Permit #2023081331
Permit Details
Status: COED
| Parcel Id: 07-11-31-7064-00090-0140 |
| Block: 00090 |
| Subdivision: 2178 - SECTION 64-LAGUNA FOREST |
| Job Phone: 904-813-0124 |
| Location Address: 8 LLACH CT |
| Type: RF - REROOF |
| Issue Date: 08/25/2023 |
| NOC: RECORDED |
| Applicant name: JORDAN R WEBB |
| Owner: ZDEBSKIY IVAN |
|
Address 23 WHITE HOUSE DR PALM COAST, FL 32164 |
| Lot: 0140 |
| Contracted Stated Job Value: ¤18,400.00 |
| Job Description: Reroof |
| Type: CN |
Contractor
REDTAIL ROOFING LLC
| Status | Location Address | State License Number | Phone |
| ACTIVE |
7643 GATE PARKWAY 104-177 JACKSONVILLE, FL 32256 |
CCC1331300 (Exp: 08/31/2026) | 904-813-0124 |
Inspection History
| Type | Request Date | Result | Inspector |
| ROOF FINAL | 11/22/2023 | Disapproved - NO FEE | BTAYLOR |
| Note: 11/20/2023 - PREVIOUS INSPECTION NOTES 11-20-23 Inspection performed via on-roof inspection as the first level roof and upper level roof had a walkable attachement (drone was not needed). The upper level ridge is missing a row of shingles on one side and the ridge caps have been placed offset in order to try and cover the section that is missing a row of shingles. Need to place the missing row of shingles at the ridge on the upper (highest) portion of the roof or provide manufactureer installation instruction showing magtching the missing row and offset redge cap. 10/23/2023 - PREVIOUS INSPECTION NOTES 10-23-23 1. Need to schedule drone inspection.Being forwarded to get scheduled for drone in spection. 11-22-23 1. Need to schedule drone inspection.Being forwarded to get scheduled for drone in spection. | |||
| ROOF FINAL | 11/22/2023 | FINAL APPROVED | BTAYLOR |
| Note: 11/22/2023 - PREVIOUS INSPECTION NOTES 11/20/2023 - PREVIOUS INSPECTION NOTES 11-20-23 Inspection performed via on-roof inspection as the first level roof and upper level roof had a walkable attachement (drone was not needed). The upper level ridge is missing a row of shingles on one side and the ridge caps have been placed offset in order to try and cover the section that is missing a row of shingles. Need to place the missing row of shingles at the ridge on the upper (highest) portion of the roof or provide manufactureer installation instruction showing magtching the missing row and offset redge cap. 10/23/2023 - PREVIOUS INSPECTION NOTES 10-23-23 1. Need to schedule drone inspection.Being forwarded to get scheduled for drone in spection. 11-22-23 1. Need to schedule drone inspection.Being forwarded to get scheduled for drone in spection. | |||
| ROOF FINAL | 11/20/2023 | Disapproved - NO FEE | LMILLER |
| Note: 11-20-23 Inspection performed via on-roof inspection as the first level roof and upper level roof had a walkable attachement (drone was not needed). The upper level ridge is missing a row of shingles on one side and the ridge caps have been placed offset in order to try and cover the section that is missing a row of shingles. Need to place the missing row of shingles at the ridge on the upper (highest) portion of the roof or provide manufactureer installation instruction showing magtching the missing row and offset redge cap. 10/23/2023 - PREVIOUS INSPECTION NOTES 10-23-23 1. Need to schedule drone inspection.Being forwarded to get scheduled for drone in spection. | |||
| ROOF FINAL | 10/23/2023 | Disapproved - NO FEE | BTAYLOR |
| Note: 10-23-23 1. Need to schedule drone inspection.Being forwarded to get scheduled for drone in spection. | |||
| ROOF AFFIDAVIT | 10/20/2023 | APPROVED | MRAMOS |
| ROOF IN PROGRESS- MIDROOF | 10/19/2023 | APPROVED | RSIMS |
| Note: 10/18/2023 - PREVIOUS INSPECTION NOTES 10-18-23 1. Not ready. | |||
| ROOF IN PROGRESS- MIDROOF | 10/18/2023 | Disapproved - NO FEE | BTAYLOR |
| Note: 10-18-23 1. Not ready. |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| ADJUSTMENT 50% | (¤45.00) | 08/25/2023 |
| ADMINISTRATIVE RESIDENTIAL | ¤30.00 | 08/25/2023 |
| INSPECTION - RESIDENTIAL | ¤60.00 | 08/25/2023 |
| SURCHARGE FS 533.721 | ¤2.00 | 08/25/2023 |
| SURCHARGE - FS 468.631 | ¤2.00 | 08/25/2023 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤49.00 |