I want to search for...
Permit #2023060491
Permit Details
Status: COED
| Parcel Id: 07-11-31-7024-00260-0320 |
| CONDITIONED SPACE: 1600 sqft |
| GARAGE: 394 sqft |
| OPENED PORCH (WITH ROOF) : 170 sqft |
| Total Square Footage: 2164 sqft |
| Block: 00260 |
| Subdivision: 2167 - SECTION 24-PINE GROVE |
| Job Phone: 386-445-9009 |
| Location Address: 85 PRINCETON LN |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 06/21/2023 |
| NOC: RECORDED |
| Applicant name: BRIAN ANDREW GAZZOLI |
| Owner: SEAGATE HOMES LLC |
|
Address SUITE 7 PALM COAST, FL 32164 |
|
Address 185 CYPRESS POINT PKWY PALM COAST, FL 32164 |
| Lot: 0320 |
| Contracted Stated Job Value: ¤300,000.00 |
| Job Description: Single Family Residence |
| Type: CN |
Contractor
SEAGATE HOMES, LLC
| Status | Location Address | Mailing Address | State License Number | Phone |
| ACTIVE |
185 CYPRESS POINT PARKWAY Palm Coast, FL 32137 |
SUITE 7 Palm Coast, FL 32137 |
CGC1518372 (Exp: 08/31/2026) | 386-246-6132 |
Sub Contractors
RICHARD H SIMMONS JR
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
PO BOX 1963 BUNNELL, FL 32110 |
ES12001217 (Exp: 08/31/2026) | 386-437-0607 | 386-437-1847 |
JONATHAN M PEARSON
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
209 N FORSYTH ST BUNNELL, FL 32110 |
CFC1425941 (Exp: 08/31/2026) | 386-597-0944 | 386-437-4996 |
CHAD DAVID GRESSANI
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
2640 BROOKSHIRE CIRCLE MELBOURNE, FL 32904 |
CCC1327235 (Exp: 08/31/2026) | 321-288-6415 | 321-729-8997 |
GARY LLOYD SHEFFIELD
| Status | Location Address | State License Number | Phone |
| ACTIVE |
48 EAGLE LAKES DRIVE FLAGLER BEACH, FL 32136 |
CAC048127 (Exp: 08/31/2026) | 386-597-3280 |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 02/06/2024 | FINAL APPROVED | MKRASKI |
| U -UTILITY RESIDENTIAL FINAL | 02/05/2024 | FINAL APPROVED | LFITZGERALD |
| Note: Inspector Notes from Inspection 9035 has potable irr with PVB -NO CROSS CONNECTION Inspector Notes from Inspection 9035 has potable irr with PVB -NO CROSS CONNECTION | |||
| BLD - BUILDING FINAL | 02/05/2024 | Disapproved - NO FEE | JSTEWART |
| Note: 2/5/24- All Doors are Locked, unable to complete inspection. 2/1/2024 - PREVIOUS INSPECTION NOTES 2/1/24- via phone | |||
| BLD - BUILDING FINAL | 02/01/2024 | CANCELLED BY APPLICANT | JSTEWART |
| Note: 2/1/24- via phone | |||
| ROW - STORMWATER FINAL | 01/31/2024 | APPROVED - AS NOTED | PFLANAGAN |
| Note: TALK TO DR JR. ABOUT THE DAMAGE ACROSSED THE STREET THERE IS A NEW CONSTRUCYION HOUSE BEING BUILT AND THERE ARE CAUSEING THE DAMAGE PASSING AS NOTED THAT THIS IS ON THE NEW BUILDER ACROSSED THE STREET | |||
| U-CROSS CONNECTION | 01/31/2024 | APPROVED - AS NOTED | LFITZGERALD |
| Note: has potable irr with PVB -NO CROSS CONNECTION | |||
| ROW - FINAL APRON (AFTER POUR) | 01/31/2024 | APPROVED | PFLANAGAN |
| Note: At the time of the inspection all minimum city requirements were met. It is the builders responsibiliy to ensure that nothing changes after this Inspection is approved. | |||
| ROW- FINAL SURVEY/GRADING CERTIFICATION | 01/30/2024 | APPROVED | FSLADISH |
| Note: Inspector Notes from Inspection 9270 12/28/23 PIPE IS GOOD. READY TO POUR AT THE TIME OF THIS INSPECTION. AT THE TIME OF THE INSPECTION CULVERT PIPE IS GOOD IS READY TO POUR, IF RAIN PLEASE, BUILDER SHOULD DOUBLE CHECK CULVERT ELEVATIONS MAKE SURE IS 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE (FRC) DRAWING 300,E RESIDENTIAL CULVERT DETAIL BEFORE POURING. At the time of the inspection all minimum city requirements were met. It is the builders responsibiliy to ensure that nothing changes after this Inspection is approved. This includes but is not limited to, the Culvert Pipe Elevation from the time of the inspection approval to the concrete pour. | |||
| ROW FIELD SURVEY /GRADING CERTIFICATION | 01/30/2024 | APPROVED - AS NOTED | FSLADISH |
| Note: 1/30/24 UPON WALKING PROPERTY DETERMINED DRAINAGE WILL WORK AS INDICATED ON SURVEY. . At the time of the inspection all minimum city requirements were met. It is the builders responsibiliy to ensure that nothing changes after this Inspection is approved. | |||
| ROW- PRE-APRON (PRE-POUR) | 12/28/2023 | APPROVED - AS NOTED | FSLADISH |
| Note: 12/28/23 PIPE IS GOOD. READY TO POUR AT THE TIME OF THIS INSPECTION. AT THE TIME OF THE INSPECTION CULVERT PIPE IS GOOD IS READY TO POUR, IF RAIN PLEASE, BUILDER SHOULD DOUBLE CHECK CULVERT ELEVATIONS MAKE SURE IS 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE (FRC) DRAWING 300,E RESIDENTIAL CULVERT DETAIL BEFORE POURING. At the time of the inspection all minimum city requirements were met. It is the builders responsibiliy to ensure that nothing changes after this Inspection is approved. This includes but is not limited to, the Culvert Pipe Elevation from the time of the inspection approval to the concrete pour. | |||
| ELECTRIC - EARLY POWER | 12/19/2023 | APPROVED - AS NOTED | KSANDOE |
| Note: Emailed FPL @ 1129. Release Power 12/18/2023 - PREVIOUS INSPECTION NOTES | |||
| ELECTRIC - EARLY POWER | 12/18/2023 | CANCELLED BY APPLICANT | KSANDOE |
| GRAVITY SEWER TEST | 12/08/2023 | APPROVED - AS NOTED | MGIBSON |
| Note: Inspector Notes from Inspection 2060 NEED ADDRESS POSTED WHERE IT CAN BE SEEN VISIBILY.. THIS WAS A VIRTUAL INSPECTION | |||
| U - SEWER TIE IN | 12/08/2023 | APPROVED - AS NOTED | MGIBSON |
| Note: Inspector Notes from Inspection 2060 NEED ADDRESS POSTED WHERE IT CAN BE SEEN VISIBILY. U-SEWR CONNECTION WAS MADE BY UTILITIES OR ANOTHER PLUMBING CONTRACTOR | |||
| LATH/BRICK/ WATER BARRIER | 10/27/2023 | APPROVED | KSANDOE |
| INSULATION | 10/19/2023 | APPROVED | KSANDOE |
| Note: Inspector Notes from Inspection 2420 1. Slab needs to be sealed @ floor box 2. Double window in "cafe" has anchor that has been screwed all the way past window frame, front double window missing anchors (behind head pressure pipe) Check on next inspection | |||
| ALL ROUGH | 10/16/2023 | APPROVED - AS NOTED | MKRASKI |
| Note: 1. Slab needs to be sealed @ floor box 2. Double window in "cafe" has anchor that has been screwed all the way past window frame, front double window missing anchors (behind head pressure pipe) Check on next inspection | |||
| ROOF VALLEY & METAL | 10/09/2023 | APPROVED | KSANDOE |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 10/06/2023 | APPROVED | KSANDOE |
| Note: 10/4/2023 - PREVIOUS INSPECTION NOTES | |||
| WALL SHEATHING | 10/04/2023 | APPROVED | KSANDOE |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 10/04/2023 | CANCELLED BY APPLICANT | KSANDOE |
| FOUND SURVEY APPROVED (OFFICE) | 09/20/2023 | APPROVED | TBAKER |
| TIE BEAM / LINTEL | 09/14/2023 | APPROVED | KSANDOE |
| Note: 9/13/2023 - PREVIOUS INSPECTION NOTES Dowels that have been drilled and filled with grout need to be cleaned out and filled with an approved epoxy. Inspector Notes from Inspection 2250 At the time of inspection, minimum requirements for monolithic slab have been met | |||
| TIE BEAM / LINTEL | 09/13/2023 | Disapproved -FEE REQUIRED | KSANDOE |
| Note: Dowels that have been drilled and filled with grout need to be cleaned out and filled with an approved epoxy. Inspector Notes from Inspection 2250 At the time of inspection, minimum requirements for monolithic slab have been met | |||
| MONOLITHIC SLAB | 08/28/2023 | APPROVED - AS NOTED | KSANDOE |
| Note: At the time of inspection, minimum requirements for monolithic slab have been met | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 08/22/2023 | APPROVED - AS NOTED | MGIBSON |
| Note: NEED ADDRESS POSTED WHERE IT CAN BE SEEN VISIBILY | |||
| WATER METER INSTALLATION REQUEST | 07/28/2023 | APPROVED | CBOWERMASTER |
Review History
| Department | Status | Date In | Date Out |
| ENGIN1 | COMPLETE | 09/20/2023 | 09/20/2023 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 09/20/2023 | 09/20/2023 |
| Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 06/12/2023 | 06/14/2023 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| CUSVC | COMPLETE | 06/12/2023 | 06/13/2023 |
| Note: Released By: HALEIGH HAND - - HHAND@PALMCOASTGOV.COM | |||
| ELEC | COMPLETE | 06/12/2023 | 06/12/2023 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 06/12/2023 | 06/12/2023 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| GAS | CANCEL | 06/12/2023 | 06/12/2023 |
| LOCATE | COMPLETE | 06/12/2023 | 06/14/2023 |
| Note: Released By: CANDACE STONE - (386)986-2539 - CSTONE@PALMCOASTGOV.COM | |||
| MECH | COMPLETE | 06/12/2023 | 06/13/2023 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| SW1 | COMPLETE | 06/12/2023 | 06/20/2023 |
| Note: Released By: GABRIEL BERTOLA - (386)986-7660 - GBERTOLA@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 06/12/2023 | 06/12/2023 |
| Note: Released By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM | |||
| SWALE | COMPLETE | 06/12/2023 | 07/24/2023 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION RESIDENTIAL | ¤40.00 | 02/06/2024 |
| CONNECTION FEES | ¤1,166.26 | 06/21/2023 |
| FIRE IMPACT FEE ADMIN | ¤12.62 | 06/21/2023 |
| FIRE IMPACT FEE ADMIN | (¤12.62) | 06/21/2023 |
| FC IMPACT FEE EMS | ¤62.00 | 06/21/2023 |
| IMPACT FEE FIRE | ¤420.52 | 06/21/2023 |
| FC IMPACT FEE LAW ENFORCEMENT | ¤218.00 | 06/21/2023 |
| FC IMPACT FEE LIBRARY | ¤268.00 | 06/21/2023 |
| IMPACT FEE PARKS | ¤1,769.15 | 06/21/2023 |
| IMPACT FEE SCHOOL | ¤5,450.00 | 06/21/2023 |
| IMPACT FEE TRANSPORTATION | ¤1,812.00 | 06/21/2023 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 06/21/2023 |
| PARKS IMPACT FEE ADMIN | ¤53.07 | 06/21/2023 |
| PARKS IMPACT FEE ADMIN | (¤53.07) | 06/21/2023 |
| SURCHARGE FS 533.721 | ¤5.45 | 06/21/2023 |
| SURCHARGE - FS 468.631 | ¤8.17 | 06/21/2023 |
| SW ENG - FOUNDATION SURVEY | ¤20.00 | 06/21/2023 |
| SW ENG INSPECTION 80 | ¤80.00 | 06/21/2023 |
| SW ENG PRE APRON | ¤30.00 | 06/21/2023 |
| SW ENG - REVIEW 20 | ¤20.00 | 06/21/2023 |
| SW ENG RES REVIEW 200 | ¤200.00 | 06/21/2023 |
| TRANS IMPACT FEE ADMIN | ¤54.36 | 06/21/2023 |
| TRANS IMPACT FEE ADMIN | (¤54.36) | 06/21/2023 |
| SEWER CREDIT | (¤1,147.00) | 06/21/2023 |
| SEWER INSPECTION | ¤25.00 | 06/21/2023 |
| SEWER CAPITAL FACILITY | ¤5,344.82 | 06/21/2023 |
| WATER CAPITAL FACILITY FEE | ¤3,923.88 | 06/21/2023 |
| SITE PLAN 30 | ¤30.00 | 06/21/2023 |
| WATER- TURN ON | ¤25.00 | 06/21/2023 |
| ADJUSTMENT 50% | (¤544.50) | 06/21/2023 |
| ADMINISTRATIVE RESIDENTIAL | ¤30.00 | 06/21/2023 |
| INSPECTION - RESIDENTIAL | ¤825.00 | 06/21/2023 |
| PLAN REVIEW - RESIDENTIAL | ¤234.00 | 06/21/2023 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤20,340.75 |