I want to search for...
Permit #2024030174
Permit Details
Status: COED
| Parcel Id: 07-11-31-7011-00090-0310 |
| CONDITIONED SPACE: 1650 sqft |
| GARAGE: 396 sqft |
| OPENED PORCH (WITH ROOF) : 119 sqft |
| Total Square Footage: 2165 sqft |
| Block: 00090 |
| Subdivision: 7011 - |
| Job Phone: 202-494-2019 |
| Location Address: 118 BEACHWAY DR |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 04/29/2024 |
| NOC: RECORDED |
| Applicant name: GARY ANDREW FISCHER |
| Owner: INB BFR FUND 1 LLC |
|
Address 3670 MAGUIRE BOULEVARD ORLANDO, FL 32803 |
|
Address SUITE 220 ORLANDO, FL 32803 |
| Lot: 0310 |
| Contracted Stated Job Value: ¤150,000.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
INB HOMES
| Status | Location Address | Mailing Address | State License Number | Phone |
| ACTIVE |
3670 MAGUIRE BLVD ORLANDO, FL 32803 |
SUITE 210 ORLANDO, FL 32803 |
CGC048746 (Exp: 08/31/2026) | 407-476-8195 |
Sub Contractors
HEATH EDWARD SANFORD
| Status | Location Address | State License Number | Phone |
| ACTIVE |
126 EAST END RD SAN MATEO, FL 32187 |
CFC1429896 (Exp: 08/31/2026) | 386-871-8823 |
ROBERT MICHAEL RENNER
| Status | Location Address | State License Number | Phone |
| ACTIVE |
531 CODISCO WAY SANFORD, FL 32771 |
CAC051477 (Exp: 08/31/2026) | 407-333-2665 |
JOSEPH C WRIGHT
| Status | Location Address | Mailing Address | State License Number | Phone | Fax |
| ACTIVE |
15 HARGROVE LANE PALM COAST, FL 32137 |
UNIT 3 D PALM COAST, FL 32137 |
EC13003278 (Exp: 08/31/2026) | 386-447-9644 | 386-447-9633 |
TERRY BRICE DICKERSON
| Status | Location Address | State License Number | Phone |
| ACTIVE |
4300 ST JOHN'S PARKWAY ALPHARETTA, GA 30009 |
CCC1326209 (Exp: 08/31/2026) | 407-548-6733 |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 12/05/2024 | FINAL APPROVED | MCONTRYMAN |
| U -UTILITY RESIDENTIAL FINAL | 12/05/2024 | FINAL APPROVED | LFITZGERALD |
| ROW - STORMWATER FINAL | 12/04/2024 | APPROVED | EMADISON |
| ROW - FINAL APRON (AFTER POUR) | 12/04/2024 | APPROVED | EMADISON |
| ROW- FINAL SURVEY/GRADING CERTIFICATION | 12/04/2024 | APPROVED | EMADISON |
| Note: 11/27/2024 - PREVIOUS INSPECTION NOTES | |||
| ROW FIELD SURVEY /GRADING CERTIFICATION | 12/04/2024 | APPROVED | EMADISON |
| ROW- FINAL SURVEY/GRADING CERTIFICATION | 11/27/2024 | Disapproved - NO FEE | EMADISON |
| U-CROSS CONNECTION | 11/26/2024 | APPROVED | DHANEY |
| ROW- PROJECT STATUS | 11/25/2024 | Status Check | EMADISON |
| ROW- PRE-APRON (PRE-POUR) | 10/23/2024 | APPROVED | TPOLACEK |
| Note: AT THE TIME OF THE INSPECTION CULVERT PIPE IS GOOD IS READY TO POUR, IF RAIN PLEASE, BUILDER SHOULD DOUBLE CHECK CULVERT ELEVATIONS MAKE SURE TO USE 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE (FRC) DRAWING 300,E RESIDENTIAL CULVERT DETAIL BEFORE POURING. CONTRACTORS WILL BE NOTIFIED WHEN TICKETS WILL BE REQUIRED WITH AN EMAIL BLAST.THE FOLLOWING IS CURRENTLY FOR INFORMATION ONLY: TICKET OF CONCRETE MIX DESIGN SHALL BE UPLOADED INTO PERMIT PORTAL. 8.a. IF FIBERGLASS OPTION IS USED, DOCUMENTATION OF THE ( FRC) CONTAINING THE FIBERGLASS MUST BE ATTACHED TO THE PERMIT PRIOR TO REQUESTING AN AFTER-POUR INSPECTION. 8.b. IF MESH OPTION IS USED, IT SHALL BE IN PLACE AT THE TIME OF THE PRE-POUR. Inspector Notes from Inspection 9470 10/15/24 TPOLACEK*** SILT FENCE IS UP SWALE IS OPEN PLEASE CLEAR OUT TEMP PIPE AND I AM APPROVING THIS AS NOTED THAT BUILDER WILL CLEAR TEMP PIPE. ++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ 10/14/2024 - PREVIOUS INSPECTION NOTES 10/14/24 TPOLACEK** NO CHANGES TO SITE PERMIT WILL GOT TO PRIORITY 1 STATUS NECT INSPECTION TOMORROW 10/15/24 10/11/2024 - PREVIOUS INSPECTION NOTES 10/11/24 TPOLACEK*** NO CHANGES SWALE STILL NEEDS TO BE OPENED AND SILT FENCE NEEDS TO BE REESTABLISHED. 10/9/2024 - PREVIOUS INSPECTION NOTES 10/09/24 TPOLACEK*** PORTA POTTY IS OUTOF SWALE HOWEVER, THE TEMP PIPE IS CRUSHED AND NOT FLOWING. BUILDER MUST OPEN SWALE ASAP BEFORE STORM AS THEY ARE HOLDING WATER. POTTY in the the Row. PER GBERTOLA | |||
| ROW - DRAINAGE | 10/15/2024 | APPROVED - AS NOTED | TPOLACEK |
| Note: 10/15/24 TPOLACEK*** SILT FENCE IS UP SWALE IS OPEN PLEASE CLEAR OUT TEMP PIPE AND I AM APPROVING THIS AS NOTED THAT BUILDER WILL CLEAR TEMP PIPE. ++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ 10/14/2024 - PREVIOUS INSPECTION NOTES 10/14/24 TPOLACEK** NO CHANGES TO SITE PERMIT WILL GOT TO PRIORITY 1 STATUS NECT INSPECTION TOMORROW 10/15/24 10/11/2024 - PREVIOUS INSPECTION NOTES 10/11/24 TPOLACEK*** NO CHANGES SWALE STILL NEEDS TO BE OPENED AND SILT FENCE NEEDS TO BE REESTABLISHED. 10/9/2024 - PREVIOUS INSPECTION NOTES 10/09/24 TPOLACEK*** PORTA POTTY IS OUTOF SWALE HOWEVER, THE TEMP PIPE IS CRUSHED AND NOT FLOWING. BUILDER MUST OPEN SWALE ASAP BEFORE STORM AS THEY ARE HOLDING WATER. POTTY in the the Row. PER GBERTOLA | |||
| ROW - DRAINAGE | 10/14/2024 | Disapproved -FEE REQUIRED | TPOLACEK |
| Note: 10/14/24 TPOLACEK** NO CHANGES TO SITE PERMIT WILL GOT TO PRIORITY 1 STATUS NECT INSPECTION TOMORROW 10/15/24 10/11/2024 - PREVIOUS INSPECTION NOTES 10/11/24 TPOLACEK*** NO CHANGES SWALE STILL NEEDS TO BE OPENED AND SILT FENCE NEEDS TO BE REESTABLISHED. 10/9/2024 - PREVIOUS INSPECTION NOTES 10/09/24 TPOLACEK*** PORTA POTTY IS OUTOF SWALE HOWEVER, THE TEMP PIPE IS CRUSHED AND NOT FLOWING. BUILDER MUST OPEN SWALE ASAP BEFORE STORM AS THEY ARE HOLDING WATER. POTTY in the the Row. PER GBERTOLA | |||
| ROW - DRAINAGE | 10/11/2024 | Disapproved - NO FEE | TPOLACEK |
| Note: 10/11/24 TPOLACEK*** NO CHANGES SWALE STILL NEEDS TO BE OPENED AND SILT FENCE NEEDS TO BE REESTABLISHED. 10/9/2024 - PREVIOUS INSPECTION NOTES 10/09/24 TPOLACEK*** PORTA POTTY IS OUTOF SWALE HOWEVER, THE TEMP PIPE IS CRUSHED AND NOT FLOWING. BUILDER MUST OPEN SWALE ASAP BEFORE STORM AS THEY ARE HOLDING WATER. POTTY in the the Row. PER GBERTOLA | |||
| ROW - DRAINAGE | 10/09/2024 | Disapproved -FEE REQUIRED | TPOLACEK |
| Note: 10/09/24 TPOLACEK*** PORTA POTTY IS OUTOF SWALE HOWEVER, THE TEMP PIPE IS CRUSHED AND NOT FLOWING. BUILDER MUST OPEN SWALE ASAP BEFORE STORM AS THEY ARE HOLDING WATER. POTTY in the the Row. PER GBERTOLA | |||
| ELECTRIC - EARLY POWER | 09/20/2024 | APPROVED - AS NOTED | KSANDOE |
| Note: 9/17/2024 - PREVIOUS INSPECTION NOTES *** NOTES ADDED BY RMARTIN 9/17/2024 12:42:35 PM *** range wire not safed off and counter switch/outlet not safed off | |||
| ROW - DRAINAGE | 09/18/2024 | APPROVED | TPOLACEK |
| Note: 09/18/24 TPOLACEK** CORRECTIONS MADE IT IS THE BUILDERS RESPOSIBILITY TO KEEP SWALE OPEN THROUGHOUT THE BUILD. 9/16/2024 - PREVIOUS INSPECTION NOTES 09/16/24 TPOLACEK*** NO CHANGS TO SITE NEXT INSPECTION WED 09/18/24 9/13/2024 - PREVIOUS INSPECTION NOTES 09/13/24 TPOLACEK*** NO CHANGES TO SITE NEXT INSPECTION MONDAY 09/16/24 9/12/2024 - PREVIOUS INSPECTION NOTES 09/12/24 TPOLACEK** ENTIRE SITE IS WASHING OUT INTO SWALE. BUILDER IS REQUIRED TO REGRADE PROPERTY AND OPEN U SWALE. REESTABLISH SILT FENCE, INSTALL TEMPORARY PIPE AND REMOVE PORTA POTTY ASAP. NEXT INSPECTION WILL BE ON 09/13/24 THIS MUST BE DONE ASAP TO AVOID A HOLD ON PERMIT | |||
| ELECTRIC - EARLY POWER | 09/17/2024 | Disapproved - NO FEE | RMARTIN |
| Note: *** NOTES ADDED BY RMARTIN 9/17/2024 12:42:35 PM *** range wire not safed off and counter switch/outlet not safed off | |||
| ROW - DRAINAGE | 09/16/2024 | Disapproved -FEE REQUIRED | TPOLACEK |
| Note: 09/16/24 TPOLACEK*** NO CHANGS TO SITE NEXT INSPECTION WED 09/18/24 9/13/2024 - PREVIOUS INSPECTION NOTES 09/13/24 TPOLACEK*** NO CHANGES TO SITE NEXT INSPECTION MONDAY 09/16/24 9/12/2024 - PREVIOUS INSPECTION NOTES 09/12/24 TPOLACEK** ENTIRE SITE IS WASHING OUT INTO SWALE. BUILDER IS REQUIRED TO REGRADE PROPERTY AND OPEN U SWALE. REESTABLISH SILT FENCE, INSTALL TEMPORARY PIPE AND REMOVE PORTA POTTY ASAP. NEXT INSPECTION WILL BE ON 09/13/24 THIS MUST BE DONE ASAP TO AVOID A HOLD ON PERMIT | |||
| ROW - DRAINAGE | 09/13/2024 | Disapproved -FEE REQUIRED | TPOLACEK |
| Note: 09/13/24 TPOLACEK*** NO CHANGES TO SITE NEXT INSPECTION MONDAY 09/16/24 9/12/2024 - PREVIOUS INSPECTION NOTES 09/12/24 TPOLACEK** ENTIRE SITE IS WASHING OUT INTO SWALE. BUILDER IS REQUIRED TO REGRADE PROPERTY AND OPEN U SWALE. REESTABLISH SILT FENCE, INSTALL TEMPORARY PIPE AND REMOVE PORTA POTTY ASAP. NEXT INSPECTION WILL BE ON 09/13/24 THIS MUST BE DONE ASAP TO AVOID A HOLD ON PERMIT | |||
| ROW - DRAINAGE | 09/12/2024 | Disapproved -FEE REQUIRED | TPOLACEK |
| Note: 09/12/24 TPOLACEK** ENTIRE SITE IS WASHING OUT INTO SWALE. BUILDER IS REQUIRED TO REGRADE PROPERTY AND OPEN U SWALE. REESTABLISH SILT FENCE, INSTALL TEMPORARY PIPE AND REMOVE PORTA POTTY ASAP. NEXT INSPECTION WILL BE ON 09/13/24 THIS MUST BE DONE ASAP TO AVOID A HOLD ON PERMIT | |||
| ROW- PROJECT STATUS | 09/12/2024 | APPROVED | TPOLACEK |
| Note: 09/12/24 TPOLACEK** ENTIRE SITE IS WASHING OUT INTO SWALE. BUILDER IS REQUIRED TO REGRADE PROPERTY AND OPEN U SWALE. REESTABLISH SILT FENCE, INSTALL TEMPORARY PIPE AND REMOVE PORTA POTTY ASAP. NEIGHBOR AT 112 SAYS THAT NEW CONSTRUCTION HAS A BLOCKED CULVERT OBSTRUCTING THE FLOW OF WATER MH | |||
| INSULATION | 08/16/2024 | APPROVED | JSTEWART |
| Note: Inspector Notes from Inspection 2420 *** NOTES ADDED BY JSTEWART 8/13/2024 9:45:43 AM *** FBCR P2503.7 NEEDS WATER TEST ON DWV - 5 FT HEAD PRESSURE ABOVE HIGHEST FIXTURE - FILL TUB TO OVERFLOW. (empty) will check at insulation. | |||
| ELECTRIC-TUG | 08/15/2024 | APPROVED | RMARTIN |
| SEWER TIE IN | 08/13/2024 | APPROVED - AS NOTED | MGIBSON |
| Note: Inspector Notes from Inspection 2075 TAP NOT MADE YET THIS WAS A VIRTUAL INSPECTION | |||
| LATH/BRICK/ WATER BARRIER | 08/13/2024 | APPROVED | JSTEWART |
| ALL ROUGH | 08/13/2024 | APPROVED - AS NOTED | JSTEWART |
| Note: *** NOTES ADDED BY JSTEWART 8/13/2024 9:45:43 AM *** FBCR P2503.7 NEEDS WATER TEST ON DWV - 5 FT HEAD PRESSURE ABOVE HIGHEST FIXTURE - FILL TUB TO OVERFLOW. (empty) will check at insulation. | |||
| ROOF VALLEY & METAL | 08/05/2024 | APPROVED | JSTEWART |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 08/01/2024 | APPROVED | JSTEWART |
| Note: Inspector Notes from Inspection 2465 Silt fence is damaged and must be repaired. Clean up job site. | |||
| GRAVITY SEWER TEST | 08/01/2024 | APPROVED - AS NOTED | MGIBSON |
| Note: TAP NOT MADE YET | |||
| ROOF SHEATHING | 07/29/2024 | APPROVED - AS NOTED | KSANDOE |
| Note: Silt fence is damaged and must be repaired. Clean up job site. | |||
| WALL SHEATHING | 07/29/2024 | APPROVED | KSANDOE |
| TIE BEAM / LINTEL | 07/19/2024 | APPROVED | JSTEWART |
| FOUND SURVEY APPROVED (OFFICE) | 07/16/2024 | APPROVED | TBAKER |
| MONOLITHIC SLAB | 07/10/2024 | APPROVED | FWILLIS |
| PLUMBING 1ST ROUGH UNDERGROUND | 07/03/2024 | APPROVED | MGIBSON |
| GEOTECHNICAL REPORT APPROVAL (OFFICE USE) | 07/02/2024 | APPROVED | JMUNSON |
| WATER METER INSTALLATION REQUEST | 06/03/2024 | APPROVED | CBOWERMASTER |
Review History
| Department | Status | Date In | Date Out |
| MECH | COMPLETE | 11/26/2024 | 12/02/2024 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| SW1 | COMPLETE | 11/13/2024 | 11/14/2024 |
| Note: Released By: JOHN HOWARD - - JHOWARD@PALMCOASTGOV.COM SW1 completed review is contingent on stormwater inspector's approval of the final survey. A failed final survey inspection and/or a revised site plan indicating any deviation from the approved site plan with significant change in drainage patterns and elevations negatively impacting neighboring lots, or the structure will result in a HOLD | |||
| ENGIN1 | COMPLETE | 11/13/2024 | 11/25/2024 |
| Note: Released By: JORDAN MYERS, C.F.M - (386)986-4789 - JMYERS@PALMCOASTGOV.COM Staff met on-site today, revised site plan is not necessary modifications needed do not require a revision. | |||
| ZON | COMPLETE | 11/13/2024 | 11/13/2024 |
| Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 11/07/2024 | 11/12/2024 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| SW1 | HOLD | 11/07/2024 | 11/08/2024 |
| Note: Held By: JOHN HOWARD - - JHOWARD@PALMCOASTGOV.COM On submission form, please identify what grading you are matching Please note it is not necessary to submit a revised site plan prior to the final survey | |||
| ZON | COMPLETE | 11/07/2024 | 11/07/2024 |
| Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 07/16/2024 | 07/16/2024 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 07/16/2024 | 07/16/2024 |
| Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM | |||
| ENGIN1 | HOLD | 07/03/2024 | 07/03/2024 |
| Note: Held By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM Formboard survey is unacceptable as foundation survey. Please submit foundation survey showing location, dimensions and elevation of finished concrete foundation/slab. | |||
| ZON | COMPLETE | 07/03/2024 | 07/03/2024 |
| Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 07/01/2024 | 07/02/2024 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 04/01/2024 | 04/01/2024 |
| Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 03/27/2024 | 03/30/2024 |
| Note: Released By: JPI | |||
| ZON | HOLD | 03/27/2024 | 03/27/2024 |
| Note: Held By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM Must have a minimum of two shade trees. You only have one | |||
| SWALE | COMPLETE | 03/06/2024 | 05/03/2024 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| BADMIN | COMPLETE | 03/05/2024 | 03/08/2024 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| BLD | HOLD | 03/05/2024 | 03/08/2024 |
| Note: Held By: JPI 1. Please provide current revision numbers for product approval numbers. 107.2.4 | |||
| CUSVC | COMPLETE | 03/05/2024 | 03/07/2024 |
| Note: Released By: HALEIGH HAND - - HHAND@PALMCOASTGOV.COM | |||
| ELEC | COMPLETE | 03/05/2024 | 03/08/2024 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 03/05/2024 | 03/06/2024 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| GAS | CANCEL | 03/05/2024 | 03/06/2024 |
| LOCATE | COMPLETE | 03/05/2024 | 03/07/2024 |
| Note: Released By: CANDACE BOWERMASTER - - CBOWERMASTER@PALMCOASTGOV.COM | |||
| MECH | COMPLETE | 03/05/2024 | 03/06/2024 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| SW1 | COMPLETE | 03/05/2024 | 03/06/2024 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| ZON | HOLD | 03/05/2024 | 03/05/2024 |
| Note: Held By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM Need a total of 8 trees for this lot size. |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| PLAN REVIEW - REVISION | ¤32.50 | 12/04/2024 |
| SW ENG - INSPECTION 20 | ¤20.00 | 12/04/2024 |
| SW ENG - INSPECTION 20 | ¤20.00 | 12/04/2024 |
| SW ENG - INSPECTION 20 | ¤20.00 | 12/04/2024 |
| SW ENG - INSPECTION 20 | ¤20.00 | 12/04/2024 |
| SW ENG - INSPECTION 20 | ¤20.00 | 12/04/2024 |
| SW ENG - INSPECTION 20 | ¤20.00 | 12/04/2024 |
| SW ENG - INSPECTION 20 | ¤20.00 | 12/04/2024 |
| SW ENG - INSPECTION 20 | ¤20.00 | 12/04/2024 |
| SW ENG REINSPECTION 20 | ¤20.00 | 12/04/2024 |
| SW ENG REINSPECTION 20 | ¤20.00 | 12/04/2024 |
| SW ENG - REVIEW 20 | ¤20.00 | 04/29/2024 |
| SW ENG RES REVIEW 200 | ¤200.00 | 04/29/2024 |
| SEWER CREDIT | (¤1,147.00) | 04/29/2024 |
| SEWER INSPECTION | ¤25.00 | 04/29/2024 |
| SEWER CAPITAL FACILITY | ¤5,441.03 | 04/29/2024 |
| WATER CAPITAL FACILITY FEE | ¤3,994.51 | 04/29/2024 |
| SITE PLAN 30 | ¤30.00 | 04/29/2024 |
| WATER- TURN ON | ¤25.00 | 04/29/2024 |
| ADJUSTMENT 50% | (¤556.86) | 04/29/2024 |
| ADMINISTRATIVE RESIDENTIAL | ¤30.00 | 04/29/2024 |
| INSPECTION - RESIDENTIAL | ¤844.25 | 04/29/2024 |
| PLAN REVIEW - RESIDENTIAL | ¤239.46 | 04/29/2024 |
| SW ENG INSPECTION 80 | ¤80.00 | 04/29/2024 |
| SW ENG PRE APRON | ¤30.00 | 04/29/2024 |
| CONNECTION FEES | ¤1,187.26 | 04/29/2024 |
| FC IMPACT FEE EMS | ¤62.00 | 04/29/2024 |
| IMPACT FEE FIRE | ¤428.09 | 04/29/2024 |
| FC IMPACT FEE LAW ENFORCEMENT | ¤218.00 | 04/29/2024 |
| FC IMPACT FEE LIBRARY | ¤268.00 | 04/29/2024 |
| IMPACT FEE PARKS | ¤1,800.99 | 04/29/2024 |
| IMPACT FEE SCHOOL | ¤5,450.00 | 04/29/2024 |
| IMPACT FEE TRANSPORTATION | ¤1,862.00 | 04/29/2024 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 04/29/2024 |
| SURCHARGE FS 533.721 | ¤5.57 | 04/29/2024 |
| SURCHARGE - FS 468.631 | ¤8.35 | 04/29/2024 |
| SW ENG - FOUNDATION SURVEY | ¤20.00 | 04/29/2024 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤20,823.15 |