Permit #2023070606

Permit Details

Status: FINAL

Parcel Id: 07-11-31-7034-00870-0060
Block: 00870
Subdivision: 2165 - SECTION 34-EASTHAMPTON
Job Phone: 386-931-6577
Location Address: 32 ERIC DR
Type: BA - BUILDING ADDITION
Issue Date: 07/14/2023
NOC: RECORDED
Applicant name: LUIS JORGE MEDEIROS
Owner: MOODY MICHAEL W & PATRICIA W H & W

Address

32 ERIC DR

PALM COAST, FL 32164

Lot: 0060
Contracted Stated Job Value: ¤50,500.00
Job Description: GARAGE ADDITION 2022050216
Type: CN
Original Permit #: 2022050216

Contractor

A PLUS HOME IMPROVEMENTS LLC
Status Location Address State License Number Phone
ACTIVE

306 S RAILROAD ST

BUNNELL, FL 32110

CRC1327024 (Exp: 08/31/2026) 386-263-2167

Sub Contractors

WILLIAM FRANK DUDLEY JR.
Status Location Address State License Number Phone
ACTIVE

P.O. BOX 978

Bunnell, FL 32110

EC0003177 (Exp: 08/31/2026) (386)437-3068
WILLIAM FRANK DUDLEY JR.
Status Location Address State License Number Phone
ACTIVE

P.O. BOX 978

Bunnell, FL 32110

EC0003177 (Exp: 08/31/2026) (386)437-3068

Inspection History

Type Request Date Result Inspector
U -UTILITY RESIDENTIAL FINAL 02/07/2025 FINAL APPROVED LFITZGERALD
ROW - FINAL INSPECTION 02/06/2025 APPROVED GBERTOLA
Note: AT THE TIME OF THE INSPECTION, ALL MINIMUM CITY REQUIREMENTS WERE MET. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED.
BLD - BUILDING FINAL 01/13/2025 FINAL APPROVED RSIMS
Note: 9/4/2024 - PREVIOUS INSPECTION NOTES *** NOTES ADDED BY JSTEWART 9/4/2024 3:53:07 PM *** 1. Please seal all ceiling penetrations. R402.4 2. All receptacles in the garage require GFCI protection. (GFCI breakers for 220). NEC 210.8 A
BLD - BUILDING FINAL 09/04/2024 Disapproved - NO FEE JSTEWART
Note: *** NOTES ADDED BY JSTEWART 9/4/2024 3:53:07 PM *** 1. Please seal all ceiling penetrations. R402.4 2. All receptacles in the garage require GFCI protection. (GFCI breakers for 220). NEC 210.8 A
ROW- PRE-APRON (PRE-POUR) 04/03/2024 APPROVED TPOLACEK
Note: 04/03/24 AT THE TIME OF THE INSPECTION CULVERT PIPE IS GOOD IS READY TO POUR, IF RAIN PLEASE, BUILDER SHOULD DOUBLE CHECK CULVERT ELEVATIONS MAKE SURE IS 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE (FRC) DRAWING 300,E RESIDENTIAL CULVERT DETAIL BEFORE POURING. ---------------------------------------------- 4/2/2024 - PREVIOUS INSPECTION NOTES 04/02/24 PIPE IS JUST WITHIN TOLERANCE HOWEVER THE PIPE IS ROTATED AND NOT SQUARE IN THE MITERED ENDS. PIPE SHOULD HAVE EQUAL MEASURMENTS TO FORM BOARDS WITH A MINIMUM OF 2" OVER THE MITERED END. IF YOU HAVE ANY QUESTIONS PLEASE CALL INSPECTOR 396-346-8986 TOM ------------------------------------------------------------------------------------------------------------------ 3/28/2024 - PREVIOUS INSPECTION NOTES 03/28/24 PIPE IS OUT OF TOLERANCE, THERE ARE WASHOUTS DUE TO RAIN THAT WILL NEED TO BE REESTABLISHED AS WELL. Culvert Out of Tolerence Swale Plan #1 Swale Plan #1. The driveway culvert inverts are to be installed within 0.1' (+/-) of the elevations indicated on the swale plan (unless otherwise approved by the City StormwaterEngineer). The finished swale elevation is with sod in place
ROW- PRE-APRON (PRE-POUR) 04/02/2024 Disapproved -FEE REQUIRED TPOLACEK
Note: 04/02/24 PIPE IS JUST WITHIN TOLERANCE HOWEVER THE PIPE IS ROTATED AND NOT SQUARE IN THE MITERED ENDS. PIPE SHOULD HAVE EQUAL MEASURMENTS TO FORM BOARDS WITH A MINIMUM OF 2" OVER THE MITERED END. IF YOU HAVE ANY QUESTIONS PLEASE CALL INSPECTOR 396-346-8986 TOM ------------------------------------------------------------------------------------------------------------------ 3/28/2024 - PREVIOUS INSPECTION NOTES 03/28/24 PIPE IS OUT OF TOLERANCE, THERE ARE WASHOUTS DUE TO RAIN THAT WILL NEED TO BE REESTABLISHED AS WELL. Culvert Out of Tolerence Swale Plan #1 Swale Plan #1. The driveway culvert inverts are to be installed within 0.1' (+/-) of the elevations indicated on the swale plan (unless otherwise approved by the City StormwaterEngineer). The finished swale elevation is with sod in place
ROW- PRE-APRON (PRE-POUR) 03/28/2024 Disapproved - NO FEE TPOLACEK
Note: 03/28/24 PIPE IS OUT OF TOLERANCE, THERE ARE WASHOUTS DUE TO RAIN THAT WILL NEED TO BE REESTABLISHED AS WELL. Culvert Out of Tolerence Swale Plan #1 Swale Plan #1. The driveway culvert inverts are to be installed within 0.1' (+/-) of the elevations indicated on the swale plan (unless otherwise approved by the City StormwaterEngineer). The finished swale elevation is with sod in place
INSULATION 11/13/2023 APPROVED JWALKER
ALL ROUGH 11/02/2023 APPROVED JWALKER
Note: 11/1/2023 - PREVIOUS INSPECTION NOTES 11/1/23 1. E-cals and plans only show one mini split installed, 2 new units have been installed. Need revision to plans and e-cals 2. All metalic boxes need to be open to ensure proper bonding 10/27/2023 8:05:59 AM- PREVIOUS INSPECTION NOTES 8/10/2023 - PREVIOUS INSPECTION NOTES 8/10/23: Incomplete plans in the permit box. No energy calcs, etc. ** Need revision submitted to and approved by the City for the additional outlets, etc. along with the new plan showing relocation of pep tank control box. Lineset, etc. not run for mini-split system.
ALL ROUGH 11/01/2023 Disapproved - NO FEE MKRASKI
Note: 11/1/23 1. E-cals and plans only show one mini split installed, 2 new units have been installed. Need revision to plans and e-cals 2. All metalic boxes need to be open to ensure proper bonding 10/27/2023 8:05:59 AM- PREVIOUS INSPECTION NOTES 8/10/2023 - PREVIOUS INSPECTION NOTES 8/10/23: Incomplete plans in the permit box. No energy calcs, etc. ** Need revision submitted to and approved by the City for the additional outlets, etc. along with the new plan showing relocation of pep tank control box. Lineset, etc. not run for mini-split system.
ALL ROUGH 10/27/2023 CANCELLED BY APPLICANT MRAMOS
Note: 8/10/2023 - PREVIOUS INSPECTION NOTES 8/10/23: Incomplete plans in the permit box. No energy calcs, etc. ** Need revision submitted to and approved by the City for the additional outlets, etc. along with the new plan showing relocation of pep tank control box. Lineset, etc. not run for mini-split system.
ALL ROUGH 08/10/2023 Disapproved -FEE REQUIRED RSIMS
Note: 8/10/23: Incomplete plans in the permit box. No energy calcs, etc. ** Need revision submitted to and approved by the City for the additional outlets, etc. along with the new plan showing relocation of pep tank control box. Lineset, etc. not run for mini-split system.
ROOF VALLEY & METAL 07/24/2023 APPROVED MKRASKI
ROOF SHEATHING / BRACES/TIES/DOWN CELL 07/21/2023 APPROVED BTAYLOR
Note: Inspector Notes from Inspection 2340 12/14/22: NEED A CLEAN SET OF PRINTS STAMPED BY THE CITY IN THE PERMIT BOX BEFORE NEXT INSPECTION! Prints in box are not stamped by the City and are in disarray. R 107.3,1. - Approved documents need to be on-site for inspections.
TIE BEAM / LINTEL 12/14/2022 APPROVED - AS NOTED RSIMS
Note: 12/14/22: NEED A CLEAN SET OF PRINTS STAMPED BY THE CITY IN THE PERMIT BOX BEFORE NEXT INSPECTION! Prints in box are not stamped by the City and are in disarray. R 107.3,1. - Approved documents need to be on-site for inspections.
MONOLITHIC SLAB 10/20/2022 APPROVED RMARTIN
Note: 10/19/2022 - PREVIOUS INSPECTION NOTES 9/22/2022 - PREVIOUS INSPECTION NOTES 1. Pipes passing through footing need to be sleeved or a relieving arch needs to be installed. 2. There is an existing Irrigation control valve box at the front left area of the slab with an access door. This box along with any controls will need to be relocted. 3. Footing call for 20" depth. 10/19/22 The Pipes have not been sleeved or arched. Remove all debris from slab and footings.
MONOLITHIC SLAB 10/19/2022 Disapproved -FEE REQUIRED JWALKER
Note: 9/22/2022 - PREVIOUS INSPECTION NOTES 1. Pipes passing through footing need to be sleeved or a relieving arch needs to be installed. 2. There is an existing Irrigation control valve box at the front left area of the slab with an access door. This box along with any controls will need to be relocted. 3. Footing call for 20" depth. 10/19/22 The Pipes have not been sleeved or arched. Remove all debris from slab and footings.
MONOLITHIC SLAB 09/22/2022 Disapproved - NO FEE JWALKER
Note: 1. Pipes passing through footing need to be sleeved or a relieving arch needs to be installed. 2. There is an existing Irrigation control valve box at the front left area of the slab with an access door. This box along with any controls will need to be relocted. 3. Footing call for 20" depth.

Review History

Department Status Date In Date Out
ZON CANCEL 03/27/2024 03/27/2024
BADMIN INFORMATION 02/13/2024 02/13/2024
Note: Marked INFORMATION By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM Incorrect Survey provided Survey is not for 32 Eric Drive
ZON HOLD 01/17/2024 01/17/2024
Note: Held By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM Site plan: Please submit any revisions to the driveway on the site plan.
ENGIN1 COMPLETE 01/09/2024 01/11/2024
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
SW1 COMPLETE 01/09/2024 01/17/2024
Note: Released By: PARREN FLANAGAN - (386)986-2392 - PFLANAGAN@PALMCOASTGOV.COM
BLD COMPLETE 10/23/2023 10/26/2023
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
ELEC COMPLETE 10/23/2023 10/27/2023
Note: Released By: PATRICK BUCKLEY - (386)986-3786 - PBUCKLEY@PALMCOASTGOV.COM
BADMIN INFORMATION 06/16/2023 06/16/2023
Note: Marked INFORMATION By: SCOTT THOMAS - - STHOMAS@PALMCOASTGOV.COM RENAME TO NOC.PDF
BLD COMPLETE 06/12/2023 06/15/2023
Note: Released By: PATRICK BUCKLEY - (386)986-3786 - PBUCKLEY@PALMCOASTGOV.COM
BADMIN INFORMATION 05/30/2023 05/30/2023
Note: Marked INFORMATION By: MICHELLE RAMOS - - MRAMOS@PALMCOASTGOV.COM Wrong address for NOC
MECH COMPLETE 05/11/2022 05/11/2022
Note: Released By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM
MECH HOLD 05/10/2022 05/11/2022
Note: Held By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM Energy Calcs need to be signed by the builder
BLD COMPLETE 05/10/2022 05/11/2022
Note: Released By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM
BLD HOLD 05/05/2022 05/06/2022
Note: Held By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM All comments below per the 2020 Florida Building Code PLAN REVIEW COMMENTS: 1. Provide Product Approval for overhead door. Per F.S. 471.025 and F.A.C. 61 G15-23.005.
ELEC COMPLETE 05/05/2022 05/06/2022
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
MECH HOLD 05/05/2022 05/05/2022
Note: Held By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM Provide Energy calcs
PLUM CANCEL 05/05/2022 05/06/2022
SW1 COMPLETE 05/05/2022 05/12/2022
Note: Released By: ROBERT GROSS - (386)986-4769 - RGROSS@PALMCOASTGOV.COM
ZON COMPLETE 05/05/2022 05/10/2022
Note: Released By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM Garage space cannot exceed 50% of the living square footage. Please provide the existing square footage of the living sq. ft. Please note what material will be used for the roof. Please be advised that it must match existing roof.

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
ADMINISTRATIVE - EXTENSION ¤40.00 02/06/2025
REINSPECTION RESIDENTIAL ¤40.00 02/06/2025
SW ENG REINSPECTION 30 ¤30.00 02/06/2025
SW ENG - REVIEW 20 ¤20.00 07/14/2023
ADJUSTMENT 50% (¤85.13) 07/14/2023
SURCHARGE FS 533.721 ¤2.00 07/14/2023
SURCHARGE - FS 468.631 ¤2.00 07/14/2023
SW ENG - INSPECTION 20 ¤20.00 07/14/2023
ADMINISTRATIVE RESIDENTIAL ¤30.00 07/14/2023
INSPECTION - RESIDENTIAL ¤140.25 07/14/2023
REINSPECTION RESIDENTIAL ¤40.00 07/14/2023
Fees Total Due: ¤0.00 Total Paid: ¤279.12