Permit #2023020526

Permit Details

Status: COED

Parcel Id: 07-11-31-7031-00420-0020
CONDITIONED SPACE: 2475 sqft
GARAGE: 495 sqft
OPENED PORCH (WITH ROOF) : 265 sqft
OPENED PORCH (WITH ROOF) : 40 sqft
Total Square Footage: 3275 sqft
Block: 00420
Subdivision: 2166 - SECTION 31-ROYAL PALMS
Job Phone: 912-258-2201
Location Address: 54 RICHMOND DR
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 03/03/2023
NOC: RECORDED
Applicant name: JAMES FUCETOLA III
Owner: PALM COAST COMMUNITIES LLC

Address

PO BOX 22547

ST SIMONS, GA 31522

Lot: 0020
Contracted Stated Job Value: ¤235,000.00
Job Description: Single Family Residence
Type: CN

Contractor

PALM COAST COMMUNITIES LLC
Status Location Address State License Number Phone
INACTIVE

PO BOX 22547

PALM COAST, FL 32164

CBC1262878 (Exp: 08/31/2026) 321-501-4617

Sub Contractors

WILLIAM FRANK DUDLEY JR.
Status Location Address State License Number Phone
ACTIVE

P.O. BOX 978

Bunnell, FL 32110

EC0003177 (Exp: 08/31/2026) (386)437-3068
OLEG BELINSKIY
Status Location Address State License Number Phone
ACTIVE

19 PINE CIRCLE DRIVE19

PALM COAST, FL 32167

CCC1325974 (Exp: 08/31/2026) 386-263-7906
GARY LLOYD SHEFFIELD
Status Location Address State License Number Phone
ACTIVE

48 EAGLE LAKES DRIVE

FLAGLER BEACH, FL 32136

CAC048127 (Exp: 08/31/2026) 386-597-3280
JEFFREY TROY SABAKA
Status Location Address State License Number Phone Fax
ACTIVE

2191 DEERWOOD ACRES DR

ST AUGUSTINE, FL 32084

CFC1427439 (Exp: 08/31/2026) 904-838-2218 904-819-0965

Inspection History

Type Request Date Result Inspector
BLD - BUILDING FINAL 10/30/2023 FINAL APPROVED JWALKER
Note: 10/27/2023 - PREVIOUS INSPECTION NOTES
BLD - BUILDING FINAL 10/27/2023 CANCELLED BY APPLICANT JWALKER
U-CROSS CONNECTION 10/25/2023 APPROVED - AS NOTED LFITZGERALD
Note: has potable irrigation with DBL CHECK- no cross connection
ROW - FINAL APRON (AFTER POUR) 10/25/2023 APPROVED FSLADISH
Note: 10/25/23 PIPE IS GOOD. CUTS MADE. CULVERT CLEAR. HOT PATCH COMPLETED. At the time of the inspection all minimum city requirements were met. It is the builders responsibiliy to ensure that nothing changes after this Inspection is approved.
ROW - STORMWATER FINAL 10/25/2023 APPROVED FSLADISH
Note: 10/25/23 EVERYTHING MET CITY STANDARDS AT THE TIME OF THIS INSPECTION. At the time of the inspection all minimum city requirements were met. It is the builders responsibiliy to ensure that nothing changes after this Inspection is approved.
U -UTILITY RESIDENTIAL FINAL 10/25/2023 FINAL APPROVED LFITZGERALD
ROW- FINAL SURVEY/GRADING CERTIFICATION 10/24/2023 APPROVED FSLADISH
ROW FIELD SURVEY /GRADING CERTIFICATION 10/24/2023 APPROVED FSLADISH
Note: 10/24/23 UPON WALKING PROPERTY DETERMINED DRAINAGE WILL WORK AS INDICATED. At the time of the inspection all minimum city requirements were met. It is the builders responsibiliy to ensure that nothing changes after this Inspection is approved.
ROW- PRE-APRON (PRE-POUR) 09/19/2023 APPROVED PFLANAGAN
Note: IT'S YOUR RESPONSIBILITY TO CHECK THE CULVERT PIPE ELEVATIONS BEFORE POURING CONCRETE FOR DRIVEWAY. ALL CONCRETE NEEDS TO BE A MINIMUM OF 3000PSI WITH FIBER OR METAL MESH TO MEET CITY'S STANDARTS. At the time of the inspection all minimum city requirements were met. It is the builders responsibiliy to ensure that nothing changes after this Inspection is approved.
ELECTRIC - EARLY POWER 09/13/2023 APPROVED JWALKER
U - SEWER TIE IN 08/29/2023 APPROVED - AS NOTED MGIBSON
Note: THIS WAS A VIRTUAL INSPECTION
PEP TANK INSTALLATION REQUEST 08/07/2023 APPROVED CBOWERMASTER
INSULATION 08/04/2023 APPROVED JWALKER
Note: Inspector Notes from Inspection 2420 7/27/23 The revision sent in is not what needs to be changed. The floor plan page 2 of the drawing does not show wall details. PAGE 2 will need to be revised and submitted showing which walls are bearing and which walls are non bearing. THIS WILL NEED TO BE COMPLETED BEFORE INSULATION INSPECTION CAN BE PASSED. 7/21/2023 - PREVIOUS INSPECTION NOTES 7/21/23 Still missing revision for bearing walls Listed at the previous Roof brace inspection. On 6/15/2023 1. Have the engineer submitt a revision to the building department showing the locations of all bearing walls on the floor plan. What size post is to be used under the girder trusses at each bearing wall also include type fo anchors to be used to support and hold down the posts. 2. Ledger board fastening detail also needs to be submitted. THE ABOVE LISTED REVISION WILL NEED TO BE SUBMITTED PRIOR TO ALL ROUGH INSPECTION.
ALL ROUGH 07/27/2023 APPROVED - AS NOTED JWALKER
Note: 7/27/23 The revision sent in is not what needs to be changed. The floor plan page 2 of the drawing does not show wall details. PAGE 2 will need to be revised and submitted showing which walls are bearing and which walls are non bearing. THIS WILL NEED TO BE COMPLETED BEFORE INSULATION INSPECTION CAN BE PASSED. 7/21/2023 - PREVIOUS INSPECTION NOTES 7/21/23 Still missing revision for bearing walls Listed at the previous Roof brace inspection. On 6/15/2023 1. Have the engineer submitt a revision to the building department showing the locations of all bearing walls on the floor plan. What size post is to be used under the girder trusses at each bearing wall also include type fo anchors to be used to support and hold down the posts. 2. Ledger board fastening detail also needs to be submitted. THE ABOVE LISTED REVISION WILL NEED TO BE SUBMITTED PRIOR TO ALL ROUGH INSPECTION.
ALL ROUGH 07/21/2023 Disapproved - NO FEE MKRASKI
Note: 7/21/23 Still missing revision for bearing walls, stopped inspection Listed at the previous Roof brace inspection. On 6/15/2023 1. Have the engineer submitt a revision to the building department showing the locations of all bearing walls on the floor plan. What size post is to be used under the girder trusses at each bearing wall also include type fo anchors to be used to support and hold down the posts. 2. Ledger board fastening detail also needs to be submitted. THE ABOVE LISTED REVISION WILL NEED TO BE SUBMITTED PRIOR TO ALL ROUGH INSPECTION.
ROOF SHEATHING / BRACES/TIES/DOWN CELL 07/18/2023 APPROVED - AS NOTED JWALKER
Note: Listed at the previous Roof brace inspection. On 6/15/2023 1. Have the engineer submitt a revision to the building department showing the locations of all bearing walls on the floor plan. What size post is to be used under the girder trusses at each bearing wall also include type fo anchors to be used to support and hold down the posts. 2. Ledger board fastening detail also needs to be submitted. THE ABOVE LISTED REVISION WILL NEED TO BE SUBMITTED PRIOR TO ALL ROUGH INSPECTION.
ROOF SHEATHING / BRACES/TIES/DOWN CELL 07/13/2023 CANCELLED BY APPLICANT WEB
LATH/BRICK/ WATER BARRIER 07/13/2023 APPROVED JWALKER
ROOF SHEATHING / BRACES/TIES/DOWN CELL 07/07/2023 CANCELLED BY APPLICANT WEB
ROOF SHEATHING / BRACES/TIES/DOWN CELL 06/30/2023 CANCELLED BY APPLICANT AWS_IVR
Note: 6/15/2023 - PREVIOUS INSPECTION NOTES 6/15/23 6/15/23 1. Truss T08 missing hold down anchor at the 2x wall. Nail straps at cmu wall. 2. Truss T09 missing hold down achor and 2x wall. Please provide a detail for bearing wall / size of post and requied anchors for both areas of trusses T08 And T09 listed above. 3. Please provide anchoring system for the ledger board at truss T10 4. Trusses T 19, 20,21,and 22 are shown sitting on a bearing wall at mid point of the trusses. Refer to Engineering pages. The wall below is not constructed as a bearing wall. 5. All bearing walls are missing the SP anchors and the tops and bottoms of the studs. 6. Floor plan is not showing locations of bearing wall. Please provide a floor plan show bearing wall locations Inspection stopped. 6/9/2023 - PREVIOUS INSPECTION NOTES 6/9/23 Below listed items have not been corrected. Over framing anchors have not been installed correctly. Straps need to be fastened to trusses below. Not folded onto nailers. 6/9/2023 - PREVIOUS INSPECTION NOTES 6/9/23 Below listed items have not been corrected. Over framing anchors have not been installed correctly. Straps need to be fastened to trusses below. Not folded onto nailers. 6/6/2023 - PREVIOUS INSPECTION NOTES 6/6/23 1.Truss engineering packets onsite however no truss layout drawing onsite or included in the prints. Please provide a truss layout print for reinspection. 2. Garage bearing wall is missing the SP anchors at the top and bottom of the 16" o.c. studs. 3. All over framing is missing hold down anchors. Refer to structual drawings for locations. Walked roof at roof sheating inspection. Roof and wall sheating passed.
ROOF SHEATHING / BRACES/TIES/DOWN CELL 06/15/2023 Disapproved -FEE REQUIRED JWALKER
Note: 6/15/23 6/15/23 1. Truss T08 missing hold down anchor at the 2x wall. Nail straps at cmu wall. 2. Truss T09 missing hold down achor and 2x wall. Please provide a detail for bearing wall / size of post and requied anchors for both areas of trusses T08 And T09 listed above. 3. Please provide anchoring system for the ledger board at truss T10 4. Trusses T 19, 20,21,and 22 are shown sitting on a bearing wall at mid point of the trusses. Refer to Engineering pages. The wall below is not constructed as a bearing wall. 5. All bearing walls are missing the SP anchors and the tops and bottoms of the studs. 6. Floor plan is not showing locations of bearing wall. Please provide a floor plan show bearing wall locations Inspection stopped. 6/9/2023 - PREVIOUS INSPECTION NOTES 6/9/23 Below listed items have not been corrected. Over framing anchors have not been installed correctly. Straps need to be fastened to trusses below. Not folded onto nailers. 6/9/2023 - PREVIOUS INSPECTION NOTES 6/9/23 Below listed items have not been corrected. Over framing anchors have not been installed correctly. Straps need to be fastened to trusses below. Not folded onto nailers. 6/6/2023 - PREVIOUS INSPECTION NOTES 6/6/23 1.Truss engineering packets onsite however no truss layout drawing onsite or included in the prints. Please provide a truss layout print for reinspection. 2. Garage bearing wall is missing the SP anchors at the top and bottom of the 16" o.c. studs. 3. All over framing is missing hold down anchors. Refer to structual drawings for locations. Walked roof at roof sheating inspection. Roof and wall sheating passed.
ROOF SHEATHING / BRACES/TIES/DOWN CELL 06/09/2023 Disapproved -FEE REQUIRED JWALKER
Note: 6/9/23 Below listed items have not been corrected. Over framing anchors have not been installed correctly. Straps need to be fastened to trusses below. Not folded onto nailers. 6/6/2023 - PREVIOUS INSPECTION NOTES 6/6/23 1.Truss engineering packets onsite however no truss layout drawing onsite or included in the prints. Please provide a truss layout print for reinspection. 2. Garage bearing wall is missing the SP anchors at the top and bottom of the 16" o.c. studs. 3. All over framing is missing hold down anchors. Refer to structual drawings for locations. Walked roof at roof sheating inspection. Roof and wall sheating passed.
ROOF VALLEY & METAL 06/07/2023 APPROVED JWALKER
Note: 6/5/2023 - PREVIOUS INSPECTION NOTES 4x4 L metal embedded in roofing cement needs to be installed at the front entry side walls.
ROOF SHEATHING / BRACES/TIES/DOWN CELL 06/06/2023 Disapproved - NO FEE JWALKER
Note: 6/6/23 1.Truss engineering packets onsite however not truss layout drawing onsite or included in the prints. Please provide a truss layout print for reinspection. 2. Garage bearing wall is missing the SP anchors at the top and bottom of the 16" o.c. studs. 3. All over framing is missing hold down anchors. Refer to structual drawings for locations. Walked roof at roof sheating inspection. Roof and wall sheating passed.
ROOF VALLEY & METAL 06/05/2023 Disapproved - NO FEE JWALKER
Note: 4x4 L metal embedded in roofing cement needs to be installed at the front entry side walls.
ROOF SHEATHING 05/26/2023 APPROVED JWALKER
WALL SHEATHING 05/26/2023 APPROVED JWALKER
FOUND SURVEY APPROVED (OFFICE) 05/24/2023 APPROVED TBAKER
TIE BEAM / LINTEL 05/16/2023 APPROVED BTAYLOR
Note: 5/12/2023 - PREVIOUS INSPECTION NOTES Window sills have been installed. 1. ALL down rods at the front entry are to be corrected not just the 4 at the columns. 5/9/23 Below listed corrections have not been made. 5/5/2023 - PREVIOUS INSPECTION NOTES 1. Fornt entry where block work steps up. Pieces of #5 rebar have been dropped into the cells and tied to the dowels giving the appearance of full length continous down rods.. Down rods are to be continous from top off wall to down and over lapped min of 25" and secured in place. 2. Precast window sills have not been installed.
TIE BEAM / LINTEL 05/12/2023 Disapproved -FEE REQUIRED JWALKER
Note: Window sills have been installed. 1. ALL down rods at the front entry are to be corrected not just the 4 at the columns. 5/9/23 Below listed corrections have not been made. 5/5/2023 - PREVIOUS INSPECTION NOTES 1. Fornt entry where block work steps up. Pieces of #5 rebar have been dropped into the cells and tied to the dowels giving the appearance of full length continous down rods.. Down rods are to be continous from top off wall to down and over lapped min of 25" and secured in place. 2. Precast window sills have not been installed.
TIE BEAM / LINTEL 05/09/2023 Disapproved - NO FEE JWALKER
Note: 5/9/23 Below listed corrections have not been made. 5/5/2023 - PREVIOUS INSPECTION NOTES 1. Fornt entry where block work steps up. Pieces of #5 rebar have been dropped into the cells and tied to the dowels giving the appearance of full length continous down rods.. Down rods are to be continous from top off wall to down and over lapped min of 25" and secured in place. 2. Precast window sills have not been installed.
TIE BEAM / LINTEL 05/05/2023 Disapproved -FEE REQUIRED JWALKER
Note: 1. Fornt entry where block work steps up. Pieces of #5 rebar have been dropped into the cells and tied to the dowels giving the appearance of full length continous down rods.. Down rods are to be continous from top off wall to down and over lapped min of 25" and secured in place. 2. Precast window sills have not been installed.
MONOLITHIC SLAB 04/27/2023 APPROVED JWALKER
Note: 4/26/2023 - PREVIOUS INSPECTION NOTES
MONOLITHIC SLAB 04/26/2023 CANCELLED BY APPLICANT JWALKER
GRAVITY SEWER TEST 04/20/2023 APPROVED MGIBSON
Note: 4/19/2023 - PREVIOUS INSPECTION NOTES Sewer line has been covered by soil wash out due to heavy rain.
PLUMBING 1ST ROUGH UNDERGROUND 04/20/2023 APPROVED - AS NOTED MGIBSON
Note: 4/19/2023 - PREVIOUS INSPECTION NOTES Water supply pipe has been covered. Unable to verify pipe size, type. and install. STEEL HEAD PLUMBING INSTALLS SCHEDUAL 40 ASTM STANDARD PIPE FOR WATER MAIN AND ALWAYS BURY'S BEYOND REQUIRED DEPTH
GRAVITY SEWER TEST 04/19/2023 Disapproved - NO FEE JWALKER
Note: Sewer line has been covered by soil wash out due to heavy rain.
PLUMBING 1ST ROUGH UNDERGROUND 04/19/2023 Disapproved - NO FEE JWALKER
Note: Water supply pipe has been covered. Unable to verify pipe size, type. and install.
PLUMBING 1ST ROUGH UNDERGROUND 04/18/2023 CANCELLED BY APPLICANT AWS_IVR
Note: 4/17/2023 - PREVIOUS INSPECTION NOTES NO TEST ON DWV HEAD TEST NOT HOLDING
GRAVITY SEWER TEST 04/18/2023 CANCELLED BY APPLICANT AWS_IVR
Note: 4/17/2023 - PREVIOUS INSPECTION NOTES SEE FIRST ROUGH NOTE
GRAVITY SEWER TEST 04/17/2023 Disapproved - NO FEE MGIBSON
Note: SEE FIRST ROUGH NOTE
PLUMBING 1ST ROUGH UNDERGROUND 04/17/2023 Disapproved -FEE REQUIRED MGIBSON
Note: NO TEST ON DWV HEAD TEST NOT HOLDING
WATER METER INSTALLATION REQUEST 03/23/2023 APPROVED CSTONE

Review History

Department Status Date In Date Out
BADMIN INFORMATION 10/17/2023 10/17/2023
Note: Marked INFORMATION By: MICHELLE RAMOS - (386)986-3780 - MRAMOS@PALMCOASTGOV.COM Termite certificate needed.
BLD COMPLETE 07/28/2023 08/03/2023
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
BLD COMPLETE 07/13/2023 07/17/2023
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
BLD HOLD 07/05/2023 07/07/2023
Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Engineered plan needs to be site specific
ENGIN1 COMPLETE 05/24/2023 05/24/2023
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
ZON COMPLETE 05/24/2023 05/24/2023
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
ELEC COMPLETE 02/21/2023 02/23/2023
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
BLD COMPLETE 02/10/2023 02/15/2023
Note: Released By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM
CUSVC COMPLETE 02/10/2023 02/13/2023
Note: Released By: HALEIGH HAND - -
ELEC HOLD 02/10/2023 02/13/2023
Note: Held By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM 1. Need smoke alarminside and outside of all bedrooms. FRC 2020 314, 315
ENGIN1 COMPLETE 02/10/2023 02/10/2023
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
LOCATE COMPLETE 02/10/2023 02/13/2023
Note: Released By: TONI CHURCHILL - -
MECH COMPLETE 02/10/2023 02/13/2023
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
SW1 COMPLETE 02/10/2023 02/21/2023
Note: Released By: ROBERT GROSS - (386)986-4769 - RGROSS@PALMCOASTGOV.COM
ZON COMPLETE 02/10/2023 02/13/2023
Note: Released By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM
SWALE COMPLETE 02/10/2023 05/12/2023
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
REINSPECTION RESIDENTIAL ¤40.00 10/27/2023
REINSPECTION RESIDENTIAL ¤40.00 10/27/2023
REINSPECTION RESIDENTIAL ¤40.00 10/27/2023
REINSPECTION RESIDENTIAL ¤40.00 10/27/2023
REINSPECTION RESIDENTIAL ¤40.00 10/27/2023
CONNECTION FEES ¤1,166.26 03/03/2023
FIRE IMPACT FEE ADMIN ¤12.62 03/03/2023
FIRE IMPACT FEE ADMIN (¤12.62) 03/03/2023
FC IMPACT FEE EMS ¤62.00 03/03/2023
IMPACT FEE FIRE ¤420.52 03/03/2023
FC IMPACT FEE LAW ENFORCEMENT ¤218.00 03/03/2023
FC IMPACT FEE LIBRARY ¤268.00 03/03/2023
IMPACT FEE PARKS ¤1,769.15 03/03/2023
IMPACT FEE SCHOOL ¤5,450.00 03/03/2023
IMPACT FEE TRANSPORTATION ¤1,812.00 03/03/2023
WATER -IRRIGATION INSPECTION ¤25.00 03/03/2023
PARKS IMPACT FEE ADMIN ¤53.07 03/03/2023
PARKS IMPACT FEE ADMIN (¤53.07) 03/03/2023
SURCHARGE FS 533.721 ¤3.56 03/03/2023
SURCHARGE - FS 468.631 ¤5.34 03/03/2023
SW ENG - FOUNDATION SURVEY ¤20.00 03/03/2023
SW ENG INSPECTION 80 ¤80.00 03/03/2023
SW ENG PRE APRON ¤30.00 03/03/2023
SW ENG - REVIEW 20 ¤20.00 03/03/2023
SW ENG RES REVIEW 200 ¤200.00 03/03/2023
TRANS IMPACT FEE ADMIN ¤54.36 03/03/2023
TRANS IMPACT FEE ADMIN (¤54.36) 03/03/2023
SEWER CREDIT (¤1,342.00) 03/03/2023
SEWER INSPECTION ¤25.00 03/03/2023
SEWER CAPITAL FACILITY ¤5,344.82 03/03/2023
WATER CAPITAL FACILITY FEE ¤3,923.88 03/03/2023
SITE PLAN 30 ¤30.00 03/03/2023
WATER- TURN ON ¤25.00 03/03/2023
ADJUSTMENT 50% (¤556.86) 03/03/2023
ADMINISTRATIVE RESIDENTIAL ¤30.00 03/03/2023
INSPECTION - RESIDENTIAL ¤844.25 03/03/2023
PLAN REVIEW - RESIDENTIAL ¤239.46 03/03/2023
Fees Total Due: ¤0.00 Total Paid: ¤20,313.38