I want to search for...
Permit #2023060755
Permit Details
Status: COED
| Parcel Id: 28-10-30-5415-00000-1130 |
| CONDITIONED SPACE: 2115 sqft |
| GARAGE: 557 sqft |
| OPENED PORCH (WITH ROOF) : 54 sqft |
| SCREEN PORCH (SOLID ROOF) : 162 sqft |
| Total Square Footage: 2888 sqft |
| Subdivision: 2310 - SAWMILL BRANCH 2A |
| Job Phone: 904-219-3385 |
| Location Address: 15 SAWMILL CT |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 07/19/2023 |
| NOC: RECORDED |
| Applicant name: RAYMOND CLIVE CROSBY |
| Owner: D R HORTON INC |
|
Address 4220 RACE TRACK ROAD SAINT JOHNS, FL 32259 |
| Lot: 113 |
| Contracted Stated Job Value: ¤211,500.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
DR HORTON, INC.
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
4220 RACE TRACK RD SAINT JOHNS, FL 32259 |
CBC058997 (Exp: 08/31/2026) | 904-268-2845 | 904-899-5992 |
Sub Contractors
PAUL ERIC FORSTER
| Status | Location Address | State License Number | Phone |
| ACTIVE |
6114 GOODMAN RD JACKSONVILLE, FL 32244 |
CFC1429261 (Exp: 08/31/2026) | 904-647-1820 |
EDWARD DOUGLAS TENNANT
| Status | Location Address | State License Number | Phone | Fax |
| INACTIVE |
3370 AGRICULTURAL CENTER DRIVE ST. AUGUSTINE , FL 32092 |
CAC1813372 (Exp: 08/31/2026) | (904)829-8898 | (904)829-6587 |
DANA SUE COOLEY
| Status | Location Address | State License Number | Phone |
| INACTIVE |
PO BOX 1718 FLAGLER BEACH, FL 32136 |
CCC1333449 (Exp: 08/31/2026) | 904-535-1680 |
JAMES M GREENSLADE
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
311 S BAY ST BUNNELL, FL 32110 |
EC13006083 (Exp: 08/31/2026) | 386-263-2960 | 386-263-2980 |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 02/09/2024 | FINAL APPROVED | KSANDOE |
| ROW - FINAL APRON (AFTER POUR) | 02/09/2024 | APPROVED | TPOLACEK |
| Note: 02/09/24 CONCRETE IS GOOD CUTS ARE MADE NO CRACKS AT THE TIME FROM THE TIME OF THE INSPECTION OF THE INSPECTION, ALL MINIMUM CITY REQUIREMENTS WERE MET. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED | |||
| ROW - STORMWATER FINAL | 02/09/2024 | APPROVED | TPOLACEK |
| Note: 02/09/24 AT THE TIME FROM THE TIME OF THE INSPECTION OF THE INSPECTION, ALL MINIMUM CITY REQUIREMENTS WERE MET. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED | |||
| U -UTILITY RESIDENTIAL FINAL | 02/09/2024 | FINAL APPROVED | DHANEY |
| ROW- FINAL SURVEY/GRADING CERTIFICATION | 02/07/2024 | APPROVED | EMADISON |
| ROW FIELD SURVEY /GRADING CERTIFICATION | 02/07/2024 | APPROVED | EMADISON |
| U-CROSS CONNECTION | 02/07/2024 | APPROVED | DHANEY |
| ELECTRIC - EARLY POWER | 01/24/2024 | APPROVED | JSTEWART |
| Note: Inspector Notes from Inspection 2200 11/29/23: FPL emailed at @ 14:45. | |||
| ROW- PRE-APRON (PRE-POUR) | 01/22/2024 | APPROVED - AS NOTED | TPOLACEK |
| Note: 01/22/24 CORRECTIONS MADE READY TO POUR. MAKE SURE IS 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE (FRC) DRAWING 300,E RESIDENTIAL ____________________________________________________________________________________________________________________ 1/19/2024 - PREVIOUS INSPECTION NOTES 01/19/24 12:53 PM RETURNED TO REINSPECT. LEFT SIDE OF APRON NEEDS TO HAVE A WING FROM 5' BACK TO 36" LEFT OF EDGE AS DISCUSSED. | |||
| ROW- PRE-APRON (PRE-POUR) | 01/19/2024 | Disapproved - NO FEE | TPOLACEK |
| Note: 01/19/24 12:53 PM RETURNED TO REINSPECT. LEFT SIDE OF APRON NEEDS TO HAVE A WING FROM 5' BACK TO 36" LEFT OF EDGE AS DISCUSSED. | |||
| GRAVITY SEWER TEST | 12/29/2023 | APPROVED - AS NOTED | MGIBSON |
| Note: THIS WAS A VIRTUAL INSPECTION | |||
| U - SEWER TIE IN | 12/29/2023 | APPROVED - AS NOTED | MGIBSON |
| Note: THIS WAS A VIRTUAL INSPECTION | |||
| INSULATION | 12/18/2023 | APPROVED | JSTEWART |
| Note: Inspector Notes from Inspection 2420 12/12/23: Check at Insulation Inspection. * Owners suite: Smoke detector is too close to supply register & in direct path. (NFPA72 - 29.8.3.4(6)). * Guest bathroom exhaust fan duct needs to be supported at 4ft intervals. Please add straps. 11/28/23: Check at All Rough Inspection. * 2ply truss T01 (back) needs nails at 4"OC on highlighted webs as required by MiTek in web connections. | |||
| LATH/BRICK/ WATER BARRIER | 12/12/2023 | APPROVED | RSIMS |
| ALL ROUGH | 12/12/2023 | APPROVED - AS NOTED | RSIMS |
| Note: 12/12/23: Check at Insulation Inspection. * Owners suite: Smoke detector is too close to supply register & in direct path. (NFPA72 - 29.8.3.4(6)). * Guest bathroom exhaust fan duct needs to be supported at 4ft intervals. Please add straps. 11/28/23: Check at All Rough Inspection. * 2ply truss T01 (back) needs nails at 4"OC on highlighted webs as required by MiTek in web connections. | |||
| ROOF VALLEY & METAL | 12/04/2023 | APPROVED | RSIMS |
| Note: Inspector Notes from Inspection 2460 11/28/23: Check at All Rough Inspection. * 2ply truss T01 (back) needs nails at 4"OC on highlighted webs as required by MiTek in web connections. | |||
| ELECTRIC-TUG | 11/29/2023 | APPROVED - AS NOTED | RSIMS |
| Note: 11/29/23: FPL emailed at @ 14:45. | |||
| WALL SHEATHING | 11/28/2023 | APPROVED | RSIMS |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 11/28/2023 | APPROVED - AS NOTED | RSIMS |
| Note: 11/28/23: Check at All Rough Inspection. * 2ply truss T01 (back) needs nails at 4"OC on highlighted webs as required by MiTek in web connections. | |||
| FOUND SURVEY APPROVED (OFFICE) | 11/27/2023 | APPROVED | TBAKER |
| MONOLITHIC SLAB | 09/21/2023 | APPROVED | JSTEWART |
| PLUMBING 1ST ROUGH UNDERGROUND | 09/12/2023 | APPROVED | MGIBSON |
| WATER METER INSTALLATION REQUEST | 07/24/2023 | APPROVED | CBOWERMASTER |
Review History
| Department | Status | Date In | Date Out |
| ZON | COMPLETE | 11/22/2023 | 11/22/2023 |
| Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 11/22/2023 | 11/27/2023 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 11/12/2023 | 11/14/2023 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| ZON | HOLD | 11/12/2023 | 11/13/2023 |
| Note: Held By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM Rear lanai appears to be encroaching in required 5' side setback | |||
| ZON | COMPLETE | 07/10/2023 | 07/10/2023 |
| Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM | |||
| MECH | COMPLETE | 07/10/2023 | 07/11/2023 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 07/10/2023 | 07/11/2023 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| SW1 | COMPLETE | 07/10/2023 | 07/18/2023 |
| Note: Released By: GABRIEL BERTOLA - (386)986-7660 - GBERTOLA@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 06/15/2023 | 06/16/2023 |
| Note: Released By: JPI | |||
| CUSVC | COMPLETE | 06/15/2023 | 06/15/2023 |
| Note: Released By: HALEIGH HAND - - HHAND@PALMCOASTGOV.COM | |||
| ELEC | COMPLETE | 06/15/2023 | 06/20/2023 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 06/15/2023 | 06/15/2023 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| GAS | CANCEL | 06/15/2023 | 06/20/2023 |
| LOCATE | COMPLETE | 06/15/2023 | 06/20/2023 |
| Note: Released By: CANDACE STONE - (386)986-2539 - CSTONE@PALMCOASTGOV.COM | |||
| MECH | HOLD | 06/15/2023 | 06/20/2023 |
| Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Direction house faces on Heatload does not match the site plan. Revise to match per R405.4.2.1 FBC Energy Conservation 2020 7Th Edition | |||
| SW1 | COMPLETE | 06/15/2023 | 06/22/2023 |
| Note: Released By: PARREN FLANAGAN - (386)986-2392 - PFLANAGAN@PALMCOASTGOV.COM | |||
| ZON | HOLD | 06/15/2023 | 06/15/2023 |
| Note: Held By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM AC pad cannot be located in the 20ft drainage easement | |||
| BADMIN | COMPLETE | 06/15/2023 | 06/20/2023 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| URB | COMPLETE | 06/15/2023 | 06/16/2023 |
| Note: Released By: JOHN BEAUDET - (386)986-2456 - JBEAUDET@PALMCOASTGOV.COM |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| WATER-METER | ¤505.39 | 07/19/2023 |
| WATER-METER | ¤419.86 | 07/19/2023 |
| ADJUSTMENT 50% | (¤484.49) | 07/19/2023 |
| ADMINISTRATIVE RESIDENTIAL | ¤30.00 | 07/19/2023 |
| INSPECTION - RESIDENTIAL | ¤731.50 | 07/19/2023 |
| PLAN REVIEW - RESIDENTIAL | ¤207.48 | 07/19/2023 |
| CONNECTION FEES | ¤25.00 | 07/19/2023 |
| FIRE IMPACT FEE ADMIN | ¤12.62 | 07/19/2023 |
| FIRE IMPACT FEE ADMIN | (¤12.62) | 07/19/2023 |
| FC IMPACT FEE EMS | ¤62.00 | 07/19/2023 |
| IMPACT FEE FIRE | ¤420.52 | 07/19/2023 |
| FC IMPACT FEE LAW ENFORCEMENT | ¤218.00 | 07/19/2023 |
| FC IMPACT FEE LIBRARY | ¤268.00 | 07/19/2023 |
| IMPACT FEE PARKS | ¤1,769.15 | 07/19/2023 |
| IMPACT FEE SCHOOL | ¤5,450.00 | 07/19/2023 |
| IMPACT FEE TRANSPORTATION | ¤3,311.00 | 07/19/2023 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 07/19/2023 |
| PARKS IMPACT FEE ADMIN | ¤53.07 | 07/19/2023 |
| PARKS IMPACT FEE ADMIN | (¤53.07) | 07/19/2023 |
| SURCHARGE FS 533.721 | ¤4.84 | 07/19/2023 |
| SURCHARGE - FS 468.631 | ¤7.27 | 07/19/2023 |
| SW ENG - FOUNDATION SURVEY | ¤20.00 | 07/19/2023 |
| SW ENG INSPECTION 80 | ¤80.00 | 07/19/2023 |
| SW ENG PRE APRON | ¤30.00 | 07/19/2023 |
| SW ENG - REVIEW 20 | ¤20.00 | 07/19/2023 |
| SW ENG RES REVIEW 200 | ¤200.00 | 07/19/2023 |
| TRANS IMPACT FEE ADMIN | ¤99.33 | 07/19/2023 |
| TRANS IMPACT FEE ADMIN | (¤99.33) | 07/19/2023 |
| SEWER INSPECTION | ¤25.00 | 07/19/2023 |
| SEWER CAPITAL FACILITY | ¤2,803.23 | 07/19/2023 |
| WATER CAPITAL FACILITY FEE | ¤2,605.24 | 07/19/2023 |
| SITE PLAN 30 | ¤30.00 | 07/19/2023 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤18,783.99 |