Permit #2023080244
Permit Details
Status: COED
| Parcel Id: 09-12-31-0000-02030-0020 |
| COMMERCIAL SQUARE FOOTAGE: 34862 sqft |
| Total Square Footage: 34862 sqft |
| Block: 02030 |
| Subdivision: - |
| Job Phone: 678-697-0613 |
| Location Address: 1 MEMORIAL MEDICAL PKWY |
| Type: BC - BUILDING COMMERCIAL |
| Issue Date: 10/13/2023 |
| NOC: RECORDED |
| Applicant name: BRUCE ROBERT ADAMS |
| Owner: MEMORIAL HOSPITAL-FLAGLER INC |
|
Address 60 MEMORIAL MEDICAL PKWY PALM COAST, FL 32164 |
| Lot: 0020 |
| Contracted Stated Job Value: ¤19,000,000.00 |
| Job Description: 2-STORY MEDICAL OFFICE BUILDING CANCER CENTER |
| Type: CN |
Contractor
THE ROBINS & MORTON GROUP
| Status | Location Address | Mailing Address | State License Number | Phone |
| ACTIVE |
423 S KELLER RD ORLANDO, FL 32810 |
#200 ORLANDO, FL 32810 |
CGC1523017 (Exp: 08/31/2026) | 407-916-7235 |
Sub Contractors
KEITH MICHAEL CAMPBELL
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
6225 POWERS AVE JACKSONVILLE, FL 32217 |
CFC1426177 (Exp: 08/31/2026) | 904-387-9996 | 904-387-9068 |
KEITH MICHAEL CAMPBELL
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
3010 W BEAVER STREET JACKSONVILLE, FL 32254 |
CMC1250524 (Exp: 08/31/2026) | 904-387-9996 | 904-387-9068 |
TODD SHANNON
| Status | Location Address | State License Number |
| INACTIVE |
7625 CURRENCY DRIVE , 0 |
CCC1334039 (Exp: 08/31/2026) |
MICHAEL W CAMPBELL
| Status | Location Address | State License Number | Phone | Fax |
| INACTIVE |
1300 FT. NEGLEY BLVD NASHVILLE, TN 37203 |
EC0001269 (Exp: 08/31/2026) | 615-350-7270 | 615-350-7242 |
Inspection History
| Type | Request Date | Result | Inspector |
| HVAC FINAL | 10/30/2024 | FINAL APPROVED | CPISCITELLI |
| Note: | |||
| BUILDING FINAL | 10/30/2024 | FINAL APPROVED | LMILLER |
| FIRE FINAL | 10/29/2024 | APPROVED | JMUNSON |
| Note: 10/28/2024 - PREVIOUS INSPECTION NOTES 10/23/2024 - PREVIOUS INSPECTION NOTES *** NOTES ADDED BY RMARTIN 10/23/2024 3:53:39 PM *** FIRE EXTINGUISHERS NEED LABLE AND CERTIFICATION Need exit sign in B114 and building numbers | |||
| U - UTILITY COMMERCIAL FINAL | 10/29/2024 | FINAL APPROVED | LFITZGERALD |
| PLUMBING FINAL | 10/29/2024 | APPROVED | MGIBSON |
| Note: 10/21/2024 - PREVIOUS INSPECTION NOTES Inspector Notes from Inspection 3070 2/20/2024 - PREVIOUS INSPECTION NOTES 2/20/24 Roof top: vent sleeve's, roof drains, water pipe sleeve's Note: RFI for the Chiller Please submit all Revisions to the building department. 2/1/2024 - PREVIOUS INSPECTION NOTES Inspection for sleeve's 2nd floor slab. 12/7/2023 - PREVIOUS INSPECTION NOTES 12/6/2023 - PREVIOUS INSPECTION NOTES New inspection due to canceled inspection 11/29/2023 - PREVIOUS INSPECTION NOTES 11/29/23 UG east side exam rooms. Revision on page CPLOOC of the prints. 6- 2" drain pipes and tie to previous inspected piping. 11/14/2023 - PREVIOUS INSPECTION NOTES Inspected ADA staff toilet area, center area toilet rooms B140, 143, and 144,. Condensation drain piping in this area inspected. High lighted areas inspected 11/14/23. Norht side of building exam room areas, toilet rooms at the waiting area, under piping not yet completed. SPOKE WITH JIM WALKER AND WAS ASKED TO CANCEL INSPECTION THIS COMPLETES THE UNDER GROUND PLUMBING INSPECTIONS. THE UNLESS SOMETHING ELSE IS ADDED OR NEEDED, ROOF DRAINS WILL NEED TO BE INSPECTED AND ALSO SPOKE TO C/M ABOUT PLUMBING CONTRACTORS STUB OUT 5' OUTSIDE OF BUILDING AND NEED TO HAVE CONNECTION MADE ON CIVIL PLANS BY BUILDING DEPARTMENT. CHANGES WERE MADE ON FIRST FLOOR GYM AREA FIRST ROUGH PLUMBING IS APPROVED BUT ''CONCRETE NOT TO BE PLACED UNTIL REVISION IS MADE TO PLAN REVIEW TO MATCH WHAT WAS INSTALLED BY PLUMBING CONTRACTOR'' DOESN'T MATCH WHAT WAS INSTALLED Inspector Notes from Inspection 3070 2/20/2024 - PREVIOUS INSPECTION NOTES 2/20/24 Roof top: vent sleeve's, roof drains, water pipe sleeve's Note: RFI for the Chiller Please submit all Revisions to the building department. 2/1/2024 - PREVIOUS INSPECTION NOTES Inspection for sleeve's 2nd floor slab. 12/7/2023 - PREVIOUS INSPECTION NOTES 12/6/2023 - PREVIOUS INSPECTION NOTES New inspection due to canceled inspection 11/29/2023 - PREVIOUS INSPECTION NOTES 11/29/23 UG east side exam rooms. Revision on page CPLOOC of the prints. 6- 2" drain pipes and tie to previous inspected piping. 11/14/2023 - PREVIOUS INSPECTION NOTES Inspected ADA staff toilet area, center area toilet rooms B140, 143, and 144,. Condensation drain piping in this area inspected. High lighted areas inspected 11/14/23. Norht side of building exam room areas, toilet rooms at the waiting area, under piping not yet completed. SPOKE WITH JIM WALKER AND WAS ASKED TO CANCEL INSPECTION THIS COMPLETES THE UNDER GROUND PLUMBING INSPECTIONS. THE UNLESS SOMETHING ELSE IS ADDED OR NEEDED, ROOF DRAINS WILL NEED TO BE INSPECTED AND ALSO SPOKE TO C/M ABOUT PLUMBING CONTRACTORS STUB OUT 5' OUTSIDE OF BUILDING AND NEED TO HAVE CONNECTION MADE ON CIVIL PLANS BY BUILDING DEPARTMENT. CHANGES WERE MADE ON FIRST FLOOR GYM AREA FIRST ROUGH PLUMBING IS APPROVED BUT ''CONCRETE NOT TO BE PLACED UNTIL REVISION IS MADE TO PLAN REVIEW TO MATCH WHAT WAS INSTALLED BY PLUMBING CONTRACTOR'' DOESN'T MATCH WHAT WAS INSTALLED THIS WAS FOR MAIN BUILDING FIRST FLOOR AND SECOND FLOOR IN PRIMARY UNITS | |||
| FIRE FINAL | 10/28/2024 | Disapproved - NO FEE | JMUNSON |
| Note: *** NOTES ADDED BY JMUNSON 10/28/2024 10:45:14 AM *** Need exit sign in B114 and building numbers 10/23/2024 - PREVIOUS INSPECTION NOTES *** NOTES ADDED BY RMARTIN 10/23/2024 3:53:39 PM *** FIRE EXTINGUISHERS NEED LABLE AND CERTIFICATION Need exit sign in B114 and building numbers | |||
| ELECTRIC FINAL | 10/25/2024 | APPROVED | JMUNSON |
| Note: 10/23/2024 - PREVIOUS INSPECTION NOTES *** NOTES ADDED BY RMARTIN 10/23/2024 3:53:05 PM *** need to fix gfci protection within 6' of sinks and outlets not working 10/22/2024 - PREVIOUS INSPECTION NOTES *** NOTES ADDED BY RMARTIN 10/22/2024 12:39:06 PM *** 1st floor partial, need to fix gfci protection within 6' of sinks and outlets not working | |||
| ROOF FINAL | 10/24/2024 | FINAL APPROVED | FWILLIS |
| FIRE FINAL | 10/23/2024 | Disapproved -FEE REQUIRED | RMARTIN |
| Note: *** NOTES ADDED BY RMARTIN 10/23/2024 3:53:39 PM *** FIRE EXTINGUISHERS NEED LABLE AND CERTIFICATION | |||
| BLD - SEWER TIE IN | 10/23/2024 | APPROVED | MGIBSON |
| GRAVITY SEWER | 10/23/2024 | APPROVED | MGIBSON |
| ELECTRIC FINAL | 10/23/2024 | Disapproved - NO FEE | RMARTIN |
| Note: *** NOTES ADDED BY RMARTIN 10/23/2024 3:53:05 PM *** need to fix gfci protection within 6' of sinks and outlets not working 10/22/2024 - PREVIOUS INSPECTION NOTES *** NOTES ADDED BY RMARTIN 10/22/2024 12:39:06 PM *** 1st floor partial, need to fix gfci protection within 6' of sinks and outlets not working | |||
| ELECTRIC FINAL | 10/22/2024 | PARTIALLY APPROVED | RMARTIN |
| Note: *** NOTES ADDED BY RMARTIN 10/22/2024 12:39:06 PM *** 1st floor partial, need to fix gfci protection within 6' of sinks and outlets not working | |||
| HVAC FINAL | 10/22/2024 | PARTIALLY APPROVED | CPISCITELLI |
| Note: 1. Need balanced return air in offices 2. MOCP for minisplits and one rtu does not match the fuses 3. Need test and balance report 10/4/2024 - PREVIOUS INSPECTION NOTES 1. Need balanced return air in offices 2. Need to test Duct detectors 3. MOCP for minisplits and one rtu does not match the fuses 4. Need test and balance report | |||
| PLUMBING FINAL | 10/21/2024 | PARTIALLY APPROVED | MGIBSON |
| HVAC FINAL | 10/04/2024 | Disapproved - NO FEE | CPISCITELLI |
| Note: 1. Need balanced return air in offices 2. Need to test Duct detectors 3. MOCP for minisplits and one rtu does not match the fuses 4. Need test and balance report | |||
| FIREWALL PENETRATIONS | 10/04/2024 | APPROVED | FWILLIS |
| Note: 7/25/2024 - PREVIOUS INSPECTION NOTES 6/4/2024 - PREVIOUS INSPECTION NOTES 6/4/24 The inspection was for the glazed aluminum curtian wall system. 6/4/2024 - PREVIOUS INSPECTION NOTES 6/4/24 Item 3 listed below as not been corrected. 6/3/24 Item 1 and 2 and 4 listed below resloved. 3. Annular space around the fire dampes will need to be sealed with approved sealant. FBC 714.4.1 exception 2 Access being installed for the smaller damper. Check for ul label. 5/30/2024 - PREVIOUS INSPECTION NOTES 5/30/24 1. Will need ladder or reach to check labels on the fire dampers. 2. 2nd floor fire wall. East side at the double doors. A 6" duct is penetrating the wall. No fire damper appears to be installed. FBC 714.1.1 3. Annular space around the fire dampes will need to be sealed with approved sealant. FBC 714.4.1 exception 2. 4. Please have the Fire damper specifications onsite at the reinspection. | |||
| ABOVE CEILING | 09/25/2024 | APPROVED | RMARTIN |
| Note: 9/13/2024 - PREVIOUS INSPECTION NOTES Upstairs office area upstairs and hallways. Need to leave areas open for electric and mechanical 9/6/2024 - PREVIOUS INSPECTION NOTES *** NOTES ADDED BY RMARTIN 9/6/2024 4:11:19 PM *** not ready 8/15/2024 - PREVIOUS INSPECTION NOTES *** NOTES ADDED BY RMARTIN 8/15/2024 2:31:33 PM *** 1st floor area by radiation rooms/hallways, need to leave areas open per Chris 8/2/2024 - PREVIOUS INSPECTION NOTES elictrical for front corridor and machine room mechanical for front corridor and machine room except for closets 7/31/2024 - PREVIOUS INSPECTION NOTES | |||
| ABOVE CEILING | 09/13/2024 | PARTIALLY APPROVED | CPISCITELLI |
| Note: Upstairs office area upstairs and hallways. Need to leave areas open for electric and mechanical 9/6/2024 - PREVIOUS INSPECTION NOTES *** NOTES ADDED BY RMARTIN 9/6/2024 4:11:19 PM *** not ready 8/15/2024 - PREVIOUS INSPECTION NOTES *** NOTES ADDED BY RMARTIN 8/15/2024 2:31:33 PM *** 1st floor area by radiation rooms/hallways, need to leave areas open per Chris 8/2/2024 - PREVIOUS INSPECTION NOTES elictrical for front corridor and machine room mechanical for front corridor and machine room except for closets 7/31/2024 - PREVIOUS INSPECTION NOTES | |||
| ABOVE CEILING | 09/06/2024 | Disapproved - NO FEE | RMARTIN |
| Note: *** NOTES ADDED BY RMARTIN 9/6/2024 4:11:19 PM *** not ready 8/15/2024 - PREVIOUS INSPECTION NOTES *** NOTES ADDED BY RMARTIN 8/15/2024 2:31:33 PM *** 1st floor area by radiation rooms/hallways, need to leave areas open per Chris 8/2/2024 - PREVIOUS INSPECTION NOTES elictrical for front corridor and machine room mechanical for front corridor and machine room except for closets 7/31/2024 - PREVIOUS INSPECTION NOTES | |||
| ABOVE CEILING | 08/15/2024 | PARTIALLY APPROVED | RMARTIN |
| Note: *** NOTES ADDED BY RMARTIN 8/15/2024 2:31:33 PM *** 1st floor area by radiation rooms/hallways, need to leave areas open per Chris 8/2/2024 - PREVIOUS INSPECTION NOTES elictrical for front corridor and machine room mechanical for front corridor and machine room except for closets 7/31/2024 - PREVIOUS INSPECTION NOTES | |||
| EXTERIOR ARCHITECTURAL FEATURES | 08/15/2024 | APPROVED | RPICATAGI |
| Note: This inpspection approves : 1. Large metalic canopy structure at main entrace SE Corner; and 2. Smaller metalic canopy structure at rear NE entrance ONLY | |||
| ABOVE CEILING | 08/02/2024 | PARTIALLY APPROVED | CPISCITELLI |
| Note: elictrical for front corridor and machine room mechanical for front corridor and machine room except for closets 7/31/2024 - PREVIOUS INSPECTION NOTES | |||
| ABOVE CEILING | 07/31/2024 | PARTIALLY APPROVED | MGIBSON |
| HVAC ROUGH | 07/30/2024 | PARTIALLY APPROVED | CPISCITELLI |
| Note: Inspected dampers in shaft and elevator 7/25/2024 - PREVIOUS INSPECTION NOTES Inspected 2nd floor dampers in floor. Need to have a detail for dampers in floor. Or a revision to move to wall of shaft 5/29/2024 - PREVIOUS INSPECTION NOTES *** NOTES ADDED BY CPISCITELLI 5/29/2024 10:02:07 AM *** Inspected 2nd floor seams except shell area 4/25/2024 - PREVIOUS INSPECTION NOTES Inspected all main trunk square duct and tap seams on first floor. Did not inspect 2 front rooms and former gym area | |||
| HVAC ROUGH | 07/25/2024 | PARTIALLY APPROVED | CPISCITELLI |
| Note: Inspected 2nd floor dampers in floor. Need to have a detail for dampers in floor. Or a revision to move to wall of shaft 5/29/2024 - PREVIOUS INSPECTION NOTES *** NOTES ADDED BY CPISCITELLI 5/29/2024 10:02:07 AM *** Inspected 2nd floor seams except shell area 4/25/2024 - PREVIOUS INSPECTION NOTES Inspected all main trunk square duct and tap seams on first floor. Did not inspect 2 front rooms and former gym area | |||
| FIREWALL PENETRATIONS | 07/25/2024 | CANCELLED BY APPLICANT | LMILLER |
| Note: 6/4/2024 - PREVIOUS INSPECTION NOTES 6/4/24 The inspection was for the glazed aluminum curtian wall system. 6/4/2024 - PREVIOUS INSPECTION NOTES 6/4/24 Item 3 listed below as not been corrected. 6/3/24 Item 1 and 2 and 4 listed below resloved. 3. Annular space around the fire dampes will need to be sealed with approved sealant. FBC 714.4.1 exception 2 Access being installed for the smaller damper. Check for ul label. 5/30/2024 - PREVIOUS INSPECTION NOTES 5/30/24 1. Will need ladder or reach to check labels on the fire dampers. 2. 2nd floor fire wall. East side at the double doors. A 6" duct is penetrating the wall. No fire damper appears to be installed. FBC 714.1.1 3. Annular space around the fire dampes will need to be sealed with approved sealant. FBC 714.4.1 exception 2. 4. Please have the Fire damper specifications onsite at the reinspection. | |||
| ELECTRIC 2ND ROUGH | 07/11/2024 | APPROVED | RMARTIN |
| Note: 7/10/2024 - PREVIOUS INSPECTION NOTES *** NOTES ADDED BY RMARTIN 7/10/2024 10:02:33 AM *** south side stair well Inspector Notes from Inspection 3190 *** NOTES ADDED BY RMARTIN 6/20/2024 8:40:44 AM *** WALLS MINUS THE BUILDOUT PERMIT Inspector Notes from Inspection 3180 *** NOTES ADDED BY RMARTIN 6/4/2024 10:18:24 AM *** walls 1st floor rooms north end 2/20/2024 - PREVIOUS INSPECTION NOTES 2/20/24 Looked at roof deck sleeves, and 2- 4'' and 1'' pvc conduits running from east side of buiding 2/7/2024 - PREVIOUS INSPECTION NOTES 2/7/24 west side parkinglot underground 1/30/24 snd floor sleeves 1/9/2024 - PREVIOUS INSPECTION NOTES 1/9/24 tilt walls 1/4/2024 - PREVIOUS INSPECTION NOTES 1/4/24 conduit inside tilt walls 12/20/23 conduit inside tilt walls 12/4/2023 - PREVIOUS INSPECTION NOTES 12/4/23 south end 11/21/2023 - PREVIOUS INSPECTION NOTES 11/21/23 north end of building 11/17/2023 - PREVIOUS INSPECTION NOTES 11/17/23 Canceled by super 11/9/2023 - PREVIOUS INSPECTION NOTES Underground for Electrical Slab on Grade for LINAC Underground Electrical (UFER) | |||
| ELECTRIC 2ND ROUGH | 07/10/2024 | PARTIALLY APPROVED | RMARTIN |
| Note: *** NOTES ADDED BY RMARTIN 7/10/2024 10:02:33 AM *** south side stair well Inspector Notes from Inspection 3190 *** NOTES ADDED BY RMARTIN 6/20/2024 8:40:44 AM *** WALLS MINUS THE BUILDOUT PERMIT Inspector Notes from Inspection 3180 *** NOTES ADDED BY RMARTIN 6/4/2024 10:18:24 AM *** walls 1st floor rooms north end 2/20/2024 - PREVIOUS INSPECTION NOTES 2/20/24 Looked at roof deck sleeves, and 2- 4'' and 1'' pvc conduits running from east side of buiding 2/7/2024 - PREVIOUS INSPECTION NOTES 2/7/24 west side parkinglot underground 1/30/24 snd floor sleeves 1/9/2024 - PREVIOUS INSPECTION NOTES 1/9/24 tilt walls 1/4/2024 - PREVIOUS INSPECTION NOTES 1/4/24 conduit inside tilt walls 12/20/23 conduit inside tilt walls 12/4/2023 - PREVIOUS INSPECTION NOTES 12/4/23 south end 11/21/2023 - PREVIOUS INSPECTION NOTES 11/21/23 north end of building 11/17/2023 - PREVIOUS INSPECTION NOTES 11/17/23 Canceled by super 11/9/2023 - PREVIOUS INSPECTION NOTES Underground for Electrical Slab on Grade for LINAC Underground Electrical (UFER) | |||
| FRAMING | 07/10/2024 | PARTIALLY APPROVED | JWALKER |
| Note: 7/10/24 Inspection for the west stair tower framing. 6/20/2024 - PREVIOUS INSPECTION NOTES *** NOTES ADDED BY LMILLER 6/20/2024 4:34:02 PM *** fraiming inspection for lobby on first and second floor only 5/16/2024 - PREVIOUS INSPECTION NOTES | |||
| PLUMBING 1ST ROUGH | 07/02/2024 | APPROVED - AS NOTED | MGIBSON |
| Note: 2/20/2024 - PREVIOUS INSPECTION NOTES 2/20/24 Roof top: vent sleeve's, roof drains, water pipe sleeve's Note: RFI for the Chiller Please submit all Revisions to the building department. 2/1/2024 - PREVIOUS INSPECTION NOTES Inspection for sleeve's 2nd floor slab. 12/7/2023 - PREVIOUS INSPECTION NOTES 12/6/2023 - PREVIOUS INSPECTION NOTES New inspection due to canceled inspection 11/29/2023 - PREVIOUS INSPECTION NOTES 11/29/23 UG east side exam rooms. Revision on page CPLOOC of the prints. 6- 2" drain pipes and tie to previous inspected piping. 11/14/2023 - PREVIOUS INSPECTION NOTES Inspected ADA staff toilet area, center area toilet rooms B140, 143, and 144,. Condensation drain piping in this area inspected. High lighted areas inspected 11/14/23. Norht side of building exam room areas, toilet rooms at the waiting area, under piping not yet completed. SPOKE WITH JIM WALKER AND WAS ASKED TO CANCEL INSPECTION THIS COMPLETES THE UNDER GROUND PLUMBING INSPECTIONS. THE UNLESS SOMETHING ELSE IS ADDED OR NEEDED, ROOF DRAINS WILL NEED TO BE INSPECTED AND ALSO SPOKE TO C/M ABOUT PLUMBING CONTRACTORS STUB OUT 5' OUTSIDE OF BUILDING AND NEED TO HAVE CONNECTION MADE ON CIVIL PLANS BY BUILDING DEPARTMENT. CHANGES WERE MADE ON FIRST FLOOR GYM AREA FIRST ROUGH PLUMBING IS APPROVED BUT ''CONCRETE NOT TO BE PLACED UNTIL REVISION IS MADE TO PLAN REVIEW TO MATCH WHAT WAS INSTALLED BY PLUMBING CONTRACTOR'' DOESN'T MATCH WHAT WAS INSTALLED | |||
| ELECTRIC 2ND ROUGH | 06/20/2024 | APPROVED - AS NOTED | RMARTIN |
| Note: *** NOTES ADDED BY RMARTIN 6/20/2024 8:40:44 AM *** WALLS MINUS THE BUILDOUT PERMIT Inspector Notes from Inspection 3180 *** NOTES ADDED BY RMARTIN 6/4/2024 10:18:24 AM *** walls 1st floor rooms north end 2/20/2024 - PREVIOUS INSPECTION NOTES 2/20/24 Looked at roof deck sleeves, and 2- 4'' and 1'' pvc conduits running from east side of buiding 2/7/2024 - PREVIOUS INSPECTION NOTES 2/7/24 west side parkinglot underground 1/30/24 snd floor sleeves 1/9/2024 - PREVIOUS INSPECTION NOTES 1/9/24 tilt walls 1/4/2024 - PREVIOUS INSPECTION NOTES 1/4/24 conduit inside tilt walls 12/20/23 conduit inside tilt walls 12/4/2023 - PREVIOUS INSPECTION NOTES 12/4/23 south end 11/21/2023 - PREVIOUS INSPECTION NOTES 11/21/23 north end of building 11/17/2023 - PREVIOUS INSPECTION NOTES 11/17/23 Canceled by super 11/9/2023 - PREVIOUS INSPECTION NOTES Underground for Electrical Slab on Grade for LINAC Underground Electrical (UFER) | |||
| FRAMING | 06/20/2024 | PARTIALLY APPROVED | LMILLER |
| Note: *** NOTES ADDED BY LMILLER 6/20/2024 4:34:02 PM *** fraiming inspection for lobby on first and second floor only 5/16/2024 - PREVIOUS INSPECTION NOTES | |||
| FOOTER | 06/12/2024 | APPROVED | AGAETANO |
| FIREWALL DRYWALL NAILING | 06/07/2024 | PARTIALLY APPROVED | JWALKER |
| Note: 6/7/24 Elevator walls approved. 5/30/2024 - PREVIOUS INSPECTION NOTES 5/30/24 2nd floor non rated walls. Fire walls approved. South stairway and elevator shaft and mechnical shaft. Not completed. 5/24/2024 - PREVIOUS INSPECTION NOTES 5/24/24 Inspection for the North side stair way. 4/19/2024 - PREVIOUS INSPECTION NOTES Inspection for 2nd floor firewall drywall nailing in the communication room only, approved. 4/12/2024 - PREVIOUS INSPECTION NOTES | |||
| HORIZONTAL ASSEMB PENETRATIONS | 06/04/2024 | CANCELLED BY APPLICANT | JWALKER |
| FIREWALL PENETRATIONS | 06/04/2024 | Disapproved - NO FEE | JWALKER |
| Note: 6/4/24 Item 3 listed below as not been corrected. 6/3/24 Item 1 and 2 and 4 listed below resloved. 3. Annular space around the fire dampes will need to be sealed with approved sealant. FBC 714.4.1 exception 2 Access being installed for the smaller damper. Check for ul label. 5/30/2024 - PREVIOUS INSPECTION NOTES 5/30/24 1. Will need ladder or reach to check labels on the fire dampers. 2. 2nd floor fire wall. East side at the double doors. A 6" duct is penetrating the wall. No fire damper appears to be installed. FBC 714.1.1 3. Annular space around the fire dampes will need to be sealed with approved sealant. FBC 714.4.1 exception 2. 4. Please have the Fire damper specifications onsite at the reinspection. | |||
| FIREWALL PENETRATIONS | 06/04/2024 | PARTIALLY APPROVED | JWALKER |
| Note: 6/4/24 The inspection was for the glazed aluminum curtian wall system. 6/4/2024 - PREVIOUS INSPECTION NOTES 6/4/24 Item 3 listed below as not been corrected. 6/3/24 Item 1 and 2 and 4 listed below resloved. 3. Annular space around the fire dampes will need to be sealed with approved sealant. FBC 714.4.1 exception 2 Access being installed for the smaller damper. Check for ul label. 5/30/2024 - PREVIOUS INSPECTION NOTES 5/30/24 1. Will need ladder or reach to check labels on the fire dampers. 2. 2nd floor fire wall. East side at the double doors. A 6" duct is penetrating the wall. No fire damper appears to be installed. FBC 714.1.1 3. Annular space around the fire dampes will need to be sealed with approved sealant. FBC 714.4.1 exception 2. 4. Please have the Fire damper specifications onsite at the reinspection. | |||
| ELECTRIC 1ST ROUGH | 06/04/2024 | APPROVED - AS NOTED | RMARTIN |
| Note: *** NOTES ADDED BY RMARTIN 6/4/2024 10:18:24 AM *** walls 1st floor rooms north end 2/20/2024 - PREVIOUS INSPECTION NOTES 2/20/24 Looked at roof deck sleeves, and 2- 4'' and 1'' pvc conduits running from east side of buiding 2/7/2024 - PREVIOUS INSPECTION NOTES 2/7/24 west side parkinglot underground 1/30/24 snd floor sleeves 1/9/2024 - PREVIOUS INSPECTION NOTES 1/9/24 tilt walls 1/4/2024 - PREVIOUS INSPECTION NOTES 1/4/24 conduit inside tilt walls 12/20/23 conduit inside tilt walls 12/4/2023 - PREVIOUS INSPECTION NOTES 12/4/23 south end 11/21/2023 - PREVIOUS INSPECTION NOTES 11/21/23 north end of building 11/17/2023 - PREVIOUS INSPECTION NOTES 11/17/23 Canceled by super 11/9/2023 - PREVIOUS INSPECTION NOTES Underground for Electrical Slab on Grade for LINAC Underground Electrical (UFER) | |||
| PLUMBING 2ND ROUGH | 06/04/2024 | PARTIALLY APPROVED | MGIBSON |
| Note: 5/30/2024 - PREVIOUS INSPECTION NOTES 5/29/2024 - PREVIOUS INSPECTION NOTES 5/17/2024 - PREVIOUS INSPECTION NOTES SECOND ROUGH WAS DONE ON ''VTR'' FOR SOUTH EAST SIDE NOT READY FOR INSPECTION, GUAGE READING LESS 30 LBS PSI. THIS WAS A PARTIAL INSPECTION WEST SIDE OF SECOND FLOOR, GUAGE ON FIRST FLOOR WAS AT 60 LBS OF PRESSURE. THIS IS ALL WATER LINES FIRST AND SECOND FLOOR PRESSURE TESTED AND APPROVED. ALSO INSPECTED SHEDUAL 80 WATER MAIN DISTRIBUTION LINE ON EXTERIOR OF BUILDING WEST SIDE | |||
| FIREWALL PENETRATIONS | 06/03/2024 | Disapproved - NO FEE | JWALKER |
| Note: 6/3/24 Item 1 and 2 and 4 listed below resloved. 3. Annular space around the fire dampes will need to be sealed with approved sealant. FBC 714.4.1 exception 2 Access being installed for the smaller damper. Check for ul label. 5/30/2024 - PREVIOUS INSPECTION NOTES 5/30/24 1. Will need ladder or reach to check labels on the fire dampers. 2. 2nd floor fire wall. East side at the double doors. A 6" duct is penetrating the wall. No fire damper appears to be installed. FBC 714.1.1 3. Annular space around the fire dampes will need to be sealed with approved sealant. FBC 714.4.1 exception 2. 4. Please have the Fire damper specifications onsite at the reinspection. | |||
| FIREWALL PENETRATIONS | 05/30/2024 | Disapproved - NO FEE | JWALKER |
| Note: 5/30/24 1. Will need ladder or reach to check labels on the fire dampers. 2. 2nd floor fire wall. East side at the double doors. A 6" duct is penetrating the wall. No fire damper appears to be installed. FBC 714.1.1 3. Annular space around the fire dampes will need to be sealed with approved sealant. FBC 714.4.1 exception 2. 4. Please have the Fire damper specifications onsite at the reinspection. | |||
| FIREWALL DRYWALL NAILING | 05/30/2024 | PARTIALLY APPROVED | JWALKER |
| Note: 5/30/24 2nd floor non rated walls. Fire walls approved. South stairway and elevator shaft and mechnical shaft. Not completed. 5/24/2024 - PREVIOUS INSPECTION NOTES 5/24/24 Inspection for the North side stair way. 4/19/2024 - PREVIOUS INSPECTION NOTES Inspection for 2nd floor firewall drywall nailing in the communication room only, approved. 4/12/2024 - PREVIOUS INSPECTION NOTES | |||
| PLUMBING 2ND ROUGH | 05/30/2024 | PARTIALLY APPROVED | MGIBSON |
| Note: 5/29/2024 - PREVIOUS INSPECTION NOTES 5/17/2024 - PREVIOUS INSPECTION NOTES SECOND ROUGH WAS DONE ON ''VTR'' FOR SOUTH EAST SIDE NOT READY FOR INSPECTION, GUAGE READING LESS 30 LBS PSI. THIS WAS A PARTIAL INSPECTION WEST SIDE OF SECOND FLOOR, GUAGE ON FIRST FLOOR WAS AT 60 LBS OF PRESSURE | |||
| INSULATION | 05/30/2024 | PARTIALLY APPROVED | JWALKER |
| Note: 5/30/24 Elevator shaft walls first floor approved. 5/15/2024 - PREVIOUS INSPECTION NOTES 5/15/24 Shaft wall insulation approved. 5/14/2024 - PREVIOUS INSPECTION NOTES 2nd floor fire walls approved. | |||
| PLUMBING 2ND ROUGH | 05/29/2024 | Disapproved - NO FEE | MGIBSON |
| Note: 5/17/2024 - PREVIOUS INSPECTION NOTES SECOND ROUGH WAS DONE ON ''VTR'' FOR SOUTH EAST SIDE NOT READY FOR INSPECTION, GUAGE READING LESS 30 LBS PSI | |||
| HVAC ROUGH | 05/29/2024 | PARTIALLY APPROVED | CPISCITELLI |
| Note: *** NOTES ADDED BY CPISCITELLI 5/29/2024 10:02:07 AM *** Inspected 2nd floor seams except shell area 4/25/2024 - PREVIOUS INSPECTION NOTES Inspected all main trunk square duct and tap seams on first floor. Did not inspect 2 front rooms and former gym area | |||
| FIREWALL DRYWALL NAILING | 05/24/2024 | PARTIALLY APPROVED | JWALKER |
| Note: 5/24/24 Inspection for the North side stair way. 4/19/2024 - PREVIOUS INSPECTION NOTES Inspection for 2nd floor firewall drywall nailing in the communication room only, approved. 4/12/2024 - PREVIOUS INSPECTION NOTES | |||
| FIREWALL FRAMING | 05/24/2024 | PARTIALLY APPROVED | JWALKER |
| Note: 5/24/24 Cat scan room framing 5/15/2024 - PREVIOUS INSPECTION NOTES 5/15/24 Shaft Wall framing approved. 4/12/2024 - PREVIOUS INSPECTION NOTES Fire walls 1st and 2nd floor at elevator stair well and 2nd floor separating wall appoved. Fire wall Framing at HVAC shaft not completed. | |||
| PLUMBING PRESSURE TEST | 05/17/2024 | CANCELLED BY INSPECTOR | MGIBSON |
| Note: 5/15/2024 - PREVIOUS INSPECTION NOTES 5/15/24 South East VTR is not holding water. Please be sure to schedule the plumbing 2nd rough inspections for 1st and 2nd floors. 5/14/2024 - PREVIOUS INSPECTION NOTES 5/14/24 1st floor water distribution pipe approved. 2nd floor not completed. SE section of the DWV needs to be reinspected. Other sections of DWV approved. 5/7/2024 - PREVIOUS INSPECTION NOTES 5/2/2024 - PREVIOUS INSPECTION NOTES 4/30/2024 - PREVIOUS INSPECTION NOTES 3/19/2024 - PREVIOUS INSPECTION NOTES Inspection for 10 roof drains. Approved. This was a partial inspection on North side for water lines and recirc lines. Lines were valved off for areas that wer inspected and approved. Guage foe water piping was alocated @ sink reading 150 lbs.This was a partial waste and vent inspection for first floor north side and 2 bathrooms on South side.have 3 area's of concern. Plumber marked with Blue paint on these area's. AREAS THAT WERE PAINTED ONLY FROM LAST INSPECTION ARE APPROVED ONLY THING THAT I LOOKED AT EVERYTHING NORTH SIDE AND EASTSIDE HAS BEEN APPROVED. NO NEED TO SCHEDUAL PRESSURE TEST INSPECTIONS MOVING FORWARD THE ONLY THING THAT SHOULD BE SCHEDULE IS SECOND ROUGH { THIS WILL INCLUDE ''VTR'' ''WATER'' AND ''SANITARY DRAINAGE'' | |||
| PLUMBING 2ND ROUGH | 05/17/2024 | CANCELLED BY APPLICANT | WEB |
| PLUMBING 2ND ROUGH | 05/17/2024 | PARTIALLY APPROVED | MGIBSON |
| Note: SECOND ROUGH WAS DONE ON ''VTR'' FOR SOUTH EAST SIDE | |||
| FRAMING | 05/16/2024 | CANCELLED BY APPLICANT | JWALKER |
| ABOVE GRADE CONCRETE WALL | 05/16/2024 | CANCELLED BY INSPECTOR | JWALKER |
| Note: 12/6/2023 - PREVIOUS INSPECTION NOTES 12/6/23 Inspected vault North, east and west wall up to 15' 4" 11/29/2023 - PREVIOUS INSPECTION NOTES Rebar inspection for south side wall at the vault. Up to 15' 4" elevation. | |||
| FOOTER | 05/16/2024 | APPROVED | JWALKER |
| Note: 5/16/24 All footer complete 12/6/2023 - PREVIOUS INSPECTION NOTES 12/6/23 Footings on the west side for the canopy columns. | |||
| TILT WALL | 05/16/2024 | APPROVED | JWALKER |
| Note: 5/16/24 All tilt walls completed 1/22/2024 - PREVIOUS INSPECTION NOTES 1/22/24 This inspection was for the bottom connection. L4x4x5/16x0'-4" W/ (1) 3/4" ø EPOXY BOLT W/ 9" MIN EMBED at each tilt wall panel. Holes drilled to 10" due to the Change of anchors to be used. RFI 62 Simpson strong tie titen HD 3/4" X 10" Anchors will be used in place of the detailed anchor system shown on page S-201 detail N1. 1/9/2024 - PREVIOUS INSPECTION NOTES 1/9/24 1) Tilt wall panels P-5, 8, 11, 12, 13 approved. 2) Awaiting engineering revision for panel P-14, Do not pour. 1/4/2024 - PREVIOUS INSPECTION NOTES 1/4/24 Walls P 1, 2, 3 ,4, 6, 7, 21, 22, 23, 24 and 25 approved 12/19/2023 - PREVIOUS INSPECTION NOTES 12/19/23 Inspection for tilt wall panels P-9, 10, 15, 16, 17, 18, 19 and 20 are approved to be poured. 12/18/2023 - PREVIOUS INSPECTION NOTES Inspected panel 9, 10, 16 and 18. Minimum rebar clearance of 1 1/2" needs to be maintained at the removable for areas. | |||
| ROOF SHEATHING / BRACE / TIE DOWN | 05/16/2024 | CANCELLED BY INSPECTOR | JWALKER |
| Note: Not needed | |||
| WALL SHEATHING | 05/16/2024 | APPROVED | JWALKER |
| Note: Rear canopy denz glass. | |||
| INSULATION | 05/15/2024 | PARTIALLY APPROVED | JWALKER |
| Note: 5/15/24 Shaft wall insulation approved. 5/14/2024 - PREVIOUS INSPECTION NOTES 2nd floor fire walls approved. | |||
| FIREWALL FRAMING | 05/15/2024 | PARTIALLY APPROVED | JWALKER |
| Note: 5/15/24 Shaft Wall framing approved. 4/12/2024 - PREVIOUS INSPECTION NOTES Fire walls 1st and 2nd floor at elevator stair well and 2nd floor separating wall appoved. Fire wall Framing at HVAC shaft not completed. | |||
| PLUMBING PRESSURE TEST | 05/15/2024 | Disapproved - NO FEE | JWALKER |
| Note: 5/15/24 South East VTR is not holding water. Please be sure to schedule the plumbing 2nd rough inspections for 1st and 2nd floors. 5/14/2024 - PREVIOUS INSPECTION NOTES 5/14/24 1st floor water distribution pipe approved. 2nd floor not completed. SE section of the DWV needs to be reinspected. Other sections of DWV approved. 5/7/2024 - PREVIOUS INSPECTION NOTES 5/2/2024 - PREVIOUS INSPECTION NOTES 4/30/2024 - PREVIOUS INSPECTION NOTES 3/19/2024 - PREVIOUS INSPECTION NOTES Inspection for 10 roof drains. Approved. This was a partial inspection on North side for water lines and recirc lines. Lines were valved off for areas that wer inspected and approved. Guage foe water piping was alocated @ sink reading 150 lbs.This was a partial waste and vent inspection for first floor north side and 2 bathrooms on South side.have 3 area's of concern. Plumber marked with Blue paint on these area's. AREAS THAT WERE PAINTED ONLY FROM LAST INSPECTION ARE APPROVED ONLY THING THAT I LOOKED AT | |||
| HVAC OTHER | 05/15/2024 | APPROVED | CPISCITELLI |
| Note: 5/14/2024 - PREVIOUS INSPECTION NOTES *** NOTES ADDED BY CPISCITELLI 5/14/2024 9:22:56 AM *** not ready still missing some connections on first floor | |||
| PLUMBING PRESSURE TEST | 05/14/2024 | PARTIALLY APPROVED | JWALKER |
| Note: 5/14/24 1st floor water distribution pipe approved. 2nd floor not completed. SE section of the DWV needs to be reinspected. Other sections of DWV approved. 5/7/2024 - PREVIOUS INSPECTION NOTES 5/2/2024 - PREVIOUS INSPECTION NOTES 4/30/2024 - PREVIOUS INSPECTION NOTES 3/19/2024 - PREVIOUS INSPECTION NOTES Inspection for 10 roof drains. Approved. This was a partial inspection on North side for water lines and recirc lines. Lines were valved off for areas that wer inspected and approved. Guage foe water piping was alocated @ sink reading 150 lbs.This was a partial waste and vent inspection for first floor north side and 2 bathrooms on South side.have 3 area's of concern. Plumber marked with Blue paint on these area's. AREAS THAT WERE PAINTED ONLY FROM LAST INSPECTION ARE APPROVED ONLY THING THAT I LOOKED AT | |||
| HVAC OTHER | 05/14/2024 | Disapproved - NO FEE | CPISCITELLI |
| Note: *** NOTES ADDED BY CPISCITELLI 5/14/2024 9:22:56 AM *** not ready still missing some connections on first floor | |||
| WINDOW NAILING | 05/14/2024 | APPROVED | JWALKER |
| INSULATION | 05/14/2024 | PARTIALLY APPROVED | JWALKER |
| Note: 2nd floor fire walls approved. | |||
| INSULATION | 05/10/2024 | APPROVED | FWILLIS |
| Note: 5/10/24 - ELEVATOR SHAFT 2ND FLOOR. HIGHLIGHTED ON DRAWINGS. 4/22/2024 - PREVIOUS INSPECTION NOTES 4/22/24 1st floor exterior walls. Excluding stair ways and linear accelarator room. 4/3/2024 - PREVIOUS INSPECTION NOTES Interior framing, insulation at the top out portion of the wall only, approved from the accelerator to the gym wall. | |||
| FIREWALL NAILING | 05/10/2024 | APPROVED | FWILLIS |
| Note: 5/10/24 - HIGHLIGHTED ON APPROVED DRAWINGS. | |||
| STOREFRONT | 05/10/2024 | APPROVED | FWILLIS |
| Note: 5/10/24 MARKED ON DRAWINGS. | |||
| WINDOW NAILING | 05/10/2024 | APPROVED | FWILLIS |
| Note: 5/10/24 - MARKED ON DRAWINGS. 4/3/2024 - PREVIOUS INSPECTION NOTES East wall windows, West wall windows and South wall windows first and second floor. 4/3/2024 Approved | |||
| FRAMING | 05/10/2024 | APPROVED | FWILLIS |
| Note: 5/10/24 - HIGHLIGHTED ON APPROVED DRAWINGS. 5/6/2024 - PREVIOUS INSPECTION NOTES 5/6/24: As noted in Applicant notes this Inspection is for the Ambulance Canopy Framing only. 4/10/2024 - PREVIOUS INSPECTION NOTES 4/10/24 ALL TOP OF PARAPETs 2x P.T. COPING IS APPROVED FOR ROOF COVERING. 4/10/2024 - PREVIOUS INSPECTION NOTES 4/10/24 Inspection for the 2nd floor interior wall framing, contractor approved to top out and one side needed areas. PLEAS NOTE fire walls will need to be scheduled under the fire wall framing inspection. 4/3/2024 - PREVIOUS INSPECTION NOTES Pressure treated coping at the top of the tilt walls. Top or the stair tower and the RTU screening not installed. | |||
| ELECTRIC 2ND ROUGH | 05/10/2024 | APPROVED | RMARTIN |
| Note: 5/9/2024 - PREVIOUS INSPECTION NOTES *** NOTES ADDED BY RMARTIN 5/9/2024 2:27:30 PM *** 2 south walls 2nd floor remaining 5/7/2024 - PREVIOUS INSPECTION NOTES 5/7/24 1st floor data box walls 5/3/2024 - PREVIOUS INSPECTION NOTES 5/3/24 2nd floor west walls 4/19/2024 - PREVIOUS INSPECTION NOTES 4/19/24 1st floor, marked on print 4/15/2024 - PREVIOUS INSPECTION NOTES MARKED ON PRINT | |||
| ELECTRIC 2ND ROUGH | 05/09/2024 | PARTIALLY APPROVED | RMARTIN |
| Note: *** NOTES ADDED BY RMARTIN 5/9/2024 2:27:30 PM *** 2 south walls 2nd floor remaining 5/7/2024 - PREVIOUS INSPECTION NOTES 5/7/24 1st floor data box walls 5/3/2024 - PREVIOUS INSPECTION NOTES 5/3/24 2nd floor west walls 4/19/2024 - PREVIOUS INSPECTION NOTES 4/19/24 1st floor, marked on print 4/15/2024 - PREVIOUS INSPECTION NOTES MARKED ON PRINT | |||
| ELECTRIC 2ND ROUGH | 05/07/2024 | PARTIALLY APPROVED | RMARTIN |
| Note: 5/7/24 1st floor data box walls 5/3/2024 - PREVIOUS INSPECTION NOTES 5/3/24 2nd floor west walls 4/19/2024 - PREVIOUS INSPECTION NOTES 4/19/24 1st floor, marked on print 4/15/2024 - PREVIOUS INSPECTION NOTES MARKED ON PRINT | |||
| PLUMBING PRESSURE TEST | 05/07/2024 | PARTIALLY APPROVED | MGIBSON |
| Note: 5/2/2024 - PREVIOUS INSPECTION NOTES 4/30/2024 - PREVIOUS INSPECTION NOTES 3/19/2024 - PREVIOUS INSPECTION NOTES Inspection for 10 roof drains. Approved. This was a partial inspection on North side for water lines and recirc lines. Lines were valved off for areas that wer inspected and approved. Guage foe water piping was alocated @ sink reading 150 lbs.This was a partial waste and vent inspection for first floor north side and 2 bathrooms on South side.have 3 area's of concern. Plumber marked with Blue paint on these area's. AREAS THAT WERE PAINTED ONLY FROM LAST INSPECTION ARE APPROVED ONLY THING THAT I LOOKED AT | |||
| FRAMING | 05/06/2024 | PARTIALLY APPROVED | RSIMS |
| Note: 5/6/24: As noted in Applicant notes this Inspection is for the Ambulance Canopy Framing only. 4/10/2024 - PREVIOUS INSPECTION NOTES 4/10/24 ALL TOP OF PARAPETs 2x P.T. COPING IS APPROVED FOR ROOF COVERING. 4/10/2024 - PREVIOUS INSPECTION NOTES 4/10/24 Inspection for the 2nd floor interior wall framing, contractor approved to top out and one side needed areas. PLEAS NOTE fire walls will need to be scheduled under the fire wall framing inspection. 4/3/2024 - PREVIOUS INSPECTION NOTES Pressure treated coping at the top of the tilt walls. Top or the stair tower and the RTU screening not installed. | |||
| ELECTRIC 2ND ROUGH | 05/03/2024 | PARTIALLY APPROVED | RMARTIN |
| Note: 5/3/24 2nd floor west walls 4/19/2024 - PREVIOUS INSPECTION NOTES 4/19/24 1st floor, marked on print 4/15/2024 - PREVIOUS INSPECTION NOTES MARKED ON PRINT | |||
| PLUMBING PRESSURE TEST | 05/02/2024 | PARTIALLY APPROVED | MGIBSON |
| Note: 4/30/2024 - PREVIOUS INSPECTION NOTES 3/19/2024 - PREVIOUS INSPECTION NOTES Inspection for 10 roof drains. Approved. This was a partial inspection on North side for water lines and recirc lines. Lines were valved off for areas that wer inspected and approved. Guage foe water piping was alocated @ sink reading 150 lbs.This was a partial waste and vent inspection for first floor north side and 2 bathrooms on South side.have 3 area's of concern. Plumber marked with Blue paint on these area's | |||
| PLUMBING PRESSURE TEST | 04/30/2024 | PARTIALLY APPROVED | MGIBSON |
| Note: 3/19/2024 - PREVIOUS INSPECTION NOTES Inspection for 10 roof drains. Approved. This was a partial inspection on North side for water lines and recirc lines. Lines were valved off for areas that wer inspected and approved. Guage foe water piping was alocated @ sink reading 150 lbs. | |||
| HVAC ROUGH | 04/25/2024 | PARTIALLY APPROVED | CPISCITELLI |
| Note: Inspected all main trunk square duct and tap seams on first floor. Did not inspect 2 front rooms and former gym area | |||
| ELECTRIC - EARLY POWER | 04/22/2024 | PARTIALLY APPROVED | RMARTIN |
| Note: Transformers in electrical room | |||
| INSULATION | 04/22/2024 | PARTIALLY APPROVED | JWALKER |
| Note: 4/22/24 1st floor exterior walls. Excluding stair ways and linear accelarator room. 4/3/2024 - PREVIOUS INSPECTION NOTES Interior framing, insulation at the top out portion of the wall only, approved from the accelerator to the gym wall. | |||
| ELECTRIC 2ND ROUGH | 04/19/2024 | PARTIALLY APPROVED | RMARTIN |
| Note: 4/19/24 1st floor, marked on print 4/15/2024 - PREVIOUS INSPECTION NOTES MARKED ON PRINT | |||
| FIREWALL DRYWALL NAILING | 04/19/2024 | PARTIALLY APPROVED | JWALKER |
| Note: Inspection for 2nd floor firewall drywall nailing in the communication room only, approved. 4/12/2024 - PREVIOUS INSPECTION NOTES | |||
| ELECTRIC 2ND ROUGH | 04/15/2024 | PARTIALLY APPROVED | RMARTIN |
| Note: MARKED ON PRINT | |||
| ELECTRIC - EARLY POWER | 04/12/2024 | APPROVED - AS NOTED | RMARTIN |
| Note: mdp only, call back when ready to power interior lighting, outlets etc. | |||
| FIREWALL DRYWALL NAILING | 04/12/2024 | CANCELLED BY APPLICANT | JWALKER |
| FIREWALL FRAMING | 04/12/2024 | PARTIALLY APPROVED | JWALKER |
| Note: Fire walls 1st and 2nd floor at elevator stair well and 2nd floor separating wall appoved. Fire wall Framing at HVAC shaft not completed. | |||
| FRAMING | 04/10/2024 | PARTIALLY APPROVED | JWALKER |
| Note: 4/10/24 Inspection for the 2nd floor interior wall framing, contractor approved to top out and one side needed areas. PLEAS NOTE fire walls will need to be scheduled under the fire wall framing inspection. 4/3/2024 - PREVIOUS INSPECTION NOTES Pressure treated coping at the top of the tilt walls. Top or the stair tower and the RTU screening not installed. | |||
| FRAMING | 04/10/2024 | PARTIALLY APPROVED | JWALKER |
| Note: 4/10/24 ALL TOP OF PARAPETs 2x P.T. COPING IS APPROVED FOR ROOF COVERING. 4/10/2024 - PREVIOUS INSPECTION NOTES 4/10/24 Inspection for the 2nd floor interior wall framing, contractor approved to top out and one side needed areas. PLEAS NOTE fire walls will need to be scheduled under the fire wall framing inspection. 4/3/2024 - PREVIOUS INSPECTION NOTES Pressure treated coping at the top of the tilt walls. Top or the stair tower and the RTU screening not installed. | |||
| FRAMING | 04/03/2024 | PARTIALLY APPROVED | JWALKER |
| Note: Pressure treated coping at the top of the tilt walls. Top or the stair tower and the RTU screening not installed. | |||
| WINDOW NAILING | 04/03/2024 | PARTIALLY APPROVED | JWALKER |
| Note: East wall windows, West wall windows and South wall windows first and second floor. 4/3/2024 Approved | |||
| INSULATION | 04/03/2024 | PARTIALLY APPROVED | JWALKER |
| Note: Interior framing, insulation at the top out portion of the wall only, approved from the accelerator to the gym wall. | |||
| FRAMING | 04/01/2024 | APPROVED | FWILLIS |
| Note: 4/1/24 - NORTH SIDE UPPER WALL SHEETROCK SCREW INSPECTION AS PER JIM WALKER. 3/28/2024 - PREVIOUS INSPECTION NOTES 3/28/24 Exterior Framing above stair 1, Approved. 3/25/2024 - PREVIOUS INSPECTION NOTES 3/25/24 Coping nailer inspection at the top of tilt walls and canopy framing coping. Details are not showing fasterners to be used and the required spacing of the fasteners to anchor the P.T. 2x's down to the top of the tilt walls. P.T. 2x's that have been used are not full width 2 x 10's. Contractor installed p.t. 2x4's side by side the 2x have been installed with tap cons spaced appx. 6' apart. Please have the engineer submit a revision to the building department showing the as built coping, Include type of fasteners to be use and spacing needed to properly anchor the coping. 3/21/2024 - PREVIOUS INSPECTION NOTES 3/21/24 Contractor is approved to install denzs glass to the back side of the upper canopy structual framing only. This is to allow roofing at the canopy to begin. Leave front of canopy structual framing exposed for inspection. 3/15/2024 - PREVIOUS INSPECTION NOTES 3/15/24 Interior steel stud framing 1st fl approved to install sheet rock from second floor ceiling down to 10' 6" above 1st floor finish. No blocking has been installed in the walls at this time. Contractor will keep sheet rock away from unsealed openings. 3/8/2024 - PREVIOUS INSPECTION NOTES t2nhis inspection was called in for the electric rooms on first and second floor however, the approved plans indicate the rooms that were inspected as Comm room. on site contractor reps indicate the interior of these rooms were inspected and apprioved by Inspector Jim Walker however there is no indicagtion of such inspection in the system. If the interior was not inspected as indicated the gyp board that was placed on the interior will need to be removed to uncover the fasteners for inspection. fasteners in the comm rooms on the exterior observed today except for front wall with door on first floor | |||
| FRAMING | 03/28/2024 | PARTIALLY APPROVED | JWALKER |
| Note: 3/28/24 Exterior Framing above stair 1, Approved. 3/25/2024 - PREVIOUS INSPECTION NOTES 3/25/24 Coping nailer inspection at the top of tilt walls and canopy framing coping. Details are not showing fasterners to be used and the required spacing of the fasteners to anchor the P.T. 2x's down to the top of the tilt walls. P.T. 2x's that have been used are not full width 2 x 10's. Contractor installed p.t. 2x4's side by side the 2x have been installed with tap cons spaced appx. 6' apart. Please have the engineer submit a revision to the building department showing the as built coping, Include type of fasteners to be use and spacing needed to properly anchor the coping. 3/21/2024 - PREVIOUS INSPECTION NOTES 3/21/24 Contractor is approved to install denzs glass to the back side of the upper canopy structual framing only. This is to allow roofing at the canopy to begin. Leave front of canopy structual framing exposed for inspection. 3/15/2024 - PREVIOUS INSPECTION NOTES 3/15/24 Interior steel stud framing 1st fl approved to install sheet rock from second floor ceiling down to 10' 6" above 1st floor finish. No blocking has been installed in the walls at this time. Contractor will keep sheet rock away from unsealed openings. 3/8/2024 - PREVIOUS INSPECTION NOTES t2nhis inspection was called in for the electric rooms on first and second floor however, the approved plans indicate the rooms that were inspected as Comm room. on site contractor reps indicate the interior of these rooms were inspected and apprioved by Inspector Jim Walker however there is no indicagtion of such inspection in the system. If the interior was not inspected as indicated the gyp board that was placed on the interior will need to be removed to uncover the fasteners for inspection. fasteners in the comm rooms on the exterior observed today except for front wall with door on first floor | |||
| FRAMING | 03/25/2024 | Disapproved - NO FEE | JWALKER |
| Note: 3/25/24 Coping nailer inspection at the top of tilt walls and canopy framing coping. Details are not showing fasterners to be used and the required spacing of the fasteners to anchor the P.T. 2x's down to the top of the tilt walls. P.T. 2x's that have been used are not full width 2 x 10's. Contractor installed p.t. 2x4's side by side the 2x have been installed with tap cons spaced appx. 6' apart. Please have the engineer submit a revision to the building department showing the as built coping, Include type of fasteners to be use and spacing needed to properly anchor the coping. 3/21/2024 - PREVIOUS INSPECTION NOTES 3/21/24 Contractor is approved to install denzs glass to the back side of the upper canopy structual framing only. This is to allow roofing at the canopy to begin. Leave front of canopy structual framing exposed for inspection. 3/15/2024 - PREVIOUS INSPECTION NOTES 3/15/24 Interior steel stud framing 1st fl approved to install sheet rock from second floor ceiling down to 10' 6" above 1st floor finish. No blocking has been installed in the walls at this time. Contractor will keep sheet rock away from unsealed openings. 3/8/2024 - PREVIOUS INSPECTION NOTES t2nhis inspection was called in for the electric rooms on first and second floor however, the approved plans indicate the rooms that were inspected as Comm room. on site contractor reps indicate the interior of these rooms were inspected and apprioved by Inspector Jim Walker however there is no indicagtion of such inspection in the system. If the interior was not inspected as indicated the gyp board that was placed on the interior will need to be removed to uncover the fasteners for inspection. fasteners in the comm rooms on the exterior observed today except for front wall with door on first floor | |||
| BUILDING OTHER | 03/25/2024 | APPROVED | JWALKER |
| Note: Chiller curbs | |||
| FRAMING | 03/21/2024 | PARTIALLY APPROVED | JWALKER |
| Note: 3/21/24 Contractor is approved to install denzs glass to the back side of the upper canopy structual framing only. This is to allow roofing at the canopy to begin. Leave front of canopy structual framing exposed for inspection. 3/15/2024 - PREVIOUS INSPECTION NOTES 3/15/24 Interior steel stud framing 1st fl approved to install sheet rock from second floor ceiling down to 10' 6" above 1st floor finish. No blocking has been installed in the walls at this time. Contractor will keep sheet rock away from unsealed openings. 3/8/2024 - PREVIOUS INSPECTION NOTES t2nhis inspection was called in for the electric rooms on first and second floor however, the approved plans indicate the rooms that were inspected as Comm room. on site contractor reps indicate the interior of these rooms were inspected and apprioved by Inspector Jim Walker however there is no indicagtion of such inspection in the system. If the interior was not inspected as indicated the gyp board that was placed on the interior will need to be removed to uncover the fasteners for inspection. fasteners in the comm rooms on the exterior observed today except for front wall with door on first floor | |||
| PLUMBING PRESSURE TEST | 03/19/2024 | PARTIALLY APPROVED | JWALKER |
| Note: Inspection for 10 roof drains. Approved. | |||
| FRAMING | 03/15/2024 | PARTIALLY APPROVED | JWALKER |
| Note: 3/15/24 Interior steel stud framing 1st fl approved to install sheet rock from second floor ceiling down to 10' 6" above 1st floor finish. No blocking has been installed in the walls at this time. Contractor will keep sheet rock away from unsealed openings. 3/8/2024 - PREVIOUS INSPECTION NOTES t2nhis inspection was called in for the electric rooms on first and second floor however, the approved plans indicate the rooms that were inspected as Comm room. on site contractor reps indicate the interior of these rooms were inspected and apprioved by Inspector Jim Walker however there is no indicagtion of such inspection in the system. If the interior was not inspected as indicated the gyp board that was placed on the interior will need to be removed to uncover the fasteners for inspection. fasteners in the comm rooms on the exterior observed today except for front wall with door on first floor | |||
| FRAMING | 03/08/2024 | PARTIALLY APPROVED | LMILLER |
| Note: this inspection was called in for the electric rooms on first and second floor however, the approved plans indicate the rooms that were inspected as Comm room. on site contractor reps indicate the interior of these rooms were inspected and apprioved by Inspector Jim Walker however there is no indicagtion of such inspection in the system. If the interior was not inspected as indicated the gyp board that was placed on the interior will need to be removed to uncover the fasteners for inspection. fasteners in the comm rooms on the exterior observed today except for front wall with door on first floor | |||
| FOUNDATION SURVEY - OFFICE USE ONLY | 03/07/2024 | APPROVED | DLEAP |
| PLUMBING 1ST ROUGH | 02/20/2024 | PARTIALLY APPROVED | JWALKER |
| Note: 2/20/24 Roof top: vent sleeve's, roof drains, water pipe sleeve's Note: RFI for the Chiller Please submit all Revisions to the building department. 2/1/2024 - PREVIOUS INSPECTION NOTES Inspection for sleeve's 2nd floor slab. 12/7/2023 - PREVIOUS INSPECTION NOTES 12/6/2023 - PREVIOUS INSPECTION NOTES New inspection due to canceled inspection 11/29/2023 - PREVIOUS INSPECTION NOTES 11/29/23 UG east side exam rooms. Revision on page CPLOOC of the prints. 6- 2" drain pipes and tie to previous inspected piping. 11/14/2023 - PREVIOUS INSPECTION NOTES Inspected ADA staff toilet area, center area toilet rooms B140, 143, and 144,. Condensation drain piping in this area inspected. High lighted areas inspected 11/14/23. Norht side of building exam room areas, toilet rooms at the waiting area, under piping not yet completed. SPOKE WITH JIM WALKER AND WAS ASKED TO CANCEL INSPECTION THIS COMPLETES THE UNDER GROUND PLUMBING INSPECTIONS. THE UNLESS SOMETHING ELSE IS ADDED OR NEEDED, ROOF DRAINS WILL NEED TO BE INSPECTED AND ALSO SPOKE TO C/M ABOUT PLUMBING CONTRACTORS STUB OUT 5' OUTSIDE OF BUILDING AND NEED TO HAVE CONNECTION MADE ON CIVIL PLANS BY BUILDING DEPARTMENT | |||
| ELECTRIC 1ST ROUGH | 02/20/2024 | PARTIALLY APPROVED | MKRASKI |
| Note: 2/20/24 Looked at roof deck sleeves, and 2- 4'' and 1'' pvc conduits running from east side of buiding 2/7/2024 - PREVIOUS INSPECTION NOTES 2/7/24 west side parkinglot underground 1/30/24 snd floor sleeves 1/9/2024 - PREVIOUS INSPECTION NOTES 1/9/24 tilt walls 1/4/2024 - PREVIOUS INSPECTION NOTES 1/4/24 conduit inside tilt walls 12/20/23 conduit inside tilt walls 12/4/2023 - PREVIOUS INSPECTION NOTES 12/4/23 south end 11/21/2023 - PREVIOUS INSPECTION NOTES 11/21/23 north end of building 11/17/2023 - PREVIOUS INSPECTION NOTES 11/17/23 Canceled by super 11/9/2023 - PREVIOUS INSPECTION NOTES Underground for Electrical Slab on Grade for LINAC Underground Electrical (UFER) | |||
| SECOND FLOOR SLAB | 02/20/2024 | APPROVED | JWALKER |
| Note: 2/20/24 Roof top slab , parapet walls, canopy roof top slab. 2/1/2024 - PREVIOUS INSPECTION NOTES 2/1/24 2nd floor slab main floor. Stair shaft 1st floor. Door openings 1st floor. Approved. 2nd floor slab at the canopy will be inspected later date. Inspected (9) 2nd floor columns, approved, contractor may procede. 1/31/2024 - PREVIOUS INSPECTION NOTES Inspected rebar at 1st floor door openings. Rebar inspection at the 2nd floor beams. Check for 3/4" clearance at Beam location FSB13. Check for Couplers and rebar install at beam FSB10 tilt wall panel 17. Next inspection will be for 2nd floor slab rebar and 1st floor stair way shaft slab and top of linear acceleartor walls. 1/30/2024 - PREVIOUS INSPECTION NOTES 1/11/2024 - PREVIOUS INSPECTION NOTES 1/9/2024 - PREVIOUS INSPECTION NOTES | |||
| COLUMN | 02/07/2024 | APPROVED | JWALKER |
| Note: 1/19/2024 - PREVIOUS INSPECTION NOTES 1/19/24 9 columns 1st floor | |||
| ELECTRIC 1ST ROUGH | 02/07/2024 | PARTIALLY APPROVED | RMARTIN |
| Note: 2/7/24 west side parkinglot underground 1/30/24 snd floor sleeves 1/9/2024 - PREVIOUS INSPECTION NOTES 1/9/24 tilt walls 1/4/2024 - PREVIOUS INSPECTION NOTES 1/4/24 conduit inside tilt walls 12/20/23 conduit inside tilt walls 12/4/2023 - PREVIOUS INSPECTION NOTES 12/4/23 south end 11/21/2023 - PREVIOUS INSPECTION NOTES 11/21/23 north end of building 11/17/2023 - PREVIOUS INSPECTION NOTES 11/17/23 Canceled by super 11/9/2023 - PREVIOUS INSPECTION NOTES Underground for Electrical Slab on Grade for LINAC Underground Electrical (UFER) | |||
| SECOND FLOOR SLAB | 02/02/2024 | PARTIALLY APPROVED | JWALKER |
| Note: 2/1/24 2nd floor slab main floor. Stair shaft 1st floor. Door openings 1st floor. Approved. 2nd floor slab at the canopy will be inspected later date. Inspected (9) 2nd floor columns, approved, contractor may procede. 1/31/2024 - PREVIOUS INSPECTION NOTES Inspected rebar at 1st floor door openings. Rebar inspection at the 2nd floor beams. Check for 3/4" clearance at Beam location FSB13. Check for Couplers and rebar install at beam FSB10 tilt wall panel 17. Next inspection will be for 2nd floor slab rebar and 1st floor stair way shaft slab and top of linear acceleartor walls. 1/30/2024 - PREVIOUS INSPECTION NOTES 1/11/2024 - PREVIOUS INSPECTION NOTES 1/9/2024 - PREVIOUS INSPECTION NOTES | |||
| PLUMBING 1ST ROUGH | 02/01/2024 | PARTIALLY APPROVED | JWALKER |
| Note: Inspection for sleeve's 2nd floor slab. 12/7/2023 - PREVIOUS INSPECTION NOTES 12/6/2023 - PREVIOUS INSPECTION NOTES New inspection due to canceled inspection 11/29/2023 - PREVIOUS INSPECTION NOTES 11/29/23 UG east side exam rooms. Revision on page CPLOOC of the prints. 6- 2" drain pipes and tie to previous inspected piping. 11/14/2023 - PREVIOUS INSPECTION NOTES Inspected ADA staff toilet area, center area toilet rooms B140, 143, and 144,. Condensation drain piping in this area inspected. High lighted areas inspected 11/14/23. Norht side of building exam room areas, toilet rooms at the waiting area, under piping not yet completed. SPOKE WITH JIM WALKER AND WAS ASKED TO CANCEL INSPECTION THIS COMPLETES THE UNDER GROUND PLUMBING INSPECTIONS. THE UNLESS SOMETHING ELSE IS ADDED OR NEEDED, ROOF DRAINS WILL NEED TO BE INSPECTED AND ALSO SPOKE TO C/M ABOUT PLUMBING CONTRACTORS STUB OUT 5' OUTSIDE OF BUILDING AND NEED TO HAVE CONNECTION MADE ON CIVIL PLANS BY BUILDING DEPARTMENT | |||
| SECOND FLOOR SLAB | 01/31/2024 | PARTIALLY APPROVED | JWALKER |
| Note: Inspected rebar at 1st floor door openings. Rebar inspection at the 2nd floor beams. Check for 3/4" clearance at Beam location FSB13. Check for Couplers and rebar install at beam FSB10 tilt wall panel 17. Next inspection will be for 2nd floor slab rebar and 1st floor stair way shaft slab and top of linear acceleartor walls. 1/30/2024 - PREVIOUS INSPECTION NOTES 1/11/2024 - PREVIOUS INSPECTION NOTES 1/9/2024 - PREVIOUS INSPECTION NOTES | |||
| SECOND FLOOR SLAB | 01/30/2024 | CANCELLED BY APPLICANT | JWALKER |
| Note: 1/11/2024 - PREVIOUS INSPECTION NOTES 1/9/2024 - PREVIOUS INSPECTION NOTES | |||
| ELECTRIC 1ST ROUGH | 01/30/2024 | APPROVED - AS NOTED | RMARTIN |
| Note: 1/30/24 snd floor sleeves 1/9/2024 - PREVIOUS INSPECTION NOTES 1/9/24 tilt walls 1/4/2024 - PREVIOUS INSPECTION NOTES 1/4/24 conduit inside tilt walls 12/20/23 conduit inside tilt walls 12/4/2023 - PREVIOUS INSPECTION NOTES 12/4/23 south end 11/21/2023 - PREVIOUS INSPECTION NOTES 11/21/23 north end of building 11/17/2023 - PREVIOUS INSPECTION NOTES 11/17/23 Canceled by super 11/9/2023 - PREVIOUS INSPECTION NOTES Underground for Electrical Slab on Grade for LINAC Underground Electrical (UFER) | |||
| TILT WALL | 01/22/2024 | PARTIALLY APPROVED | JWALKER |
| Note: 1/22/24 This inspection was for the bottom connection. L4x4x5/16x0'-4" W/ (1) 3/4" ø EPOXY BOLT W/ 9" MIN EMBED at each tilt wall panel. Holes drilled to 10" due to the Change of anchors to be used. RFI 62 Simpson strong tie titen HD 3/4" X 10" Anchors will be used in place of the detailed anchor system shown on page S-201 detail N1. 1/9/2024 - PREVIOUS INSPECTION NOTES 1/9/24 1) Tilt wall panels P-5, 8, 11, 12, 13 approved. 2) Awaiting engineering revision for panel P-14, Do not pour. 1/4/2024 - PREVIOUS INSPECTION NOTES 1/4/24 Walls P 1, 2, 3 ,4, 6, 7, 21, 22, 23, 24 and 25 approved 12/19/2023 - PREVIOUS INSPECTION NOTES 12/19/23 Inspection for tilt wall panels P-9, 10, 15, 16, 17, 18, 19 and 20 are approved to be poured. 12/18/2023 - PREVIOUS INSPECTION NOTES Inspected panel 9, 10, 16 and 18. Minimum rebar clearance of 1 1/2" needs to be maintained at the removable for areas. | |||
| COLUMN | 01/19/2024 | PARTIALLY APPROVED | JWALKER |
| Note: 1/19/24 9 columns 1st floor | |||
| SECOND FLOOR SLAB | 01/11/2024 | CANCELLED BY APPLICANT | JWALKER |
| Note: 1/9/2024 - PREVIOUS INSPECTION NOTES | |||
| MONOLITHIC SLAB | 01/11/2024 | APPROVED | JWALKER |
| Note: 1/11/24 Inspection for the Linac lid. 1/9/2024 - PREVIOUS INSPECTION NOTES 1/9/24 Inspected 12" rebar embedment holes only at the liner accelrator lid. RFI revision 146. Depth of drilled holes approved. 1/8/2024 - PREVIOUS INSPECTION NOTES All the drilled holes into the existing linear walls for the steel reinforcing of the lid, will need to be completed to check for correct depth. (Reference RFI 146 revision) | |||
| MONOLITHIC SLAB | 01/09/2024 | PARTIALLY APPROVED | JWALKER |
| Note: 1/9/24 Inspected 12" rebar embedment holes only at the liner accelrator lid. RFI revision 146. Depth of drilled holes approved. 1/8/2024 - PREVIOUS INSPECTION NOTES All the drilled holes into the existing linear walls for the steel reinforcing of the lid, will need to be completed to check for correct depth. (Reference RFI 146 revision) | |||
| SECOND FLOOR SLAB | 01/09/2024 | CANCELLED BY APPLICANT | JWALKER |
| TILT WALL | 01/09/2024 | PARTIALLY APPROVED | JWALKER |
| Note: 1/9/24 1) Tilt wall panels P-5, 8, 11, 12, 13 approved. 2) Awaiting engineering revision for panel P-14, Do not pour. 1/4/2024 - PREVIOUS INSPECTION NOTES 1/4/24 Walls P 1, 2, 3 ,4, 6, 7, 21, 22, 23, 24 and 25 approved 12/19/2023 - PREVIOUS INSPECTION NOTES 12/19/23 Inspection for tilt wall panels P-9, 10, 15, 16, 17, 18, 19 and 20 are approved to be poured. 12/18/2023 - PREVIOUS INSPECTION NOTES Inspected panel 9, 10, 16 and 18. Minimum rebar clearance of 1 1/2" needs to be maintained at the removable for areas. | |||
| ELECTRIC 1ST ROUGH | 01/09/2024 | PARTIALLY APPROVED | RMARTIN |
| Note: 1/9/24 tilt walls 1/4/2024 - PREVIOUS INSPECTION NOTES 1/4/24 conduit inside tilt walls 12/20/23 conduit inside tilt walls 12/4/2023 - PREVIOUS INSPECTION NOTES 12/4/23 south end 11/21/2023 - PREVIOUS INSPECTION NOTES 11/21/23 north end of building 11/17/2023 - PREVIOUS INSPECTION NOTES 11/17/23 Canceled by super 11/9/2023 - PREVIOUS INSPECTION NOTES Underground for Electrical Slab on Grade for LINAC Underground Electrical (UFER) | |||
| SECOND FLOOR SLAB | 01/08/2024 | CANCELLED BY APPLICANT | WEB |
| MONOLITHIC SLAB | 01/08/2024 | Disapproved - NO FEE | JWALKER |
| Note: All the drilled holes into the existing linear walls for the steel reinforcing of the lid, will need to be completed to check for correct depth. (Reference RFI 146 revision) | |||
| TILT WALL | 01/04/2024 | PARTIALLY APPROVED | JWALKER |
| Note: 1/4/24 Walls P 1, 2, 3 ,4, 6, 7, 21, 22, 23, 24 and 25 approved 12/19/2023 - PREVIOUS INSPECTION NOTES 12/19/23 Inspection for tilt wall panels P-9, 10, 15, 16, 17, 18, 19 and 20 are approved to be poured. 12/18/2023 - PREVIOUS INSPECTION NOTES Inspected panel 9, 10, 16 and 18. Minimum rebar clearance of 1 1/2" needs to be maintained at the removable for areas. | |||
| ELECTRIC 1ST ROUGH | 01/04/2024 | PARTIALLY APPROVED | RMARTIN |
| Note: 1/4/24 conduit inside tilt walls 12/20/23 conduit inside tilt walls 12/4/2023 - PREVIOUS INSPECTION NOTES 12/4/23 south end 11/21/2023 - PREVIOUS INSPECTION NOTES 11/21/23 north end of building 11/17/2023 - PREVIOUS INSPECTION NOTES 11/17/23 Canceled by super 11/9/2023 - PREVIOUS INSPECTION NOTES Underground for Electrical Slab on Grade for LINAC Underground Electrical (UFER) | |||
| ELECTRIC 1ST ROUGH | 12/20/2023 | APPROVED - AS NOTED | RMARTIN |
| Note: 12/20/23 conduit inside tilt walls 12/4/2023 - PREVIOUS INSPECTION NOTES 12/4/23 south end 11/21/2023 - PREVIOUS INSPECTION NOTES 11/21/23 north end of building 11/17/2023 - PREVIOUS INSPECTION NOTES 11/17/23 Canceled by super 11/9/2023 - PREVIOUS INSPECTION NOTES Underground for Electrical Slab on Grade for LINAC Underground Electrical (UFER) | |||
| TILT WALL | 12/19/2023 | PARTIALLY APPROVED | JWALKER |
| Note: 1/19/23 Inspection for tilt wall panels P-9, 10, 15, 16, 17, 18, 19 and 20 are approved to be poured. 12/18/2023 - PREVIOUS INSPECTION NOTES Inspected panel 9, 10, 16 and 18. Minimum rebar clearance of 1 1/2" needs to be maintained at the removable for areas. | |||
| TILT WALL | 12/18/2023 | Disapproved - NO FEE | JWALKER |
| Note: Inspected panel 9, 10, 16 and 18. Minimum rebar clearance of 1 1/2" needs to be maintained at the removable for areas. | |||
| MONOLITHIC SLAB | 12/18/2023 | APPROVED | JWALKER |
| Note: 12/13/2023 - PREVIOUS INSPECTION NOTES 1. Turn down mono slab footings at perimeter missing width the width of the footing and size of rebar details. See page 201 detail N-1. 2. Electrical conduit running against the form boards at the footings will need to be relocated. 3. All piping running through the footings require a sleeve 2x the size of the pipe or a releiving arch. P-305.3 4. The footing pads for the linear accelrator doors are not installed. Hole depth for the rebar into the existing footing are approved. Please provide specs for type of epoxy to be used. 5. The minimum slab debth is to be 5" areas checked are not meeting the minimum, Please remove excess soil and tamp down. 6. 6 x 6 wire mesh will need to be lifted and supported through out the slab area. | |||
| MONOLITHIC SLAB | 12/13/2023 | Disapproved - NO FEE | JWALKER |
| Note: 1. Turn down mono slab footings at perimeter missing width the width of the footing and size of rebar details. See page 201 detail N-1. 2. Electrical conduit running against the form boards at the footings will need to be relocated. 3. All piping running through the footings require a sleeve 2x the size of the pipe or a releiving arch. P-305.3 4. The footing pads for the linear accelrator doors are not installed. Hole depth for the rebar into the existing footing are approved. Please provide specs for type of epoxy to be used. 5. The minimum slab debth is to be 5" areas checked are not meeting the minimum, Please remove excess soil and tamp down. 6. 6 x 6 wire mesh will need to be lifted and supported through out the slab area. | |||
| PLUMBING 1ST ROUGH | 12/08/2023 | APPROVED - AS NOTED | MGIBSON |
| Note: 12/7/2023 - PREVIOUS INSPECTION NOTES 12/6/2023 - PREVIOUS INSPECTION NOTES New inspection due to canceled inspection 11/29/2023 - PREVIOUS INSPECTION NOTES 11/29/23 UG east side exam rooms. Revision on page CPLOOC of the prints. 6- 2" drain pipes and tie to previous inspected piping. 11/14/2023 - PREVIOUS INSPECTION NOTES Inspected ADA staff toilet area, center area toilet rooms B140, 143, and 144,. Condensation drain piping in this area inspected. High lighted areas inspected 11/14/23. Norht side of building exam room areas, toilet rooms at the waiting area, under piping not yet completed. SPOKE WITH JIM WALKER AND WAS ASKED TO CANCEL INSPECTION THIS COMPLETES THE UNDER GROUND PLUMBING INSPECTIONS. THE UNLESS SOMETHING ELSE IS ADDED OR NEEDED, ROOF DRAINS WILL NEED TO BE INSPECTED AND ALSO SPOKE TO C/M ABOUT PLUMBING CONTRACTORS STUB OUT 5' OUTSIDE OF BUILDING AND NEED TO HAVE CONNECTION MADE ON CIVIL PLANS BY BUILDING DEPARTMENT | |||
| PLUMBING 1ST ROUGH | 12/07/2023 | CANCELLED BY APPLICANT | JWALKER |
| Note: 12/6/2023 - PREVIOUS INSPECTION NOTES New inspection due to canceled inspection 11/29/2023 - PREVIOUS INSPECTION NOTES 11/29/23 UG east side exam rooms. Revision on page CPLOOC of the prints. 6- 2" drain pipes and tie to previous inspected piping. 11/14/2023 - PREVIOUS INSPECTION NOTES Inspected ADA staff toilet area, center area toilet rooms B140, 143, and 144,. Condensation drain piping in this area inspected. High lighted areas inspected 11/14/23. Norht side of building exam room areas, toilet rooms at the waiting area, under piping not yet completed. SPOKE WITH JIM WALKER AND WAS ASKED TO CANCEL INSPECTION | |||
| PLUMBING 1ST ROUGH | 12/06/2023 | CANCELLED BY APPLICANT | MGIBSON |
| Note: New inspection due to canceled inspection 11/29/2023 - PREVIOUS INSPECTION NOTES 11/29/23 UG east side exam rooms. Revision on page CPLOOC of the prints. 6- 2" drain pipes and tie to previous inspected piping. 11/14/2023 - PREVIOUS INSPECTION NOTES Inspected ADA staff toilet area, center area toilet rooms B140, 143, and 144,. Condensation drain piping in this area inspected. High lighted areas inspected 11/14/23. Norht side of building exam room areas, toilet rooms at the waiting area, under piping not yet completed. SPOKE WITH JIM WALKER AND WAS ASKED TO CANCEL INSPECTION | |||
| ABOVE GRADE CONCRETE WALL | 12/06/2023 | PARTIALLY APPROVED | JWALKER |
| Note: 12/6/23 Inspected vault North, east and west wall up to 15' 4" 11/29/2023 - PREVIOUS INSPECTION NOTES Rebar inspection for south side wall at the vault. Up to 15' 4" elevation. | |||
| FOOTER | 12/06/2023 | PARTIALLY APPROVED | JWALKER |
| Note: 12/6/23 Footings on the west side for the canopy columns. | |||
| PLUMBING 1ST ROUGH | 12/05/2023 | CANCELLED BY APPLICANT | WEB |
| Note: 11/29/2023 - PREVIOUS INSPECTION NOTES 11/29/23 UG east side exam rooms. Revision on page CPLOOC of the prints. 6- 2" drain pipes and tie to previous inspected piping. 11/14/2023 - PREVIOUS INSPECTION NOTES Inspected ADA staff toilet area, center area toilet rooms B140, 143, and 144,. Condensation drain piping in this area inspected. High lighted areas inspected 11/14/23. Norht side of building exam room areas, toilet rooms at the waiting area, under piping not yet completed. | |||
| ELECTRIC UNDERGROUND | 12/05/2023 | APPROVED | RMARTIN |
| ELECTRIC 1ST ROUGH | 12/04/2023 | PARTIALLY APPROVED | RMARTIN |
| Note: 12/4/23 south end 11/21/2023 - PREVIOUS INSPECTION NOTES 11/21/23 north end of building 11/17/2023 - PREVIOUS INSPECTION NOTES 11/17/23 Canceled by super 11/9/2023 - PREVIOUS INSPECTION NOTES Underground for Electrical Slab on Grade for LINAC Underground Electrical (UFER) | |||
| PLUMBING 1ST ROUGH | 11/29/2023 | PARTIALLY APPROVED | JWALKER |
| Note: 11/29/23 UG east side exam rooms. Revision on page CPLOOC of the prints. 6- 2" drain pipes and tie to previous inspected piping. 11/14/2023 - PREVIOUS INSPECTION NOTES Inspected ADA staff toilet area, center area toilet rooms B140, 143, and 144,. Condensation drain piping in this area inspected. High lighted areas inspected 11/14/23. Norht side of building exam room areas, toilet rooms at the waiting area, under piping not yet completed. | |||
| ABOVE GRADE CONCRETE WALL | 11/29/2023 | PARTIALLY APPROVED | JWALKER |
| Note: Rebar inspection for south side wall at the vault. Up to 15' 4" elevation. | |||
| SHEARWALL | 11/29/2023 | CANCELLED BY APPLICANT | WEB |
| FOOTER | 11/21/2023 | APPROVED | FWILLIS |
| Note: 11/21/23 - FOOTER FOR CANOPY 11/17/2023 - PREVIOUS INSPECTION NOTES 11/8/2023 - PREVIOUS INSPECTION NOTES 11/8/23 - ELEVATOR PIT BEING POURED TOMORROW. "D" FOOTER NOT POURED TODAY. "A" and "B" POURED TODAY. 11/7/2023 - PREVIOUS INSPECTION NOTES INCLUDING ELEVATOR PIT AND STAIRS. "A" AND "B" FOOTER SIDES. | |||
| ELECTRIC 1ST ROUGH | 11/21/2023 | PARTIALLY APPROVED | RMARTIN |
| Note: 11/21/23 north end of building 11/17/2023 - PREVIOUS INSPECTION NOTES 11/17/23 Canceled by super 11/9/2023 - PREVIOUS INSPECTION NOTES Underground for Electrical Slab on Grade for LINAC Underground Electrical (UFER) | |||
| ELECTRIC 1ST ROUGH | 11/17/2023 | CANCELLED BY APPLICANT | MKRASKI |
| Note: 11/17/23 Canceled by super 11/9/2023 - PREVIOUS INSPECTION NOTES Underground for Electrical Slab on Grade for LINAC Underground Electrical (UFER) | |||
| FOOTER | 11/17/2023 | CANCELLED BY APPLICANT | JWALKER |
| Note: 11/8/2023 - PREVIOUS INSPECTION NOTES 11/8/23 - ELEVATOR PIT BEING POURED TOMORROW. "D" FOOTER NOT POURED TODAY. "A" and "B" POURED TODAY. 11/7/2023 - PREVIOUS INSPECTION NOTES INCLUDING ELEVATOR PIT AND STAIRS. "A" AND "B" FOOTER SIDES. | |||
| PLUMBING 1ST ROUGH | 11/14/2023 | PARTIALLY APPROVED | JWALKER |
| Note: Inspected ADA staff toilet area, center area toilet rooms B140, 143, and 144,. Condensation drain piping in this area inspected. High lighted areas inspected 11/14/23. Norht side of building exam room areas, toilet rooms at the waiting area, under piping not yet completed. | |||
| ELECTRIC 1ST ROUGH | 11/13/2023 | PARTIALLY APPROVED | JMUNSON |
| Note: 11/9/2023 - PREVIOUS INSPECTION NOTES Underground for Electrical Slab on Grade for LINAC Underground Electrical (UFER) | |||
| TILT WALL | 11/13/2023 | CANCELLED BY INSPECTOR | PBUCKLEY |
| Note: Wrong inspection type. This was not a tilt wall inspection but a foundation wall inspection instead. Added a different inspection type for this and assigned to Jim Walker "Retaining Wall Inspection". Patrick Buckley | |||
| RETAINING WALL FOUNDATION | 11/13/2023 | PARTIALLY APPROVED | JWALKER |
| Note: Inspection for the 4' foundations walls at the elevator pit. | |||
| ELECTRIC 1ST ROUGH | 11/09/2023 | PARTIALLY APPROVED | JMUNSON |
| Note: Underground for Electrical Slab on Grade for LINAC | |||
| MONOLITHIC SLAB | 11/09/2023 | CANCELLED BY APPLICANT | WEB |
| Note: 11/8/2023 - PREVIOUS INSPECTION NOTES WILL POUR ON MONDAY. | |||
| MONOLITHIC SLAB | 11/09/2023 | APPROVED | JWALKER |
| Note: This inspection was for the LINEAR ACCELERATOR slab. New inspection due to canceled inspection 11/8/2023 - PREVIOUS INSPECTION NOTES WILL POUR ON MONDAY. | |||
| PLUMBING 1ST ROUGH | 11/09/2023 | APPROVED | JWALKER |
| Note: This inspection for the underground at the LINEAR ACCELERATOR slab area. | |||
| MONOLITHIC SLAB | 11/08/2023 | CANCELLED BY APPLICANT | FWILLIS |
| Note: WILL POUR ON MONDAY. | |||
| FOOTER | 11/08/2023 | PARTIALLY APPROVED | FWILLIS |
| Note: 11/8/23 - ELEVATOR PIT BEING POURED TOMORROW. "D" FOOTER NOT POURED TODAY. "A" and "B" POURED TODAY. 11/7/2023 - PREVIOUS INSPECTION NOTES INCLUDING ELEVATOR PIT AND STAIRS. "A" AND "B" FOOTER SIDES. | |||
| FOOTER | 11/07/2023 | Disapproved -FEE REQUIRED | FWILLIS |
| Note: INCLUDING ELEVATOR PIT AND STAIRS. "A" AND "B" FOOTER SIDES. | |||
| FOOTER | 11/02/2023 | APPROVED | FWILLIS |
| Note: 7 COLUMN FOOTERS |
Review History
| Department | Status | Date In | Date Out |
| ARCHR | COMPLETE | 06/03/2024 | 06/03/2024 |
| Note: Released By: RICHARD PICATAGI - (386)986-3760 - RPICATAGI@PALMCOASTGOV.COM | |||
| MECH | COMPLETE | 06/03/2024 | 06/13/2024 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 06/03/2024 | 06/14/2024 |
| Note: Released By: PATRICK BUCKLEY - (386)986-3786 - PBUCKLEY@PALMCOASTGOV.COM | |||
| ELEC | COMPLETE | 06/03/2024 | 06/13/2024 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| ARCHR | COMPLETE | 06/03/2024 | 06/13/2024 |
| Note: Released By: RICHARD PICATAGI - (386)986-3760 - RPICATAGI@PALMCOASTGOV.COM | |||
| DSD | COMPLETE | 06/03/2024 | 06/11/2024 |
| Note: Released By: DAMARIS RAMIREZ - (386)986-3750 - DRAMIREZ@PALMCOASTGOV.COM | |||
| FI1 | COMPLETE | 06/03/2024 | 06/06/2024 |
| Note: Released By: LEE MILLER - (386)986-3783 - WMILLER@PALMCOASTGOV.COM | |||
| ARCHR | HOLD | 05/15/2024 | 05/29/2024 |
| Note: Held By: RICHARD PICATAGI - (386)986-3760 - RPICATAGI@PALMCOASTGOV.COM Proposed facade color SW 6102 (LRV21) does not meet the required LRV of 25 for eathtones. Architect shall select alnternate color with LRV 25 or higher | |||
| BLD | COMPLETE | 05/15/2024 | 05/29/2024 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| DSD | HOLD | 05/15/2024 | 05/28/2024 |
| Note: Held By: DAMARIS RAMIREZ - (386)986-3750 - DRAMIREZ@PALMCOASTGOV.COM Narrative shows that there is some re-grading and some elevation plans being modified. These have to be submitted as a Development Order modification and is not part of the building permit vertical plan modification. | |||
| ELEC | COMPLETE | 05/15/2024 | 05/30/2024 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| FI1 | COMPLETE | 05/15/2024 | 05/29/2024 |
| Note: Released By: LEE MILLER - (386)986-3783 - WMILLER@PALMCOASTGOV.COM | |||
| GAS | CANCEL | 05/15/2024 | 05/24/2024 |
| MECH | COMPLETE | 05/15/2024 | 05/24/2024 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| PLUM | COMPLETE | 05/15/2024 | 05/29/2024 |
| Note: Released By: PATRICK BUCKLEY - (386)986-3786 - PBUCKLEY@PALMCOASTGOV.COM | |||
| UD1 | COMPLETE | 05/15/2024 | 05/20/2024 |
| Note: Released By: GREG DEGLER - - GDEGLER@PALMCOASTGOV.COM | |||
| BADMIN | INFORMATION | 04/15/2024 | 04/15/2024 |
| Note: Marked INFORMATION By: BARBIE BEMBRY - (386)986-3780 - BUILDINGDIVISION@PALMCOASTGOV.COM Civil plans are not reviewed on the building construction permt, civil plans are reviewed through the Planning Division. Please contact Dennis Leap or Damaris Ramirez for direction 386-986-3751. | |||
| PLENG | COMPLETE | 03/07/2024 | 03/07/2024 |
| Note: Released By: DENNIS R. LEAP, P.E. - (386)986-2482 - DLEAP@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 02/27/2024 | 03/07/2024 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| FI1 | COMPLETE | 02/27/2024 | 03/01/2024 |
| Note: Released By: LEE MILLER - (386)986-3783 - WMILLER@PALMCOASTGOV.COM | |||
| MECH | COMPLETE | 02/27/2024 | 03/05/2024 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| ELEC | COMPLETE | 02/27/2024 | 03/04/2024 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| PLUM | COMPLETE | 02/27/2024 | 03/06/2024 |
| Note: Released By: JIM WALKER - - JWALKER@PALMCOASTGOV.COM | |||
| FI1 | HOLD | 12/14/2023 | 12/15/2023 |
| Note: Held By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM 1. Submit a engineer revision letter stating what is being changed. | |||
| BLD | HOLD | 12/14/2023 | 12/15/2023 |
| Note: Held By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM 1. Submit a engineer revision letter stating what is being changed. | |||
| BLD | COMPLETE | 11/03/2023 | 11/16/2023 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| ELEC | COMPLETE | 11/03/2023 | 11/07/2023 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| FI1 | HOLD | 11/03/2023 | 11/14/2023 |
| Note: Held By: LEE MILLER - (386)986-3783 - WMILLER@PALMCOASTGOV.COM All fire safety systems included in the submittal are very limited cursory reviews (Any sprinkler, standpipe, alarm, fire underground documents submitted with this permit are not to be used for inspections on those systems and a note stating such must be added to those pages). Please place the above requested note on the FP pages and the Cover sheet for review. | |||
| MECH | COMPLETE | 11/03/2023 | 11/09/2023 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| PLUM | COMPLETE | 11/03/2023 | 11/17/2023 |
| Note: Released By: PATRICK BUCKLEY - (386)986-3786 - PBUCKLEY@PALMCOASTGOV.COM | |||
| FI1 | COMPLETE | 10/12/2023 | 10/13/2023 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| MECH | COMPLETE | 10/12/2023 | 10/13/2023 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 10/06/2023 | 10/11/2023 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| MECH | HOLD | 10/06/2023 | 10/11/2023 |
| Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Provide engineered drawings for roof ladder inside of building or put note on plans that this will be a defferred submittal | |||
| UD1 | COMPLETE | 10/06/2023 | 10/10/2023 |
| Note: Released By: BRICE WRIGHT - (386)986-2398 - BWRIGHT@PALMCOASTGOV.COM | |||
| FI1 | HOLD | 10/06/2023 | 10/10/2023 |
| Note: Held By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM 3. You will need seperate permits for Fire Sprinkler, Fire Alarm, BDA and FIre Underground. You will need to note this on your COVER PAGE 6. Need to classify what type of fire extinguishers are going to be installed. NFPA 10 5 | |||
| BLD | HOLD | 09/20/2023 | 09/25/2023 |
| Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM REPEAT COMMENT: 2. Correct allowable area factor for S1 SM occupancy. Not 92,000 sq. ft. It is 52,500 sq. ft per Table 506.2 for Type IIB construction. Explain how you arrived at 138,000 sq. ft.? Explain how the S1 occupancy areas in this building total 138,000 sq. ft.? Is this a mistake? See No. 4 below. (REMOVE ALLOWABLE AREA FACTOR S1 AND AND TOTAL ALLOWABLE AREA. NOT NEEDED FOR THIS PROJECT. IF WANTING TO CLAIM THIS, THEN PROVIDE COMPLETE CALCULATION OTHERWISE NOT NEEDED. NEW COMMENT: Remove reference to H1 occupancy separation- 1hr. This is a single occupancy classification | |||
| ELEC | COMPLETE | 09/20/2023 | 09/25/2023 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| FI1 | HOLD | 09/20/2023 | 09/29/2023 |
| Note: Held By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM NEED TO PROVIDE PLAN SHEET NUMBERS AND PAGES IN RESPONSE TO ALL COMMENTS. 1. Please provide information on the knox box for rapid entry access of fire department per NFPA 1, 18.2.2.2, FFPC 1 - 18.2.3.4.1.2 and AHJ. And place the following on the cover sheet: Please select FLAGLER COUNTY DEPT. of EMERGENCY MANAGEMENT, for jurisdiction or agency even though it is going in the city. This way it will get it keyed correctly. https://www.knoxbox.com/Products/Commercial-KnoxBoxes 3. You will need seperate permits for Fire Sprinkler, Fire Alarm, BDA and FIre Underground. You will need to note this on your cover page. 4. Need to add Fire extinguisher in lobby area, back stairwell. 5. Need to add Fire extinguisher in lobby area first floor. 6. Need to classify what type of fire extinguishers are going to be installed. NFPA 10 5 | |||
| MECH | HOLD | 09/20/2023 | 09/25/2023 |
| Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM PARTIAL REPEAT COMMENT: Provide construction details on fixed ladder inside building per 306.5 FBC Mechanical 2020 7Th edition or put note on plans for deferred submittal. | |||
| UD1 | HOLD | 09/20/2023 | 09/28/2023 |
| Note: Held By: BRICE WRIGHT - (386)986-2398 - BWRIGHT@PALMCOASTGOV.COM Update details W-26, W-18, R-1, R-2 to the City of Palm Coast current standards. | |||
| UD1 | HOLD | 09/19/2023 | 09/20/2023 |
| Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Need to upload missing documents | |||
| ELEC | HOLD | 09/19/2023 | 09/20/2023 |
| Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Need to upload missing documents | |||
| MECH | HOLD | 09/19/2023 | 09/20/2023 |
| Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Need to upload missing documents | |||
| FI1 | HOLD | 09/19/2023 | 09/20/2023 |
| Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Need to upload missing documents | |||
| BLD | HOLD | 09/19/2023 | 09/20/2023 |
| Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Need to upload missing documents | |||
| ARCHR | COMPLETE | 08/03/2023 | 08/16/2023 |
| Note: Released By: RICHARD PICATAGI - (386)986-3760 - RPICATAGI@PALMCOASTGOV.COM | |||
| BLD | HOLD | 08/03/2023 | 08/22/2023 |
| Note: Held By: PATRICK BUCKLEY - (386)986-3786 - PBUCKLEY@PALMCOASTGOV.COM Plan Sheet G101 1. Provide Risk Category. Yes I am aware its shown on a structural page. Overall project design and code analysis criteria by Architect of Record neeeds to also show the Risk Category. 2. Correct allowable area factor for S1 SM occupancy. Not 92,000 sq. ft. It is 52,500 sq. ft per Table 506.2 for Type IIB construction. Explain how you arrived at 138,000 sq. ft.? Explain how the S1 occupancy areas in this building total 138,000 sq. ft.? Is this a mistake? See No. 4 below. 3. Identify total areas of incidental occupancies per Section 509 and indicate area percentage per Section 509.3. Provide separate calculations for each floor not to exceed 10%. Identify separation and / or protection requirements (if any) per Sections 509.4, 509.4.1, 509.4.2 and Table 509. 4. Provide occupancy classifications for other accessory occupancies in building such as storage areas. Sections 508.2 and 508.2.1. Prove the aggregate areas of all accessory occupancies do not exceed 10% of the floor area for each floor and do not exceed tabular values for non-sprinklered buildings in Table 506.2 Plan Sheet S002 1. Modify Foundation Note F3 to indicate compaction test reports approved by EOR forwarded to the Palm Coast Building Official by GC or similar language. . 2. Modify General Notes by adding a note indicating all shop drawings and deferred submittals approved by the EOR forwarded to the Palm Coast Building Official by GC or similar language. . Miscellaneous 1. Provide copy of geotechnical investigation report signed and sealed by a Florida licensed professional engineer. Photocopy o.k. | |||
| DSD | COMPLETE | 08/03/2023 | 08/03/2023 |
| Note: Released By: DAMARIS RAMIREZ - (386)986-3750 - DRAMIREZ@PALMCOASTGOV.COM | |||
| ELEC | HOLD | 08/03/2023 | 08/17/2023 |
| Note: Held By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM 1. Submit a labeling packet showing the correct labels on all electrical equipment. NEC 2017 110.22 2.Service equipment needs to have there fault current ratings. NEC 2017 110.24 For equipment rated 800 amps and more you need to show and have panic hardware on entrance doors and egress doors and doors must open in the way of egress. NEC 2017 110.26 ( C ) (3) 3. Main Panel MSA says it is located in Waiting C 100. You will need to show that on the plans and mark out its working space on the plans and have labels where no one can sit or have anything in front of it. NEC 2017 110.26 E 4. MSA Panel is shown in room A101 but panel schedule says a different room. They need to match. 5. Need to have the working space marked out in front of MSA switchgear. NEC 2017 110.26 ( C ) (2) 6. All enclosure types shall be labeled according to. NEC 2017 110.28 and table 110.28 Where equipment operating at 1000 volts, nominal, or less to ground and likely to require examination, adjustment, servicing, or maintenance while energized is required by installation instructions or function to be located in a space with limited access, all of the following shall apply: NEC 2017 110.26 (A) (4) 7. On page E300 its shows electric rooms with working space marked out in front of them. You need to have the dimension’s on those markings. 8. Note says to go by Florida Energy code 6th edition. Need to update the code. Page 311 9. Need to show size and type of the transformers in the electrical rooms. 10. Please confirm Linear Accelerator is plug and cord connected and a disconnect is not needed in the room. 11. Switch for the lighting in the elevator pit must be readily accessible by pit door. NEC 2017 620.24 12. Building support room A107 shows a motion sensor in the room for lighting. This would need a manual override. NEC 2017 110.26 (D) | |||
| FI1 | HOLD | 08/03/2023 | 08/18/2023 |
| Note: Held By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM 1. Please provide information on the knox box for rapid entry access of fire department per NFPA 1, 18.2.2.2, FFPC 1 - 18.2.3.4.1.2 and AHJ. And place the following on the cover sheet: Please select FLAGLER COUNTY DEPT. of EMERGENCY MANAGEMENT, for jurisdiction or agency even though it is going in the city. This way it will get it keyed correctly. https://www.knoxbox.com/Products/Commercial-KnoxBoxes 2. FDC can not be on the building per the site development permit that was issused and per the AHJ. Refer to site development permit for the location. 3. You will need seperate permits for Fire Sprinkler, Fire Alarm, BDA and FIre Underground. You will need to note this on your cover page. 4. Need to show actaul travel distance between the fire extinguishers. NFPA 10 6.2.1.2.2 5. Need to classify what type of fire extinguishers are going to be installed. NFPA 10 5 6. Riser room is in the same room as all of the electrical equipment. You need to show and prove that you will have proper working space for all equipment including electrical and fire sprinkler. FBC 2020 901.8. Show dimension on plans proving that it can all go in one room. 7. We beleive it illadvised that you put the fire sprinker system and the electrical equipment in the same room and you should consult with a fire protection engineer on the placement. 8.. Fire sprinkler system needs to continue on into the empty space on 2nd flor since this is one system 9.. Need pull station in empty space on 2nd floor. | |||
| GAS | CANCEL | 08/03/2023 | 08/18/2023 |
| MECH | HOLD | 08/03/2023 | 08/18/2023 |
| Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM 1. Provide Heatload Calculation per C403.2.1 FBC Energy Conservation 2020 7Th edition 2. Provide note on plan for system commissioning per C408 FBC Energy Conservation 2020 7Th edition 3. Provide details on fixed ladder per 306.5 FBC Mechanical 2020 7Th edition | |||
| PLUM | COMPLETE | 08/03/2023 | 08/21/2023 |
| Note: Released By: PATRICK BUCKLEY - (386)986-3786 - PBUCKLEY@PALMCOASTGOV.COM | |||
| UD1 | HOLD | 08/03/2023 | 08/08/2023 |
| Note: Held By: BRICE WRIGHT - (386)986-2398 - BWRIGHT@PALMCOASTGOV.COM 1.Fees, agreements and FDEP permits, or Engineers Letter of Determination shall be completed prior to issuance of the Site Development permit. 2. Call-out sewer lift station within the project should remain private. 3. Look over in make sure all standards are current. |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| PLAN REVIEW - REVISION | ¤32.50 | 10/30/2024 |
| PLAN REVIEW - REVISION | ¤32.50 | 10/30/2024 |
| PLAN REVIEW - REVISION | ¤32.50 | 10/30/2024 |
| REINSPECTION - COMMERCIAL | ¤60.00 | 10/30/2024 |
| REINSPECTION - COMMERCIAL | ¤60.00 | 10/30/2024 |
| FC IMPACT FEE EMS | ¤2,240.00 | 10/13/2023 |
| IMPACT FEE FIRE | ¤23,800.00 | 10/13/2023 |
| FC IMPACT FEE LAW ENFORCEMENT | ¤8,715.00 | 10/13/2023 |
| IMPACT FEE TRANSPORTATION | ¤140,175.00 | 10/13/2023 |
| SURCHARGE FS 533.721 | ¤822.13 | 10/13/2023 |
| SURCHARGE - FS 468.631 | ¤1,233.19 | 10/13/2023 |
| SITE PLAN 30 | ¤30.00 | 10/13/2023 |
| ADJUSTMENT 50% | (¤82,212.50) | 10/13/2023 |
| ADMINISTRATIVE - COMMERCIAL | ¤75.00 | 10/13/2023 |
| INSPECTION COMMERCIAL | ¤133,000.00 | 10/13/2023 |
| INSPECTION - FIRE COMMERCIAL | ¤4,750.00 | 10/13/2023 |
| PLAN REVIEW - COMMERCIAL | ¤26,600.00 | 10/13/2023 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤259,445.32 |