Permit #2024030837

Permit Details

Status: COED

Parcel Id: 07-11-31-7063-00470-0010
CONDITIONED SPACE: 1506 sqft
GARAGE: 399 sqft
OPENED PORCH (WITH ROOF) : 116 sqft
Total Square Footage: 2021 sqft
Block: 00470
Subdivision: -
Job Phone: 202-494-2019
Location Address: 1 ZAUNSTOWN PL
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 04/10/2024
NOC: RECORDED
Applicant name: GARY ANDREW FISCHER
Owner: FELDMAN PAUL ESQ TRUSTEE

Address

2750 NE 185TH STREET

AVENTURA, FL 33180

Address

SUITE 203

AVENTURA, FL 33180

Lot: 0010
Contracted Stated Job Value: ¤150,000.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

INB HOMES
Status Location Address Mailing Address State License Number Phone
ACTIVE

3670 MAGUIRE BLVD

ORLANDO, FL 32803

SUITE 210

ORLANDO, FL 32803

CGC048746 (Exp: 08/31/2026) 407-476-8195

Sub Contractors

ROBERT MICHAEL RENNER
Status Location Address State License Number Phone
ACTIVE

531 CODISCO WAY

SANFORD, FL 32771

CAC051477 (Exp: 08/31/2026) 407-333-2665
HEATH EDWARD SANFORD
Status Location Address State License Number Phone
ACTIVE

126 EAST END RD

SAN MATEO, FL 32187

CFC1429896 (Exp: 08/31/2026) 386-871-8823
JOSEPH C WRIGHT
Status Location Address Mailing Address State License Number Phone Fax
ACTIVE

15 HARGROVE LANE

PALM COAST, FL 32137

UNIT 3 D

PALM COAST, FL 32137

EC13003278 (Exp: 08/31/2026) 386-447-9644 386-447-9633
TERRY BRICE DICKERSON
Status Location Address State License Number Phone
ACTIVE

4300 ST JOHN'S PARKWAY

ALPHARETTA, GA 30009

CCC1326209 (Exp: 08/31/2026) 407-548-6733

Inspection History

Type Request Date Result Inspector
BLD - BUILDING FINAL 12/17/2024 FINAL APPROVED MCONTRYMAN
Note: 12/13/2024 - PREVIOUS INSPECTION NOTES 12/13/2024 1. Mising bath vent cover at soffit. 2. ODU AC not anchored. 3. ODU AC needs 3" clearance from grpound. FBCR M1305.1.4.1 4. AC drainage line needs to be brought up off ground. 5. Hot water revesed in kitchen. FBCR P2722.2
ROW - STORMWATER FINAL 12/17/2024 APPROVED - AS NOTED FSLADISH
Note: 12/17/24 SWALE CORRECTION MADE AT THE TIME OF THIS INSPECTION GRADE HAS BEEN MET IN ACCORDANCE WITH COPC REQUIREMENTS. APPROVING AS NOTED. AT THE TIME OF THIS INSPECTIONS ALL COPC REQUIREMENTS WERE MET, NEITHER THE INSPECTOR NOR THE CITY IS RESPONSIBLE IF, FOR WHATEVER REASON, SITE CONDITIONS CHANGE OVER TIME AFTER THE INSPECTION. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED. _________________________________________________________________________________________________________________________ 12/13/2024 - PREVIOUS INSPECTION NOTES 12/13/24 NOT READY FOR INSPECTION CANCELLED AS A COURTESY DUE TO THE FACT I WAS ALREADY HERE FOR THE AFTER POUR INSPECTION. BILL ASKED TO CANCEL. ________________________________________________________________________________________________________________________ Inspector Notes from Inspection 9465 12/12/24 SPOKE WITH BILL CM AND AFTER DISCUSSUION HE UNDERSTANDS WHAT WE NEED HIM TO DO ON THE RIGHT SIDE OUT OF THE CULVERT. I AM GOING TO APPROVE THIS AS A OURTESY SO HE CAN MOVE AHEAD WITH HIS INSPECTIONS AND THE CORRECTION WILL BE MADE BEFORE ROW FINAL PASSAGE. ______________________________________________________________________________________________________________________ 12/12/2024 - PREVIOUS INSPECTION NOTES 12/12/24 PLEASE READ PREVIOUS NOTES. YOU ARE GOING TO HAVE TO MATCH GRADE AT THE RIGHT SIDE FRONT SWALE PROPERTY GRADE. YOU CAN EITHER COME OUT OF THE RIGHT SIDE OF THE CULVERT PIPE AT A 2:1 SLOPE TO A 21.10 TO A 21.18 TO PROPERTY LINE. OR YOU CAN START BACK AT THE CORNER WHERE IT IS 21.10 AND RUN IT FLAT TO A 2:1 SLOPE INTO AND OUT OF THE CULVERT PIPE THEN 21.10 FLAT TO PROPERTY LINE. BASICALLY THE RIGHT SIDE IS WAY TO LOW COMPARED TO PROPERTY LINE AND WILL NOT ALLOW POSITIVE DRAINAGE TO THE CUL DE SAC DITCH. I AM AS A COURTESY NOT GOING TO FEE YOU. IF YOU HAVE ANY QUESTIONS PLEASE REACH OUT TO ME AND I WILL DO MY BEST TO DISCUSS IT OT MEET YOU THERE WHEN I AM ABLE. AT THIS TIME IF THE PROPERTY STAKE IS CORRECT ON THE RIGHT SIDE YOU WILL NEED TO REMOVE THE HIGH SPOT AND THAT MAY ASSIST YOU WITH GRADE. 12/9/2024 - PREVIOUS INSPECTION NOTES 12/9/24 UPON WALKING PROPERTY DETERMINED SURVEY IS SHOWING CORRECTLY. ON THE RIGHT SIDE OF THE CULVERT IN THE FRONT SWALE THERE IS A LARGE DIFFERENCE IN ELEVATION AT THE PROPERTY LIN. YOU WILL NEED TO COME OUT OF THE CORNER AT THE AT YOUR CURRENT ELEVATON OF 21.10 AND RUN THAT FLAT TO YOUR 2:1 DROP INTO LEFT SIDE CULVERT COME OUT ON A 2:1 SLOPE ON THE RIGHT SIDE CULVERT TO A 21.10 FLAT TO THE PROPERTY LINE TO COME AS CLOSE AS POSSIBLE TO GRADE AT PROPERTY LINE AS THE DRAINAGE FLOWS LEFT TO RIGHT AND DUMPS INTO COPC DITCH IN THE CUL DE SAC. _________________________________________________________________________________________________________________________ Inspector Notes from Inspection 9463 12/9/24 WITH THE EXCEPTION OF THE RIGHT SIDE SWALE ELEVATION GOING FROM 20.75 TO A 21.18 EVERYTHING ELSE LOOKS ACCEPTABLE. WILL DETERMINE DURING FIELD SURVEY WHAT I AM SEEING IN FIELD ON THE RIGHT SIDE FRONT SWALE AREA IN QUESTION. APPROVING AS NOTED.
U -UTILITY RESIDENTIAL FINAL 12/13/2024 FINAL APPROVED BWRIGHT
ROW - STORMWATER FINAL 12/13/2024 CANCELLED BY APPLICANT FSLADISH
Note: 12/13/24 NOT READY FOR INSPECTION CANCELLED AS A COURTESY DUE TO THE FACT I WAS ALREADY HERE FOR THE AFTER POUR INSPECTION. BILL ASKED TO CANCEL. ________________________________________________________________________________________________________________________ Inspector Notes from Inspection 9465 12/12/24 SPOKE WITH BILL CM AND AFTER DISCUSSUION HE UNDERSTANDS WHAT WE NEED HIM TO DO ON THE RIGHT SIDE OUT OF THE CULVERT. I AM GOING TO APPROVE THIS AS A OURTESY SO HE CAN MOVE AHEAD WITH HIS INSPECTIONS AND THE CORRECTION WILL BE MADE BEFORE ROW FINAL PASSAGE. ______________________________________________________________________________________________________________________ 12/12/2024 - PREVIOUS INSPECTION NOTES 12/12/24 PLEASE READ PREVIOUS NOTES. YOU ARE GOING TO HAVE TO MATCH GRADE AT THE RIGHT SIDE FRONT SWALE PROPERTY GRADE. YOU CAN EITHER COME OUT OF THE RIGHT SIDE OF THE CULVERT PIPE AT A 2:1 SLOPE TO A 21.10 TO A 21.18 TO PROPERTY LINE. OR YOU CAN START BACK AT THE CORNER WHERE IT IS 21.10 AND RUN IT FLAT TO A 2:1 SLOPE INTO AND OUT OF THE CULVERT PIPE THEN 21.10 FLAT TO PROPERTY LINE. BASICALLY THE RIGHT SIDE IS WAY TO LOW COMPARED TO PROPERTY LINE AND WILL NOT ALLOW POSITIVE DRAINAGE TO THE CUL DE SAC DITCH. I AM AS A COURTESY NOT GOING TO FEE YOU. IF YOU HAVE ANY QUESTIONS PLEASE REACH OUT TO ME AND I WILL DO MY BEST TO DISCUSS IT OT MEET YOU THERE WHEN I AM ABLE. AT THIS TIME IF THE PROPERTY STAKE IS CORRECT ON THE RIGHT SIDE YOU WILL NEED TO REMOVE THE HIGH SPOT AND THAT MAY ASSIST YOU WITH GRADE. 12/9/2024 - PREVIOUS INSPECTION NOTES 12/9/24 UPON WALKING PROPERTY DETERMINED SURVEY IS SHOWING CORRECTLY. ON THE RIGHT SIDE OF THE CULVERT IN THE FRONT SWALE THERE IS A LARGE DIFFERENCE IN ELEVATION AT THE PROPERTY LIN. YOU WILL NEED TO COME OUT OF THE CORNER AT THE AT YOUR CURRENT ELEVATON OF 21.10 AND RUN THAT FLAT TO YOUR 2:1 DROP INTO LEFT SIDE CULVERT COME OUT ON A 2:1 SLOPE ON THE RIGHT SIDE CULVERT TO A 21.10 FLAT TO THE PROPERTY LINE TO COME AS CLOSE AS POSSIBLE TO GRADE AT PROPERTY LINE AS THE DRAINAGE FLOWS LEFT TO RIGHT AND DUMPS INTO COPC DITCH IN THE CUL DE SAC. _________________________________________________________________________________________________________________________ Inspector Notes from Inspection 9463 12/9/24 WITH THE EXCEPTION OF THE RIGHT SIDE SWALE ELEVATION GOING FROM 20.75 TO A 21.18 EVERYTHING ELSE LOOKS ACCEPTABLE. WILL DETERMINE DURING FIELD SURVEY WHAT I AM SEEING IN FIELD ON THE RIGHT SIDE FRONT SWALE AREA IN QUESTION. APPROVING AS NOTED.
ROW - FINAL APRON (AFTER POUR) 12/13/2024 APPROVED FSLADISH
Note: 12/13/24 AT THE TIME OF THE INSPECTION ALL MINIMUM CITY REQUIREMENTS WERE MET. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED. PIPE ELEVATION IS GOOD, CUTS ARE MADE, CULVERT CLEAR, HOT PATCH COMPLETE. Inspector Notes from Inspection 9465 12/12/24 SPOKE WITH BILL CM AND AFTER DISCUSSUION HE UNDERSTANDS WHAT WE NEED HIM TO DO ON THE RIGHT SIDE OUT OF THE CULVERT. I AM GOING TO APPROVE THIS AS A OURTESY SO HE CAN MOVE AHEAD WITH HIS INSPECTIONS AND THE CORRECTION WILL BE MADE BEFORE ROW FINAL PASSAGE. ______________________________________________________________________________________________________________________ 12/12/2024 - PREVIOUS INSPECTION NOTES 12/12/24 PLEASE READ PREVIOUS NOTES. YOU ARE GOING TO HAVE TO MATCH GRADE AT THE RIGHT SIDE FRONT SWALE PROPERTY GRADE. YOU CAN EITHER COME OUT OF THE RIGHT SIDE OF THE CULVERT PIPE AT A 2:1 SLOPE TO A 21.10 TO A 21.18 TO PROPERTY LINE. OR YOU CAN START BACK AT THE CORNER WHERE IT IS 21.10 AND RUN IT FLAT TO A 2:1 SLOPE INTO AND OUT OF THE CULVERT PIPE THEN 21.10 FLAT TO PROPERTY LINE. BASICALLY THE RIGHT SIDE IS WAY TO LOW COMPARED TO PROPERTY LINE AND WILL NOT ALLOW POSITIVE DRAINAGE TO THE CUL DE SAC DITCH. I AM AS A COURTESY NOT GOING TO FEE YOU. IF YOU HAVE ANY QUESTIONS PLEASE REACH OUT TO ME AND I WILL DO MY BEST TO DISCUSS IT OT MEET YOU THERE WHEN I AM ABLE. AT THIS TIME IF THE PROPERTY STAKE IS CORRECT ON THE RIGHT SIDE YOU WILL NEED TO REMOVE THE HIGH SPOT AND THAT MAY ASSIST YOU WITH GRADE. 12/9/2024 - PREVIOUS INSPECTION NOTES 12/9/24 UPON WALKING PROPERTY DETERMINED SURVEY IS SHOWING CORRECTLY. ON THE RIGHT SIDE OF THE CULVERT IN THE FRONT SWALE THERE IS A LARGE DIFFERENCE IN ELEVATION AT THE PROPERTY LIN. YOU WILL NEED TO COME OUT OF THE CORNER AT THE AT YOUR CURRENT ELEVATON OF 21.10 AND RUN THAT FLAT TO YOUR 2:1 DROP INTO LEFT SIDE CULVERT COME OUT ON A 2:1 SLOPE ON THE RIGHT SIDE CULVERT TO A 21.10 FLAT TO THE PROPERTY LINE TO COME AS CLOSE AS POSSIBLE TO GRADE AT PROPERTY LINE AS THE DRAINAGE FLOWS LEFT TO RIGHT AND DUMPS INTO COPC DITCH IN THE CUL DE SAC. _________________________________________________________________________________________________________________________ Inspector Notes from Inspection 9463 12/9/24 WITH THE EXCEPTION OF THE RIGHT SIDE SWALE ELEVATION GOING FROM 20.75 TO A 21.18 EVERYTHING ELSE LOOKS ACCEPTABLE. WILL DETERMINE DURING FIELD SURVEY WHAT I AM SEEING IN FIELD ON THE RIGHT SIDE FRONT SWALE AREA IN QUESTION. APPROVING AS NOTED.
BLD - BUILDING FINAL 12/13/2024 Disapproved - NO FEE PKNAPIK
Note: 12/13/2024 1. Mising bath vent cover at soffit. 2. ODU AC not anchored. 3. ODU AC needs 3" clearance from grpound. FBCR M1305.1.4.1 4. AC drainage line needs to be brought up off ground. 5. Hot water revesed in kitchen. FBCR P2722.2
U-CROSS CONNECTION 12/12/2024 APPROVED DHANEY
ROW FIELD SURVEY /GRADING CERTIFICATION 12/12/2024 Disapproved - NO FEE FSLADISH
Note: 12/12/24 PLEASE READ PREVIOUS NOTES. YOU ARE GOING TO HAVE TO MATCH GRADE AT THE RIGHT SIDE FRONT SWALE PROPERTY GRADE. YOU CAN EITHER COME OUT OF THE RIGHT SIDE OF THE CULVERT PIPE AT A 2:1 SLOPE TO A 21.10 TO A 21.18 TO PROPERTY LINE. OR YOU CAN START BACK AT THE CORNER WHERE IT IS 21.10 AND RUN IT FLAT TO A 2:1 SLOPE INTO AND OUT OF THE CULVERT PIPE THEN 21.10 FLAT TO PROPERTY LINE. BASICALLY THE RIGHT SIDE IS WAY TO LOW COMPARED TO PROPERTY LINE AND WILL NOT ALLOW POSITIVE DRAINAGE TO THE CUL DE SAC DITCH. I AM AS A COURTESY NOT GOING TO FEE YOU. IF YOU HAVE ANY QUESTIONS PLEASE REACH OUT TO ME AND I WILL DO MY BEST TO DISCUSS IT OT MEET YOU THERE WHEN I AM ABLE. AT THIS TIME IF THE PROPERTY STAKE IS CORRECT ON THE RIGHT SIDE YOU WILL NEED TO REMOVE THE HIGH SPOT AND THAT MAY ASSIST YOU WITH GRADE. 12/9/2024 - PREVIOUS INSPECTION NOTES 12/9/24 UPON WALKING PROPERTY DETERMINED SURVEY IS SHOWING CORRECTLY. ON THE RIGHT SIDE OF THE CULVERT IN THE FRONT SWALE THERE IS A LARGE DIFFERENCE IN ELEVATION AT THE PROPERTY LIN. YOU WILL NEED TO COME OUT OF THE CORNER AT THE AT YOUR CURRENT ELEVATON OF 21.10 AND RUN THAT FLAT TO YOUR 2:1 DROP INTO LEFT SIDE CULVERT COME OUT ON A 2:1 SLOPE ON THE RIGHT SIDE CULVERT TO A 21.10 FLAT TO THE PROPERTY LINE TO COME AS CLOSE AS POSSIBLE TO GRADE AT PROPERTY LINE AS THE DRAINAGE FLOWS LEFT TO RIGHT AND DUMPS INTO COPC DITCH IN THE CUL DE SAC. _________________________________________________________________________________________________________________________ Inspector Notes from Inspection 9463 12/9/24 WITH THE EXCEPTION OF THE RIGHT SIDE SWALE ELEVATION GOING FROM 20.75 TO A 21.18 EVERYTHING ELSE LOOKS ACCEPTABLE. WILL DETERMINE DURING FIELD SURVEY WHAT I AM SEEING IN FIELD ON THE RIGHT SIDE FRONT SWALE AREA IN QUESTION. APPROVING AS NOTED.
ROW FIELD SURVEY /GRADING CERTIFICATION 12/12/2024 APPROVED - AS NOTED FSLADISH
Note: 12/12/24 SPOKE WITH BILL CM AND AFTER DISCUSSUION HE UNDERSTANDS WHAT WE NEED HIM TO DO ON THE RIGHT SIDE OUT OF THE CULVERT. I AM GOING TO APPROVE THIS AS A OURTESY SO HE CAN MOVE AHEAD WITH HIS INSPECTIONS AND THE CORRECTION WILL BE MADE BEFORE ROW FINAL PASSAGE. ______________________________________________________________________________________________________________________ 12/12/2024 - PREVIOUS INSPECTION NOTES 12/12/24 PLEASE READ PREVIOUS NOTES. YOU ARE GOING TO HAVE TO MATCH GRADE AT THE RIGHT SIDE FRONT SWALE PROPERTY GRADE. YOU CAN EITHER COME OUT OF THE RIGHT SIDE OF THE CULVERT PIPE AT A 2:1 SLOPE TO A 21.10 TO A 21.18 TO PROPERTY LINE. OR YOU CAN START BACK AT THE CORNER WHERE IT IS 21.10 AND RUN IT FLAT TO A 2:1 SLOPE INTO AND OUT OF THE CULVERT PIPE THEN 21.10 FLAT TO PROPERTY LINE. BASICALLY THE RIGHT SIDE IS WAY TO LOW COMPARED TO PROPERTY LINE AND WILL NOT ALLOW POSITIVE DRAINAGE TO THE CUL DE SAC DITCH. I AM AS A COURTESY NOT GOING TO FEE YOU. IF YOU HAVE ANY QUESTIONS PLEASE REACH OUT TO ME AND I WILL DO MY BEST TO DISCUSS IT OT MEET YOU THERE WHEN I AM ABLE. AT THIS TIME IF THE PROPERTY STAKE IS CORRECT ON THE RIGHT SIDE YOU WILL NEED TO REMOVE THE HIGH SPOT AND THAT MAY ASSIST YOU WITH GRADE. 12/9/2024 - PREVIOUS INSPECTION NOTES 12/9/24 UPON WALKING PROPERTY DETERMINED SURVEY IS SHOWING CORRECTLY. ON THE RIGHT SIDE OF THE CULVERT IN THE FRONT SWALE THERE IS A LARGE DIFFERENCE IN ELEVATION AT THE PROPERTY LIN. YOU WILL NEED TO COME OUT OF THE CORNER AT THE AT YOUR CURRENT ELEVATON OF 21.10 AND RUN THAT FLAT TO YOUR 2:1 DROP INTO LEFT SIDE CULVERT COME OUT ON A 2:1 SLOPE ON THE RIGHT SIDE CULVERT TO A 21.10 FLAT TO THE PROPERTY LINE TO COME AS CLOSE AS POSSIBLE TO GRADE AT PROPERTY LINE AS THE DRAINAGE FLOWS LEFT TO RIGHT AND DUMPS INTO COPC DITCH IN THE CUL DE SAC. _________________________________________________________________________________________________________________________ Inspector Notes from Inspection 9463 12/9/24 WITH THE EXCEPTION OF THE RIGHT SIDE SWALE ELEVATION GOING FROM 20.75 TO A 21.18 EVERYTHING ELSE LOOKS ACCEPTABLE. WILL DETERMINE DURING FIELD SURVEY WHAT I AM SEEING IN FIELD ON THE RIGHT SIDE FRONT SWALE AREA IN QUESTION. APPROVING AS NOTED.
ROW- FINAL SURVEY/GRADING CERTIFICATION 12/09/2024 APPROVED - AS NOTED FSLADISH
Note: 12/9/24 WITH THE EXCEPTION OF THE RIGHT SIDE SWALE ELEVATION GOING FROM 20.75 TO A 21.18 EVERYTHING ELSE LOOKS ACCEPTABLE. WILL DETERMINE DURING FIELD SURVEY WHAT I AM SEEING IN FIELD ON THE RIGHT SIDE FRONT SWALE AREA IN QUESTION. APPROVING AS NOTED.
ROW FIELD SURVEY /GRADING CERTIFICATION 12/09/2024 Disapproved - NO FEE FSLADISH
Note: 12/9/24 UPON WALKING PROPERTY DETERMINED SURVEY IS SHOWING CORRECTLY. ON THE RIGHT SIDE OF THE CULVERT IN THE FRONT SWALE THERE IS A LARGE DIFFERENCE IN ELEVATION AT THE PROPERTY LIN. YOU WILL NEED TO COME OUT OF THE CORNER AT THE AT YOUR CURRENT ELEVATON OF 21.10 AND RUN THAT FLAT TO YOUR 2:1 DROP INTO LEFT SIDE CULVERT COME OUT ON A 2:1 SLOPE ON THE RIGHT SIDE CULVERT TO A 21.10 FLAT TO THE PROPERTY LINE TO COME AS CLOSE AS POSSIBLE TO GRADE AT PROPERTY LINE AS THE DRAINAGE FLOWS LEFT TO RIGHT AND DUMPS INTO COPC DITCH IN THE CUL DE SAC. _________________________________________________________________________________________________________________________ Inspector Notes from Inspection 9463 12/9/24 WITH THE EXCEPTION OF THE RIGHT SIDE SWALE ELEVATION GOING FROM 20.75 TO A 21.18 EVERYTHING ELSE LOOKS ACCEPTABLE. WILL DETERMINE DURING FIELD SURVEY WHAT I AM SEEING IN FIELD ON THE RIGHT SIDE FRONT SWALE AREA IN QUESTION. APPROVING AS NOTED.
ROW- PRE-APRON (PRE-POUR) 10/29/2024 APPROVED FSLADISH
Note: 10/29/24 PIPE ELEVATION IS GOOD AT THE TIME OF THIS INSPECTION. READY TO POUR. AT THE TIME OF THE INSPECTION CULVERT PIPE IS GOOD IS READY TO POUR, IF RAIN PLEASE, BUILDER SHOULD DOUBLE CHECK CULVERT ELEVATIONS MAKE SURE IS 3000 PSI CONCRETE REINFORCED WITH WWF 6X6G.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE (FRC) DRAWING 300,E RESIDENTIAL CULVERT DETAIL 10/25/2024 - PREVIOUS INSPECTION NOTES THE CULVERT IS FLOWING THE WRONG DIRECTION TO THE SWALE PLAN DETAIL.
GRAVITY SEWER TEST 10/28/2024 APPROVED MGIBSON
SEWER TIE IN 10/28/2024 APPROVED MGIBSON
ROW- PRE-APRON (PRE-POUR) 10/25/2024 Disapproved - NO FEE PFLANAGAN
Note: THE CULVERT IS FLOWING THE WRONG DIRECTION TO THE SWALE PLAN DETAIL.
ROW - DRAINAGE 10/15/2024 APPROVED - AS NOTED FSLADISH
Note: 10/15/24 TEMPORARY PIPE IS OPEN TO FLOW AND PORTA POTTY ON BUILDING SITE AT THE TIME OF THIS INSPECTION. _______________________________________________________________________________________________________________________ 10/14/2024 - PREVIOUS INSPECTION NOTES 10/14/24 NO CHANGES. NOTHING REQUIRED ON PREVIOUS INSPECTION NOTES COMPLETED AT THE TIME OF THIS INSPECTION. ________________________________________________________________________________________________________________________ 10/11/2024 - PREVIOUS INSPECTION NOTES STILL NEED TO BE FIX ALL BELOW -------------------------------------------------------------------- 10/7/2024 - PREVIOUS INSPECTION NOTES 10/7/24 YOU NEED TO CLEAN THE DIRT/SILT OUT OF YOUR TEMPORARY CULVERT PIPE AND MAKE SURE IT IS AT GRADE TO ALLOW SWALE TO HAVE POSITIVE DRAINAGE. YOU NEED TO MOVE YOUR PORTA POTTY OUT OF THE COPC SWALE ROW AND PLACE IT ON YOUR SITE. WILL BE BACK 10/7/24 FOR COMPLIANCE REINSPECTION.
ROW - DRAINAGE 10/14/2024 Disapproved -FEE REQUIRED FSLADISH
Note: 10/14/24 NO CHANGES. NOTHING REQUIRED ON PREVIOUS INSPECTION NOTES COMPLETED AT THE TIME OF THIS INSPECTION. ________________________________________________________________________________________________________________________ 10/11/2024 - PREVIOUS INSPECTION NOTES STILL NEED TO BE FIX ALL BELOW -------------------------------------------------------------------- 10/7/2024 - PREVIOUS INSPECTION NOTES 10/7/24 YOU NEED TO CLEAN THE DIRT/SILT OUT OF YOUR TEMPORARY CULVERT PIPE AND MAKE SURE IT IS AT GRADE TO ALLOW SWALE TO HAVE POSITIVE DRAINAGE. YOU NEED TO MOVE YOUR PORTA POTTY OUT OF THE COPC SWALE ROW AND PLACE IT ON YOUR SITE. WILL BE BACK 10/7/24 FOR COMPLIANCE REINSPECTION.
ROW - DRAINAGE 10/11/2024 Disapproved - NO FEE PFLANAGAN
Note: STILL NEED TO BE FIX ALL BELOW -------------------------------------------------------------------- 10/7/2024 - PREVIOUS INSPECTION NOTES 10/7/24 YOU NEED TO CLEAN THE DIRT/SILT OUT OF YOUR TEMPORARY CULVERT PIPE AND MAKE SURE IT IS AT GRADE TO ALLOW SWALE TO HAVE POSITIVE DRAINAGE. YOU NEED TO MOVE YOUR PORTA POTTY OUT OF THE COPC SWALE ROW AND PLACE IT ON YOUR SITE. WILL BE BACK 10/7/24 FOR COMPLIANCE REINSPECTION.
ROW - DRAINAGE 10/07/2024 Disapproved - NO FEE FSLADISH
Note: 10/7/24 YOU NEED TO CLEAN THE DIRT/SILT OUT OF YOUR TEMPORARY CULVERT PIPE AND MAKE SURE IT IS AT GRADE TO ALLOW SWALE TO HAVE POSITIVE DRAINAGE. YOU NEED TO MOVE YOUR PORTA POTTY OUT OF THE COPC SWALE ROW AND PLACE IT ON YOUR SITE. WILL BE BACK 10/11/24 FOR COMPLIANCE REINSPECTION.
ELECTRIC - EARLY POWER 10/04/2024 APPROVED PKNAPIK
Note: 10/3/2024 - PREVIOUS INSPECTION NOTES 10-3-24 1. Pep tank wiring not safed off.
ELECTRIC - EARLY POWER 10/03/2024 Disapproved - NO FEE BTAYLOR
Note: 10-3-24 1. Pep tank wiring not safed off.
PEP TANK INSTALLATION REQUEST 09/18/2024 APPROVED CBOWERMASTER
LATH/BRICK/ WATER BARRIER 09/13/2024 APPROVED KSANDOE
ELECTRIC - EARLY POWER 09/12/2024 CANCELLED BY APPLICANT WEB
SEWER TIE IN 09/12/2024 CANCELLED BY APPLICANT WEB
GRAVITY SEWER TEST 09/12/2024 CANCELLED BY APPLICANT WEB
INSULATION 09/11/2024 APPROVED BTAYLOR
Note: 9/9/2024 - PREVIOUS INSPECTION NOTES Previous note has not been addressed FBCR M1601.4.1 Bathroom exhaust duct needs two mechanical fasteners Inspector Notes from Inspection 2420 Please add secondary mechanical fastener to bathroom exhaust ducts
INSULATION 09/09/2024 Disapproved -FEE REQUIRED KSANDOE
Note: Previous note has not been addressed FBCR M1601.4.1 Bathroom exhaust duct needs two mechanical fasteners Inspector Notes from Inspection 2420 Please add secondary mechanical fastener to bathroom exhaust ducts
ALL ROUGH 09/04/2024 APPROVED - AS NOTED KSANDOE
Note: Please add secondary mechanical fastener to bathroom exhaust ducts
ROOF SHEATHING / BRACES/TIES/DOWN CELL 08/29/2024 APPROVED BTAYLOR
Note: 8/28/2024 - PREVIOUS INSPECTION NOTES *** NOTES ADDED BY LMILLER 8/28/2024 11:14:24 AM *** Check all highlighted details on plans (detrails were not completed properly, check all and complete per plan details) per FBC 107.3. 8/26/2024 - PREVIOUS INSPECTION NOTES 8/23/2024 - PREVIOUS INSPECTION NOTES 08-23-2024 Drawings are ripped and dirty. Please provide a clean set of approved drawings for all inspections. 08-26-2024 1. S4.0 BM3 not per plan. Flitch plate needs to be continuous. 2. GE01-D2 front gable not per plan. 3. Lanai framing, (ridge, jack rafters), no anchors or details. 4. Roof sheathing is approved. Contractor can continue with shingles at own risk. 2.
ROOF SHEATHING / BRACES/TIES/DOWN CELL 08/28/2024 Disapproved -FEE REQUIRED LMILLER
Note: *** NOTES ADDED BY LMILLER 8/28/2024 11:14:24 AM *** Check all highlighted details on plans (detrails were not completed properly, check all and complete per plan details) per FBC 107.3. 8/26/2024 - PREVIOUS INSPECTION NOTES 8/23/2024 - PREVIOUS INSPECTION NOTES 08-23-2024 Drawings are ripped and dirty. Please provide a clean set of approved drawings for all inspections. 08-26-2024 1. S4.0 BM3 not per plan. Flitch plate needs to be continuous. 2. GE01-D2 front gable not per plan. 3. Lanai framing, (ridge, jack rafters), no anchors or details. 4. Roof sheathing is approved. Contractor can continue with shingles at own risk. 2.
WALL SHEATHING 08/27/2024 APPROVED KSANDOE
ROOF SHEATHING / BRACES/TIES/DOWN CELL 08/26/2024 Disapproved -FEE REQUIRED AGAETANO
Note: 8/23/2024 - PREVIOUS INSPECTION NOTES 08-23-2024 Drawings are ripped and dirty. Please provide a clean set of approved drawings for all inspections. 08-26-2024 1. S4.0 BM3 not per plan. Flitch plate needs to be continuous. 2. GE01-D2 front gable not per plan. 3. Lanai framing, (ridge, jack rafters), no anchors or details. 4. Roof sheathing is approved. Contractor can continue with shingles at own risk. 2.
ROOF SHEATHING / BRACES/TIES/DOWN CELL 08/23/2024 Disapproved - NO FEE AGAETANO
Note: 08-23-2024 Drawings are ripped and dirty. Please provide a clean set of approved drawings for all inspections.
ROOF VALLEY & METAL 08/16/2024 APPROVED BTAYLOR
ELECTRIC-TUG 08/15/2024 APPROVED RMARTIN
TUB SET 08/15/2024 APPROVED MGIBSON
Note: Inspector Notes from Inspection 2060 ADDRESS NEEDS TO POSTED FOR ''911'' PURPOSES
ROOF SHEATHING 08/12/2024 APPROVED BTAYLOR
TIE BEAM / LINTEL 07/31/2024 APPROVED KSANDOE
FOUND SURVEY APPROVED (OFFICE) 07/26/2024 APPROVED TBAKER
MONOLITHIC SLAB 07/12/2024 APPROVED KSANDOE
PLUMBING 1ST ROUGH UNDERGROUND 07/10/2024 APPROVED - AS NOTED MGIBSON
Note: ADDRESS NEEDS TO POSTED FOR ''911'' PURPOSES
GEOTECHNICAL REPORT APPROVAL (OFFICE USE) 06/25/2024 APPROVED JMUNSON
WATER METER INSTALLATION REQUEST 05/01/2024 APPROVED CBOWERMASTER

Review History

Department Status Date In Date Out
MECH COMPLETE 12/09/2024 12/11/2024
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
BLD COMPLETE 08/15/2024 08/19/2024
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
ENGIN1 COMPLETE 07/25/2024 07/26/2024
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
ENGIN1 COMPLETE 07/25/2024 07/26/2024
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
ZON COMPLETE 07/25/2024 07/25/2024
Note: Released By: LIBBY RAYBURN - - LRAYBURN@PALMCOASTGOV.COM
ENGIN1 HOLD 07/03/2024 07/10/2024
Note: Held By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM Formboard survey is unacceptable as foundation survey. Please submit foundation survey showing location, dimensions and elevation of finished concrete foundation/slab.
ZON COMPLETE 07/03/2024 07/03/2024
Note: Released By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM
BADMIN INFORMATION 07/03/2024 07/03/2024
Note: Marked INFORMATION By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM We do not except form board surveys
BADMIN INFORMATION 07/03/2024 07/03/2024
Note: Marked INFORMATION By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM we do not except foam board surveys
BLD COMPLETE 06/21/2024 06/25/2024
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Letter must be accompanied by a signed and sealed inspection and certification letter by the geotechnical engineer of record. Engineer’s letter to confirm the following: Site clearing / over excavation was completed and inspected by engineer prior to the placement of fill and engineer confirms clearing and over excavation work is acceptable. Engineer to confirm fill materials were suitable and within specifications. Engineer to confirm the required number and location of field density tests were completed. Engineer to include certification statement in accordance with Florida Administrative Code 61G15-18.011 (4) Field dentisty Test Must be digiutally signed and sealed. (Third request)
ENGIN1 HOLD 06/21/2024 06/21/2024
Note: Held By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM Formboard survey is unacceptable as foundation survey.
ZON COMPLETE 06/21/2024 06/21/2024
Note: Released By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM
BLD HOLD 06/14/2024 06/14/2024
Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Letter must be accompanied by a signed and sealed inspection and certification letter by the geotechnical engineer of record. Engineer’s letter to confirm the following: Site clearing / over excavation was completed and inspected by engineer prior to the placement of fill and engineer confirms clearing and over excavation work is acceptable. Engineer to confirm fill materials were suitable and within specifications. Engineer to confirm the required number and location of field density tests were completed. Engineer to include certification statement in accordance with Florida Administrative Code 61G15-18.011 (4) Field dentisty Test Must be digiutally signed and sealed. (Third request)
BLD HOLD 06/10/2024 06/14/2024
Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Letter must be accompanied by a signed and sealed inspection and certification letter by the geotechnical engineer of record. Engineer’s letter to confirm the following: Site clearing / over excavation was completed and inspected by engineer prior to the placement of fill and engineer confirms clearing and over excavation work is acceptable. Engineer to confirm fill materials were suitable and within specifications. Engineer to confirm the required number and location of field density tests were completed. Engineer to include certification statement in accordance with Florida Administrative Code 61G15-18.011 (4) Field dentisty Test Must be digiutally signed and sealed. (Third request)
BLD HOLD 06/04/2024 06/10/2024
Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Letter must be accompanied by a signed and sealed inspection and certification letter by the geotechnical engineer of record. Engineer’s letter to confirm the following: Site clearing / over excavation was completed and inspected by engineer prior to the placement of fill and engineer confirms clearing and over excavation work is acceptable. Engineer to confirm fill materials were suitable and within specifications. Engineer to confirm the required number and location of field density tests were completed. Engineer to include certification statement in accordance with Florida Administrative Code 61G15-18.011 (4) Field dentisty Test Must be digiutally signed and sealed. (Second request)
BLD HOLD 05/02/2024 05/06/2024
Note: Held By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM Letter must be accompanied by a signed and sealed inspection and certification letter by the geotechnical engineer of record. Engineer’s letter to confirm the following: Site clearing / over excavation was completed and inspected by engineer prior to the placement of fill and engineer confirms clearing and over excavation work is acceptable. Engineer to confirm fill materials were suitable and within specifications. Engineer to confirm the required number and location of field density tests were completed. Engineer to include certification statement in accordance with Florida Administrative Code 61G15-18.011 (4) Field dentisty Test Must be digiutally signed and sealed.
ZON COMPLETE 04/01/2024 04/01/2024
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
MECH COMPLETE 04/01/2024 04/04/2024
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
ENGIN1 COMPLETE 04/01/2024 04/01/2024
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
SW1 COMPLETE 04/01/2024 04/01/2024
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
BADMIN COMPLETE 03/19/2024 03/25/2024
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
BLD COMPLETE 03/19/2024 03/21/2024
Note: Released By: JPI
CUSVC COMPLETE 03/19/2024 03/19/2024
Note: Released By: HALEIGH HAND - - HHAND@PALMCOASTGOV.COM
ELEC COMPLETE 03/19/2024 03/25/2024
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
ENGIN1 COMPLETE 03/19/2024 03/19/2024
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
GAS CANCEL 03/19/2024 03/22/2024
LOCATE COMPLETE 03/19/2024 03/21/2024
Note: Released By: TONI CHURCHILL - - TCHURCHILL@PALMCOASTGOV.COM
MECH HOLD 03/19/2024 03/22/2024
Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM 1. Direction house faces on Energy Calcs does not match the site plan. Revise to match per R405.4.2.1 FBC Energy Conservation 2023 8Th Edition 2. Design location on heatload needs to be Daytona Beach
SW1 COMPLETE 03/19/2024 03/19/2024
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
ZON HOLD 03/19/2024 03/21/2024
Note: Held By: LIBBY MUSGROVE - (386)986-3780 - LMUSGROVE@PALMCOASTGOV.COM walkway width must be provided on siteplan
SWALE COMPLETE 03/19/2024 06/04/2024
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
REINSPECTION RESIDENTIAL ¤40.00 12/12/2024
REINSPECTION RESIDENTIAL ¤40.00 12/12/2024
REINSPECTION RESIDENTIAL ¤40.00 12/12/2024
SW ENG - INSPECTION 20 ¤20.00 12/12/2024
SW ENG - INSPECTION 20 ¤20.00 12/12/2024
SW ENG - INSPECTION 20 ¤20.00 12/12/2024
SW ENG - INSPECTION 20 ¤20.00 12/12/2024
SW ENG INSPECTION 80 ¤80.00 04/10/2024
SW ENG PRE APRON ¤30.00 04/10/2024
SW ENG - REVIEW 20 ¤20.00 04/10/2024
SW ENG RES REVIEW 200 ¤200.00 04/10/2024
SEWER CREDIT (¤850.00) 04/10/2024
SEWER INSPECTION ¤25.00 04/10/2024
SEWER CAPITAL FACILITY ¤5,441.03 04/10/2024
WATER CAPITAL FACILITY FEE ¤3,994.51 04/10/2024
SITE PLAN 30 ¤30.00 04/10/2024
CONNECTION FEES ¤1,187.26 04/10/2024
FC IMPACT FEE EMS ¤62.00 04/10/2024
IMPACT FEE FIRE ¤428.09 04/10/2024
FC IMPACT FEE LAW ENFORCEMENT ¤218.00 04/10/2024
FC IMPACT FEE LIBRARY ¤268.00 04/10/2024
IMPACT FEE PARKS ¤1,800.99 04/10/2024
IMPACT FEE SCHOOL ¤5,450.00 04/10/2024
IMPACT FEE TRANSPORTATION ¤1,862.00 04/10/2024
WATER -IRRIGATION INSPECTION ¤25.00 04/10/2024
SURCHARGE FS 533.721 ¤5.14 04/10/2024
SURCHARGE - FS 468.631 ¤7.72 04/10/2024
SW ENG - FOUNDATION SURVEY ¤20.00 04/10/2024
WATER- TURN ON ¤25.00 04/10/2024
ADJUSTMENT 50% (¤514.50) 04/10/2024
ADMINISTRATIVE RESIDENTIAL ¤30.00 04/10/2024
INSPECTION - RESIDENTIAL ¤778.25 04/10/2024
PLAN REVIEW - RESIDENTIAL ¤220.74 04/10/2024
Fees Total Due: ¤0.00 Total Paid: ¤21,044.23