Permit #2024020489
Permit Details
Status: FINAL
| Parcel Id: 07-11-31-7007-00340-0110 |
| OPENED PORCH (WITH ROOF) : 320 sqft |
| Total Square Footage: 320 sqft |
| Block: 00340 |
| Subdivision: 2185 - SECTION 7-FLORIDA PARK |
| Job Phone: 908-334-6117 |
| Location Address: 23 FORSYTHE LN |
| Type: BA - BUILDING ADDITION |
| Issue Date: 03/25/2024 |
| NOC: RECORDED |
| Applicant name: KIM EUGENE ADAMS |
| Owner: HEBERT MICHELLE & COLLEEN H&W |
|
Address 99 FORSYTHE LANE PALM COAST, FL 32137 |
| Lot: 0110 |
| Contracted Stated Job Value: ¤6,000.00 |
| Job Description: PAVER PATIO COVERED PORCH |
| Type: CN |
Contractor
JMD QUALITY CONSTRUCTION, LLC
| Status | Location Address | State License Number | Phone |
| ACTIVE |
300 CANOPY WALK LANE APT 342 ZEPHYRHILLS, FL 33542 |
CGC1526854 (Exp: 08/31/2026) | 908-334-6117 |
Sub Contractors
WILLIAM TODD SIKES
| Status | Location Address | State License Number | Phone |
| ACTIVE |
83 PORT ROYAL DR ST AUGUSTINE, FL 32084 |
EC0002726 (Exp: 08/31/2026) | 904-762-8762 |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 10/03/2024 | FINAL APPROVED | HCAMACHO |
| U -UTILITY RESIDENTIAL FINAL | 09/16/2024 | FINAL APPROVED | DHANEY |
| ROW- FINAL SURVEY/GRADING CERTIFICATION | 09/11/2024 | APPROVED | EMADISON |
| ROW FIELD SURVEY /GRADING CERTIFICATION | 09/11/2024 | APPROVED | EMADISON |
| ROW - FINAL INSPECTION | 09/11/2024 | APPROVED | EMADISON |
| ALL ROUGH | 05/17/2024 | APPROVED | JSTEWART |
| Note: 5/7/2024 - PREVIOUS INSPECTION NOTES 5/7/24 Previous items not resolved, Letter must be submitted and approved by Building dept. before re-inspection Need the following 1. Need detail from engineer for repair to rafters that were notched more than one fourth at bearing per WFCM (wood Frame Construction Manual) 2.5.1.1.4 2. Need to complete the nailing at the bottom post connectors as discussed with contractor on site (missing nailes) | |||
| ROOF VALLEY & METAL | 05/14/2024 | APPROVED | BTAYLOR |
| ALL ROUGH | 05/07/2024 | Disapproved -FEE REQUIRED | MKRASKI |
| Note: 5/7/24 Previous items not resolved, Letter must be submitted and approved by Building dept. before re-inspection Need the following 1. Need detail from engineer for repair to rafters that were notched more than one fourth at bearing per WFCM (wood Frame Construction Manual) 2.5.1.1.4 2. Need to complete the nailing at the bottom post connectors as discussed with contractor on site (missing nailes) | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 04/17/2024 | APPROVED | LMILLER |
| Note: 4-17-24 Notes below resolved 4/10/2024 - PREVIOUS INSPECTION NOTES 04-10-2024 1. Rafters have been cut incorrectly. Bearing point not full width of wood beams. Please submit a revision to the building department as built or install correctly and have on site. 2. A1.1Roof Plan. Nailer behind rafters not fastened. Please provide engineering for fastening of rafter nailers. 3. A1.1 Valley Framing detail have no support. 4. LVL ridge at existing roof arrea has no support. Please provide engineering how LVL ridge is to be supported to the building department and have on site. 5. Roof sheathing is approved. Contractor can proceed at own risk to cover roof. | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 04/10/2024 | Disapproved - NO FEE | AGAETANO |
| Note: 04-10-2024 1. Rafters have been cut incorrectly. Bearing point not full width of wood beams. Please submit a revision to the building department as built or install correctly and have on site. 2. A1.1Roof Plan. Nailer behind rafters not fastened. Please provide engineering for fastening of rafter nailers. 3. A1.1 Valley Framing detail have no support. 4. LVL ridge at existing roof arrea has no support. Please provide engineering how LVL ridge is to be supported to the building department and have on site. 5. Roof sheathing is approved. Contractor can proceed at own risk to cover roof. | |||
| MONOLITHIC SLAB | 03/27/2024 | APPROVED | JWALKER |
Review History
| Department | Status | Date In | Date Out |
| BADMIN | INFORMATION | 05/08/2024 | 05/08/2024 |
| Note: Marked INFORMATION By: BARBIE BEMBRY - (386)986-3780 - BUILDINGDIVISION@PALMCOASTGOV.COM Please rename your files correctly and resubmit. | |||
| BLD | COMPLETE | 05/08/2024 | 05/14/2024 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| SW1 | COMPLETE | 02/13/2024 | 02/20/2024 |
| Note: Released By: GABRIEL BERTOLA - (386)986-7660 - GBERTOLA@PALMCOASTGOV.COM | |||
| ELEC | COMPLETE | 02/13/2024 | 02/13/2024 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 02/12/2024 | 02/16/2024 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 02/12/2024 | 02/13/2024 |
| Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| PLAN REVIEW - REVISION | ¤32.50 | 10/02/2024 |
| REINSPECTION RESIDENTIAL | ¤40.00 | 10/02/2024 |
| SURCHARGE FS 533.721 | ¤2.00 | 03/25/2024 |
| SURCHARGE - FS 468.631 | ¤2.00 | 03/25/2024 |
| SITE PLAN 30 | ¤30.00 | 03/25/2024 |
| ADJUSTMENT 50% | (¤77.50) | 03/25/2024 |
| ADMINISTRATIVE RESIDENTIAL | ¤30.00 | 03/25/2024 |
| INSPECTION - RESIDENTIAL | ¤60.00 | 03/25/2024 |
| PLAN REVIEW - RESIDENTIAL | ¤65.00 | 03/25/2024 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤184.00 |