Permit #2023080129

Permit Details

Status: COED

Parcel Id: 07-11-31-7030-00050-0060
CONDITIONED SPACE: 1650 sqft
GARAGE: 396 sqft
OPENED PORCH (WITH ROOF) : 119 sqft
Total Square Footage: 2165 sqft
Block: 00050
Subdivision: 2154 - SECTION 30-ROYAL PALMS
Job Phone: 202-494-2019
Location Address: 10 RAEMOND LN
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 09/18/2023
NOC: RECORDED
Applicant name: GARY ANDREW FISCHER
Owner: INB FUND 2 LLC

Address

3670 MAGUIRE BOULEVARD SUITE 220

ORLANDO, FL 32803

Lot: 0060
Contracted Stated Job Value: ¤150,000.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

INB HOMES
Status Location Address Mailing Address State License Number Phone
ACTIVE

3670 MAGUIRE BLVD

ORLANDO, FL 32803

SUITE 210

ORLANDO, FL 32803

CGC048746 (Exp: 08/31/2026) 407-476-8195

Sub Contractors

ROBERT MICHAEL RENNER
Status Location Address State License Number Phone
ACTIVE

531 CODISCO WAY

SANFORD, FL 32771

CAC051477 (Exp: 08/31/2026) 407-333-2665
HEATH EDWARD SANFORD
Status Location Address State License Number Phone
ACTIVE

126 EAST END RD

SAN MATEO, FL 32187

CFC1429896 (Exp: 08/31/2026) 386-871-8823
TERRY BRICE DICKERSON
Status Location Address State License Number Phone
ACTIVE

4300 ST JOHN'S PARKWAY

ALPHARETTA, GA 30009

CCC1326209 (Exp: 08/31/2026) 407-548-6733
JOSEPH C WRIGHT
Status Location Address Mailing Address State License Number Phone Fax
ACTIVE

15 HARGROVE LANE

PALM COAST, FL 32137

UNIT 3 D

PALM COAST, FL 32137

EC13003278 (Exp: 08/31/2026) 386-447-9644 386-447-9633

Inspection History

Type Request Date Result Inspector
BLD - BUILDING FINAL 03/21/2024 FINAL APPROVED AGAETANO
Note: 3/19/2024 - PREVIOUS INSPECTION NOTES
BLD - BUILDING FINAL 03/19/2024 CANCELLED BY APPLICANT WEB
BLD - BUILDING FINAL 03/19/2024 CANCELLED BY APPLICANT JWALKER
U-CROSS CONNECTION 03/19/2024 APPROVED - AS NOTED LFITZGERALD
Note: no irr-no crossconnection
ROW - STORMWATER FINAL 03/19/2024 APPROVED EMADISON
Note: ** 03/19/24 CORRECTIONS MADE ** ** At the time of the inspection all minimum city requirements were met. It is the builders responsibility to ensure that nothing changes after this Inspection is approved. _______________________________________________________________________________________________________________ 3/15/2024 - PREVIOUS INSPECTION NOTES ** 03/15/24 BUILDER NEEDS TO REVIEW NOTES FROM PREVIOUS FIELD SURVEY INSPECTION THAT WAS APPROVED AS NOTED THE CORRECTIONS NEEDED WERE ALSO IN THE (ROW STORMWATER FINAL) ** RIGHT SIDE SWALE AT PROPERTY LINE SHAVE DOWN HIGH SPOT AND RAISE LOW SPOT ___________________________________________________________________________________________________________________ Inspector Notes from Inspection 9465 ** 03/14/24 RIGHT SIDE SWALE AT PROPERTY LINE SHAVE DOWN HIGH SPOT AND RAISE LOW SPOT
U -UTILITY RESIDENTIAL FINAL 03/15/2024 FINAL APPROVED LFITZGERALD
ROW - FINAL APRON (AFTER POUR) 03/15/2024 APPROVED EMADISON
Note: ** At the time of the inspection all minimum city requirements were met. It is the builders responsibility to ensure that nothing changes after this Inspection is approved.
ROW - STORMWATER FINAL 03/15/2024 Disapproved -FEE REQUIRED EMADISON
Note: ** 03/15/24 BUILDER NEEDS TO REVIEW NOTES FROM PREVIOUS FIELD SURVEY INSPECTION THAT WAS APPROVED AS NOTED THE CORRECTIONS NEEDED WERE ALSO IN THE (ROW STORMWATER FINAL) ** RIGHT SIDE SWALE AT PROPERTY LINE SHAVE DOWN HIGH SPOT AND RAISE LOW SPOT ___________________________________________________________________________________________________________________ Inspector Notes from Inspection 9465 ** 03/14/24 RIGHT SIDE SWALE AT PROPERTY LINE SHAVE DOWN HIGH SPOT AND RAISE LOW SPOT
ROW- FINAL SURVEY/GRADING CERTIFICATION 03/14/2024 APPROVED EMADISON
ROW FIELD SURVEY /GRADING CERTIFICATION 03/14/2024 APPROVED - AS NOTED EMADISON
Note: ** 03/14/24 RIGHT SIDE SWALE AT PROPERTY LINE SHAVE DOWN HIGH SPOT AND RAISE LOW SPOT
ROW- PRE-APRON (PRE-POUR) 02/23/2024 APPROVED PFLANAGAN
Note: IT'S YOUR RESPONSIBILITY TO CHECK THE CULVERT ELEVATIONS BEFORE POURING CONCRETE. ALL CONCRETE NEEDS TO BE A MINIMUM OF 3000PSI WITH FIBER OR WITH METAL MESH IN THE CONCRETE TO MEET ALL CITY'S STANDARDS. At the time of the inspection all minimum city requirements were met. It is the builders responsibiliy to ensure that nothing changes after this Inspection is approved.
U - SEWER TIE IN 02/09/2024 APPROVED MGIBSON
Note: 2/7/2024 - PREVIOUS INSPECTION NOTES Inspector Notes from Inspection 2060 1. Water service pipe is either covered or not installed. Pipe will need to be installed and exposed at the mono slab inspection. SEE GRAVITY SEWER NOTE
GRAVITY SEWER TEST 02/09/2024 APPROVED MGIBSON
Note: 2/7/2024 - PREVIOUS INSPECTION NOTES Inspector Notes from Inspection 2060 1. Water service pipe is either covered or not installed. Pipe will need to be installed and exposed at the mono slab inspection. GRAVITY SEWER NOT RAN, NORE IS SEWER TAP MADE
ELECTRIC - EARLY POWER 02/08/2024 APPROVED JWALKER
ELECTRIC-TUG 02/07/2024 APPROVED JWALKER
Note: 1/11/2024 - PREVIOUS INSPECTION NOTES NEED TO RE-ATTACH GROUNDING ELECTRODE CONDUCTOR TO 2ND GROUND ROD
GRAVITY SEWER TEST 02/07/2024 Disapproved -FEE REQUIRED MGIBSON
Note: Inspector Notes from Inspection 2060 1. Water service pipe is either covered or not installed. Pipe will need to be installed and exposed at the mono slab inspection. GRAVITY SEWER NOT RAN, NORE IS SEWER TAP MADE
U - SEWER TIE IN 02/07/2024 Disapproved - NO FEE MGIBSON
Note: Inspector Notes from Inspection 2060 1. Water service pipe is either covered or not installed. Pipe will need to be installed and exposed at the mono slab inspection. SEE GRAVITY SEWER NOTE
PEP TANK INSTALLATION REQUEST 01/30/2024 APPROVED BVITALE
LATH/BRICK/ WATER BARRIER 01/24/2024 APPROVED JWALKER
Note: 1/23/2024 - PREVIOUS INSPECTION NOTES The zip tape used at the rear slider needs to have wire mesh over top of it installed. Zip tape is not an approved sub surface for plaster.
LATH/BRICK/ WATER BARRIER 01/23/2024 Disapproved - NO FEE JWALKER
Note: The zip tape used at the rear slider needs to have wire mesh over top of it installed. Zip tape is not an approved sub surface for plaster.
INSULATION 01/17/2024 APPROVED JWALKER
Note: Inspector Notes from Inspection 2420 1. The 14" flex duct above the living room area is not supported and is being constricted at the turns. The duct needs to be lengthened, lifted off the trusses bottom chords and supported. Reseal where it meets the supply plenum also. Please have correction completed prior to scheduling the insulation inspection.
ALL ROUGH 01/12/2024 APPROVED - AS NOTED JWALKER
Note: 1. The 14" flex duct above the living room area is not supported and is being constricted at the turns. The duct needs to be lengthened, lifted off the trusses bottom chords and supported. Reseal where it meets the supply plenum also. Please have correction completed prior to scheduling the insulation inspection.
ELECTRIC-TUG 01/11/2024 Disapproved - NO FEE RMARTIN
Note: NEED TO RE-ATTACH GROUNDING ELECTRODE CONDUCTOR TO 2ND GROUND ROD
ROOF VALLEY & METAL 01/08/2024 APPROVED JWALKER
Note: 1/4/2024 - PREVIOUS INSPECTION NOTES 1/4/24 Correction listed below still has not been made. 12/28/2023 - PREVIOUS INSPECTION NOTES 12/28/23 Below listed correction has not been made. 12/18/2023 - PREVIOUS INSPECTION NOTES 1. The left side and rear of the building roof. 1st row of synthetic underlayment is to be double. R-905
ROOF VALLEY & METAL 01/04/2024 Disapproved -FEE REQUIRED JWALKER
Note: 1/4/24 Correction listed below still has not been made. 12/28/2023 - PREVIOUS INSPECTION NOTES 12/28/23 Below listed correction has not been made. 12/18/2023 - PREVIOUS INSPECTION NOTES 1. The left side and rear of the building roof. 1st row of synthetic underlayment is to be double. R-905
ROOF VALLEY & METAL 01/03/2024 CANCELLED BY APPLICANT WEB
Note: 12/28/2023 - PREVIOUS INSPECTION NOTES 12/28/23 Below listed correction has not been made. 12/18/2023 - PREVIOUS INSPECTION NOTES 1. The left side and rear of the building roof. 1st row of synthetic underlayment is to be double. R-905
ROOF VALLEY & METAL 12/28/2023 Disapproved -FEE REQUIRED JWALKER
Note: 12/28/23 Below listed correction has not been made. 12/18/2023 - PREVIOUS INSPECTION NOTES 1. The left side and rear of the building roof. 1st row of synthetic underlayment is to be double. R-905
ROOF VALLEY & METAL 12/18/2023 Disapproved - NO FEE JWALKER
Note: 1. The left side and rear of the building roof. 1st row of synthetic underlayment is to be double. R-905
WALL SHEATHING 12/13/2023 APPROVED JWALKER
ROOF SHEATHING / BRACES/TIES/DOWN CELL 12/13/2023 APPROVED JWALKER
FOUND SURVEY APPROVED (OFFICE) 12/06/2023 APPROVED TBAKER
TIE BEAM / LINTEL 12/01/2023 APPROVED JWALKER
MONOLITHIC SLAB 11/13/2023 APPROVED JWALKER
Note: 11/9/2023 - PREVIOUS INSPECTION NOTES 11/9/23 1. Rear prorch, slider wall right side corner. the F-1 footing at the corner 2' x 2' has not been dug. 2. The water service pipe listed from the plumbing 1st rough has not been corrected. 1. Water service pipe is either covered or not installed. Pipe will need to be installed and exposed at the mono slab inspection.
MONOLITHIC SLAB 11/09/2023 Disapproved - NO FEE JWALKER
Note: 11/9/23 1. Rear prorch, slider wall right side corner. the F-1 footing at the corner 2' x 2' has not been dug. 2. The water service pipe listed from the plumbing 1st rough has not been corrected. 1. Water service pipe is either covered or not installed. Pipe will need to be installed and exposed at the mono slab inspection.
PLUMBING 1ST ROUGH UNDERGROUND 11/03/2023 APPROVED - AS NOTED JWALKER
Note: 1. Water service pipe is either covered or not installed. Pipe will need to be installed and exposed at the mono slab inspection.
WATER METER INSTALLATION REQUEST 10/11/2023 APPROVED CBOWERMASTER

Review History

Department Status Date In Date Out
MECH COMPLETE 03/14/2024 03/14/2024
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
BLD COMPLETE 01/24/2024 01/25/2024
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
ENGIN1 COMPLETE 12/06/2023 12/06/2023
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
ZON COMPLETE 12/06/2023 12/06/2023
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
ENGIN1 HOLD 11/01/2023 11/02/2023
Note: Held By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM Formboard survey is unacceptable as foundation survey. Please submit foundation survey showing location, dimensions and elevation of finished concrete foundation/slab.
ZON COMPLETE 11/01/2023 11/01/2023
Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM
SW1 COMPLETE 09/01/2023 09/12/2023
Note: Released By: GABRIEL BERTOLA - (386)986-7660 - GBERTOLA@PALMCOASTGOV.COM
ENGIN1 COMPLETE 09/01/2023 09/01/2023
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
ZON COMPLETE 09/01/2023 09/01/2023
Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM
CUSVC COMPLETE 08/15/2023 08/16/2023
Note: Released By: HALEIGH HAND - - HHAND@PALMCOASTGOV.COM
SW1 HOLD 08/15/2023 08/23/2023
Note: Held By: PARREN FLANAGAN - (386)986-2392 - PFLANAGAN@PALMCOASTGOV.COM PLEASE READ NOTES ON LAST REVIEW FOR CHANGES
ZON COMPLETE 08/15/2023 08/15/2023
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
BLD COMPLETE 08/15/2023 08/17/2023
Note: Released By: JPI
SWALE COMPLETE 08/03/2023 09/18/2023
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
BLD COMPLETE 08/02/2023 08/10/2023
Note: Released By: JPI
CUSVC HOLD 08/02/2023 08/02/2023
Note: Held By: HALEIGH HAND - - HHAND@PALMCOASTGOV.COM Please correct the utility application to reflect the correct parcel number and property address.
ELEC COMPLETE 08/02/2023 08/03/2023
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
ENGIN1 COMPLETE 08/02/2023 08/03/2023
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
GAS CANCEL 08/02/2023 08/04/2023
LOCATE COMPLETE 08/02/2023 08/03/2023
Note: Released By: CANDACE BOWERMASTER - - CBOWERMASTER@PALMCOASTGOV.COM
MECH COMPLETE 08/02/2023 08/04/2023
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
SW1 HOLD 08/02/2023 08/03/2023
Note: Held By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM The front property line/right away elevation are to be equal to or greater than thecenterline of the road elevation. As per Land Development Code Technical Manual, Section 300, Drawing 300.D,
ZON HOLD 08/02/2023 08/03/2023
Note: Held By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM AC pad location on landscape plan doesn't match plans and site plan All windows and doors facing ROW must have banding placed around them
BADMIN COMPLETE 08/02/2023 08/10/2023
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
SW ENG REINSPECTION 20 ¤20.00 03/18/2024
REINSPECTION RESIDENTIAL ¤40.00 03/15/2024
REINSPECTION RESIDENTIAL ¤40.00 03/15/2024
REINSPECTION RESIDENTIAL ¤40.00 03/15/2024
CONNECTION FEES ¤1,166.26 09/18/2023
FIRE IMPACT FEE ADMIN ¤12.62 09/18/2023
FIRE IMPACT FEE ADMIN (¤12.62) 09/18/2023
FC IMPACT FEE EMS ¤62.00 09/18/2023
IMPACT FEE FIRE ¤420.52 09/18/2023
FC IMPACT FEE LAW ENFORCEMENT ¤218.00 09/18/2023
FC IMPACT FEE LIBRARY ¤268.00 09/18/2023
IMPACT FEE PARKS ¤1,769.15 09/18/2023
IMPACT FEE SCHOOL ¤5,450.00 09/18/2023
IMPACT FEE TRANSPORTATION ¤1,812.00 09/18/2023
WATER -IRRIGATION INSPECTION ¤25.00 09/18/2023
PARKS IMPACT FEE ADMIN ¤53.07 09/18/2023
PARKS IMPACT FEE ADMIN (¤53.07) 09/18/2023
SURCHARGE FS 533.721 ¤3.75 09/18/2023
SURCHARGE - FS 468.631 ¤5.63 09/18/2023
SW ENG - FOUNDATION SURVEY ¤20.00 09/18/2023
SW ENG INSPECTION 80 ¤80.00 09/18/2023
SW ENG PRE APRON ¤30.00 09/18/2023
SW ENG - REVIEW 20 ¤20.00 09/18/2023
SW ENG RES REVIEW 200 ¤200.00 09/18/2023
TRANS IMPACT FEE ADMIN ¤54.36 09/18/2023
TRANS IMPACT FEE ADMIN (¤54.36) 09/18/2023
SEWER CREDIT (¤1,147.00) 09/18/2023
SEWER INSPECTION ¤25.00 09/18/2023
SEWER CAPITAL FACILITY ¤5,344.82 09/18/2023
WATER CAPITAL FACILITY FEE ¤3,923.88 09/18/2023
SITE PLAN 30 ¤30.00 09/18/2023
WATER- TURN ON ¤25.00 09/18/2023
ADJUSTMENT 50% (¤375.06) 09/18/2023
ADMINISTRATIVE RESIDENTIAL ¤30.00 09/18/2023
INSPECTION - RESIDENTIAL ¤561.00 09/18/2023
PLAN REVIEW - RESIDENTIAL ¤159.12 09/18/2023