Permit #2022100372

Permit Details

Status: COED

Parcel Id: 07-11-31-7032-00740-0070
CONDITIONED SPACE: 1721 sqft
GARAGE: 455 sqft
OPENED PORCH (WITH ROOF) : 110 sqft
OPENED PORCH (WITH ROOF) : 173 sqft
Total Square Footage: 2459 sqft
Block: 00740
Subdivision: 2155 - SECTION 32-ROYAL PALMS
Job Phone: 631-929-5500
Location Address: 26 ROLLINS LN
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 02/01/2023
NOC: RECORDED
Applicant name: NICHOLAS JOHN ZOUMAS
Owner: WICKAPOGUE RE DEVELOPMENT LLC

Address

SUITE 300

ORLANDO, FL 32819

Address

7450 DR PHILLIPS BLVD

ORLANDO, FL 32819

Lot: 0070
Contracted Stated Job Value: ¤160,000.00
Job Description: Single Family Home
Type: CN

Contractor

JNS CONTRACTING FLORIDA, LLC
Status Location Address State License Number Phone
ACTIVE

256 ROUTE 25A

WADING RIVER, NY 11792

CGC1527793 (Exp: 08/31/2026) 631-929-5500

Sub Contractors

NICHOLAS JOHN ZOUMAS
Status Location Address State License Number Phone
ACTIVE

256 ROUTE 25A

WADING RIVER, NY 11792

CGC1527793 (Exp: 08/31/2026) 631-929-5500
JOSEPH HORATIO STRADA JR
Status Location Address State License Number Phone
ACTIVE

3400 ST JOHNS PARKWAY

SANFORD, FL 32771

EC13003715 (Exp: 08/31/2026) 877-906-1113
JAMES MCGOVERN
Status Location Address Phone Fax
ACTIVE

PO BOX 354295

PALM COAST, FL 32137

(386)931-8940 (386)986-4835
JUAN CARLOS GONZALEZ
Status Location Address State License Number
ACTIVE

1328 COUNTY ROAD 308

CRESCENT CITY, FL 32112

RF11067806 (Exp: 08/31/2027)
ROBERT MICHAEL RENNER
Status Location Address State License Number Phone
ACTIVE

531 CODISCO WAY

SANFORD, FL 32771

CAC051477 (Exp: 08/31/2026) 407-333-2665

Inspection History

Type Request Date Result Inspector
BLD - BUILDING FINAL 07/17/2023 FINAL APPROVED JWALKER
Note: 7/10/2023 - PREVIOUS INSPECTION NOTES 1. Microwave exhaust duct has been damaged and no longer connected to the vent termination in the attic. 2. Seal the garage ceiling at the AHU supply plenum. 3. Please post the insulation placard. Common place is stapled to the truss at the attic access. 4. The attic access light fixture is not installed. Hanging down.
BLD - BUILDING FINAL 07/10/2023 Disapproved - NO FEE JWALKER
Note: 1. Microwave exhaust duct has been damaged and no longer connected to the vent termination in the attic. 2. Seal the garage ceiling at the AHU supply plenum. 3. Please post the insulation placard. Common place is stapled to the truss at the attic access. 4. The attic access light fixture is not installed. Hanging down.
ROW - STORMWATER FINAL 07/10/2023 APPROVED FSLADISH
Note: 07/10/23 MEETS THE MINIMUM CITY STANDARDS. LOOKED OK AT THE TIME OF THIS FINAL INSPECTION.
U -UTILITY RESIDENTIAL FINAL 07/10/2023 FINAL APPROVED LFITZGERALD
ROW- PROJECT STATUS 06/13/2023 CANCELLED BY INSPECTOR PFLANAGAN
ROW - FINAL APRON (AFTER POUR) 06/12/2023 APPROVED PFLANAGAN
ROW- FINAL SURVEY/GRADING CERTIFICATION 06/12/2023 APPROVED PFLANAGAN
ROW FIELD SURVEY /GRADING CERTIFICATION 06/12/2023 APPROVED PFLANAGAN
ELECTRIC - EARLY POWER 05/19/2023 APPROVED JWALKER
Note: 5/16/2023 - PREVIOUS INSPECTION NOTES Kitchen counter top outlets are not safed off.
ELECTRIC - EARLY POWER 05/16/2023 Disapproved - NO FEE JWALKER
Note: Kitchen counter top outlets are not safed off.
ROW- PRE-APRON (PRE-POUR) 04/26/2023 APPROVED FSLADISH
Note: 04/26/23 READY TO POUR AT THE TIME OF THE INSPECTION CULVERT PIPE IS GOOD IS READY TO POUR, IF RAIN PLEASE, BUILDER SHOULD DOUBLE CHECK CULVERT ELEVATIONS BEFORE POURING. MAKE SURE IS 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE (FRC) DRAWING 300,E RESIDENTIAL CULVERT DETAIL
LATH/BRICK/ WATER BARRIER 04/05/2023 APPROVED JWALKER
Note: 3/30/2023 - PREVIOUS INSPECTION NOTES Metal lath above the garage and the front entry has not been completed. Metal lath is to be fastened a minimum of 16" o.c. vertically and 7" o.c. horizontally.
LATH/BRICK/ WATER BARRIER 03/30/2023 Disapproved - NO FEE JWALKER
Note: Metal lath above the garage and the front entry has not been completed. Metal lath is to be fastened a minimum of 16" o.c. vertically and 7" o.c. horizontally.
GRAVITY SEWER TEST 03/28/2023 APPROVED MGIBSON
U - SEWER TIE IN 03/28/2023 APPROVED MGIBSON
U-CROSS CONNECTION 03/28/2023 APPROVED - AS NOTED JHARDING
Note: Nn irrigation, no cross connections.
INSULATION 03/27/2023 APPROVED JWALKER
Note: Inspector Notes from Inspection 2420 1. The 18" flex needs to be lifted off the ceiling chord to allow for proper insulation fill. 2. Rear slider has not been installed. 3. Set the head jamb screws at the front door. 4. Tub drain needs to be sealed. Check for corrections at insulation inspection.
ALL ROUGH 03/23/2023 APPROVED - AS NOTED JWALKER
Note: 1. The 18" flex needs to be lifted off the ceiling chord to allow for proper insulation fill. 2. Rear slider has not been installed. 3. Set the head jamb screws at the front door. 4. Tub drain needs to be sealed. Check for corrections at insulation inspection.
ROOF VALLEY & METAL 03/08/2023 APPROVED JWALKER
Note: 3/2/2023 - PREVIOUS INSPECTION NOTES 3/2/233 Plywood at truss T12 not corrected. Underlayment fastening not corrected. 2/28/2023 - PREVIOUS INSPECTION NOTES 1. Missed roof deck nailing at truss T-12 4th row up. Truss CJ05 front left bedroom first row above the window. 2. Underlayment is to be fastened a minimum of 6" o.c. at the laps and ends.
ROOF VALLEY & METAL 03/02/2023 Disapproved -FEE REQUIRED JWALKER
Note: 3/2/233 Plywood at truss T12 not corrected. Underlayment fastening not corrected. 2/28/2023 - PREVIOUS INSPECTION NOTES 1. Missed roof deck nailing at truss T-12 4th row up. Truss CJ05 front left bedroom first row above the window. 2. Underlayment is to be fastened a minimum of 6" o.c. at the laps and ends.
WALL SHEATHING 02/28/2023 APPROVED JWALKER
ROOF SHEATHING / BRACES/TIES/DOWN CELL 02/28/2023 APPROVED - AS NOTED JWALKER
Note: Missed roof deck nailing at truss T-12 4th row up. Truss CJ05 front left bedroom first row above the window.
ROOF VALLEY & METAL 02/28/2023 Disapproved - NO FEE JWALKER
Note: 1. Missed roof deck nailing at truss T-12 4th row up. Truss CJ05 front left bedroom first row above the window. 2. Underlayment is to be fastened a minimum of 6" o.c. at the laps and ends.
ELECTRIC-TUG 02/28/2023 APPROVED JWALKER
TIE BEAM / LINTEL 02/17/2023 APPROVED JWALKER
Note: 2/16/2023 - PREVIOUS INSPECTION NOTES 2/16/23: Block is not repaired as required. Identified in previous inspection. 2/14/2023 - PREVIOUS INSPECTION NOTES Right side wall where the plumbing is, block has been removed and filled with motar. Reinstall block and grout corretly. Block are already starting to sag.
TIE BEAM / LINTEL 02/16/2023 Disapproved -FEE REQUIRED RSIMS
Note: 2/16/23: Block is not repaired as required. Identified in previous inspection. 2/14/2023 - PREVIOUS INSPECTION NOTES Right side wall where the plumbing is, block has been removed and filled with motar. Reinstall block and grout corretly. Block are already starting to sag.
FOUND SURVEY APPROVED (OFFICE) 02/16/2023 APPROVED AMOBLEY
TIE BEAM / LINTEL 02/14/2023 Disapproved - NO FEE JWALKER
Note: Right side wall where the plumbing is, block has been removed and filled with motar. Reinstall block and grout corretly. Block are already starting to sag.
MONOLITHIC SLAB 02/09/2023 APPROVED RSIMS
Note: 2/8/2023 - PREVIOUS INSPECTION NOTES 2/8/23: 1). Remove roots from slab areas as highlighted on plan. 2). Back left side of garage footer has dirt cave in. (highlighted on plan) 3). Left side of entry the rebar needs to be centered in the footer better. 4). Electrical conduit for kitchen island needs to be buried in the dirt & not above plastic within the slab. 2/7/2023 - PREVIOUS INSPECTION NOTES No rebar has been installed. Please ensure work is complete before scheduling inspections.
MONOLITHIC SLAB 02/08/2023 Disapproved -FEE REQUIRED RSIMS
Note: 2/8/23: 1). Remove roots from slab areas as highlighted on plan. 2). Back left side of garage footer has dirt cave in. (highlighted on plan) 3). Left side of entry the rebar needs to be centered in the footer better. 4). Electrical conduit for kitchen island needs to be buried in the dirt & not above plastic within the slab. 2/7/2023 - PREVIOUS INSPECTION NOTES No rebar has been installed. Please ensure work is complete before scheduling inspections.
MONOLITHIC SLAB 02/07/2023 Disapproved -FEE REQUIRED JWALKER
Note: No rebar has been installed. Please ensure work is complete before scheduling inspections.
MONOLITHIC SLAB 02/06/2023 CANCELLED BY APPLICANT JWALKER
PLUMBING 1ST ROUGH UNDERGROUND 02/02/2023 APPROVED MGIBSON
WATER METER INSTALLATION REQUEST 02/02/2023 APPROVED TSCHWEERS

Review History

Department Status Date In Date Out
MECH COMPLETE 06/20/2023 06/20/2023
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
MECH COMPLETE 02/27/2023 02/27/2023
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
ENGIN1 COMPLETE 02/16/2023 02/16/2023
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
ZON COMPLETE 02/16/2023 02/16/2023
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
SW1 COMPLETE 10/19/2022 10/26/2022
Note: Released By: ROBERT GROSS - (386)986-4769 - RGROSS@PALMCOASTGOV.COM
ENGIN1 COMPLETE 10/19/2022 10/19/2022
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
ZON COMPLETE 10/19/2022 10/19/2022
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
BLD COMPLETE 10/07/2022 10/10/2022
Note: Released By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM
CUSVC COMPLETE 10/07/2022 10/12/2022
Note: Released By: CYNTHIA SCHWEERS - - CSCHWEERS@PALMCOASSTGOV.COM
ELEC COMPLETE 10/07/2022 10/10/2022
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
ENGIN1 COMPLETE 10/07/2022 10/07/2022
Note: Released By: JOHN HOWARD - - JHOWARD@PALMCOASTGOV.COM
LOCATE COMPLETE 10/07/2022 10/13/2022
Note: Released By: CANDACE STONE - - CSTONE@PALMCOASTGOV.COM
MECH COMPLETE 10/07/2022 10/10/2022
Note: Released By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM
SW1 HOLD 10/07/2022 10/10/2022
Note: Held By: PARREN FLANAGAN - (386)986-2392 - PFLANAGAN@PALMCOASTGOV.COM NEED TO MAKE BOTH PROPERTY LINE A COMMON SWALE
ZON COMPLETE 10/07/2022 10/10/2022
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
SWALE COMPLETE 10/07/2022 02/21/2023
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
PLAN REVIEW - REVISION ¤32.50 06/28/2023
PLAN REVIEW - REVISION ¤32.50 06/28/2023
REINSPECTION RESIDENTIAL ¤40.00 06/28/2023
REINSPECTION RESIDENTIAL ¤40.00 06/28/2023
REINSPECTION RESIDENTIAL ¤40.00 06/28/2023
REINSPECTION RESIDENTIAL ¤40.00 06/28/2023
CONTRACTOR CHANGE ¤20.00 06/28/2023
SW ENG REINSPECTION 20 ¤20.00 06/28/2023
SW ENG - REVIEW 20 ¤20.00 02/01/2023
SW ENG RES REVIEW 200 ¤200.00 02/01/2023
TRANS IMPACT FEE ADMIN ¤52.92 02/01/2023
TRANS IMPACT FEE ADMIN (¤52.92) 02/01/2023
SEWER CREDIT (¤934.92) 02/01/2023
SEWER INSPECTION ¤25.00 02/01/2023
SEWER CAPITAL FACILITY ¤5,344.82 02/01/2023
WATER CREDIT (¤345.89) 02/01/2023
WATER CAPITAL FACILITY FEE ¤3,923.88 02/01/2023
SITE PLAN 30 ¤30.00 02/01/2023
FIRE IMPACT FEE ADMIN ¤12.62 02/01/2023
FIRE IMPACT FEE ADMIN (¤12.62) 02/01/2023
IMPACT FEE FIRE ¤420.52 02/01/2023
IMPACT FEE PARKS ¤1,769.15 02/01/2023
IMPACT FEE SCHOOL ¤5,450.00 02/01/2023
IMPACT FEE TRANSPORTATION ¤1,764.00 02/01/2023
WATER -IRRIGATION INSPECTION ¤25.00 02/01/2023
PARKS IMPACT FEE ADMIN ¤53.07 02/01/2023
PARKS IMPACT FEE ADMIN (¤53.07) 02/01/2023
SURCHARGE FS 533.721 ¤2.69 02/01/2023
SURCHARGE - FS 468.631 ¤4.04 02/01/2023
SW ENG - FOUNDATION SURVEY ¤20.00 02/01/2023
SW ENG INSPECTION 80 ¤80.00 02/01/2023
SW ENG PRE APRON ¤30.00 02/01/2023
CONNECTION FEES ¤1,166.26 02/01/2023
WATER- TURN ON ¤25.00 02/01/2023
ADJUSTMENT 50% (¤405.07) 02/01/2023
ADMINISTRATIVE RESIDENTIAL ¤30.00 02/01/2023
INSPECTION - RESIDENTIAL ¤607.75 02/01/2023
PLAN REVIEW - RESIDENTIAL ¤172.38 02/01/2023
Fees Total Due: ¤0.00 Total Paid: ¤19,689.61