.1 (1) 3. Need water test on tubTUB TEST, P2503.1 NEW PLUMBING SHALL BE TESTED INSPECTED AND APPROVED BY THE BUILDING OFFICIAL 6/25/2024 - PREVIOUS INSPECTION NOTES *** NOTES ADDED BY LMILLER 6/25/2024 2:40:19 PM *** 1. Missing nail plates. FBCR M1308.2 (dry exaust top plate)M1502.5 2. Plumbing in shower wall is going to be moved to the opposite wall, (do not call for reinspect until all changes have been performed as the plumbing will need another test after changes) 3. Ground metal box (check all) NEC.314.4 4. Need to box out around electric panel 5. Need 5ft head testFBC CHAPTER 25 SECTION P2503.5.1 (1) 6. Need water test on tubTUB TEST, P2503.1 NEW PLUMBING SHALL BE TESTED INSPECTED AND APPROVED BY THE BUILDING OFFICIAL 7. need second attachement for ducts at bath exaust DUCTS MUST BE SEALED: FBC, R-M1601.4.1 CONNECTIONS IN DUCTWORK SHALL BE SECURELY FASTENED AND SEALED 6/17/2024 - PREVIOUS INSPECTION NOTES Due to sheet rock already installed. The contractor will need to contact the cheif building inspector Robert Martin for further instructions.
ALL ROUGH 06/28/2024 APPROVED - AS NOTED LMILLER
Note: *** NOTES ADDED BY LMILLER 6/28/2024 10:17:45 AM *** 1. Missing nail plates. FBCR M1308.2 (dry exaust top plate)M1502.5 (wrong Nail plates used) 2. Need 5ft head testFBC CHAPTER 25 SECTION P2503.5.1 (1) 3. Need water test on tubTUB TEST, P2503.1 NEW PLUMBING SHALL BE TESTED INSPECTED AND APPROVED BY THE BUILDING OFFICIAL 6/25/2024 - PREVIOUS INSPECTION NOTES *** NOTES ADDED BY LMILLER 6/25/2024 2:40:19 PM *** 1. Missing nail plates. FBCR M1308.2 (dry exaust top plate)M1502.5 2. Plumbing in shower wall is going to be moved to the opposite wall, (do not call for reinspect until all changes have been performed as the plumbing will need another test after changes) 3. Ground metal box (check all) NEC.314.4 4. Need to box out around electric panel 5. Need 5ft head testFBC CHAPTER 25 SECTION P2503.5.1 (1) 6. Need water test on tubTUB TEST, P2503.1 NEW PLUMBING SHALL BE TESTED INSPECTED AND APPROVED BY THE BUILDING OFFICIAL 7. need second attachement for ducts at bath exaust DUCTS MUST BE SEALED: FBC, R-M1601.4.1 CONNECTIONS IN DUCTWORK SHALL BE SECURELY FASTENED AND SEALED 6/17/2024 - PREVIOUS INSPECTION NOTES Due to sheet rock already installed. The contractor will need to contact the cheif building inspector Robert Martin for further instructions.
ALL ROUGH 06/25/2024 Disapproved -FEE REQUIRED LMILLER
Note: *** NOTES ADDED BY LMILLER 6/25/2024 2:40:19 PM *** 1. Missing nail plates. FBCR M1308.2 (dry exaust top plate)M1502.5 2. Plumbing in shower wall is going to be moved to the opposite wall, (do not call for reinspect until all changes have been performed as the plumbing will need another test after changes) 3. Ground metal box (check all) NEC.314.4 4. Need to box out around electric panel 5. Need 5ft head testFBC CHAPTER 25 SECTION P2503.5.1 (1) 6. Need water test on tubTUB TEST, P2503.1 NEW PLUMBING SHALL BE TESTED INSPECTED AND APPROVED BY THE BUILDING OFFICIAL 7. need second attachement for ducts at bath exaust DUCTS MUST BE SEALED: FBC, R-M1601.4.1 CONNECTIONS IN DUCTWORK SHALL BE SECURELY FASTENED AND SEALED 6/17/2024 - PREVIOUS INSPECTION NOTES Due to sheet rock already installed. The contractor will need to contact the cheif building inspector Robert Martin for further instructions.
ALL ROUGH 06/17/2024 Disapproved - NO FEE JWALKER
Note: Due to sheet rock already installed. The contractor will need to contact the cheif building inspector Robert Martin for further instructions.
LATH/BRICK/ WATER BARRIER 06/17/2024 APPROVED JWALKER
Note: Inspector Notes from Inspection 2467 07-14-2023 Job site is a mess. Please remove trash prior to next insperction. Please post job box in front.
GRAVITY SEWER TEST 02/14/2024 APPROVED - AS NOTED MGIBSON
Note: THIS WAS A VIRTUAL INSPECTION, NEED TO CHANGE PLUMBING SUB CONTRACTOR TO KEHEL
U - SEWER TIE IN 02/14/2024 APPROVED - AS NOTED MGIBSON
Note: THIS WAS A VIRTUAL INSPECTION
ELECTRIC TEMP POLE 01/16/2024 APPROVED - AS NOTED AGAETANO
Note: 01-16-2024 Please have trash removed prior to inspection.
TUB SET 01/08/2024 CANCELLED BY INSPECTOR MGIBSON
Note: BUILDING DEPARTMENT DOES NOT DO SINGLE TRADE INSPECTIONS FOR ONE&TWO FAMILY DWELLINGS,SCHEDUAL A ALL ROUGH INSPECTION
ELECTRIC 2ND ROUGH 11/13/2023 CANCELLED BY INSPECTOR LMILLER
Note: we do not do second roughs on residential properties, call in all rough when ready
ROW - DRAINAGE 10/20/2023 Disapproved -FEE REQUIRED RGROSS
Note: Pallet and trash still in the swale. Rear right and left silt fence still needs reestablished to prevent washout..Photo attached. 10/19/2023 - PREVIOUS INSPECTION NOTES ** 10/19/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/20/23 10/18/2023 - PREVIOUS INSPECTION NOTES ** 10/18/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/19/23 ____________________________________________________________________________________________________________________ 10/17/2023 - PREVIOUS INSPECTION NOTES ** 10/17/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/18/23 _______________________________________________________________________________________________________________________ 10/16/2023 - PREVIOUS INSPECTION NOTES ** 10/16/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/17/23 ______________________________________________________________________________________________________________________ 10/11/2023 - PREVIOUS INSPECTION NOTES ** 10/11/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/16/23 ____________________________________________________________________________________________________________________ _____________________________________________________________________________________________________________________ rjg. Caller at 58 says there is no dumpster and the builder is allowing trash and debri to fill the swale causisng a back up of storm water. Also says the silt fence to protect the canal is collapsed.
ROW - DRAINAGE 10/19/2023 Disapproved -FEE REQUIRED EMADISON
Note: ** 10/19/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/20/23 10/18/2023 - PREVIOUS INSPECTION NOTES ** 10/18/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/19/23 ____________________________________________________________________________________________________________________ 10/17/2023 - PREVIOUS INSPECTION NOTES ** 10/17/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/18/23 _______________________________________________________________________________________________________________________ 10/16/2023 - PREVIOUS INSPECTION NOTES ** 10/16/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/17/23 ______________________________________________________________________________________________________________________ 10/11/2023 - PREVIOUS INSPECTION NOTES ** 10/11/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/16/23 ____________________________________________________________________________________________________________________ _____________________________________________________________________________________________________________________ rjg. Caller at 58 says there is no dumpster and the builder is allowing trash and debri to fill the swale causisng a back up of storm water. Also says the silt fence to protect the canal is collapsed.
ROW - DRAINAGE 10/18/2023 Disapproved - NO FEE EMADISON
Note: ** 10/18/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/19/23 ____________________________________________________________________________________________________________________ 10/17/2023 - PREVIOUS INSPECTION NOTES ** 10/17/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/18/23 _______________________________________________________________________________________________________________________ 10/16/2023 - PREVIOUS INSPECTION NOTES ** 10/16/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/17/23 ______________________________________________________________________________________________________________________ 10/11/2023 - PREVIOUS INSPECTION NOTES ** 10/11/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/16/23 ____________________________________________________________________________________________________________________ _____________________________________________________________________________________________________________________ rjg. Caller at 58 says there is no dumpster and the builder is allowing trash and debri to fill the swale causisng a back up of storm water. Also says the silt fence to protect the canal is collapsed.
ROW - DRAINAGE 10/17/2023 Disapproved - NO FEE EMADISON
Note: ** 10/17/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/18/23 _______________________________________________________________________________________________________________________ 10/16/2023 - PREVIOUS INSPECTION NOTES ** 10/16/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/17/23 ______________________________________________________________________________________________________________________ 10/11/2023 - PREVIOUS INSPECTION NOTES ** 10/11/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/16/23 ____________________________________________________________________________________________________________________ _____________________________________________________________________________________________________________________ rjg. Caller at 58 says there is no dumpster and the builder is allowing trash and debri to fill the swale causisng a back up of storm water. Also says the silt fence to protect the canal is collapsed.
ROW - DRAINAGE 10/16/2023 Disapproved -FEE REQUIRED EMADISON
Note: ** 10/16/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/17/23 ______________________________________________________________________________________________________________________ 10/11/2023 - PREVIOUS INSPECTION NOTES ** 10/11/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/16/23 ____________________________________________________________________________________________________________________ _____________________________________________________________________________________________________________________ rjg. Caller at 58 says there is no dumpster and the builder is allowing trash and debri to fill the swale causisng a back up of storm water. Also says the silt fence to protect the canal is collapsed.
ROW - DRAINAGE 10/11/2023 Disapproved - NO FEE EMADISON
Note: ** 10/11/23 BUILDER NEEDS TO REMOVE CONSTRUCTION DEBRIS AND TRASH FROM THE ROAD SIDE SWALE AS WELL AS TRASH FROM AROUND SITE . ** BUILDER NEEDS TO RE-ESTABLISH SILT FENCE AROUND SITE AND EXTEND UP BOTH PROPERTY LINE ** YOU WILL ALSO BE REQUIRED TO REPAIRE WASOUTS ALONG PROPERTY LINES AND SOD WITH SOD THAT WILL MATCH THE ADJACENT PROPERTIES ** FOLLOW UP INSPECTION ON 10/16/23 ____________________________________________________________________________________________________________________ _____________________________________________________________________________________________________________________ rjg. Caller at 58 says there is no dumpster and the builder is allowing trash and debri to fill the swale causisng a back up of storm water. Also says the silt fence to protect the canal is collapsed.
ROW - DRAINAGE 08/03/2023 APPROVED EMADISON
Note: ** 08/02/ 23 NEED TO REMOVE PORT-A-JOHN FROM ROAD SIDE SWALE PUT ONTO SITE NOTED IN EARLIER INSPECTION BELIEVE WAS AN OVERSITE AND NOT MOVED ** FOLLOW UP INSPECTION ON 08/03/23 8/2/2023 - PREVIOUS INSPECTION NOTES ** 08/01/ 23 NEED TO REMOVE PORT-A-JOHN FROM ROAD SIDE SWALE PUT ONTO SITE NOTED IN EARLIER INSPECTION BELIEVE WAS AN OVERSITE AND NOT MOVED ** FOLLOW UP INSPECTION ON 08/02/23 _______________________________________________________________________________________________________________________ 7/31/2023 - PREVIOUS INSPECTION NOTES ** 07/31 23 NEED TO REMOVE PORT-A-JOHN FROM ROAD SIDE SWALE PUT ONTO SITE NOTED IN EARLIER INSPECTION BELIEVE WAS AN OVERSITE AND NOT MOVED ** FOLLOW UP INSPECTION ON 08/01/23 ___________________________________________________________________________________________________________________ 7/28/2023 - PREVIOUS INSPECTION NOTES ** 07/28/23 NEED TO REMOVE PORT-A-JOHN FROM ROAD SIDE SWALE PUT ONTO SITE NOTED IN EARLIER INSPECTION BELIEVE WAS AN OVERSITE AND NOT MOVED ** BE BACK ON 07/31/23 ________________________________________________________________________________________________________________________ 7/27/2023 - PREVIOUS INSPECTION NOTES ** 07/27/23 WORK AND CORRECTIONS CONTINUE ON SITE ** FOLLOW UP INSPECTION ON 07/28/23 _________________________________________________________________________________________________________________________ 2023 - PREVIOUS INSPECTION NOTES ** 07/26/23 MEET WITH GRADE CONTRACTOR ON SITE IN PROCESS OF DOING ALL NOTATED ISSUES WILL ** FOLLOW UP INSPECTION ON 07/27/23 _____________________________________________________________________________________________________________________ 7/25/2023 - PREVIOUS INSPECTION NOTES ** 07/25/23 ** THIS SITE REQUIRES IMMEDIATE ATTENTION FOR DRAINAGE ISSUE AS YOUR SITE IS NEGATIVELY IMPACTING ADJACENT PROPERTIES AS WELL AS THE CANAL SYSTEM AND STORMWATER SYSTEM BUILDER NEEDS TO INSTALL SILT FENCE AROUND THE ENTIRE JOB SITE INCLUDING ALONG THE SEAWALL TO PREVENT FURTHER EROSION OF SEDIMENT INTO THE CANAL, ALSO REQUIRING A SECOND SILT FENCE TO BE INSTALL 5 FEET FROM THE SILT FENCE ALONG SEAWALL MUST BURY BOTTOM 4 INCHES OF THE SILT FENCE IN THE GROUND. ** NEED TO OPEN THE ROAD SIDE SWALE IN FRONT IMMEDIATELY BY EITHER INSTALLING A TEMPORARY CULVERT PIPE OR OPENING SWALE AND MAINTAINING ON A DAILY BASIS. ** NEED TO REMOVE PORT-A-JOHN FROM ROAD SIDE SWALE AND PUT ON JOB SITE IMMEDIATELY ** REMOVE ALL LOOSE TRASH AND DEBRIS FROM JOB SIDE TO PREVENT IT FROM ENTERING THE STORMWATER DRAINAGE SYSTEM ** SEE ALL ATTACHED PHOTOS ** FOLLOW UP INSPECTION ON 07/28/23 rjg. Per caller at 58. Builder has the swale blocked and the silt fence in the rear and/or side is failing and silt is falling into the canal.
ROW - DRAINAGE 08/02/2023 Disapproved -FEE REQUIRED EMADISON
Note: ** 08/02/ 23 NEED TO REMOVE PORT-A-JOHN FROM ROAD SIDE SWALE PUT ONTO SITE NOTED IN EARLIER INSPECTION BELIEVE WAS AN OVERSITE AND NOT MOVED ** FOLLOW UP INSPECTION ON 08/03/23 ** 08/01/ 23 NEED TO REMOVE PORT-A-JOHN FROM ROAD SIDE SWALE PUT ONTO SITE NOTED IN EARLIER INSPECTION BELIEVE WAS AN OVERSITE AND NOT MOVED ** FOLLOW UP INSPECTION ON 08/02/23 _______________________________________________________________________________________________________________________ 7/31/2023 - PREVIOUS INSPECTION NOTES ** 07/31 23 NEED TO REMOVE PORT-A-JOHN FROM ROAD SIDE SWALE PUT ONTO SITE NOTED IN EARLIER INSPECTION BELIEVE WAS AN OVERSITE AND NOT MOVED ** FOLLOW UP INSPECTION ON 08/01/23 ___________________________________________________________________________________________________________________ 7/28/2023 - PREVIOUS INSPECTION NOTES ** 07/28/23 NEED TO REMOVE PORT-A-JOHN FROM ROAD SIDE SWALE PUT ONTO SITE NOTED IN EARLIER INSPECTION BELIEVE WAS AN OVERSITE AND NOT MOVED ** BE BACK ON 07/31/23 ________________________________________________________________________________________________________________________ 7/27/2023 - PREVIOUS INSPECTION NOTES ** 07/27/23 WORK AND CORRECTIONS CONTINUE ON SITE ** FOLLOW UP INSPECTION ON 07/28/23 _________________________________________________________________________________________________________________________ 2023 - PREVIOUS INSPECTION NOTES ** 07/26/23 MEET WITH GRADE CONTRACTOR ON SITE IN PROCESS OF DOING ALL NOTATED ISSUES WILL ** FOLLOW UP INSPECTION ON 07/27/23 _____________________________________________________________________________________________________________________ 7/25/2023 - PREVIOUS INSPECTION NOTES ** 07/25/23 ** THIS SITE REQUIRES IMMEDIATE ATTENTION FOR DRAINAGE ISSUE AS YOUR SITE IS NEGATIVELY IMPACTING ADJACENT PROPERTIES AS WELL AS THE CANAL SYSTEM AND STORMWATER SYSTEM BUILDER NEEDS TO INSTALL SILT FENCE AROUND THE ENTIRE JOB SITE INCLUDING ALONG THE SEAWALL TO PREVENT FURTHER EROSION OF SEDIMENT INTO THE CANAL, ALSO REQUIRING A SECOND SILT FENCE TO BE INSTALL 5 FEET FROM THE SILT FENCE ALONG SEAWALL MUST BURY BOTTOM 4 INCHES OF THE SILT FENCE IN THE GROUND. ** NEED TO OPEN THE ROAD SIDE SWALE IN FRONT IMMEDIATELY BY EITHER INSTALLING A TEMPORARY CULVERT PIPE OR OPENING SWALE AND MAINTAINING ON A DAILY BASIS. ** NEED TO REMOVE PORT-A-JOHN FROM ROAD SIDE SWALE AND PUT ON JOB SITE IMMEDIATELY ** REMOVE ALL LOOSE TRASH AND DEBRIS FROM JOB SIDE TO PREVENT IT FROM ENTERING THE STORMWATER DRAINAGE SYSTEM ** SEE ALL ATTACHED PHOTOS ** FOLLOW UP INSPECTION ON 07/28/23 rjg. Per caller at 58. Builder has the swale blocked and the silt fence in the rear and/or side is failing and silt is falling into the canal.
ROW - DRAINAGE 08/01/2023 Disapproved -FEE REQUIRED EMADISON
Note: ** 08/01/ 23 NEED TO REMOVE PORT-A-JOHN FROM ROAD SIDE SWALE PUT ONTO SITE NOTED IN EARLIER INSPECTION BELIEVE WAS AN OVERSITE AND NOT MOVED ** FOLLOW UP INSPECTION ON 08/02/23 _______________________________________________________________________________________________________________________ 7/31/2023 - PREVIOUS INSPECTION NOTES ** 07/31 23 NEED TO REMOVE PORT-A-JOHN FROM ROAD SIDE SWALE PUT ONTO SITE NOTED IN EARLIER INSPECTION BELIEVE WAS AN OVERSITE AND NOT MOVED ** FOLLOW UP INSPECTION ON 08/01/23 ___________________________________________________________________________________________________________________ 7/28/2023 - PREVIOUS INSPECTION NOTES ** 07/28/23 NEED TO REMOVE PORT-A-JOHN FROM ROAD SIDE SWALE PUT ONTO SITE NOTED IN EARLIER INSPECTION BELIEVE WAS AN OVERSITE AND NOT MOVED ** BE BACK ON 07/31/23 ________________________________________________________________________________________________________________________ 7/27/2023 - PREVIOUS INSPECTION NOTES ** 07/27/23 WORK AND CORRECTIONS CONTINUE ON SITE ** FOLLOW UP INSPECTION ON 07/28/23 _________________________________________________________________________________________________________________________ 2023 - PREVIOUS INSPECTION NOTES ** 07/26/23 MEET WITH GRADE CONTRACTOR ON SITE IN PROCESS OF DOING ALL NOTATED ISSUES WILL ** FOLLOW UP INSPECTION ON 07/27/23 _____________________________________________________________________________________________________________________ 7/25/2023 - PREVIOUS INSPECTION NOTES ** 07/25/23 ** THIS SITE REQUIRES IMMEDIATE ATTENTION FOR DRAINAGE ISSUE AS YOUR SITE IS NEGATIVELY IMPACTING ADJACENT PROPERTIES AS WELL AS THE CANAL SYSTEM AND STORMWATER SYSTEM BUILDER NEEDS TO INSTALL SILT FENCE AROUND THE ENTIRE JOB SITE INCLUDING ALONG THE SEAWALL TO PREVENT FURTHER EROSION OF SEDIMENT INTO THE CANAL, ALSO REQUIRING A SECOND SILT FENCE TO BE INSTALL 5 FEET FROM THE SILT FENCE ALONG SEAWALL MUST BURY BOTTOM 4 INCHES OF THE SILT FENCE IN THE GROUND. ** NEED TO OPEN THE ROAD SIDE SWALE IN FRONT IMMEDIATELY BY EITHER INSTALLING A TEMPORARY CULVERT PIPE OR OPENING SWALE AND MAINTAINING ON A DAILY BASIS. ** NEED TO REMOVE PORT-A-JOHN FROM ROAD SIDE SWALE AND PUT ON JOB SITE IMMEDIATELY ** REMOVE ALL LOOSE TRASH AND DEBRIS FROM JOB SIDE TO PREVENT IT FROM ENTERING THE STORMWATER DRAINAGE SYSTEM ** SEE ALL ATTACHED PHOTOS ** FOLLOW UP INSPECTION ON 07/28/23 rjg. Per caller at 58. Builder has the swale blocked and the silt fence in the rear and/or side is failing and silt is falling into the canal.
ROW - DRAINAGE 07/31/2023 Disapproved -FEE REQUIRED EMADISON
Note: ** 07/31 23 NEED TO REMOVE PORT-A-JOHN FROM ROAD SIDE SWALE PUT ONTO SITE NOTED IN EARLIER INSPECTION BELIEVE WAS AN OVERSITE AND NOT MOVED ** FOLLOW UP INSPECTION ON 08/01/23 ___________________________________________________________________________________________________________________ 7/28/2023 - PREVIOUS INSPECTION NOTES ** 07/28/23 NEED TO REMOVE PORT-A-JOHN FROM ROAD SIDE SWALE PUT ONTO SITE NOTED IN EARLIER INSPECTION BELIEVE WAS AN OVERSITE AND NOT MOVED ** BE BACK ON 07/31/23 ________________________________________________________________________________________________________________________ 7/27/2023 - PREVIOUS INSPECTION NOTES ** 07/27/23 WORK AND CORRECTIONS CONTINUE ON SITE ** FOLLOW UP INSPECTION ON 07/28/23 _________________________________________________________________________________________________________________________ 2023 - PREVIOUS INSPECTION NOTES ** 07/26/23 MEET WITH GRADE CONTRACTOR ON SITE IN PROCESS OF DOING ALL NOTATED ISSUES WILL ** FOLLOW UP INSPECTION ON 07/27/23 _____________________________________________________________________________________________________________________ 7/25/2023 - PREVIOUS INSPECTION NOTES ** 07/25/23 ** THIS SITE REQUIRES IMMEDIATE ATTENTION FOR DRAINAGE ISSUE AS YOUR SITE IS NEGATIVELY IMPACTING ADJACENT PROPERTIES AS WELL AS THE CANAL SYSTEM AND STORMWATER SYSTEM BUILDER NEEDS TO INSTALL SILT FENCE AROUND THE ENTIRE JOB SITE INCLUDING ALONG THE SEAWALL TO PREVENT FURTHER EROSION OF SEDIMENT INTO THE CANAL, ALSO REQUIRING A SECOND SILT FENCE TO BE INSTALL 5 FEET FROM THE SILT FENCE ALONG SEAWALL MUST BURY BOTTOM 4 INCHES OF THE SILT FENCE IN THE GROUND. ** NEED TO OPEN THE ROAD SIDE SWALE IN FRONT IMMEDIATELY BY EITHER INSTALLING A TEMPORARY CULVERT PIPE OR OPENING SWALE AND MAINTAINING ON A DAILY BASIS. ** NEED TO REMOVE PORT-A-JOHN FROM ROAD SIDE SWALE AND PUT ON JOB SITE IMMEDIATELY ** REMOVE ALL LOOSE TRASH AND DEBRIS FROM JOB SIDE TO PREVENT IT FROM ENTERING THE STORMWATER DRAINAGE SYSTEM ** SEE ALL ATTACHED PHOTOS ** FOLLOW UP INSPECTION ON 07/28/23 rjg. Per caller at 58. Builder has the swale blocked and the silt fence in the rear and/or side is failing and silt is falling into the canal.
ROW - DRAINAGE 07/28/2023 PARTIALLY APPROVED EMADISON
Note: ** 07/28/23 NEED TO REMOVE PORT-A-JOHN FROM ROAD SIDE SWALE PUT ONTO SITE NOTED IN EARLIER INSPECTION BELIEVE WAS AN OVERSITE AND NOT MOVED ** BE BACK ON 07/31/23 ________________________________________________________________________________________________________________________ 7/27/2023 - PREVIOUS INSPECTION NOTES ** 07/27/23 WORK AND CORRECTIONS CONTINUE ON SITE ** FOLLOW UP INSPECTION ON 07/28/23 _________________________________________________________________________________________________________________________ 2023 - PREVIOUS INSPECTION NOTES ** 07/26/23 MEET WITH GRADE CONTRACTOR ON SITE IN PROCESS OF DOING ALL NOTATED ISSUES WILL ** FOLLOW UP INSPECTION ON 07/27/23 _____________________________________________________________________________________________________________________ 7/25/2023 - PREVIOUS INSPECTION NOTES ** 07/25/23 ** THIS SITE REQUIRES IMMEDIATE ATTENTION FOR DRAINAGE ISSUE AS YOUR SITE IS NEGATIVELY IMPACTING ADJACENT PROPERTIES AS WELL AS THE CANAL SYSTEM AND STORMWATER SYSTEM BUILDER NEEDS TO INSTALL SILT FENCE AROUND THE ENTIRE JOB SITE INCLUDING ALONG THE SEAWALL TO PREVENT FURTHER EROSION OF SEDIMENT INTO THE CANAL, ALSO REQUIRING A SECOND SILT FENCE TO BE INSTALL 5 FEET FROM THE SILT FENCE ALONG SEAWALL MUST BURY BOTTOM 4 INCHES OF THE SILT FENCE IN THE GROUND. ** NEED TO OPEN THE ROAD SIDE SWALE IN FRONT IMMEDIATELY BY EITHER INSTALLING A TEMPORARY CULVERT PIPE OR OPENING SWALE AND MAINTAINING ON A DAILY BASIS. ** NEED TO REMOVE PORT-A-JOHN FROM ROAD SIDE SWALE AND PUT ON JOB SITE IMMEDIATELY ** REMOVE ALL LOOSE TRASH AND DEBRIS FROM JOB SIDE TO PREVENT IT FROM ENTERING THE STORMWATER DRAINAGE SYSTEM ** SEE ALL ATTACHED PHOTOS ** FOLLOW UP INSPECTION ON 07/28/23 rjg. Per caller at 58. Builder has the swale blocked and the silt fence in the rear and/or side is failing and silt is falling into the canal.
ROW - DRAINAGE 07/28/2023 CANCELLED BY INSPECTOR GBERTOLA
Note: 7/25/2023 - PREVIOUS INSPECTION NOTES ** 07/25/23 ** THIS SITE REQUIRES IMMEDIATE ATTENTION FOR DRAINAGE ISSUE AS YOUR SITE IS NEGATIVELY IMPACTING ADJACENT PROPERTIES AS WELL AS THE CANAL SYSTEM AND STORMWATER SYSTEM BUILDER NEEDS TO INSTALL SILT FENCE AROUND THE ENTIRE JOB SITE INCLUDING ALONG THE SEAWALL TO PREVENT FURTHER EROSION OF SEDIMENT INTO THE CANAL, ALSO REQUIRING A SECOND SILT FENCE TO BE INSTALL 5 FEET FROM THE SILT FENCE ALONG SEAWALL MUST BURY BOTTOM 4 INCHES OF THE SILT FENCE IN THE GROUND. ** NEED TO OPEN THE ROAD SIDE SWALE IN FRONT IMMEDIATELY BY EITHER INSTALLING A TEMPORARY CULVERT PIPE OR OPENING SWALE AND MAINTAINING ON A DAILY BASIS. ** NEED TO REMOVE PORT-A-JOHN FROM ROAD SIDE SWALE AND PUT ON JOB SITE IMMEDIATELY ** REMOVE ALL LOOSE TRASH AND DEBRIS FROM JOB SIDE TO PREVENT IT FROM ENTERING THE STORMWATER DRAINAGE SYSTEM ** SEE ALL ATTACHED PHOTOS ** FOLLOW UP INSPECTION ON 07/28/23 rjg. Per caller at 58. Builder has the swale blocked and the silt fence in the rear and/or side is failing and silt is falling into the canal.
ROW - DRAINAGE 07/27/2023 PARTIALLY APPROVED EMADISON
Note: ** 07/27/23 WORK AND CORRECTIONS CONTINUE ON SITE ** FOLLOW UP INSPECTION ON 07/28/23 _________________________________________________________________________________________________________________________ 2023 - PREVIOUS INSPECTION NOTES ** 07/26/23 MEET WITH GRADE CONTRACTOR ON SITE IN PROCESS OF DOING ALL NOTATED ISSUES WILL ** FOLLOW UP INSPECTION ON 07/27/23 _____________________________________________________________________________________________________________________ 7/25/2023 - PREVIOUS INSPECTION NOTES ** 07/25/23 ** THIS SITE REQUIRES IMMEDIATE ATTENTION FOR DRAINAGE ISSUE AS YOUR SITE IS NEGATIVELY IMPACTING ADJACENT PROPERTIES AS WELL AS THE CANAL SYSTEM AND STORMWATER SYSTEM BUILDER NEEDS TO INSTALL SILT FENCE AROUND THE ENTIRE JOB SITE INCLUDING ALONG THE SEAWALL TO PREVENT FURTHER EROSION OF SEDIMENT INTO THE CANAL, ALSO REQUIRING A SECOND SILT FENCE TO BE INSTALL 5 FEET FROM THE SILT FENCE ALONG SEAWALL MUST BURY BOTTOM 4 INCHES OF THE SILT FENCE IN THE GROUND. ** NEED TO OPEN THE ROAD SIDE SWALE IN FRONT IMMEDIATELY BY EITHER INSTALLING A TEMPORARY CULVERT PIPE OR OPENING SWALE AND MAINTAINING ON A DAILY BASIS. ** NEED TO REMOVE PORT-A-JOHN FROM ROAD SIDE SWALE AND PUT ON JOB SITE IMMEDIATELY ** REMOVE ALL LOOSE TRASH AND DEBRIS FROM JOB SIDE TO PREVENT IT FROM ENTERING THE STORMWATER DRAINAGE SYSTEM ** SEE ALL ATTACHED PHOTOS ** FOLLOW UP INSPECTION ON 07/28/23 rjg. Per caller at 58. Builder has the swale blocked and the silt fence in the rear and/or side is failing and silt is falling into the canal.
ROW - DRAINAGE 07/26/2023 PARTIALLY APPROVED EMADISON
Note: ** 07/26/23 MEET WITH GRADE CONTRACTOR ON SITE IN PROCESS OF DOING ALL NOTATED ISSUES WILL ** FOLLOW UP INSPECTION ON 07/27/23 _____________________________________________________________________________________________________________________ 7/25/2023 - PREVIOUS INSPECTION NOTES ** 07/25/23 ** THIS SITE REQUIRES IMMEDIATE ATTENTION FOR DRAINAGE ISSUE AS YOUR SITE IS NEGATIVELY IMPACTING ADJACENT PROPERTIES AS WELL AS THE CANAL SYSTEM AND STORMWATER SYSTEM BUILDER NEEDS TO INSTALL SILT FENCE AROUND THE ENTIRE JOB SITE INCLUDING ALONG THE SEAWALL TO PREVENT FURTHER EROSION OF SEDIMENT INTO THE CANAL, ALSO REQUIRING A SECOND SILT FENCE TO BE INSTALL 5 FEET FROM THE SILT FENCE ALONG SEAWALL MUST BURY BOTTOM 4 INCHES OF THE SILT FENCE IN THE GROUND. ** NEED TO OPEN THE ROAD SIDE SWALE IN FRONT IMMEDIATELY BY EITHER INSTALLING A TEMPORARY CULVERT PIPE OR OPENING SWALE AND MAINTAINING ON A DAILY BASIS. ** NEED TO REMOVE PORT-A-JOHN FROM ROAD SIDE SWALE AND PUT ON JOB SITE IMMEDIATELY ** REMOVE ALL LOOSE TRASH AND DEBRIS FROM JOB SIDE TO PREVENT IT FROM ENTERING THE STORMWATER DRAINAGE SYSTEM ** SEE ALL ATTACHED PHOTOS ** FOLLOW UP INSPECTION ON 07/28/23 rjg. Per caller at 58. Builder has the swale blocked and the silt fence in the rear and/or side is failing and silt is falling into the canal.
ROW - DRAINAGE 07/25/2023 Disapproved -FEE REQUIRED EMADISON
Note: ** 07/25/23 ** THIS SITE REQUIRES IMMEDIATE ATTENTION FOR DRAINAGE ISSUE AS YOUR SITE IS NEGATIVELY IMPACTING ADJACENT PROPERTIES AS WELL AS THE CANAL SYSTEM AND STORMWATER SYSTEM BUILDER NEEDS TO INSTALL SILT FENCE AROUND THE ENTIRE JOB SITE INCLUDING ALONG THE SEAWALL TO PREVENT FURTHER EROSION OF SEDIMENT INTO THE CANAL, ALSO REQUIRING A SECOND SILT FENCE TO BE INSTALL 5 FEET FROM THE SILT FENCE ALONG SEAWALL MUST BURY BOTTOM 4 INCHES OF THE SILT FENCE IN THE GROUND. ** NEED TO OPEN THE ROAD SIDE SWALE IN FRONT IMMEDIATELY BY EITHER INSTALLING A TEMPORARY CULVERT PIPE OR OPENING SWALE AND MAINTAINING ON A DAILY BASIS. ** NEED TO REMOVE PORT-A-JOHN FROM ROAD SIDE SWALE AND PUT ON JOB SITE IMMEDIATELY ** REMOVE ALL LOOSE TRASH AND DEBRIS FROM JOB SIDE TO PREVENT IT FROM ENTERING THE STORMWATER DRAINAGE SYSTEM ** SEE ALL ATTACHED PHOTOS ** FOLLOW UP INSPECTION ON 07/28/23 rjg. Per caller at 58. Builder has the swale blocked and the silt fence in the rear and/or side is failing and silt is falling into the canal.
ROOF VALLEY & METAL 07/14/2023 APPROVED - AS NOTED AGAETANO
Note: 07-14-2023 Job site is a mess. Please remove trash prior to next insperction. Please post job box in front.
ROOF SHEATHING / BRACES/TIES/DOWN CELL 07/05/2023 APPROVED BTAYLOR
Note: 6/30/2023 - PREVIOUS INSPECTION NOTES 6-30-23 missing required bracing (check all) 5/30/2023 - PREVIOUS INSPECTION NOTES Inspector Notes from Inspection 2340 1/17/2023 - PREVIOUS INSPECTION NOTES 01-17-2023 Dowels missed. Noted on drawings. Please have trash removed prior to next inspection. 01-19-2023 1. Please have trash removed prior to next inspection. 2. ADDRESS MUST BE POSTED AND PLAINLY VISIBLE TO INSPECTORS. IF ADDRESS IS NOT PLAINLY VISIBLE, INSPECTORS WILL NOT PERFORM INSPECTIONS AND A REINSPECTION FEE WILL BE ISSUED. Florida Building Code-Building Section 501.2. R319.1 Residential R319.1 Address identification. Buildings shall be provided with approved address identification. The address identification shall be legible and placed in a position that is visible from the street or road fronting the property. Address identification characters shall contrast with their background. Address numbers shall be Arabic numbers or alphabetical letters. Numbers shall not be spelled out. Each character shall be not less than 4 inches (102 mm) in height with a stroke width of not less than 0.5 inch (12.7 mm). Where required by the fire code official, address identification shall be provided in additional approved locations to facilitate emergency response. Where access is by means of a private road and the building address cannot be viewed from the public way, a monument, pole or other sign or means shall be used to identify the structure. Address identification shall be maintained. 05-30-2023 Above issue has not been addressed. 1. Job box is not accessible. Weeds and grass surround it. 2. ADDRESS MUST BE POSTED AND PLAINLY VISIBLE TO INSPECTORS. IF ADDRESS IS NOT PLAINLY VISIBLE, INSPECTORS WILL NOT PERFORM INSPECTIONS AND A REINSPECTION FEE WILL BE ISSUED. Florida Building Code-Building Section 501.2. R319.1 Residential R319.1 Address identification. Buildings shall be provided with approved address identification. The address identification shall be legible and placed in a position that is visible from the street or road fronting the property. Address identification characters shall contrast with their background. Address numbers shall be Arabic numbers or alphabetical letters. Numbers shall not be spelled out. Each character shall be not less than 4 inches (102 mm) in height with a stroke width of not less than 0.5 inch (12.7 mm). Where required by the fire code official, address identification shall be provided in additional approved locations to facilitate emergency response. Where access is by means of a private road and the building address cannot be viewed from the public way, a monument, pole or other sign or means shall be used to identify the structure. Address identification shall be maintained. 3. Trash has not been removed as noted on prior inspections. 4. Silt fence is down and soil is into the neighbors yard and canal. 5. Soil has washed away and undermined the columns and footings at the lanai locations. Inspection stopped.
ROOF SHEATHING / BRACES/TIES/DOWN CELL 06/30/2023 Disapproved -FEE REQUIRED LMILLER
Note: 6-30-23 missing required bracing (check all) 5/30/2023 - PREVIOUS INSPECTION NOTES Inspector Notes from Inspection 2340 1/17/2023 - PREVIOUS INSPECTION NOTES 01-17-2023 Dowels missed. Noted on drawings. Please have trash removed prior to next inspection. 01-19-2023 1. Please have trash removed prior to next inspection. 2. ADDRESS MUST BE POSTED AND PLAINLY VISIBLE TO INSPECTORS. IF ADDRESS IS NOT PLAINLY VISIBLE, INSPECTORS WILL NOT PERFORM INSPECTIONS AND A REINSPECTION FEE WILL BE ISSUED. Florida Building Code-Building Section 501.2. R319.1 Residential R319.1 Address identification. Buildings shall be provided with approved address identification. The address identification shall be legible and placed in a position that is visible from the street or road fronting the property. Address identification characters shall contrast with their background. Address numbers shall be Arabic numbers or alphabetical letters. Numbers shall not be spelled out. Each character shall be not less than 4 inches (102 mm) in height with a stroke width of not less than 0.5 inch (12.7 mm). Where required by the fire code official, address identification shall be provided in additional approved locations to facilitate emergency response. Where access is by means of a private road and the building address cannot be viewed from the public way, a monument, pole or other sign or means shall be used to identify the structure. Address identification shall be maintained. 05-30-2023 Above issue has not been addressed. 1. Job box is not accessible. Weeds and grass surround it. 2. ADDRESS MUST BE POSTED AND PLAINLY VISIBLE TO INSPECTORS. IF ADDRESS IS NOT PLAINLY VISIBLE, INSPECTORS WILL NOT PERFORM INSPECTIONS AND A REINSPECTION FEE WILL BE ISSUED. Florida Building Code-Building Section 501.2. R319.1 Residential R319.1 Address identification. Buildings shall be provided with approved address identification. The address identification shall be legible and placed in a position that is visible from the street or road fronting the property. Address identification characters shall contrast with their background. Address numbers shall be Arabic numbers or alphabetical letters. Numbers shall not be spelled out. Each character shall be not less than 4 inches (102 mm) in height with a stroke width of not less than 0.5 inch (12.7 mm). Where required by the fire code official, address identification shall be provided in additional approved locations to facilitate emergency response. Where access is by means of a private road and the building address cannot be viewed from the public way, a monument, pole or other sign or means shall be used to identify the structure. Address identification shall be maintained. 3. Trash has not been removed as noted on prior inspections. 4. Silt fence is down and soil is into the neighbors yard and canal. 5. Soil has washed away and undermined the columns and footings at the lanai locations. Inspection stopped.
WALL SHEATHING 06/30/2023 CANCELLED BY INSPECTOR LMILLER
Note: inspection not needed (no wall sheathing) 5/30/2023 - PREVIOUS INSPECTION NOTES Inspector Notes from Inspection 2340 1/17/2023 - PREVIOUS INSPECTION NOTES 01-17-2023 Dowels missed. Noted on drawings. Please have trash removed prior to next inspection. 01-19-2023 1. Please have trash removed prior to next inspection. 2. ADDRESS MUST BE POSTED AND PLAINLY VISIBLE TO INSPECTORS. IF ADDRESS IS NOT PLAINLY VISIBLE, INSPECTORS WILL NOT PERFORM INSPECTIONS AND A REINSPECTION FEE WILL BE ISSUED. Florida Building Code-Building Section 501.2. R319.1 Residential R319.1 Address identification. Buildings shall be provided with approved address identification. The address identification shall be legible and placed in a position that is visible from the street or road fronting the property. Address identification characters shall contrast with their background. Address numbers shall be Arabic numbers or alphabetical letters. Numbers shall not be spelled out. Each character shall be not less than 4 inches (102 mm) in height with a stroke width of not less than 0.5 inch (12.7 mm). Where required by the fire code official, address identification shall be provided in additional approved locations to facilitate emergency response. Where access is by means of a private road and the building address cannot be viewed from the public way, a monument, pole or other sign or means shall be used to identify the structure. Address identification shall be maintained. 05-30-2023 1. Job box is not accessible. Weeds and grass surround it. 2. ADDRESS MUST BE POSTED AND PLAINLY VISIBLE TO INSPECTORS. IF ADDRESS IS NOT PLAINLY VISIBLE, INSPECTORS WILL NOT PERFORM INSPECTIONS AND A REINSPECTION FEE WILL BE ISSUED. Florida Building Code-Building Section 501.2. R319.1 Residential R319.1 Address identification. Buildings shall be provided with approved address identification. The address identification shall be legible and placed in a position that is visible from the street or road fronting the property. Address identification characters shall contrast with their background. Address numbers shall be Arabic numbers or alphabetical letters. Numbers shall not be spelled out. Each character shall be not less than 4 inches (102 mm) in height with a stroke width of not less than 0.5 inch (12.7 mm). Where required by the fire code official, address identification shall be provided in additional approved locations to facilitate emergency response. Where access is by means of a private road and the building address cannot be viewed from the public way, a monument, pole or other sign or means shall be used to identify the structure. Address identification shall be maintained. 3. Trash has not been removed as noted on prior inspections. 4. Silt fence is down and soil is into the neighbors yard and canal. 5. Soil has washed away and undermined the columns and footings at the lanai locations. Inspection stopped.
ROOF SHEATHING / BRACES/TIES/DOWN CELL 05/30/2023 Disapproved -FEE REQUIRED AGAETANO
Note: Inspector Notes from Inspection 2340 1/17/2023 - PREVIOUS INSPECTION NOTES 01-17-2023 Dowels missed. Noted on drawings. Please have trash removed prior to next inspection. 01-19-2023 1. Please have trash removed prior to next inspection. 2. ADDRESS MUST BE POSTED AND PLAINLY VISIBLE TO INSPECTORS. IF ADDRESS IS NOT PLAINLY VISIBLE, INSPECTORS WILL NOT PERFORM INSPECTIONS AND A REINSPECTION FEE WILL BE ISSUED. Florida Building Code-Building Section 501.2. R319.1 Residential R319.1 Address identification. Buildings shall be provided with approved address identification. The address identification shall be legible and placed in a position that is visible from the street or road fronting the property. Address identification characters shall contrast with their background. Address numbers shall be Arabic numbers or alphabetical letters. Numbers shall not be spelled out. Each character shall be not less than 4 inches (102 mm) in height with a stroke width of not less than 0.5 inch (12.7 mm). Where required by the fire code official, address identification shall be provided in additional approved locations to facilitate emergency response. Where access is by means of a private road and the building address cannot be viewed from the public way, a monument, pole or other sign or means shall be used to identify the structure. Address identification shall be maintained. 05-30-2023 Above issue has not been addressed. 1. Job box is not accessible. Weeds and grass surround it. 2. ADDRESS MUST BE POSTED AND PLAINLY VISIBLE TO INSPECTORS. IF ADDRESS IS NOT PLAINLY VISIBLE, INSPECTORS WILL NOT PERFORM INSPECTIONS AND A REINSPECTION FEE WILL BE ISSUED. Florida Building Code-Building Section 501.2. R319.1 Residential R319.1 Address identification. Buildings shall be provided with approved address identification. The address identification shall be legible and placed in a position that is visible from the street or road fronting the property. Address identification characters shall contrast with their background. Address numbers shall be Arabic numbers or alphabetical letters. Numbers shall not be spelled out. Each character shall be not less than 4 inches (102 mm) in height with a stroke width of not less than 0.5 inch (12.7 mm). Where required by the fire code official, address identification shall be provided in additional approved locations to facilitate emergency response. Where access is by means of a private road and the building address cannot be viewed from the public way, a monument, pole or other sign or means shall be used to identify the structure. Address identification shall be maintained. 3. Trash has not been removed as noted on prior inspections. 4. Silt fence is down and soil is into the neighbors yard and canal. 5. Soil has washed away and undermined the columns and footings at the lanai locations. Inspection stopped.
WALL SHEATHING 05/30/2023 Disapproved -FEE REQUIRED AGAETANO
Note: Inspector Notes from Inspection 2340 1/17/2023 - PREVIOUS INSPECTION NOTES 01-17-2023 Dowels missed. Noted on drawings. Please have trash removed prior to next inspection. 01-19-2023 1. Please have trash removed prior to next inspection. 2. ADDRESS MUST BE POSTED AND PLAINLY VISIBLE TO INSPECTORS. IF ADDRESS IS NOT PLAINLY VISIBLE, INSPECTORS WILL NOT PERFORM INSPECTIONS AND A REINSPECTION FEE WILL BE ISSUED. Florida Building Code-Building Section 501.2. R319.1 Residential R319.1 Address identification. Buildings shall be provided with approved address identification. The address identification shall be legible and placed in a position that is visible from the street or road fronting the property. Address identification characters shall contrast with their background. Address numbers shall be Arabic numbers or alphabetical letters. Numbers shall not be spelled out. Each character shall be not less than 4 inches (102 mm) in height with a stroke width of not less than 0.5 inch (12.7 mm). Where required by the fire code official, address identification shall be provided in additional approved locations to facilitate emergency response. Where access is by means of a private road and the building address cannot be viewed from the public way, a monument, pole or other sign or means shall be used to identify the structure. Address identification shall be maintained. 05-30-2023 1. Job box is not accessible. Weeds and grass surround it. 2. ADDRESS MUST BE POSTED AND PLAINLY VISIBLE TO INSPECTORS. IF ADDRESS IS NOT PLAINLY VISIBLE, INSPECTORS WILL NOT PERFORM INSPECTIONS AND A REINSPECTION FEE WILL BE ISSUED. Florida Building Code-Building Section 501.2. R319.1 Residential R319.1 Address identification. Buildings shall be provided with approved address identification. The address identification shall be legible and placed in a position that is visible from the street or road fronting the property. Address identification characters shall contrast with their background. Address numbers shall be Arabic numbers or alphabetical letters. Numbers shall not be spelled out. Each character shall be not less than 4 inches (102 mm) in height with a stroke width of not less than 0.5 inch (12.7 mm). Where required by the fire code official, address identification shall be provided in additional approved locations to facilitate emergency response. Where access is by means of a private road and the building address cannot be viewed from the public way, a monument, pole or other sign or means shall be used to identify the structure. Address identification shall be maintained. 3. Trash has not been removed as noted on prior inspections. 4. Silt fence is down and soil is into the neighbors yard and canal. 5. Soil has washed away and undermined the columns and footings at the lanai locations. Inspection stopped.
FOUND SURVEY APPROVED (OFFICE) 01/23/2023 APPROVED TBAKER
TIE BEAM / LINTEL 01/19/2023 APPROVED - AS NOTED AGAETANO
Note: 1/17/2023 - PREVIOUS INSPECTION NOTES 01-17-2023 Dowels missed. Noted on drawings. Please have trash removed prior to next inspection. 01-19-2023 1. Please have trash removed prior to next inspection. 2. ADDRESS MUST BE POSTED AND PLAINLY VISIBLE TO INSPECTORS. IF ADDRESS IS NOT PLAINLY VISIBLE, INSPECTORS WILL NOT PERFORM INSPECTIONS AND A REINSPECTION FEE WILL BE ISSUED. Florida Building Code-Building Section 501.2. R319.1 Residential R319.1 Address identification. Buildings shall be provided with approved address identification. The address identification shall be legible and placed in a position that is visible from the street or road fronting the property. Address identification characters shall contrast with their background. Address numbers shall be Arabic numbers or alphabetical letters. Numbers shall not be spelled out. Each character shall be not less than 4 inches (102 mm) in height with a stroke width of not less than 0.5 inch (12.7 mm). Where required by the fire code official, address identification shall be provided in additional approved locations to facilitate emergency response. Where access is by means of a private road and the building address cannot be viewed from the public way, a monument, pole or other sign or means shall be used to identify the structure. Address identification shall be maintained.
TIE BEAM / LINTEL 01/17/2023 Disapproved - NO FEE AGAETANO
Note: 01-17-2023 Dowels missed. Noted on drawings. Please have trash removed prior to next inspection.
MONOLITHIC SLAB 12/22/2022 APPROVED AGAETANO
Note: 12/21/2022 - PREVIOUS INSPECTION NOTES 12-21-2022 1. Compaction test not on site. 2. ADDRESS MUST BE POSTED AND PLAINLY VISIBLE TO INSPECTORS. IF ADDRESS IS NOT PLAINLY VISIBLE, INSPECTORS WILL NOT PERFORM INSPECTIONS AND A REINSPECTION FEE WILL BE ISSUED. Florida Building Code-Building Section 501.2. R319.1 Residential 3. Job box is not needs attention. Not installled.
MONOLITHIC SLAB 12/21/2022 Disapproved - NO FEE AGAETANO
Note: 12-21-2022 1. Compaction test not on site. 2. ADDRESS MUST BE POSTED AND PLAINLY VISIBLE TO INSPECTORS. IF ADDRESS IS NOT PLAINLY VISIBLE, INSPECTORS WILL NOT PERFORM INSPECTIONS AND A REINSPECTION FEE WILL BE ISSUED. Florida Building Code-Building Section 501.2. R319.1 Residential 3. Job box is not needs attention. Not installled.
PLUMBING 1ST ROUGH UNDERGROUND 12/14/2022 APPROVED MGIBSON
WATER METER INSTALLATION REQUEST 08/30/2022 APPROVED CSTONE
Note: THIS IS A REINSPECTION ADDED ON 8/26/2022 4:03:32 PM Stumps left side property
WATER METER INSTALLATION REQUEST 08/26/2022 Disapproved - NO FEE CSTONE
Note: Stumps left side property

Review History

Department Status Date In Date Out
ZON COMPLETE 03/05/2025 03/05/2025
Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM
ZON HOLD 03/03/2025 03/03/2025
Note: Held By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM Please add an additional 2 foundation plantings to the rear of the home on the latest landscape plan: When the rear yard of a home faces a saltwater canal, lake, or golf course, an additional four shrubs shall be planted along the rear of the home.
BADMIN INFORMATION 02/27/2025 02/27/2025
Note: Marked INFORMATION By: BARBIE BEMBRY - (386)986-3780 - BUILDINGDIVISION@PALMCOASTGOV.COM If you are submitting a revised lanscape plans, please enter a description of changes in on the revision sheet and remove the previous approval stamps from the plans submitted.
MECH COMPLETE 02/24/2025 02/26/2025
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
ZON HOLD 02/24/2025 02/24/2025
Note: Held By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM Foundation plantings: a.Residential homes shall provide foundation plantings consisting of 16 shrubs. On interior lots, eight shrubs shall be planted in front of the home, and four shrubs planted on each side of the home. On corner lots, six shrubs shall be planted on each side of the home facing a street, and four shrubs planted on the interior side of the home. When the rear yard of a home faces a saltwater canal, lake, or golf course, an additional four shrubs shall be planted along the rear of the home. There must be 7 gallon screening plantings around the mechanical equipment. A minimum of one shade tree shall be planted. Crepe myrtle is not a shade tree. Unable to determine from your legend if you are planting crepe myrtles or magnolias, noting that the magnolia would count as a shade tree. The tree in the front of the home must be moved off of the front property line and out of the utility easement. Please relocate it at least 5' from the front property line (within the lot lines).
ENGIN1 COMPLETE 01/20/2023 01/23/2023
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
ZON COMPLETE 01/20/2023 01/20/2023
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
MECH COMPLETE 07/13/2022 07/13/2022
Note: Released By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM
ZON COMPLETE 07/13/2022 07/14/2022
Note: Released By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM
PLFM COMPLETE 06/22/2022 06/22/2022
Note: Released By: JORDAN MYERS, C.F.M - (386)986-2320 - JMYERS@PALMCOASTGOV.COM According to the Site Plan and Survey submitted on 6/15/22, the structure does not fall within SFHA. No elevation certificates will be required.
SWALE COMPLETE 06/21/2022 09/16/2022
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
BLD COMPLETE 06/20/2022 06/23/2022
Note: Released By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM
CUSVC COMPLETE 06/20/2022 06/22/2022
Note: Released By: HALEIGH HAND - -
ELEC COMPLETE 06/20/2022 06/21/2022
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
ENGIN1 COMPLETE 06/20/2022 06/21/2022
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
LOCATE COMPLETE 06/20/2022 06/24/2022
Note: Released By: CANDACE STONE - - CSTONE@PALMCOASTGOV.COM
MECH HOLD 06/20/2022 06/21/2022
Note: Held By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM Orientation of Energy Calcs does not match the site plan. Revise to match per R405.4.2.1 FBC Energy Conservation 2020 7Th Edition
SW1 COMPLETE 06/20/2022 06/27/2022
Note: Released By: PARREN FLANAGAN - (386)986-2392 - PFLANAGAN@PALMCOASTGOV.COM
ZON HOLD 06/20/2022 06/22/2022
Note: Held By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM Additional foundation plantings required along the rear this backs to the canal

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
ADMINISTRATIVE - EXTENSION ¤40.00 03/28/2025
PLAN REVIEW - REVISION ¤32.50 03/28/2025
REINSPECTION RESIDENTIAL ¤40.00 03/28/2025
REINSPECTION RESIDENTIAL ¤40.00 03/28/2025
REINSPECTION RESIDENTIAL ¤40.00 03/28/2025
REINSPECTION RESIDENTIAL ¤40.00 03/28/2025
CONTRACTOR CHANGE ¤20.00 03/28/2025
CONTRACTOR CHANGE ¤20.00 03/28/2025
CONTRACTOR CHANGE ¤20.00 03/28/2025
CONTRACTOR CHANGE ¤20.00 03/28/2025
SW ENG - INSPECTION 20 ¤20.00 03/28/2025
SW ENG - INSPECTION 20 ¤20.00 03/28/2025
SW ENG - INSPECTION 20 ¤20.00 03/28/2025
SW ENG - INSPECTION 20 ¤20.00 03/28/2025
SW ENG - INSPECTION 20 ¤20.00 03/28/2025
SW ENG - INSPECTION 20 ¤20.00 03/28/2025
SW ENG - INSPECTION 20 ¤20.00 03/28/2025
SW ENG - INSPECTION 20 ¤20.00 03/28/2025
SW ENG - INSPECTION 20 ¤20.00 03/28/2025
SW ENG - INSPECTION 20 ¤20.00 03/28/2025
SW ENG - INSPECTION 20 ¤20.00 03/28/2025
SW ENG - INSPECTION 20 ¤20.00 03/28/2025
SW ENG - INSPECTION 20 ¤20.00 03/28/2025
SW ENG - INSPECTION 20 ¤20.00 03/28/2025
SW ENG - INSPECTION 20 ¤20.00 03/28/2025
SW ENG - INSPECTION 20 ¤20.00 03/28/2025
SW ENG REINSPECTION 20 ¤20.00 03/28/2025
SW ENG REINSPECTION 20 ¤20.00 03/28/2025
SW ENG REINSPECTION 30 ¤30.00 03/28/2025
SW ENG - REVIEW 20 ¤20.00 08/18/2022
SW ENG RES REVIEW 200 ¤200.00 08/18/2022
3% TRANS IMPACT FEE CREDIT (¤52.92) 08/18/2022
SEWER CREDIT (¤1,147.00) 08/18/2022
SEWER INSPECTION ¤25.00 08/18/2022
SEWER CAPITAL FACILITY ¤4,939.76 08/18/2022
WATER CAPITAL FACILITY FEE ¤3,626.50 08/18/2022
SITE PLAN 30 ¤30.00 08/18/2022
WATER- TURN ON ¤25.00 08/18/2022
ADJUSTMENT 50% (¤606.28) 08/18/2022
SW ENG INSPECTION 80 ¤80.00 08/18/2022
SW ENG PRE APRON ¤30.00 08/18/2022
3% FIRE IMPACT FEE CREDIT (¤11.66) 08/18/2022
IMPACT FEE FIRE ¤388.65 08/18/2022
IMPACT FEE PARKS ¤1,455.13 08/18/2022
IMPACT FEE SCHOOL ¤3,600.00 08/18/2022
IMPACT FEE TRANSPORTATION ¤1,764.00 08/18/2022
WATER -IRRIGATION INSPECTION ¤25.00 08/18/2022
3% PARKS IMPACT FEE CREDIT (¤43.65) 08/18/2022
SURCHARGE FS 533.721 ¤3.85 08/18/2022
SURCHARGE - FS 468.631 ¤5.77 08/18/2022
SW ENG - FOUNDATION SURVEY ¤20.00 08/18/2022
CONNECTION FEES ¤1,077.88 08/18/2022
ADMINISTRATIVE RESIDENTIAL ¤30.00 08/18/2022
INSPECTION - RESIDENTIAL ¤921.25 08/18/2022
PLAN REVIEW - RESIDENTIAL ¤261.30 08/18/2022
Fees Total Due: ¤0.00 Total Paid: ¤17,370.08