I want to search for...

Permit #2024050570

Permit Details

Status: COED

Parcel Id: 07-11-31-7057-00800-0080
CONDITIONED SPACE: 2594 sqft
GARAGE: 586 sqft
OPENED PORCH (WITH ROOF) : 256 sqft
Total Square Footage: 3436 sqft
Block: 00800
Subdivision: -
Job Phone: 386-237-5837
Location Address: 9 ULLEMAY CT
Type: DU - DUPLEX
Issue Date: 12/13/2024
NOC: RECORDED
Applicant name: MARSEL GILMANSHIN
Owner: CHTONDA VASSILI P & LIALLA NOUROUCHEVA H&W

Address

9 WAINSHIRE PL

PALM COAST, FL 32164

Lot: 0080
Contracted Stated Job Value: ¤350,000.00
Job Description: DUPLEX
Type: CN

Contractor

GILMANS DEVELOPMENT CORP
Status Location Address State License Number Phone
ACTIVE

4873 PALM COAST PARKWAY NW #4

PALM COAST, FL 32137

CBC1263180 (Exp: 08/31/2026) 386-237-5837

Sub Contractors

OLEG BELINSKIY
Status Location Address State License Number Phone
ACTIVE

19 PINE CIRCLE DRIVE19

PALM COAST, FL 32167

CCC1325974 (Exp: 08/31/2026) 386-263-7906
GARY S WELBORN
Status Location Address State License Number Phone Fax
ACTIVE

1709 North Nova Road

Holly Hill, 32117

CFC1426839 (Exp: 08/31/2026) (386) 257-1172 386-252-5979
MAXIM BUDNIK
Status Location Address State License Number
ACTIVE

3 WAVECREST PL

PALM COAST, FL 32164

CAC1818445 (Exp: 08/31/2026)
MAXIM BUDNIK
Status Location Address State License Number Phone
ACTIVE

9788 HALSEY RD

JACKSONVILLE, FL 32246

EC13007415 (Exp: 08/31/2026) 904-509-7306

Inspection History

Type Request Date Result Inspector
BLD - BUILDING FINAL 10/14/2025 FINAL APPROVED MCONTRYMAN
Note: 9/26/2025 - PREVIOUS INSPECTION NOTES 9/26/25 Both sides: 1. Energy calcs do not match units installed (breakers are okay) FBC(A) 107.4 2. Range needs to be GFCi protected NEC 210.8 3. Fridge needs to be GFCi or ARc Fault protected NEC 210.8 4. Outlet on immediate outside wall of guest bath needs to be GFCi prottected NEC 210.8 5. Deadbolt missing on front entry doors and hole not plugged/filled (different knobs on site but not installed) FBC 402.5.1.1 A Side: 1. Termite plaque not posted on electrical panel FBC R105.11 B Side: 1. Loose tub spout in guest bath FBC-P2705.1 2. Anti tip on range not secured FBCR M1901.2
BLD - BUILDING FINAL 09/26/2025 Disapproved -FEE REQUIRED MCONTRYMAN
Note: 9/26/25 Both sides: 1. Energy calcs do not match units installed (breakers are okay) FBC(A) 107.4 2. Range needs to be GFCi protected NEC 210.8 3. Fridge needs to be GFCi or ARc Fault protected NEC 210.8 4. Outlet on immediate outside wall of guest bath needs to be GFCi prottected NEC 210.8 5. Deadbolt missing on front entry doors and hole not plugged/filled (different knobs on site but not installed) FBC 402.5.1.1 A Side: 1. Termite plaque not posted on electrical panel FBC R105.11 B Side: 1. Loose tub spout in guest bath FBC-P2705.1 2. Anti tip on range not secured FBCR M1901.2
U -UTILITY RESIDENTIAL FINAL 09/04/2025 FINAL APPROVED BHAINES
ROW - FINAL INSPECTION 08/28/2025 APPROVED RRICKS
Note: 8/28/25 SPOKE TO THE CM AND INFORMED HIM TO REMOVE THE SMALL AMOUNT OF DEBRIS AROUND BRASS CAP. AT THE TIME OF THIS INSPECTION ALL MINIMUM COPC REQUIREMENTS ARE MET. BUILDER TO BE HELD RESPONSIBLE IF, FOR WHATEVER REASON, SITE CONDITIONS CHANGE OVER TIME AFTER THE INSPECTION. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED. THIS INCLUDES BUT IS NOT LIMITED TO THE CULVERT PIPE ELEVATION APPROVAL FOR THE CONCRETE POUR. *** INSPECTORS NOTE.YOU WILL NEED TO REMOVE THE HIGH SPOT AT AND JUST OVER THE RIGHT SIDE FRONT SWALE PROPERTY LINE BEFORE ROW FINAL PASSAGE TO ALLOW POSITIVE SWALE DRAINAGE FLOW.***
ROW - FINAL APRON (AFTER POUR) 07/11/2025 APPROVED FSLADISH
Note: 7/11/25 PIPE ELEVATION IS GOOD, CUTS ARE MADE, CULVERT CLEAR, HOT PATCH COMPLETE. AT THE TIME OF THE INSPECTION ALL MINIMUM CITY REQUIREMENTS WERE MET. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED. _______________________________________________________________________________________________________________________ Inspector Notes from Inspection 9465 Inspector Notes from Inspection 9463 7/7/25 YOUR SITE PLAN SHOWS A COMMON SWALE ON THE LEFT SIDE PROPERTY, YOUR SITE PLAN SHOWS AN INSIDE SWALE.. I WILL DETERMINE ON FIELD SURVEY IF THIS WILL WORK. APPROVING THIS FINAL SURVEY AS NOTED. 7/7/25 UPON WALKING PROPERTY DETERMINED DRAINAGE WILL WORK WITHOUT ADVERSE DRAINAGE ON THE LEFT SIDE. YOU WILL NEED TO REMOVE THE HIGH SPOT AT AND JUST OVER THE RIGHT SIDE FRONT SWALE PROPERTY LINE BEFORE ROW FINAL PASSAGE TO ALLOW POSITIVE SWALE DRAINAGE FLOW. AREA IS OUTLINED IN PINK PAINT.
ROW- FINAL SURVEY/GRADING CERTIFICATION 07/07/2025 APPROVED - AS NOTED FSLADISH
Note: 7/7/25 YOUR SITE PLAN SHOWS A COMMON SWALE ON THE LEFT SIDE PROPERTY, YOUR SITE PLAN SHOWS AN INSIDE SWALE.. I WILL DETERMINE ON FIELD SURVEY IF THIS WILL WORK. APPROVING THIS FINAL SURVEY AS NOTED.
ROW FIELD SURVEY /GRADING CERTIFICATION 07/07/2025 APPROVED - AS NOTED FSLADISH
Note: Inspector Notes from Inspection 9463 7/7/25 YOUR SITE PLAN SHOWS A COMMON SWALE ON THE LEFT SIDE PROPERTY, YOUR SITE PLAN SHOWS AN INSIDE SWALE.. I WILL DETERMINE ON FIELD SURVEY IF THIS WILL WORK. APPROVING THIS FINAL SURVEY AS NOTED. 7/7/25 UPON WALKING PROPERTY DETERMINED DRAINAGE WILL WORK WITHOUT ADVERSE DRAINAGE ON THE LEFT SIDE. YOU WILL NEED TO REMOVE THE HIGH SPOT AT AND JUST OVER THE RIGHT SIDE FRONT SWALE PROPERTY LINE BEFORE ROW FINAL PASSAGE TO ALLOW POSITIVE SWALE DRAINAGE FLOW. AREA IS OUTLINED IN PINK PAINT.
U-CROSS CONNECTION 06/27/2025 APPROVED BWRIGHT
Note: No IRR. No CC
ROW- PRE-APRON (PRE-POUR) 06/04/2025 APPROVED FSLADISH
Note: 6/4/25 AT THE TIME OF THE INSPECTION CULVERT PIPE IS GOOD IS READY TO POUR, IF RAIN PLEASE, BUILDER SHOULD DOUBLE CHECK CULVERT ELEVATIONS MAKE SURE IS 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE (FRC) DRAWING 300,E RESIDENTIAL CULVERT DETAIL BEFORE POURING. TICKET OF CONCRETE MIX DESIGN SHALL BE UPLOADED INTO PERMIT PORTAL. 8.a. IF FIBERGLASS OPTION IS USED, DOCUMENTATION OF THE ( FRC) CONTAINING THE FIBERGLASS MUST BE ATTACHED TO THE PERMIT PRIOR TO REQUESTING AN AFTER-POUR INSPECTION. 8.b. IF MESH OPTION IS USED, IT SHALL BE IN PLACE AT THE TIME OF THE PRE-POUR.
ELECTRIC - EARLY POWER 05/28/2025 APPROVED - AS NOTED BTAYLOR
Note: 5-28-25 1. Emailed FPL at 3:03. 5/27/2025 - PREVIOUS INSPECTION NOTES 1. Meter mains missing SPD
ELECTRIC - EARLY POWER 05/27/2025 Disapproved - NO FEE MKRASKI
Note: 1. Meter mains missing SPD
INSULATION 05/16/2025 APPROVED MCONTRYMAN
Note: 5/2/2025 - PREVIOUS INSPECTION NOTES 5/1/2025 - PREVIOUS INSPECTION NOTES 5-1-25 1. Missing garage man doors in both units.
GRAVITY SEWER TEST 05/15/2025 APPROVED MGIBSON
SEWER TIE IN 05/15/2025 APPROVED MGIBSON
INSULATION 05/02/2025 CANCELLED BY APPLICANT BTAYLOR
Note: 5/1/2025 - PREVIOUS INSPECTION NOTES 5-1-25 1. Missing garage man doors in both units.
INSULATION 05/01/2025 PARTIALLY APPROVED BTAYLOR
Note: 5-1-25 1. Missing garage man doors in both units.
LATH/BRICK/ WATER BARRIER 04/30/2025 APPROVED BTAYLOR
ALL ROUGH 04/28/2025 APPROVED BTAYLOR
Note: 4/21/2025 - PREVIOUS INSPECTION NOTES 4/21/25 1. Need product approval sheet on site FBC(A) 107.3.1 2. No energy calcs on site FBC(A) 107.3.1 3. Framing above electrical panels need to have solid blocking for annular spacing NEC 302.11(4) & 302.11.1 4. Window in left side 2nd br exceeds max shim spacing of 1/4" FBCR 609.1
ALL ROUGH 04/21/2025 Disapproved -FEE REQUIRED MCONTRYMAN
Note: 4/21/25 1. Need product approval sheet on site FBC(A) 107.3.1 2. No energy calcs on site FBC(A) 107.3.1 3. Framing above electrical panels need to have solid blocking for annular spacing NEC 302.11(4) & 302.11.1 4. Window in left side 2nd br exceeds max shim spacing of 1/4" FBCR 609.1
FIREWALL FINAL 04/16/2025 APPROVED BTAYLOR
Note: Inspector Notes from Inspection 2443 Need address posted R319.1 4/3/2025 - PREVIOUS INSPECTION NOTES 4/1/2025 - PREVIOUS INSPECTION NOTES 1. Silt fence needs to be repaired to orginal condition FBC 3307.1 2. No plans on site FBC 107.3.1 3. Firewall framing inspection has not been passed yet FBC [A] 110.6
FIREWALL DRYWALL NAILING 04/08/2025 APPROVED - AS NOTED KSANDOE
Note: Need address posted R319.1 4/3/2025 - PREVIOUS INSPECTION NOTES 4/1/2025 - PREVIOUS INSPECTION NOTES 1. Silt fence needs to be repaired to orginal condition FBC 3307.1 2. No plans on site FBC 107.3.1 3. Firewall framing inspection has not been passed yet FBC [A] 110.6
FIREWALL DRYWALL NAILING 04/03/2025 CANCELLED BY APPLICANT BTAYLOR
Note: 4/1/2025 - PREVIOUS INSPECTION NOTES 1. Silt fence needs to be repaired to orginal condition FBC 3307.1 2. No plans on site FBC 107.3.1 3. Firewall framing inspection has not been passed yet FBC [A] 110.6
FIREWALL FRAMING 04/03/2025 APPROVED BTAYLOR
FIREWALL DRYWALL NAILING 04/01/2025 Disapproved - NO FEE MKRASKI
Note: 1. Silt fence needs to be repaired to orginal condition FBC 3307.1 2. No plans on site FBC 107.3.1 3. Firewall framing inspection has not been passed yet FBC [A] 110.6
ROOF VALLEY & METAL 03/28/2025 APPROVED BTAYLOR
WALL SHEATHING 03/25/2025 APPROVED BTAYLOR
ROOF SHEATHING / BRACES/TIES/DOWN CELL 03/25/2025 APPROVED - AS NOTED BTAYLOR
Note: 3-25-25 1. Need to add HUS26 buckets on trusses in garage. Truss 20-29. 2. Missing engineering on truss 05 on A side. Check at next inspection.
FOUND SURVEY APPROVED (OFFICE) 03/24/2025 APPROVED RRICKS
TIE BEAM / LINTEL 03/07/2025 APPROVED MCONTRYMAN
Note: 3/5/2025 - PREVIOUS INSPECTION NOTES 3-5-25 1. Nothing has been resolved. 3/3/2025 - PREVIOUS INSPECTION NOTES 3/3/25 1. Bed joints exceed the 1/2" max for all large windows. Solid blocking is to be put in to allow for proper grout joint spacing FBCR 606.3.1
TIE BEAM / LINTEL 03/05/2025 Disapproved -FEE REQUIRED BTAYLOR
Note: 3-5-25 1. Nothing has been resolved. 3/3/2025 - PREVIOUS INSPECTION NOTES 3/3/25 1. Bed joints exceed the 1/2" max for all large windows. Solid blocking is to be put in to allow for proper grout joint spacing FBCR 606.3.1
TIE BEAM / LINTEL 03/03/2025 Disapproved - NO FEE MCONTRYMAN
Note: 3/3/25 1. Bed joints exceed the 1/2" max for all large windows. Solid blocking is to be put in to allow for proper grout joint spacing FBCR 606.3.1
MONOLITHIC SLAB 02/10/2025 APPROVED BTAYLOR
PLUMBING 1ST ROUGH UNDERGROUND 02/04/2025 APPROVED MGIBSON
GEOTECHNICAL REPORT APPROVAL (OFFICE USE) 02/03/2025 APPROVED PKNAPIK
WATER METER INSTALLATION REQUEST 12/26/2024 APPROVED CBOWERMASTER

Review History

Department Status Date In Date Out
MECH COMPLETE 10/09/2025 10/10/2025
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
BADMIN COMPLETE 10/08/2025 10/08/2025
Note: Released By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM
MECH HOLD 10/08/2025 10/08/2025
Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Energy Calcs need to be signed by the owner/ owner agent below the preparer per R103.1.1.2 FBC Energy Conservation 2023 8Th edition
MECH COMPLETE 10/08/2025 10/09/2025
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
BADMIN HOLD 10/02/2025 10/02/2025
Note: Held By: BARBIE BEMBRY - (386)986-3780 - BUILDINGDIVISION@PALMCOASTGOV.COM Rename your files and upload them under the correct document type. (see document submittal requirements for instructions)
BADMIN INFORMATION 07/03/2025 07/03/2025
Note: Marked INFORMATION By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM repeat comment The final survey should be uploaded under the final survey document type and the file named 'final survey'.
BADMIN INFORMATION 07/01/2025 07/01/2025
Note: Marked INFORMATION By: BARBIE BEMBRY - (386)986-3780 - BUILDINGDIVISION@PALMCOASTGOV.COM The final survey should be uploaded under the final survey document type and the file named 'final survey'.
ENGIN1 COMPLETE 02/18/2025 02/19/2025
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
ZON COMPLETE 02/18/2025 02/18/2025
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
BADMIN INFORMATION 02/18/2025 02/18/2025
Note: Marked INFORMATION By: NICOLE DIMATTINA - - NDIMATTINA@PALMCOASTGOV.COM Reminder foundation surveys should now be formboard surveys
BLD COMPLETE 01/29/2025 02/03/2025
Note: Released By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM
MECH COMPLETE 08/13/2024 08/16/2024
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
ZON COMPLETE 08/05/2024 08/06/2024
Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM
MECH HOLD 08/05/2024 08/08/2024
Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Indoor design temp on heatload must be a minimum of 75 degrees per R302.1 FBC Energy Conservation 2023 8Th edition (Second Request) Energy Calcs not uploaded
BADMIN COMPLETE 08/05/2024 08/12/2024
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
ELEC COMPLETE 08/05/2024 08/12/2024
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
ENGIN1 COMPLETE 05/13/2024 05/13/2024
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
SW1 COMPLETE 05/13/2024 05/13/2024
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
BADMIN HOLD 05/13/2024 05/17/2024
Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Provide geotechnical investigation report in accordance with FBCB Section 1803.2.  Report to be conducted per Sections 1803.3 through 1803.5.  Completed report shall comply with Section 1803.6.  Report shall be signed and sealed by a Florida licensed professional engineer in accordance with F.S. 471.025 and Florida Administrative Code Sections 61G15-30.001 and 61G15-23.001 through .005. You can request a deferred submittal by providing a letter on company letterhead. After the geotechnical report is approved by the City of Palm Coast, then the engineer must provide a signed and sealed letter certifying the entire process was completed in accordance with the engineer’s specifications. The engineer’s letter must include a certification statement in accordance with the Florida Administrative Code 61G15-18.011 (4).
BLD COMPLETE 05/13/2024 05/14/2024
Note: Released By: JPI
CUSVC COMPLETE 05/13/2024 05/14/2024
Note: Released By: HALEIGH HAND - - HHAND@PALMCOASTGOV.COM
ELEC HOLD 05/13/2024 05/20/2024
Note: Held By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM 1. Submit a duplex riser diagram that includes all wire sizes and breaker sizes. Also must include the surge protectors and outside disconnects. NEC 2020 230.67, 230.85
GAS CANCEL 05/13/2024 05/17/2024
LOCATE COMPLETE 05/13/2024 05/16/2024
Note: Released By: CANDACE BOWERMASTER - - CBOWERMASTER@PALMCOASTGOV.COM
MECH HOLD 05/13/2024 05/17/2024
Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Indoor design temp on heatload must be a minimum of 75 degrees per R302.1 FBC Energy Conservation 2023 8Th edition
ZON HOLD 05/13/2024 05/14/2024
Note: Held By: SCOTT THOMAS - (386)986-3780 - STHOMAS@PALMCOASTGOV.COM CHECK BOX COLOR MATERIAL SHEET FOR ACCENT COLOR
SWALE COMPLETE 05/13/2024 09/06/2024
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
PLAN REVIEW - REVISION ¤32.50 11/06/2025
REINSPECTION RESIDENTIAL ¤40.00 11/06/2025
REINSPECTION RESIDENTIAL ¤40.00 11/06/2025
REINSPECTION RESIDENTIAL ¤40.00 11/06/2025
CONTRACTOR CHANGE ¤20.00 11/06/2025
CONTRACTOR CHANGE ¤20.00 11/06/2025
PLAN REVIEW - RESIDENTIAL ¤377.52 12/13/2024
FC IMPACT FEE EMS ¤124.00 12/13/2024
FC IMPACT FEE LAW ENFORCEMENT ¤436.00 12/13/2024
IMPACT FEE FIRE ¤856.18 12/13/2024
FC IMPACT FEE LIBRARY ¤536.00 12/13/2024
ADJUSTMENT 10% (¤173.85) 12/13/2024
INSPECTION - RESIDENTIAL ¤1,331.00 12/13/2024
WATER- TURN ON ¤25.00 12/13/2024
ADMINISTRATIVE RESIDENTIAL ¤30.00 12/13/2024
IMPACT FEE PARKS ¤3,600.18 12/13/2024
IMPACT FEE TRANSPORTATION ¤2,890.00 12/13/2024
IMPACT FEE SCHOOL ¤10,900.00 12/13/2024
WATER -IRRIGATION INSPECTION ¤25.00 12/13/2024
SURCHARGE - FS 468.631 ¤23.47 12/13/2024
SURCHARGE FS 533.721 ¤15.65 12/13/2024
SW ENG - FOUNDATION SURVEY ¤20.00 12/13/2024
SW ENG INSPECTION 80 ¤80.00 12/13/2024
SW ENG - REVIEW 20 ¤20.00 12/13/2024
SW ENG PRE APRON ¤30.00 12/13/2024
SW ENG RES REVIEW 200 ¤200.00 12/13/2024
SEWER CREDIT (¤1,700.00) 12/13/2024
SEWER INSPECTION ¤25.00 12/13/2024
SEWER CAPITAL FACILITY ¤6,120.52 12/13/2024
WATER CAPITAL FACILITY FEE ¤4,351.14 12/13/2024
CONNECTION FEES ¤1,187.26 12/13/2024
SITE PLAN 30 ¤30.00 12/13/2024
SITE PLAN 30 ¤30.00 12/12/2024
SITE PLAN 30 (¤30.00) 12/12/2024
SEWER CAPITAL FACILITY ¤6,120.52 12/12/2024
WATER CAPITAL FACILITY FEE ¤4,351.14 12/12/2024
WATER CAPITAL FACILITY FEE (¤4,351.14) 12/12/2024
SEWER INSPECTION ¤25.00 12/12/2024
SEWER CAPITAL FACILITY (¤6,120.52) 12/12/2024
SEWER CREDIT (¤1,700.00) 12/12/2024
SEWER INSPECTION (¤25.00) 12/12/2024
SEWER CREDIT ¤1,700.00 12/12/2024
SW ENG - REVIEW 20 (¤20.00) 12/12/2024
SW ENG - REVIEW 20 ¤20.00 12/12/2024
SW ENG RES REVIEW 200 ¤200.00 12/12/2024
SW ENG RES REVIEW 200 (¤200.00) 12/12/2024
SW ENG INSPECTION 80 ¤80.00 12/12/2024
SW ENG PRE APRON ¤30.00 12/12/2024
SW ENG PRE APRON (¤30.00) 12/12/2024
SW ENG INSPECTION 80 (¤80.00) 12/12/2024
SURCHARGE - FS 468.631 (¤23.47) 12/12/2024
SURCHARGE - FS 468.631 ¤23.47 12/12/2024
SW ENG - FOUNDATION SURVEY ¤20.00 12/12/2024
SW ENG - FOUNDATION SURVEY (¤20.00) 12/12/2024
SURCHARGE FS 533.721 ¤15.65 12/12/2024
SURCHARGE FS 533.721 (¤15.65) 12/12/2024
IMPACT FEE TRANSPORTATION (¤2,890.00) 12/12/2024
IMPACT FEE TRANSPORTATION ¤2,890.00 12/12/2024
WATER -IRRIGATION INSPECTION ¤25.00 12/12/2024
WATER -IRRIGATION INSPECTION (¤25.00) 12/12/2024
IMPACT FEE PARKS ¤3,600.18 12/12/2024
IMPACT FEE SCHOOL ¤10,900.00 12/12/2024
IMPACT FEE SCHOOL (¤10,900.00) 12/12/2024
ADMINISTRATIVE RESIDENTIAL ¤30.00 12/12/2024
INSPECTION - RESIDENTIAL ¤1,331.00 12/12/2024
INSPECTION - RESIDENTIAL (¤1,331.00) 12/12/2024
ADJUSTMENT 10% (¤173.85) 12/12/2024
ADJUSTMENT 10% ¤173.85 12/12/2024
WATER- TURN ON ¤25.00 12/12/2024
WATER- TURN ON (¤25.00) 12/12/2024
PLAN REVIEW - RESIDENTIAL (¤377.52) 12/12/2024
ADMINISTRATIVE RESIDENTIAL (¤30.00) 12/12/2024
CONNECTION FEES ¤1,187.26 12/12/2024
CONNECTION FEES (¤1,187.26) 12/12/2024
IMPACT FEE PARKS (¤3,600.18) 12/12/2024
FC IMPACT FEE LAW ENFORCEMENT (¤436.00) 12/12/2024
FC IMPACT FEE LAW ENFORCEMENT ¤436.00 12/12/2024
FC IMPACT FEE LIBRARY ¤536.00 12/12/2024
FC IMPACT FEE LIBRARY (¤536.00) 12/12/2024
FC IMPACT FEE EMS ¤124.00 12/12/2024
IMPACT FEE FIRE ¤856.18 12/12/2024
IMPACT FEE FIRE (¤856.18) 12/12/2024
PLAN REVIEW - RESIDENTIAL ¤377.52 12/12/2024
FC IMPACT FEE EMS (¤124.00) 12/12/2024
Fees Total Due: ¤0.00 Total Paid: ¤31,552.57