I want to search for...
Permit #2023101287
Permit Details
Status: COED
| Parcel Id: 07-11-31-7037-01270-0190 |
| CONDITIONED SPACE: 1500 sqft |
| GARAGE: 396 sqft |
| OPENED PORCH (WITH ROOF) : 19 sqft |
| OPENED PORCH (WITH ROOF) : 100 sqft |
| Total Square Footage: 2015 sqft |
| Block: 01270 |
| Subdivision: 2176 - SECTION 37-LAKEVIEW |
| Job Phone: 202-494-2019 |
| Location Address: 18 LONDONDERRY DR |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 12/07/2023 |
| NOC: RECORDED |
| Applicant name: GARY ANDREW FISCHER |
| Owner: INB FUND 2 LLC |
|
Address 3670 MAGUIRE BOULEVARD SUITE 220 ORLANDO, FL 32803 |
| Lot: 0190 |
| Contracted Stated Job Value: ¤150,000.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
INB HOMES
| Status | Location Address | Mailing Address | State License Number | Phone |
| ACTIVE |
3670 MAGUIRE BLVD ORLANDO, FL 32803 |
SUITE 210 ORLANDO, FL 32803 |
CGC048746 (Exp: 08/31/2026) | 407-476-8195 |
Sub Contractors
HEATH EDWARD SANFORD
| Status | Location Address | State License Number | Phone |
| ACTIVE |
126 EAST END RD SAN MATEO, FL 32187 |
CFC1429896 (Exp: 08/31/2026) | 386-871-8823 |
ROBERT MICHAEL RENNER
| Status | Location Address | State License Number | Phone |
| ACTIVE |
531 CODISCO WAY SANFORD, FL 32771 |
CAC051477 (Exp: 08/31/2026) | 407-333-2665 |
JOSEPH HORATIO STRADA JR
| Status | Location Address | State License Number | Phone |
| ACTIVE |
3400 ST JOHNS PARKWAY SANFORD, FL 32771 |
EC13003715 (Exp: 08/31/2026) | 877-906-1113 |
TERRY BRICE DICKERSON
| Status | Location Address | State License Number | Phone |
| ACTIVE |
4300 ST JOHN'S PARKWAY ALPHARETTA, GA 30009 |
CCC1326209 (Exp: 08/31/2026) | 407-548-6733 |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 06/26/2024 | Disapproved -FEE REQUIRED | AGAETANO |
| Note: 06-26-2024 1. Dumpster in yard. 2. Job Johnny on site. 3. AC being worked on. 4. Railing steps not installed. Cooktop not installed. Drawings are a mess. Contractor not ready. A complete inspection is rquired. | |||
| BLD - BUILDING FINAL | 06/26/2024 | FINAL APPROVED | AGAETANO |
| Note: | |||
| ROW - STORMWATER FINAL | 06/26/2024 | APPROVED | EMADISON |
| U -UTILITY RESIDENTIAL FINAL | 06/26/2024 | FINAL APPROVED | DHANEY |
| Note: Inspector Notes from Inspection 9035 Has a PVB on IRR | |||
| ROW- PROJECT STATUS | 06/25/2024 | APPROVED | GBERTOLA |
| Note: THE BUILDER NEEDS TO ELEVATE THE BACK PROPERTY LINE TO PREVENT WATER FROM LEAVING YOUR PROPERTY. | |||
| ROW - FINAL APRON (AFTER POUR) | 06/25/2024 | APPROVED | GBERTOLA |
| Note: AT THE TIME OF THE INSPECTION, ALL MINIMUM CITY REQUIREMENTS WERE MET. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED. THIS INCLUDES BUT IS NOT LIMITED TO THE CULVERT PIPE ELEVATION APPROVAL FOR THE CONCRETE POUR. | |||
| ROW FIELD SURVEY /GRADING CERTIFICATION | 06/25/2024 | APPROVED | GBERTOLA |
| Note: 6/25/24=AT THE TIME OF THE INSPECTION, ALL MINIMUM CITY REQUIREMENTS WERE MET. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED. THIS INCLUDES BUT IS NOT LIMITED TO THE CULVERT PIPE ELEVATION APPROVAL FOR THE CONCRETE POUR. THE BUILDER NEEDS TO ELEVATE THE BACK PROPERTY LINE TO PREVENT WATER FROM LEAVING THE PROPERTY. THE BUILDER INSTALLED A SWALE BY THE PROPERTY LINE TO HELP DIRECT THE WATER FORWARD. ++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ 6/21/2024 - PREVIOUS INSPECTION NOTES THE FINAL SURVEY HAS BEEN APPROVED IN THE OFFICE, BUT THE BUILDER NEEDS TO SUBMIT A NEW FINAL SURVEY WITH ALL THE CORRECTIONS. IN THE FIELD, WATER IS IMPACTING THE NEIGHBOR ON THE BACK PROPERTY. ON THE LEFT SIDE OF THE HOUSE, THERE IS A SIGNIFICANT ISSUE WITH WATER NOT DRAINING FORWARD. | |||
| ROW- FINAL SURVEY/GRADING CERTIFICATION | 06/21/2024 | APPROVED | GBERTOLA |
| Note: 6/21/24=AT THE TIME OF THE INSPECTION, ALL MINIMUM CITY REQUIREMENTS WERE MET. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED. THIS INCLUDES BUT IS NOT LIMITED TO THE CULVERT PIPE ELEVATION APPROVAL FOR THE CONCRETE POUR. ** 04/25/24 READY TO POUR ** At the time of the inspection all minimum city requirements were met. It is the builders responsibility to ensure that nothing changes after this Inspection is approved. This includes but is not limited to, the Culvert Pipe Elevation from the time of the inspection approval to the concrete pour. **MAKE SURE THERE IS 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE (FRC) DRAWING 300,E RESIDENTIAL CULVERT DETAIL | |||
| ROW FIELD SURVEY /GRADING CERTIFICATION | 06/21/2024 | Disapproved - NO FEE | GBERTOLA |
| Note: THE FINAL SURVEY HAS BEEN APPROVED IN THE OFFICE, BUT THE BUILDER NEEDS TO SUBMIT A NEW FINAL SURVEY WITH ALL THE CORRECTIONS. IN THE FIELD, WATER IS IMPACTING THE NEIGHBOR ON THE BACK PROPERTY. ON THE LEFT SIDE OF THE HOUSE, THERE IS A SIGNIFICANT ISSUE WITH WATER NOT DRAINING FORWARD. | |||
| U-CROSS CONNECTION | 06/12/2024 | APPROVED - AS NOTED | BWRIGHT |
| Note: Has a PVB on IRR | |||
| ROW- PRE-APRON (PRE-POUR) | 04/25/2024 | APPROVED - AS NOTED | EMADISON |
| Note: ** 04/25/24 READY TO POUR ** At the time of the inspection all minimum city requirements were met. It is the builders responsibility to ensure that nothing changes after this Inspection is approved. This includes but is not limited to, the Culvert Pipe Elevation from the time of the inspection approval to the concrete pour. **MAKE SURE THERE IS 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE (FRC) DRAWING 300,E RESIDENTIAL CULVERT DETAIL | |||
| ELECTRIC - EARLY POWER | 04/19/2024 | APPROVED | JSTEWART |
| GRAVITY SEWER TEST | 04/16/2024 | APPROVED | MGIBSON |
| Note: Inspector Notes from Inspection 2060 NEED TEMPORARY DRAINAGGE PIPE ACCROSS SWELL AREA | |||
| SEWER TIE IN | 04/16/2024 | APPROVED | MGIBSON |
| Note: Inspector Notes from Inspection 2060 NEED TEMPORARY DRAINAGGE PIPE ACCROSS SWELL AREA | |||
| PEP TANK INSTALLATION REQUEST | 03/22/2024 | APPROVED | BVITALE |
| INSULATION | 03/18/2024 | APPROVED | FWILLIS |
| ALL ROUGH | 03/12/2024 | APPROVED | JSTEWART |
| Note: 3/8/2024 - PREVIOUS INSPECTION NOTES 3/8/24- 1. Exterior Lights (3) are not installed at Front entry column walls, and right Of garage opening. per plans 2. Please have a mechanical fastener at all bathroom Exhaust fan duct connection. 3/6/2024 - PREVIOUS INSPECTION NOTES 03-06-2024 1. Energy calcs and mechanical layout not on site. 2. Back bathroom exhaust not sealed at roof deck. | |||
| LATH/BRICK/ WATER BARRIER | 03/11/2024 | APPROVED | FWILLIS |
| ALL ROUGH | 03/08/2024 | Disapproved - NO FEE | JSTEWART |
| Note: 3/8/24- 1. Exterior Lights (3) are not installed at Front entry column walls, and right Of garage opening. per plans 2. Please have a mechanical fastener at all bathroom Exhaust fan duct connection. 3/6/2024 - PREVIOUS INSPECTION NOTES 03-06-2024 1. Energy calcs and mechanical layout not on site. 2. Back bathroom exhaust not sealed at roof deck. | |||
| ALL ROUGH | 03/06/2024 | Disapproved - NO FEE | AGAETANO |
| Note: 03-06-2024 1. Energy calcs and mechanical layout not on site. 2. Back bathroom exhaust not sealed at roof deck. | |||
| ELECTRIC-TUG | 03/06/2024 | APPROVED | RMARTIN |
| ROOF VALLEY & METAL | 02/28/2024 | APPROVED | FWILLIS |
| WALL SHEATHING | 02/23/2024 | APPROVED | FWILLIS |
| Note: 2/20/2024 - PREVIOUS INSPECTION NOTES Sheathing needs to be removed to see truss straps on lani | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 02/23/2024 | APPROVED | FWILLIS |
| Note: 2/20/2024 - PREVIOUS INSPECTION NOTES 1. Lani truss straps have been covered by sheathing need to remove sheathing to check nails on straps 2. Need full set of plans on sit for inspection 3. No load bearing door open detail | |||
| ROOF SHEATHING | 02/22/2024 | APPROVED | FWILLIS |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 02/20/2024 | Disapproved - NO FEE | MKRASKI |
| Note: 1. Lani truss straps have been covered by sheathing need to remove sheathing to check nails on straps 2. Need full set of plans on sit for inspection 3. No load bearing door open detail | |||
| WALL SHEATHING | 02/20/2024 | Disapproved - NO FEE | MKRASKI |
| Note: Sheathing needs to be removed to see truss straps on lani | |||
| TIE BEAM / LINTEL | 02/02/2024 | APPROVED | FWILLIS |
| Note: Inspector Notes from Inspection 2250 NEED TO PROVIDE PROOF OF TERMITE PROTECTION AT NEXT INSPECTION. | |||
| FOUND SURVEY APPROVED (OFFICE) | 02/02/2024 | APPROVED | TBAKER |
| MONOLITHIC SLAB | 01/24/2024 | APPROVED - AS NOTED | FWILLIS |
| Note: NEED TO PROVIDE PROOF OF TERMITE PROTECTION AT NEXT INSPECTION. | |||
| ROW - DRAINAGE | 01/23/2024 | APPROVED - AS NOTED | EMADISON |
| Note: ** 01/23/24 CORRECTIONS MADE ** IT IS THE BUILDERS RESPONSIBILITY TO MAINTAIN THE DRAINAGE OF THE JOB SITE ________________________________________________________________________________________________________________ 1/22/2024 - PREVIOUS INSPECTION NOTES ** 01/22/24 NO CORRECTIONS HAVE BEEN MADE SINCE PREVIOUS INSPECTION ** BUILDER NEEDDS TO OPEN THE ROAD SIDE SWALE TO ALLOW THE STORMWATER TO FLOW AND NOT BACK UP CREATING A MEGATIVE IMPACT ON ADJACENT PROPERTIES OR THE ROAD WAY ** NEED TO PUT PORT-A-JOHN ONTO JOBSITE REMOVE IT FROM EDGE OF ROAD AND RIGHT OF WAY (ROW) ** SEE ATTACHED PHOTOS ** FOLLOW UP INSPECTION ON 01/23/24 ____________________________________________________________________________________________________________________ 1/16/2024 - PREVIOUS INSPECTION NOTES ** 01/16/24 BUILDER NEEDDS TO OPEN THE ROAD SIDE SWALE TO ALLOW THE STORMWATER TO FLOW AND NOT BACK UP CREATING A MEGATIVE IMPACT ON ADJACENT PROPERTIES OR THE ROAD WAY ** NEED TO PUT PORT-A-JOHN ONTO JOBSITE REMOVE IT FROM EDGE OF ROAD AND RIGHT OF WAY (ROW) ** SEE ATTACHED PHOTOS ** FOLLOW UP INSPECTION ON 01/20/24 | |||
| ROW - DRAINAGE | 01/20/2024 | Disapproved -FEE REQUIRED | EMADISON |
| Note: ** 01/22/24 NO CORRECTIONS HAVE BEEN MADE SINCE PREVIOUS INSPECTION ** BUILDER NEEDDS TO OPEN THE ROAD SIDE SWALE TO ALLOW THE STORMWATER TO FLOW AND NOT BACK UP CREATING A MEGATIVE IMPACT ON ADJACENT PROPERTIES OR THE ROAD WAY ** NEED TO PUT PORT-A-JOHN ONTO JOBSITE REMOVE IT FROM EDGE OF ROAD AND RIGHT OF WAY (ROW) ** SEE ATTACHED PHOTOS ** FOLLOW UP INSPECTION ON 01/23/24 ____________________________________________________________________________________________________________________ 1/16/2024 - PREVIOUS INSPECTION NOTES ** 01/16/24 BUILDER NEEDDS TO OPEN THE ROAD SIDE SWALE TO ALLOW THE STORMWATER TO FLOW AND NOT BACK UP CREATING A MEGATIVE IMPACT ON ADJACENT PROPERTIES OR THE ROAD WAY ** NEED TO PUT PORT-A-JOHN ONTO JOBSITE REMOVE IT FROM EDGE OF ROAD AND RIGHT OF WAY (ROW) ** SEE ATTACHED PHOTOS ** FOLLOW UP INSPECTION ON 01/20/24 | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 01/19/2024 | APPROVED - AS NOTED | MGIBSON |
| Note: NEED TEMPORARY DRAINAGGE PIPE ACCROSS SWELL AREA | |||
| ROW - DRAINAGE | 01/16/2024 | Disapproved - NO FEE | EMADISON |
| Note: ** 01/16/24 BUILDER NEEDDS TO OPEN THE ROAD SIDE SWALE TO ALLOW THE STORMWATER TO FLOW AND NOT BACK UP CREATING A MEGATIVE IMPACT ON ADJACENT PROPERTIES OR THE ROAD WAY ** NEED TO PUT PORT-A-JOHN ONTO JOBSITE REMOVE IT FROM EDGE OF ROAD AND RIGHT OF WAY (ROW) ** SEE ATTACHED PHOTOS ** FOLLOW UP INSPECTION ON 01/20/24 | |||
| ROW - DRAINAGE | 01/04/2024 | APPROVED | EMADISON |
| Note: 1/3/2024 - PREVIOUS INSPECTION NOTES ** 01/03/24 BUILDER NEEDS TO REMOVE THE DIRT PILES FROM THE EDGE OF ROADWAY AS THIS IS CREATING A SAFETY HAZARD FOR PEDESTRIANS , MOTORISTS, AND BICYCLISTS THIS NEEDS TO BE DONE IMMEDIATELY ** REMOVE PORT-A-JOHN FROM THE ROW AND EDGE OF ROADWAY PUT ONTO JOB SITE ** SEE ATTACHED PHOTOS ** FOLLOW UP INSPECTION 01/04/24 DUE TO ROAD WAY HAZARD | |||
| ROW - DRAINAGE | 01/03/2024 | Disapproved - NO FEE | EMADISON |
| Note: ** 01/03/24 BUILDER NEEDS TO REMOVE THE DIRT PILES FROM THE EDGE OF ROADWAY AS THIS IS CREATING A SAFETY HAZARD FOR PEDESTRIANS , MOTORISTS, AND BICYCLISTS THIS NEEDS TO BE DONE IMMEDIATELY ** REMOVE PORT-A-JOHN FROM THE ROW AND EDGE OF ROADWAY PUT ONTO JOB SITE ** SEE ATTACHED PHOTOS ** FOLLOW UP INSPECTION 01/04/24 DUE TO ROAD WAY HAZARD | |||
| WATER METER INSTALLATION REQUEST | 12/21/2023 | APPROVED | BVITALE |
Review History
| Department | Status | Date In | Date Out |
| MECH | COMPLETE | 06/07/2024 | 06/12/2024 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 02/02/2024 | 02/02/2024 |
| Note: Released By: SCOTT THOMAS - (386)986-3780 - STHOMAS@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 02/02/2024 | 02/02/2024 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 01/24/2024 | 01/25/2024 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 01/19/2024 | 01/19/2024 |
| Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM | |||
| ENGIN1 | HOLD | 01/19/2024 | 01/19/2024 |
| Note: Held By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM Formboard survey is unacceptable as foundation survey. Please submit foundation survey showing location, dimensions and elevation of finished concrete foundation/slab. | |||
| ENGIN1 | COMPLETE | 12/20/2023 | 12/20/2023 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| SW1 | COMPLETE | 12/20/2023 | 12/20/2023 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 12/20/2023 | 12/20/2023 |
| Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 11/09/2023 | 11/09/2023 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| SWALE | COMPLETE | 10/30/2023 | 12/29/2023 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 10/27/2023 | 10/30/2023 |
| Note: Released By: JPI | |||
| CUSVC | COMPLETE | 10/27/2023 | 10/30/2023 |
| Note: Released By: HALEIGH HAND - - HHAND@PALMCOASTGOV.COM | |||
| ELEC | COMPLETE | 10/27/2023 | 10/31/2023 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 10/27/2023 | 10/30/2023 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| GAS | CANCEL | 10/27/2023 | 10/31/2023 |
| LOCATE | COMPLETE | 10/27/2023 | 10/31/2023 |
| Note: Released By: CANDACE BOWERMASTER - - CBOWERMASTER@PALMCOASTGOV.COM | |||
| MECH | COMPLETE | 10/27/2023 | 10/31/2023 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| SW1 | COMPLETE | 10/27/2023 | 11/08/2023 |
| Note: Released By: JEFF CREWS - - JCREWS@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 10/27/2023 | 10/30/2023 |
| Note: Released By: MICHELLE RAMOS - (386)986-3780 - MRAMOS@PALMCOASTGOV.COM | |||
| BADMIN | COMPLETE | 10/27/2023 | 10/31/2023 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| PLAN REVIEW - REVISION | ¤32.50 | 06/25/2024 |
| SW ENG - INSPECTION 20 | ¤20.00 | 06/25/2024 |
| SW ENG - INSPECTION 20 | ¤20.00 | 06/25/2024 |
| SW ENG - INSPECTION 20 | ¤20.00 | 06/25/2024 |
| SW ENG - INSPECTION 20 | ¤20.00 | 06/25/2024 |
| SW ENG - INSPECTION 20 | ¤20.00 | 06/25/2024 |
| SW ENG REINSPECTION 20 | ¤20.00 | 06/25/2024 |
| SW ENG - REVIEW 20 | ¤20.00 | 12/07/2023 |
| SW ENG RES REVIEW 200 | ¤200.00 | 12/07/2023 |
| SEWER CREDIT | (¤1,342.00) | 12/07/2023 |
| SEWER INSPECTION | ¤25.00 | 12/07/2023 |
| SEWER CAPITAL FACILITY | ¤5,344.82 | 12/07/2023 |
| WATER CAPITAL FACILITY FEE | ¤3,923.88 | 12/07/2023 |
| SITE PLAN 30 | ¤30.00 | 12/07/2023 |
| SW ENG INSPECTION 80 | ¤80.00 | 12/07/2023 |
| SW ENG PRE APRON | ¤30.00 | 12/07/2023 |
| WATER- TURN ON | ¤25.00 | 12/07/2023 |
| ADJUSTMENT 50% | (¤346.82) | 12/07/2023 |
| ADMINISTRATIVE RESIDENTIAL | ¤30.00 | 12/07/2023 |
| INSPECTION - RESIDENTIAL | ¤517.00 | 12/07/2023 |
| PLAN REVIEW - RESIDENTIAL | ¤146.64 | 12/07/2023 |
| CONNECTION FEES | ¤1,166.26 | 12/07/2023 |
| FC IMPACT FEE EMS | ¤62.00 | 12/07/2023 |
| IMPACT FEE FIRE | ¤428.09 | 12/07/2023 |
| FC IMPACT FEE LAW ENFORCEMENT | ¤218.00 | 12/07/2023 |
| FC IMPACT FEE LIBRARY | ¤268.00 | 12/07/2023 |
| IMPACT FEE PARKS | ¤1,800.99 | 12/07/2023 |
| IMPACT FEE SCHOOL | ¤5,450.00 | 12/07/2023 |
| IMPACT FEE TRANSPORTATION | ¤1,812.00 | 12/07/2023 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 12/07/2023 |
| SURCHARGE FS 533.721 | ¤3.47 | 12/07/2023 |
| SURCHARGE - FS 468.631 | ¤5.20 | 12/07/2023 |
| SW ENG - FOUNDATION SURVEY | ¤20.00 | 12/07/2023 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤20,095.03 |