I want to search for...
Permit #2022120211
Permit Details
Status: COED
| Parcel Id: 07-11-31-7026-00730-0420 |
| CONDITIONED SPACE: 1502 sqft |
| GARAGE: 436 sqft |
| OPENED PORCH (WITH ROOF) : 304 sqft |
| Total Square Footage: 2242 sqft |
| Block: 00730 |
| Subdivision: 2153 - SECTION 26-PINE GROVE |
| Job Phone: 407-580-2657 |
| Location Address: 18 PITT LN |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 03/10/2023 |
| NOC: RECORDED |
| Applicant name: GENE WARREN SLONE |
| Owner: SINGH SORISHA & DEO S |
|
Address 1347 NW 63RD TERRACE MARGATE, FL 33063 |
| Lot: 0420 |
| Contracted Stated Job Value: ¤300,000.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
FLORIDA GREEN CONSTRUCTION INC.
| Status | Location Address | State License Number | Phone |
| INACTIVE |
870 E RETTA STREET DELEON SPRINGS, FL 32130 |
CBC1260957 (Exp: 08/31/2026) | 407-580-2657 |
Sub Contractors
JOHN EDWARD GAMBONE
| Status | Location Address | Mailing Address | State License Number | Phone |
| ACTIVE |
15 HARGROVE LN PALM COAST, FL 32137 |
1G PALM COAST, FL 32137 |
EC13006037 (Exp: 08/31/2026) | 386-586-9144 |
KERRY DWAIN AYLESWORTH II
| Status | Location Address | Mailing Address | State License Number | Phone |
| ACTIVE |
2820 LEWIS SPEEDWAY ST AUGUSTINE, FL 32084 |
STE B ST AUGUSTINE, FL 32084 |
CAC1820713 (Exp: 08/31/2026) | 904-342-5709 |
ERIC FRANCO
| Status | Location Address | Mailing Address | State License Number | Phone |
| INACTIVE |
840 DELTONA BLVD DELTONA, FL 32725 |
STE F2 DELTONA, FL 32725 |
CCC1327280 (Exp: 08/31/2026) | 386-575-4007 |
JONATHAN M PEARSON
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
209 N FORSYTH ST BUNNELL, FL 32110 |
CFC1425941 (Exp: 08/31/2026) | 386-597-0944 | 386-437-4996 |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 04/16/2024 | FINAL APPROVED | RSIMS |
| Note: 4/16/24: Waiting for virtual confirmation of soffit repair at Master bathroom exhaust vent. | |||
| ROW - STORMWATER FINAL | 04/15/2024 | APPROVED | EMADISON |
| Note: ** At the time of the inspection all minimum city requirements were met. It is the builders responsibility to ensure that nothing changes after this Inspection is approved. | |||
| U -UTILITY RESIDENTIAL FINAL | 04/15/2024 | APPROVED - AS NOTED | LFITZGERALD |
| Note: sewer C/O still not raised-please raise as already indicated and send photo to me when done 4/11/2024 - PREVIOUS INSPECTION NOTES remove excess soils /trash from water meter pit -soils remove to bottom of check valves/raise sewer C/O so it doesnt get covered over by sod but not too high so not chopped by mower=flush with sod-Also need to raise pep tank lid-utility informed | |||
| ROW - STORMWATER FINAL | 04/11/2024 | CANCELLED BY APPLICANT | EMADISON |
| U -UTILITY RESIDENTIAL FINAL | 04/11/2024 | Disapproved -FEE REQUIRED | LFITZGERALD |
| Note: remove excess soils /trash from water meter pit -soils remove to bottom of check valves/raise sewer C/O so it doesnt get covered over by sod but not too high so not chopped by mower=flush with sod-Also need to raise pep tank lid-utility informed | |||
| ROW - FINAL APRON (AFTER POUR) | 04/11/2024 | APPROVED | EMADISON |
| Note: ** At the time of the inspection all minimum city requirements were met. It is the builders responsibility to ensure that nothing changes after this Inspection is approved. | |||
| U-CROSS CONNECTION | 04/11/2024 | APPROVED - AS NOTED | LFITZGERALD |
| Note: has otable irrigation with PVB installed-no cross connection | |||
| ROW- FINAL SURVEY/GRADING CERTIFICATION | 04/09/2024 | APPROVED | TPOLACEK |
| Note: 04/09/24 UPON WALKING PROPERTY DRAINAGE WILL WORK AS INDICATED ON FINAL SURVEY. AT THE OF THE INSPECTION, ALL MINIMUM CITY REQUIREMENTS WERE MET. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED. | |||
| ROW FIELD SURVEY /GRADING CERTIFICATION | 04/09/2024 | APPROVED | TPOLACEK |
| Note: 04/09/24 AT THE TIME OF THE INSPECTION, ALL MINIMUM CITY REQUIREMENTS WERE MET.NIETHER THE INSPECTOR NOR THE CITY IS RESPONSIBLE IF, FOR WHATEVER REASON, SITE CONDITIONS CHANGE OVER TIME AFTER THE INSPECTION. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED. TO ENSURE PROPER DRAINAGE OF STORMWATER ON THE PROPERTY, WE NEED TO IDENTIFY THE HIGH POINT AT THE CENTER OF THE PROPERTY LINE. FROM THERE, WE WILL CREATE A SWALE ON BOTH SIDES OF THE PROPERTY LINE TO DIRECT THE WATER FLOW TO THE LEFT AND RIGHT. WE NEED TO CREATE A 4/1 SLOPE BEFORE THE PROPERTY LINE AND THEN USE A COMMON SWALE TO GUIDE THE WATER TOWARD THE EMPTY LOT. ON THE RIGHT SIDE, A SWALE NEEDS TO BE INSTALLED BY THE PROPERTY LINE TO MANAGE THE STORMWATER FLOW | |||
| ROW- PRE-APRON (PRE-POUR) | 03/21/2024 | APPROVED | TPOLACEK |
| Note: 03/21/24 AT THE TIME OF THE INSPECTION CULVERT PIPE IS GOOD IS READY TO POUR, IF RAIN PLEASE, BUILDER SHOULD DOUBLE CHECK CULVERT ELEVATIONS MAKE SURE IS 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE (FRC) DRAWING 300,E RESIDENTIAL CULVERT DETAIL BEFORE POURING. 3/18/2024 - PREVIOUS INSPECTION NOTES ** 03/18/24 SITE NOT READY FOR INSPECTION POUR AREA UNDER WATER TOO WET TO POUR ** SEE ATTACHED PHOTOS _________________________________________________________________________________________________________________ 3/15/2024 - PREVIOUS INSPECTION NOTES 03/15/24 PIPE IS OUT OF TOLERANCE THAT WAS AGREED UPON. CULVERT PIPE NEEDS TO BE 8' ON CENTER FROM EDGE OF ROAD. FRONT BOARD AT ROAD NEEDS TO EQUAL TO EXISTING EDGE OF ROAD PRIOR TO CONSTRUCTION. WILL NOT FEE THIS INSPECTION --------------------------------------------------------------------- 3/6/2024 - PREVIOUS INSPECTION NOTES THIS IS NOT FORMED UP YET NOT FEEING YOU ON THIS INSPECTION ----------------------------------------------------------------------------------------- 2/15/24= I INSTRUCTED THE BUILDER AND JASON TO INSTALL THE CULVERT PIPE AT THE BOTTOM OF THE CULVERT'S ELEVATION.per gbertola MEET WITH BUILDER ABOUT THE CULVERT ELEVATION NEEDS TO SET CULVERT AT 24.40 FLAT TO GET THE COVERAGE OVER THE CULVERT AND MIGHT NEED TO TAKE OUT SOME CONCRETE TO GET THE COVERAGE ALSO meeting with Jason | |||
| ROW- PRE-APRON (PRE-POUR) | 03/18/2024 | Disapproved -FEE REQUIRED | EMADISON |
| Note: ** 03/18/24 SITE NOT READY FOR INSPECTION POUR AREA UNDER WATER TOO WET TO POUR ** SEE ATTACHED PHOTOS _________________________________________________________________________________________________________________ 3/15/2024 - PREVIOUS INSPECTION NOTES 03/15/24 PIPE IS OUT OF TOLERANCE THAT WAS AGREED UPON. CULVERT PIPE NEEDS TO BE 8' ON CENTER FROM EDGE OF ROAD. FRONT BOARD AT ROAD NEEDS TO EQUAL TO EXISTING EDGE OF ROAD PRIOR TO CONSTRUCTION. WILL NOT FEE THIS INSPECTION --------------------------------------------------------------------- 3/6/2024 - PREVIOUS INSPECTION NOTES THIS IS NOT FORMED UP YET NOT FEEING YOU ON THIS INSPECTION ----------------------------------------------------------------------------------------- 2/15/24= I INSTRUCTED THE BUILDER AND JASON TO INSTALL THE CULVERT PIPE AT THE BOTTOM OF THE CULVERT'S ELEVATION.per gbertola MEET WITH BUILDER ABOUT THE CULVERT ELEVATION NEEDS TO SET CULVERT AT 24.40 FLAT TO GET THE COVERAGE OVER THE CULVERT AND MIGHT NEED TO TAKE OUT SOME CONCRETE TO GET THE COVERAGE ALSO meeting with Jason | |||
| ROW- PRE-APRON (PRE-POUR) | 03/15/2024 | Disapproved - NO FEE | TPOLACEK |
| Note: 03/15/24 PIPE IS OUT OF TOLERANCE THAT WAS AGREED UPON. CULVERT PIPE NEEDS TO BE 8' ON CENTER FROM EDGE OF ROAD. FRONT BOARD AT ROAD NEEDS TO EQUAL TO EXISTING EDGE OF ROAD PRIOR TO CONSTRUCTION. WILL NOT FEE THIS INSPECTION --------------------------------------------------------------------- 3/6/2024 - PREVIOUS INSPECTION NOTES THIS IS NOT FORMED UP YET NOT FEEING YOU ON THIS INSPECTION ----------------------------------------------------------------------------------------- 2/15/24= I INSTRUCTED THE BUILDER AND JASON TO INSTALL THE CULVERT PIPE AT THE BOTTOM OF THE CULVERT'S ELEVATION.per gbertola MEET WITH BUILDER ABOUT THE CULVERT ELEVATION NEEDS TO SET CULVERT AT 24.40 FLAT TO GET THE COVERAGE OVER THE CULVERT AND MIGHT NEED TO TAKE OUT SOME CONCRETE TO GET THE COVERAGE ALSO meeting with Jason | |||
| ROW- PRE-APRON (PRE-POUR) | 03/06/2024 | Disapproved - NO FEE | PFLANAGAN |
| Note: THIS IS NOT FORMED UP YET NOT FEEING YOU ON THIS INSPECTION ----------------------------------------------------------------------------------------- 2/15/24= I INSTRUCTED THE BUILDER AND JASON TO INSTALL THE CULVERT PIPE AT THE BOTTOM OF THE CULVERT'S ELEVATION.per gbertola MEET WITH BUILDER ABOUT THE CULVERT ELEVATION NEEDS TO SET CULVERT AT 24.40 FLAT TO GET THE COVERAGE OVER THE CULVERT AND MIGHT NEED TO TAKE OUT SOME CONCRETE TO GET THE COVERAGE ALSO meeting with Jason | |||
| ELECTRIC - EARLY POWER | 02/27/2024 | APPROVED | RSIMS |
| Note: 2/27/24: FPL emailed to release power. Inspector Notes from Inspection 2200 Emailed FPL @ 1025. Release Power | |||
| ROW- PROJECT STATUS | 02/15/2024 | APPROVED - AS NOTED | GBERTOLA |
| Note: 2/15/24= I INSTRUCTED THE BUILDER AND JASON TO INSTALL THE CULVERT PIPE AT THE BOTTOM OF THE CULVERT'S ELEVATION.per gbertola MEET WITH BUILDER ABOUT THE CULVERT ELEVATION NEEDS TO SET CULVERT AT 24.40 FLAT TO GET THE COVERAGE OVER THE CULVERT AND MIGHT NEED TO TAKE OUT SOME CONCRETE TO GET THE COVERAGE ALSO meeting with Jason | |||
| ROW- PROJECT STATUS | 01/23/2024 | APPROVED - AS NOTED | PFLANAGAN |
| Note: MEET WITH BUILDER ABOUT THE CULVERT ELEVATION NEEDS TO SET CULVERT AT 24.40 FLAT TO GET THE COVERAGE OVER THE CULVERT AND MIGHT NEED TO TAKE OUT SOME CONCRETE TO GET THE COVERAGE ALSO | |||
| ROW- PRE-APRON (PRE-POUR) | 01/10/2024 | PARTIALLY APPROVED | RGROSS |
| Note: See Applicant note. Approved for the upper portion of the driveway. This will be a two part pour. Another Pre pour will be required after the pipe is set and the ROW is poured. This is a Flag Lot. 1/8/2024 - PREVIOUS INSPECTION NOTES Not ready for inspection. | |||
| ROW- PRE-APRON (PRE-POUR) | 01/08/2024 | Disapproved -FEE REQUIRED | RGROSS |
| Note: Not ready for inspection. | |||
| ROW- PROJECT STATUS | 12/19/2023 | APPROVED | GBERTOLA |
| Note: TO ENSURE PROPER DRAINAGE OF STORMWATER ON THE PROPERTY, WE NEED TO IDENTIFY THE HIGH POINT AT THE CENTER OF THE PROPERTY LINE. FROM THERE, WE WILL CREATE A SWALE ON BOTH SIDES OF THE PROPERTY LINE TO DIRECT THE WATER FLOW TO THE LEFT AND RIGHT. WE NEED TO CREATE A 4/1 SLOPE BEFORE THE PROPERTY LINE AND THEN USE A COMMON SWALE TO GUIDE THE WATER TOWARD THE EMPTY LOT. ON THE RIGHT SIDE, A SWALE NEEDS TO BE INSTALLED BY THE PROPERTY LINE TO MANAGE THE STORMWATER FLOW | |||
| U - SEWER TIE IN | 11/21/2023 | APPROVED | MGIBSON |
| GRAVITY SEWER TEST | 11/21/2023 | APPROVED | MGIBSON |
| PEP TANK INSTALLATION REQUEST | 10/24/2023 | APPROVED | CBOWERMASTER |
| LATH/BRICK/ WATER BARRIER | 10/18/2023 | APPROVED | KSANDOE |
| INSULATION | 10/04/2023 | APPROVED | KSANDOE |
| ALL ROUGH | 09/29/2023 | APPROVED | KSANDOE |
| ELECTRIC-TUG | 07/20/2023 | APPROVED - AS NOTED | KSANDOE |
| Note: Emailed FPL @ 1025. Release Power | |||
| ROOF VALLEY & METAL | 07/18/2023 | APPROVED | KSANDOE |
| Note: Inspector Notes from Inspection 2460 T12 bracing in wrong location Missing 2 LSTA21 garage entry door | |||
| WALL SHEATHING | 06/30/2023 | APPROVED | KSANDOE |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 06/30/2023 | APPROVED - AS NOTED | KSANDOE |
| Note: T12 bracing in wrong location Missing 2 LSTA21 garage entry door | |||
| FOUND SURVEY APPROVED (OFFICE) | 06/02/2023 | APPROVED | TBAKER |
| TIE BEAM / LINTEL | 06/02/2023 | APPROVED | KSANDOE |
| MONOLITHIC SLAB | 05/11/2023 | APPROVED | MKRASKI |
| MONOLITHIC SLAB | 05/10/2023 | Disapproved -FEE REQUIRED | KSANDOE |
| Note: Missing corner dowel at entry. Marked on plans 5/9/2023 - PREVIOUS INSPECTION NOTES 1. Dowel layout does not match, need revision subbmitted and approved throught bulding dept. 2. Ufer ground not per NEC 250.53(g) | |||
| MONOLITHIC SLAB | 05/09/2023 | Disapproved - NO FEE | MKRASKI |
| Note: 1. Dowel layout does not match, need revision subbmitted and approved throught bulding dept. 2. Ufer ground not per NEC 250.53(g) | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 05/04/2023 | APPROVED | MGIBSON |
| WATER METER INSTALLATION REQUEST | 03/29/2023 | APPROVED | CSTONE |
Review History
| Department | Status | Date In | Date Out |
| MECH | COMPLETE | 04/03/2024 | 04/05/2024 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| MECH | HOLD | 04/01/2024 | 04/03/2024 |
| Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Energy calcs submitted match the previously approved ones | |||
| ENGIN1 | COMPLETE | 06/02/2023 | 06/02/2023 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 06/02/2023 | 06/02/2023 |
| Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 01/26/2023 | 01/26/2023 |
| Note: Released By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 01/26/2023 | 01/26/2023 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| SW1 | COMPLETE | 01/26/2023 | 02/01/2023 |
| Note: Released By: PARREN FLANAGAN - (386)986-2392 - PFLANAGAN@PALMCOASTGOV.COM | |||
| MECH | COMPLETE | 01/26/2023 | 01/26/2023 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| ZON | HOLD | 01/19/2023 | 01/19/2023 |
| Note: Held By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM Site Plan: Garages must have a driveway extending for a minimum of 20 feetin front of each garage door. Then the Turnaround can begin. Driveway materials allowed are concrete and paver only. | |||
| ENGIN1 | COMPLETE | 01/19/2023 | 01/19/2023 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| SW1 | COMPLETE | 01/19/2023 | 01/25/2023 |
| Note: Released By: GABRIEL BERTOLA - (386)986-7660 - GBERTOLA@PALMCOASTGOV.COM | |||
| BADMIN | INFORMATION | 01/18/2023 | 01/18/2023 |
| Note: Marked INFORMATION By: BARBIE BEMBRY - (386)986-3780 - BUILDINGDIVISION@PALMCOASTGOV.COM You uploaded duplicate documents multiple times. Only one copy of a document is to be uploaded. | |||
| BADMIN | INFORMATION | 12/22/2022 | 12/22/2022 |
| Note: Marked INFORMATION By: BARBIE BEMBRY - (386)986-3780 - BUILDINGDIVISION@PALMCOASTGOV.COM You uploaded a site plan under plans. Please rename the file and upload under the correct document type. | |||
| BLD | COMPLETE | 12/06/2022 | 12/12/2022 |
| Note: Released By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM All comments below per the 2020 Florida Building Code PLAN REVIEW COMMENTS: 1. Provide product approval for the double glass door in the dinning area. | |||
| CUSVC | COMPLETE | 12/06/2022 | 12/07/2022 |
| Note: Released By: HALEIGH HAND - - | |||
| ELEC | COMPLETE | 12/06/2022 | 12/06/2022 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 12/06/2022 | 12/06/2022 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| LOCATE | COMPLETE | 12/06/2022 | 12/08/2022 |
| Note: Released By: TONI CHURCHILL - - | |||
| MECH | HOLD | 12/06/2022 | 12/06/2022 |
| Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Duct layout is not readable. Provide new duct layout | |||
| SW1 | COMPLETE | 12/06/2022 | 12/14/2022 |
| Note: Released By: ROBERT GROSS - (386)986-4769 - RGROSS@PALMCOASTGOV.COM | |||
| ZON | HOLD | 12/06/2022 | 12/07/2022 |
| Note: Held By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM Site plan: Walk way to entrance missing add and include tthe width of walkway. Turn around needs to be max 9' wide and 18' in length. Please provide the width of the driveway in front of the garage doors. landscape plans: One tree for every 2500 square ft. All calculations are rounded to the nearest whole number. This property requires 7 Trees | |||
| SWALE | COMPLETE | 12/06/2022 | 03/24/2023 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| PLAN REVIEW - REVISION | ¤32.50 | 04/11/2024 |
| REINSPECTION FEE | ¤40.00 | 04/11/2024 |
| SW ENG REINSPECTION 20 | ¤20.00 | 04/02/2024 |
| SW ENG REINSPECTION 20 | ¤20.00 | 04/02/2024 |
| SW ENG REINSPECTION 20 | ¤20.00 | 04/02/2024 |
| SW ENG REINSPECTION 30 | ¤30.00 | 04/02/2024 |
| SW ENG REINSPECTION 30 | ¤30.00 | 04/02/2024 |
| REINSPECTION RESIDENTIAL | ¤40.00 | 04/02/2024 |
| CONNECTION FEES | ¤1,166.26 | 03/10/2023 |
| CONTRACTOR CHANGE | ¤20.00 | 03/10/2023 |
| CONTRACTOR CHANGE | ¤20.00 | 03/10/2023 |
| CONTRACTOR CHANGE | ¤20.00 | 03/10/2023 |
| CONTRACTOR CHANGE | ¤20.00 | 03/10/2023 |
| CONTRACTOR CHANGE | ¤20.00 | 03/10/2023 |
| FIRE IMPACT FEE ADMIN | ¤12.62 | 03/10/2023 |
| FIRE IMPACT FEE ADMIN | (¤12.62) | 03/10/2023 |
| FC IMPACT FEE EMS | ¤62.00 | 03/10/2023 |
| IMPACT FEE FIRE | ¤420.52 | 03/10/2023 |
| FC IMPACT FEE LAW ENFORCEMENT | ¤218.00 | 03/10/2023 |
| FC IMPACT FEE LIBRARY | ¤268.00 | 03/10/2023 |
| FC IMPACT FEE LIBRARY | ¤268.00 | 03/10/2023 |
| IMPACT FEE PARKS | ¤1,769.15 | 03/10/2023 |
| IMPACT FEE SCHOOL | ¤5,450.00 | 03/10/2023 |
| IMPACT FEE TRANSPORTATION | ¤1,764.00 | 03/10/2023 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 03/10/2023 |
| PARKS IMPACT FEE ADMIN | ¤53.07 | 03/10/2023 |
| PARKS IMPACT FEE ADMIN | (¤53.07) | 03/10/2023 |
| SW ENG - REVIEW 20 | ¤20.00 | 03/10/2023 |
| SW ENG RES REVIEW 200 | ¤200.00 | 03/10/2023 |
| TRANS IMPACT FEE ADMIN | ¤52.92 | 03/10/2023 |
| TRANS IMPACT FEE ADMIN | (¤52.92) | 03/10/2023 |
| SEWER CREDIT | (¤81.08) | 03/10/2023 |
| SEWER INSPECTION | ¤25.00 | 03/10/2023 |
| SEWER CAPITAL FACILITY | ¤5,344.82 | 03/10/2023 |
| WATER CAPITAL FACILITY FEE | ¤3,923.88 | 03/10/2023 |
| SITE PLAN 30 | ¤30.00 | 03/10/2023 |
| SURCHARGE FS 533.721 | ¤3.49 | 03/10/2023 |
| SURCHARGE - FS 468.631 | ¤5.24 | 03/10/2023 |
| SW ENG - FOUNDATION SURVEY | ¤20.00 | 03/10/2023 |
| SW ENG INSPECTION 80 | ¤80.00 | 03/10/2023 |
| SW ENG PRE APRON | ¤30.00 | 03/10/2023 |
| WATER- TURN ON | ¤25.00 | 03/10/2023 |
| ADJUSTMENT 50% | (¤544.50) | 03/10/2023 |
| ADMINISTRATIVE RESIDENTIAL | ¤30.00 | 03/10/2023 |
| INSPECTION - RESIDENTIAL | ¤825.00 | 03/10/2023 |
| PLAN REVIEW - RESIDENTIAL | ¤234.00 | 03/10/2023 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤21,914.28 |