Permit #2022081219
Permit Details
Status: FINAL
| Parcel Id: 27-10-30-0000-01010-0010 |
| Block: 01010 |
| Subdivision: - |
| Job Phone: 386-931-7331 |
| Location Address: 6500 BELLE TERRE PKWY |
| Type: FU - FIRE UNDERGROUND |
| Issue Date: 09/07/2022 |
| NOC: RECORDED |
| Applicant name: SCOTT DALE SOWERS |
| Owner: PALM COAST UNITED METHODIST CHURCH INC |
|
Address 5200 BELLE TERRE PKWY PALM COAST, FL 32137 |
| Lot: 0010 |
| Contracted Stated Job Value: ¤31,215.00 |
| Job Description: Underground Fire Line - Palm Coast United Methodist Church |
| Type: CN |
Contractor
S E CLINE CONSTRUCTION INC
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
PO BOX 354425 PALM COAST, FL 32137 |
FPC12-000038 (Exp: 06/30/2026) | 386-446-6426 | 386-446-6481 |
Inspection History
| Type | Request Date | Result | Inspector |
| FIRE FINAL | 12/19/2023 | FINAL APPROVED | RMARTIN |
| Note: Inspector Notes from Inspection 5123 11/2/23 Did this inspection on a previouse day, contractor met on site to do the flow and flush 8/24/2023 - PREVIOUS INSPECTION NOTES 8/24/23 Pulled up behind cline silverado on site in front of hydrant and he left, on site at 10:25 2/27/2023 - PREVIOUS INSPECTION NOTES no oner on site to test | |||
| HYDRANT FLOW TEST | 11/02/2023 | APPROVED - AS NOTED | RMARTIN |
| Note: 11/2/23 Did this inspection on a previouse day, contractor met on site to do the flow and flush 8/24/2023 - PREVIOUS INSPECTION NOTES 8/24/23 Pulled up behind cline silverado on site in front of hydrant and he left, on site at 10:25 2/27/2023 - PREVIOUS INSPECTION NOTES no oner on site to test | |||
| FIRE SYSTEM FLUSH | 11/02/2023 | APPROVED - AS NOTED | RMARTIN |
| Note: 11/2/23 Did this inspection on a previouse day, contractor met on site to do the flow and flush 2/27/2023 - PREVIOUS INSPECTION NOTES notes below were NOT resolved need to have system ready flush prior to our arrival. (came by earlier today around 10:30am and the system was not readyto be flushed, came back at about 12:30 pm, system sitll not ready). Recall inspection when ready to flush 11/14/2022 - PREVIOUS INSPECTION NOTES 11/4/2022 - PREVIOUS INSPECTION NOTES Flushed 6 inch pipe before hooked up to riser. Need to flush Risers still and FDC line 11/14/22 still need to flush dry line to building | |||
| HYDRANT FLOW TEST | 08/24/2023 | Disapproved -FEE REQUIRED | RMARTIN |
| Note: 8/24/23 Pulled up behind cline silverado on site in front of hydrant and he left, on site at 10:25 2/27/2023 - PREVIOUS INSPECTION NOTES no oner on site to test | |||
| HYDRANT FLOW TEST | 02/27/2023 | CANCELLED BY APPLICANT | LMILLER |
| Note: no oner on site to test | |||
| FIRE SYSTEM FLUSH | 02/27/2023 | Disapproved -FEE REQUIRED | LMILLER |
| Note: notes below were NOT resolved need to have system ready flush prior to our arrival. (came by earlier today around 10:30am and the system was not readyto be flushed, came back at about 12:30 pm, system sitll not ready). Recall inspection when ready to flush 11/14/2022 - PREVIOUS INSPECTION NOTES 11/4/2022 - PREVIOUS INSPECTION NOTES Flushed 6 inch pipe before hooked up to riser. Need to flush Risers still and FDC line 11/14/22 still need to flush dry line to building | |||
| FIRE MAIN HYDROSTATIC/BACKFLOW PREVENTOR | 02/22/2023 | APPROVED | RMARTIN |
| FIRE MAIN PLACEMENT /SIZE/THRUST /BLOCKING | 11/14/2022 | APPROVED | RMARTIN |
| Note: 11/4/2022 - PREVIOUS INSPECTION NOTES 10/12/2022 - PREVIOUS INSPECTION NOTES 10/5/2022 - PREVIOUS INSPECTION NOTES NEED TO SCHEDULE YOUR OWN INSPECTIONS, NEED TO HAVE APPROVED PLANS ON SITE FOR ALL INSPECTIONS, LOOKED AT 1/2 UNDERGROUND 11/4/22 Looked at FDC line. Still need to see connection to 6inch pipe and riser 10/12/22 Marked on plans section of pipe plooked at | |||
| FIRE SYSTEM FLUSH | 11/14/2022 | PARTIALLY APPROVED | RMARTIN |
| Note: 11/4/2022 - PREVIOUS INSPECTION NOTES Flushed 6 inch pipe before hooked up to riser. Need to flush Risers still and FDC line 11/14/22 still need to flush dry line to building | |||
| FIRE SYSTEM FLUSH | 11/04/2022 | PARTIALLY APPROVED | JMUNSON |
| Note: Flushed 6 inch pipe before hooked up to riser. Need to flush Risers still and FDC line | |||
| FIRE MAIN PLACEMENT /SIZE/THRUST /BLOCKING | 11/04/2022 | PARTIALLY APPROVED | JMUNSON |
| Note: 10/12/2022 - PREVIOUS INSPECTION NOTES 10/5/2022 - PREVIOUS INSPECTION NOTES NEED TO SCHEDULE YOUR OWN INSPECTIONS, NEED TO HAVE APPROVED PLANS ON SITE FOR ALL INSPECTIONS, LOOKED AT 1/2 UNDERGROUND 11/4/22 Looked at FDC line. Still need to see connection to 6inch pipe and riser 10/12/22 Marked on plans section of pipe plooked at | |||
| HYDRANT FLOW TEST | 11/04/2022 | CANCELLED BY APPLICANT | WEB |
| FIRE MAIN PLACEMENT /SIZE/THRUST /BLOCKING | 10/12/2022 | PARTIALLY APPROVED | JMUNSON |
| Note: 10/5/2022 - PREVIOUS INSPECTION NOTES NEED TO SCHEDULE YOUR OWN INSPECTIONS, NEED TO HAVE APPROVED PLANS ON SITE FOR ALL INSPECTIONS, LOOKED AT 1/2 UNDERGROUND 10/12/22 Marked on plans section of pipe plooked at | |||
| FIRE MAIN PLACEMENT /SIZE/THRUST /BLOCKING | 10/05/2022 | PARTIALLY APPROVED | RMARTIN |
| Note: NEED TO SCHEDULE YOUR OWN INSPECTIONS, NEED TO HAVE APPROVED PLANS ON SITE FOR ALL INSPECTIONS, LOOKED AT 1/2 UNDERGROUND |
Review History
| Department | Status | Date In | Date Out |
| BADMIN | COMPLETE | 09/07/2022 | 09/07/2022 |
| Note: Released By: MARGA DEFREITAS - - MDEFREITAS@PALMCOASTGOV.COM | |||
| FI1 | COMPLETE | 08/30/2022 | 09/06/2022 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| BADMIN | HOLD | 08/30/2022 | 08/30/2022 |
| Note: Held By: BARBIE BEMBRY - (386)986-3780 - BUILDINGDIVISION@PALMCOASTGOV.COM A new permit application with the correct address of 6500 Belle Terre is required. The incorrect address was chosen upon submittal. | |||
| FI1 | HOLD | 08/22/2022 | 08/30/2022 |
| Note: Held By: LEE MILLER - (386)986-3783 - WMILLER@PALMCOASTGOV.COM 1. Need to remove W-27 Double Backflow device from the plans (the fire line has a Double Backflow at the street). | |||
| UD1 | COMPLETE | 08/22/2022 | 08/24/2022 |
| Note: Released By: CHRIS JOHNSON - (386)986-2384 - CJOHNSON@PALMCOASTGOV.COM |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION - COMMERCIAL | ¤60.00 | 08/24/2023 |
| REINSPECTION - COMMERCIAL | ¤60.00 | 08/24/2023 |
| SURCHARGE FS 533.721 | ¤2.68 | 09/07/2022 |
| SURCHARGE - FS 468.631 | ¤4.02 | 09/07/2022 |
| SW ENG - INSPECTION 20 | ¤20.00 | 09/07/2022 |
| ADJUSTMENT 50% | (¤261.10) | 09/07/2022 |
| ADMINISTRATIVE - COMMERCIAL | ¤75.00 | 09/07/2022 |
| INSPECTION - FIRE COMMERCIAL | ¤79.20 | 09/07/2022 |
| PLAN REVIEW - COMMERCIAL | ¤368.00 | 09/07/2022 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤407.80 |