Permit #2022081181
Permit Details
Status: FINAL
| Parcel Id: 22-11-30-5545-00000-0040 |
| Block: 00000 |
| Subdivision: 2246 - SANDLAKE SUBDIVISION |
| Job Phone: 386-931-5710 |
| Location Address: 4800 US HWY 1 N |
| Type: CSD - COMMERCIAL SITE DEVELOPMENT |
| Issue Date: 01/30/2024 |
| NOC: Unknown |
| Applicant name: CHELSEA MARIE BARNEY |
| Owner: MPW PALM COAST LLC & MCFT PALM COAST LLC |
|
Address 2918-A MARTINSVILLE ROAD GREENSBORO, NC 27408 |
| Lot: 0040 |
| Job Description: SITE WORK: EVOLVE UTILITY WATERMAIN ROUTE |
| Type: CN |
Contractor
4C'S TRUCKING & EXCAVATION INC
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
PO BOX 2682 BUNNELL, FL 32110 |
CGC1525599 (Exp: 08/31/2026) | 386-437-1257 | 386-437-4468 |
Inspection History
| Type | Request Date | Result | Inspector |
| U - UTILITY COMMERCIAL FINAL | 10/16/2025 | APPROVED - AS NOTED | BWRIGHT |
| Note: 10/8/2025 - PREVIOUS INSPECTION NOTES A substantial walk-through for utilities with as-builts will need to be scheduled before this inspection can be completed. Inspection was did by Donald Haney before he retired. | |||
| UC-FINAL SITE INSPECTION | 10/08/2025 | Disapproved - NO FEE | LFITZGERALD |
| Note: a walk through of the area of completed water main /fm inatall will be required | |||
| UC-FINAL SITE INSPECTION | 10/08/2025 | APPROVED - AS NOTED | LFITZGERALD |
| Note: Inspector Notes from Inspection 9108 all proposed work now completed 10/8/2025 - PREVIOUS INSPECTION NOTES a walk through of the area of completed water main /fm inatall will be required both sides US1 where wm/fm were installed inspected-spoke with Herb who informed that silt fence currently up is from paving operation on US1.temp power pole at corner of coperate/US1 not his/remove containers of oil next to power pole | |||
| U - UTILITY COMMERCIAL FINAL | 10/08/2025 | Disapproved - NO FEE | BWRIGHT |
| Note: A substantial walk-through for utilities with as-builts will need to be scheduled before this inspection can be completed. | |||
| UC-MOT MAINTENANCE OF TRAFFIC | 10/08/2025 | APPROVED - AS NOTED | LFITZGERALD |
| Note: all proposed work now completed | |||
| MAINT BOND ACCEPTANCE (OFFICE) | 09/10/2025 | APPROVED | DRAMIREZ |
| CLOSE OUT DOCUMENTS | 09/04/2025 | APPROVED | DRAMIREZ |
| PLANNING - OFFICE USE - FINAL AS-BUILT SURVEY | 11/26/2024 | APPROVED | DRAMIREZ |
| UC-SUBSTANTIAL WALK-THRU | 11/14/2024 | APPROVED - AS NOTED | DHANEY |
| Note: *** NOTES ADDED BY DHANEY 11/14/2024 2:01:45 PM *** Note; gate valve/valve box by forestry entrance was damaged , Contractor is making repairs . | |||
| UC- PRELIMINARY AS-BUILTS | 11/14/2024 | APPROVED | DHANEY |
| U-WATER MAIN DISINFECTION | 11/13/2024 | APPROVED | DHANEY |
| U-WATER MAIN DISINFECTION SAMPLING | 11/13/2024 | APPROVED | DHANEY |
| UROW -FINAL GRADE PRIOR SOD | 11/13/2024 | FINAL APPROVED | DHANEY |
| U-SEWER FORCE MAIN INSTALL/TESTING | 11/12/2024 | APPROVED | DHANEY |
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | 11/07/2024 | APPROVED | DHANEY |
| Note: 7/12/2024 - PREVIOUS INSPECTION NOTES *** NOTES ADDED BY DHANEY 7/12/2024 9:00:05 AM *** New Water main on US 1 (app. 6,000 ft) Will be feeding Evolve Dev. Test good . 3/4/2024 - PREVIOUS INSPECTION NOTES Inprogress . | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 09/10/2024 | APPROVED | DHANEY |
| Note: *** NOTES ADDED BY DHANEY 9/10/2024 9:35:04 AM *** Fence was ok , this project site is by State RT. US 1 only . 4/1/2024 - PREVIOUS INSPECTION NOTES Appears fence not completed yet - still open area by pond . | |||
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | 07/12/2024 | PARTIALLY APPROVED | DHANEY |
| Note: *** NOTES ADDED BY DHANEY 7/12/2024 9:00:05 AM *** New Water main on US 1 (app. 6,000 ft) Will be feeding Evolve Dev. Test good . 3/4/2024 - PREVIOUS INSPECTION NOTES Inprogress . | |||
| PLAN - PRE-CON 386-986-3750 | 05/01/2024 | APPROVED | DHANEY |
| CONSTRUCTION ENTRANCE | 04/01/2024 | APPROVED | DHANEY |
| UC-CONSTRUCTION ENTRANCE | 04/01/2024 | APPROVED | DHANEY |
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 04/01/2024 | PARTIALLY APPROVED | DHANEY |
| Note: Appears fence not completed yet - still open area by pond . | |||
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | 03/04/2024 | PARTIALLY APPROVED | DHANEY |
| Note: Inprogress . | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 02/28/2024 | APPROVED | DHANEY |
Review History
| Department | Status | Date In | Date Out |
| BLD | CANCEL | 08/22/2022 | 08/22/2022 |
| ELEC | CANCEL | 08/22/2022 | 08/22/2022 |
| PLENG | COMPLETE | 08/22/2022 | 08/22/2022 |
| Note: Released By: DENNIS R. LEAP, P.E. - (386)986-2482 - DLEAP@PALMCOASTGOV.COM | |||
| PLLA | CANCEL | 08/22/2022 | 08/24/2022 |
| UD1 | COMPLETE | 08/22/2022 | 08/22/2022 |
| Note: Released By: CHRIS JOHNSON - (386)986-2384 - CJOHNSON@PALMCOASTGOV.COM |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| ADJUSTMENT 50% | (¤62.50) | 01/30/2024 |
| ADMINISTRATIVE- SITE DEVELOP | ¤125.00 | 01/30/2024 |
| SITE INSPECTION | ¤280.00 | 01/30/2024 |
| SITE PLAN 30 | ¤30.00 | 01/30/2024 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤372.50 |