Permit #2023040893
Permit Details
Status: FINAL
| Parcel Id: 07-11-31-7032-00590-0100 |
| Block: 00590 |
| Subdivision: 2155 - SECTION 32-ROYAL PALMS |
| Job Phone: 386-236-9610 |
| Location Address: 8 ROCKNE LN |
| Type: PO - POOL |
| Issue Date: 05/10/2023 |
| NOC: RECORDED |
| Applicant name: SAMANTHA JESSICA ALEXANDER |
| Owner: DENNING MARLO F & MICHAEL W W&H |
|
Address 8 ROCKNE LN PALM COAST, FL 32164 |
| Lot: 0100 |
| Contracted Stated Job Value: ¤77,000.00 |
| Job Description: SWIMMING POOL (EXISTING FENCE) |
| Type: CN |
Contractor
AGUA POOLS AND SPA INC
| Status | Location Address | State License Number | Phone |
| ACTIVE |
3438 LONGLEAF ROAD , |
CPC1459907 (Exp: 08/31/2026) | 386-492-6910 |
Sub Contractors
CHARLES K DAVIS
| Status | Location Address | State License Number | Phone |
| INACTIVE |
1410 RIDGEWOOD AVE HOLLY HILL, FL 32117 |
EC13011552 (Exp: 08/31/2026) | 386-236-9610 |
Inspection History
| Type | Request Date | Result | Inspector |
| POOL FINAL | 04/17/2024 | FINAL APPROVED | AGAETANO |
| Note: 4/16/2024 - PREVIOUS INSPECTION NOTES 2/8/2024 - PREVIOUS INSPECTION NOTES 1. Vacuum guage not installed at the pool pump for TDH test. 2. Fence barrier is to be a minimum of 48" off of the grade.. 3. Clearance under the left side gate/ barrier can be no more that 2" from the grade to the bottom of the gate. 4. The sreen door latch at the lania is to be a minimum of 54" to the latch. 5. Interior alarm for the pool guard type alarm not installed. 04-16-2024 Above issue has not been resolved. Clearance under the left side gate/ barrier can be no more that 2" from the grade to the bottom of the gate. Sod needs to be placed under gate. | |||
| POOL FINAL | 04/16/2024 | Disapproved - NO FEE | AGAETANO |
| Note: 2/8/2024 - PREVIOUS INSPECTION NOTES 1. Vacuum guage not installed at the pool pump for TDH test. 2. Fence barrier is to be a minimum of 48" off of the grade.. 3. Clearance under the left side gate/ barrier can be no more that 2" from the grade to the bottom of the gate. 4. The sreen door latch at the lania is to be a minimum of 54" to the latch. 5. Interior alarm for the pool guard type alarm not installed. 04-16-2024 Above issue has not been resolved. Clearance under the left side gate/ barrier can be no more that 2" from the grade to the bottom of the gate. Sod needs to be placed under gate. Piling up dirt into a mound is not considered the grade. | |||
| POOL FINAL | 02/08/2024 | Disapproved - NO FEE | JWALKER |
| Note: 1. Vacuum guage not installed at the pool pump for TDH test. 2. Fence barrier is to be a minimum of 48" off of the grade..From the side facing away from the pool. 3. Clearance under the left side gate/ barrier can be no more that 2" from the grade to the bottom of the gate. 4. The sreen door latch at the lania is to be a minimum of 54" to the latch. 5. Interior alarm for the pool guard type alarm not installed. | |||
| POOL FINAL | 02/07/2024 | CANCELLED BY APPLICANT | JWALKER |
| U -UTILITY RESIDENTIAL FINAL | 02/06/2024 | FINAL APPROVED | LFITZGERALD |
| ROW FIELD SURVEY /GRADING CERTIFICATION | 02/05/2024 | APPROVED | PFLANAGAN |
| Note: MEET WITH MIKE AND HOMEOWNER AND HOMEOWNER THEY ARE NOT HAVING ANY STANDING WATER IN THE LOW AREAS AND WITH LAST NIGHT RAIN NO WATER TODAY ---------------------------------------------------------------------------------- 1/26/2024 - PREVIOUS INSPECTION NOTES THE FIELD INSPECTION SHOWS WATER WILL SIT IN BACK LEFT OF BACKYARD AND ALL WATER IS IMPACTING THE LOT BEHIND THIS LOT. NEED TO FIX ALL AREAS | |||
| ROW - FINAL INSPECTION | 02/05/2024 | APPROVED | PFLANAGAN |
| Note: At the time of the inspection all minimum city requirements were met. It is the builders responsibiliy to ensure that nothing changes after this Inspection is approved. | |||
| ROW- PROJECT STATUS | 02/05/2024 | APPROVED | PFLANAGAN |
| Note: MEETING WITH MIKE FOR DRAINAGE OF BACK YARD 1PM | |||
| ROW- FINAL SURVEY/GRADING CERTIFICATION | 01/26/2024 | APPROVED | PFLANAGAN |
| Note: SURVEY SHOWS THE WATER WILL NOT IMPACT THE ADJACENT LOTS NOW ------------------------------------------------------------------------------ 11/27/2023 - PREVIOUS INSPECTION NOTES THE FINAL SURVEY DOESN'T SHOW LOW AREAS IN THE BACK RIGHT BY THE SHED AND LEFT BACK CORNER OF THE LOT NEED TO FIX GRADING SO WATER WILL NOT SIT IN THOSE AREAS AND DON'T IMPACT THE ADJACENT LOT BRHIND IT. WHEN BUILDING A POOL ALL GRADING NEEDS TO BE UP TO ALL CITY'S STANDARDS FOR THE GRADING. | |||
| ROW FIELD SURVEY /GRADING CERTIFICATION | 01/26/2024 | Disapproved - NO FEE | PFLANAGAN |
| Note: THE FIELD INSPECTION SHOWS WATER WILL SIT IN BACK LEFT OF BACKYARD AND ALL WATER IS IMPACTING THE LOT BEHIND THIS LOT. NEED TO FIX ALL AREAS | |||
| ROW- FINAL SURVEY/GRADING CERTIFICATION | 11/27/2023 | Disapproved - NO FEE | PFLANAGAN |
| Note: THE FINAL SURVEY DOESN'T SHOW LOW AREAS IN THE BACK RIGHT BY THE SHED AND LEFT BACK CORNER OF THE LOT NEED TO FIX GRADING SO WATER WILL NOT SIT IN THOSE AREAS AND DON'T IMPACT THE ADJACENT LOT BRHIND IT. WHEN BUILDING A POOL ALL GRADING NEEDS TO BE UP TO ALL CITY'S STANDARDS FOR THE GRADING. | |||
| ELECTRIC AND ALARM | 08/24/2023 | APPROVED | JWALKER |
| POOL DECK | 08/02/2023 | APPROVED | MKRASKI |
| POOL DECK | 08/01/2023 | Disapproved - NO FEE | JWALKER |
| Note: Slab area needs to be tamped down | |||
| POOL DECK | 07/31/2023 | CANCELLED BY APPLICANT | WEB |
| STEEL AND GROUND | 07/06/2023 | APPROVED | JWALKER |
| Note: 7/5/2023 - PREVIOUS INSPECTION NOTES 1. Clean all soil wash outs rebar is to have 3" ground clearance 2. Plumbing line pressure gauge at the spa area is not operating when valve was open gauged did not move. Line not filled. | |||
| STEEL AND GROUND | 07/05/2023 | Disapproved - NO FEE | JWALKER |
| Note: 1. Clean all soil wash outs rebar is to have 3" ground clearance 2. Plumbing line pressure gauge at the spa area is not operating when valve was open gauged did not move. Line not filled. |
Review History
| Department | Status | Date In | Date Out |
| BLD | COMPLETE | 05/31/2023 | 06/01/2023 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| SW1 | COMPLETE | 05/31/2023 | 06/08/2023 |
| Note: Released By: ROBERT GROSS - (386)986-4769 - RGROSS@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 05/31/2023 | 05/31/2023 |
| Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM | |||
| SW1 | COMPLETE | 05/04/2023 | 05/09/2023 |
| Note: Released By: PARREN FLANAGAN - (386)986-2392 - PFLANAGAN@PALMCOASTGOV.COM | |||
| SW1 | HOLD | 04/27/2023 | 05/04/2023 |
| Note: Held By: PARREN FLANAGAN - (386)986-2392 - PFLANAGAN@PALMCOASTGOV.COM CAN NOT DRAIN WATER TO THE BACK ALL DRAINAGE NEED TO GO FROM BACK TO THE FRONT ROAD SIDE SWALE | |||
| ZON | COMPLETE | 04/27/2023 | 04/27/2023 |
| Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 04/18/2023 | 04/20/2023 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| ELEC | COMPLETE | 04/18/2023 | 04/20/2023 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| MECH | COMPLETE | 04/18/2023 | 04/19/2023 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| SW1 | HOLD | 04/18/2023 | 04/25/2023 |
| Note: Held By: FRANK SLADISH - - FSLADISH@PALMCOASTGOV.COM Lot drainage features and patterns must be clearly depicted and include flow arrows. | |||
| ZON | COMPLETE | 04/18/2023 | 04/19/2023 |
| Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| SW ENG REINSPECTION 20 | ¤20.00 | 02/06/2024 |
| SW ENG - REVIEW 20 | ¤20.00 | 05/10/2023 |
| SITE PLAN 30 | ¤30.00 | 05/10/2023 |
| ADJUSTMENT 50% | (¤127.50) | 05/10/2023 |
| ADMINISTRATIVE RESIDENTIAL | ¤30.00 | 05/10/2023 |
| INSPECTION- POOL | ¤160.00 | 05/10/2023 |
| PLAN REVIEW - RESIDENTIAL | ¤65.00 | 05/10/2023 |
| SURCHARGE FS 533.721 | ¤2.00 | 05/10/2023 |
| SURCHARGE - FS 468.631 | ¤2.00 | 05/10/2023 |
| SW ENG INSPECTION 40 | ¤40.00 | 05/10/2023 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤241.50 |