Permit #2023091162
Permit Details
Status: FINAL
| Parcel Id: 29-10-31-5540-00000-0320 |
| Block: 00000 |
| Subdivision: 5540 - |
| Job Phone: (386)931-7331 |
| Location Address: 58 OLD OAK DR S |
| Type: SW - SEAWALL |
| Issue Date: 11/03/2023 |
| NOC: RECORDED |
| Applicant name: SCOTT DALE SOWERS |
| Owner: BRAYTON SALLY & THOMAS E CIOFFI W&H |
|
Address 56 OLD OAK DRIVE S PALM COAST, FL 32137 |
| Lot: 0320 |
| Contracted Stated Job Value: ¤25,000.00 |
| Job Description: Installation of 100 LF of Coquina Revetment Shoreline Stabilization |
| Type: CN |
Contractor
S E CLINE CONSTRUCTION, INC
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
PO BOX 354425 PALM COAST, FL 32137 |
CGC061947 (Exp: 08/31/2028) | (386)446-6426 | (386)446-6481 |
Inspection History
| Type | Request Date | Result | Inspector |
| SEAWALL FINAL | 03/11/2024 | FINAL APPROVED | LMILLER |
| Note: 3-11-24 note below resolved 3/1/2024 - PREVIOUS INSPECTION NOTES 03-01-2024 Turbidity barrier not removed. | |||
| SEAWALL FINAL | 03/01/2024 | Disapproved - NO FEE | AGAETANO |
| Note: 03-01-2024 Turbidity barrier not removed. | |||
| ROW - STORMWATER FINAL | 02/28/2024 | APPROVED | GBERTOLA |
| Note: AT THE TIME OF THE INSPECTION, ALL MINIMUM CITY REQUIREMENTS WERE MET. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED ** 12/04/23 TURBIDITY BARRIER TO REMAIN IN PLACE THROUGH OUT THE ENTIRE CONST4RUCTION PROCESS Inspector Notes from Inspection 9215 ** 12/04/23 TURBIDITY BARRIER TO REMAIN IN PLACE THROUGH OUT THE ENTIRE CONST4RUCTION PROCESS | |||
| ROW - FINAL INSPECTION | 02/28/2024 | APPROVED | GBERTOLA |
| Note: AT THE TIME OF THE INSPECTION, ALL MINIMUM CITY REQUIREMENTS WERE MET. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED ** 12/04/23 TURBIDITY BARRIER TO REMAIN IN PLACE THROUGH OUT THE ENTIRE CONST4RUCTION PROCESS Inspector Notes from Inspection 9215 ** 12/04/23 TURBIDITY BARRIER TO REMAIN IN PLACE THROUGH OUT THE ENTIRE CONST4RUCTION PROCESS | |||
| SEAWALL DEADMAN CAP | 01/29/2024 | APPROVED | AGAETANO |
| ROW -TURBIDITY BARRER | 12/04/2023 | APPROVED - AS NOTED | EMADISON |
| Note: ** 12/04/23 TURBIDITY BARRIER TO REMAIN IN PLACE THROUGH OUT THE ENTIRE CONST4RUCTION PROCESS | |||
| WILDLIFE CHECK - ENVIRONMENTAL | 10/31/2023 | APPROVED | DRODRIGUEZ |
Review History
| Department | Status | Date In | Date Out |
| PLENV | COMPLETE | 10/31/2023 | 10/31/2023 |
| Note: Released By: DYLAN RODRIGUEZ - - DRODRIGUEZ@PALMCOASTGOV.COM The documents provided meet the criteria of the 10.04.01 of the LDC for wildlife protection. The burrow is outside of work area by the required 25 feet. If burrow is impacted in the future further coordination may be required. It is recommended this 25 foot area is flagged to avoid distubance during consturction activity. | |||
| ENGIN1 | COMPLETE | 09/27/2023 | 09/28/2023 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| SW1 | COMPLETE | 09/27/2023 | 09/28/2023 |
| Note: Released By: PARREN FLANAGAN - (386)986-2392 - PFLANAGAN@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 09/27/2023 | 09/27/2023 |
| Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM Zoning does not review these coquina revetements on the ICW. They are approved by state agencies. | |||
| PLENV | HOLD | 09/27/2023 | 10/02/2023 |
| Note: Held By: DYLAN RODRIGUEZ - - DRODRIGUEZ@PALMCOASTGOV.COM Staff conduced a site visit on 10/02/23 and found potentially occupied Gopher Tortoise burrow. Please either provide a Gopher Tortoise survey by a QEP that shows the burrow is not within 25ft of construction activities or an approved After Action Report from FWC after relocation activities have been completed. |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| ADJUSTMENT 50% | (¤141.25) | 11/03/2023 |
| ADMINISTRATIVE - COMMERCIAL | ¤75.00 | 11/03/2023 |
| INSPECTION COMMERCIAL | ¤175.00 | 11/03/2023 |
| PLAN REVIEW - MISC 32.50 | ¤32.50 | 11/03/2023 |
| SURCHARGE FS 533.721 | ¤2.00 | 11/03/2023 |
| SURCHARGE - FS 468.631 | ¤2.12 | 11/03/2023 |
| SW ENG REVIEW- 40 | ¤40.00 | 11/03/2023 |
| SW ENG - INSPECTION 20 | ¤20.00 | 11/03/2023 |
| SW ENG - REVIEW 20 | ¤20.00 | 11/03/2023 |
| SITE PLAN 15 | ¤15.00 | 11/03/2023 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤240.37 |