I want to search for...

Permit #2024050701

Permit Details

Status: COED

Parcel Id: 07-11-31-7032-00730-0200
CONDITIONED SPACE: 2306 sqft
GARAGE: 466 sqft
OPENED PORCH (WITH ROOF) : 142 sqft
OPENED PORCH (WITH ROOF) : 32 sqft
Total Square Footage: 2946 sqft
Block: 00730
Subdivision: 7032 -
Job Phone: 831-383-2883
Location Address: 1 ROLLINS LN
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 08/29/2024
NOC: RECORDED
Applicant name: EDWARD LEE DAUBERT JR
Owner: BRITE LAND INVESTMENT FUND LP

Address

21380 LORIAN ROAD

CLEVELAND, OH 44126

Lot: 0200
Contracted Stated Job Value: ¤252,000.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

BRITE BUILDING GROUP LLC
Status Location Address State License Number Phone
ACTIVE

6751 FORUM DRIVE SUITE 210

ORLANDO, FL 32821

CBC1266303 (Exp: 08/31/2026) 831-383-2883

Sub Contractors

DUSTIN L ESTEP
Status Location Address State License Number Phone Fax
ACTIVE

2041 N HIAWASSEE RD

APOPKA, FL 32703

CCC1330971 (Exp: 08/31/2026) 407-702-0206 352-988-6629
JOSEPH HORATIO STRADA JR
Status Location Address State License Number Phone
ACTIVE

3400 ST JOHNS PARKWAY

SANFORD, FL 32771

EC13003715 (Exp: 08/31/2026) 877-906-1113
JOSEPH H STRADA JR
Status Location Address State License Number Phone
ACTIVE

3400 ST JOHNS PKWY

SANFORD, FL 32771

CAC043953 (Exp: 08/31/2026) 877-906-1113
JOSEPH HORATIO STRADA JR
Status Location Address State License Number Phone
ACTIVE

3400 ST JOHNS PARKWAY

, 0

CFC1432331 (Exp: 08/31/2026) 877-906-1113

Inspection History

Type Request Date Result Inspector
U -UTILITY RESIDENTIAL FINAL 03/12/2026 FINAL APPROVED BWRIGHT
Note: Inspector Notes from Inspection 9035 No CC. IRR with potable water using PVB
BLD - BUILDING FINAL 03/10/2026 APPROVED CVANSTRAHLEN
Note: 3/6/2026 - PREVIOUS INSPECTION NOTES Please fix items before next inspection #1-FBC [A] 107.4-MECHANICAL EQUIPMENT DOES NOT MATCH ENERGY CALCS #2- Seal up soffit penetrations for electrical mast #3-M1502.4.7 Exhaust duct required. Where space for a clothes dryer is provided, an exhaust duct system shall be installed. Where the clothes dryer is not installed at the time of occupancy the exhaust duct shall be capped or plugged in the space in which it originates and identified and marked “future use.”
U-CROSS CONNECTION 03/06/2026 APPROVED - AS NOTED BWRIGHT
Note: No CC. IRR with potable water using PVB
BLD - BUILDING FINAL 03/06/2026 Disapproved -FEE REQUIRED CVANSTRAHLEN
Note: Please fix items before next inspection #1-FBC [A] 107.4-MECHANICAL EQUIPMENT DOES NOT MATCH ENERGY CALCS #2- Seal up soffit penetrations for electrical mast #3-M1502.4.7 Exhaust duct required. Where space for a clothes dryer is provided, an exhaust duct system shall be installed. Where the clothes dryer is not installed at the time of occupancy the exhaust duct shall be capped or plugged in the space in which it originates and identified and marked “future use.”
ROW - STORMWATER FINAL 03/06/2026 APPROVED FSLADISH
Note: 3/6/26 AT THE TIME OF THE INSPECTION, ALL MINIMUM CITY REQUIREMENTS WERE MET. IT IS THE BUILDER'S AND/OR HOMEOWNER’S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED.
U -UTILITY RESIDENTIAL FINAL 03/06/2026 Disapproved - NO FEE BWRIGHT
Note: Sewer clean-out is to close to 2 Roller back property line and need to be straighten.
ROW - FINAL APRON (AFTER POUR) 03/06/2026 APPROVED FSLADISH
Note: 3/6/26 AT THE TIME OF THE INSPECTION, ALL MINIMUM CITY REQUIREMENTS WERE MET. IT IS THE BUILDER'S AND/OR HOMEOWNER’S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED.
ROW- FINAL SURVEY/GRADING CERTIFICATION 03/05/2026 APPROVED FSLADISH
ROW FIELD SURVEY /GRADING CERTIFICATION 03/05/2026 APPROVED FSLADISH
Note: 3/4/26 AT THE TIME OF THE INSPECTION, ALL MINIMUM CITY REQUIREMENTS WERE MET. IT IS THE BUILDER'S AND/OR HOMEOWNER’S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED.
ELECTRIC - EARLY POWER 01/16/2026 APPROVED CVANSTRAHLEN
Note: EMAIL TO FPL 1/14/2026 - PREVIOUS INSPECTION NOTES PLEASE FIX ITEMS BEFORE NEXT INSPECTION #1-GROUND WIRE MISSING STRIP ON CONNECTING BOLD ( MAIN METTER BASE PANEL ) #2- TUG CONDUIT PIPEB NEED SUPPORT ATTACH ON EXTERIOR WALL ( CLAMP BROKEN )
ELECTRIC - EARLY POWER 01/14/2026 Disapproved -FEE REQUIRED CVANSTRAHLEN
Note: PLEASE FIX ITEMS BEFORE NEXT INSPECTION #1-GROUND WIRE MISSING STRIP ON CONNECTING BOLD ( MAIN METTER BASE PANEL ) #2- TUG CONDUIT PIOPE NEED SUPPORT ATTACH ON EXTERIOR WALL ( CLAMP BROKEN )
ROW- PRE-APRON (PRE-POUR) 01/05/2026 APPROVED - AS NOTED FSLADISH
Note: 1/6/26 CULVERT PIPE IS FLAT WITHIN SWALE PLAN DIAGRAM ALLOWABLE ELEVATION AT THE TIME OF THIS INSPECTION. PIPE INVERT IS GOOD AT THIS INSPECTION. BUILDER REFER TO CONCRETE (FRC) DRAWING 300,E RESIDENTIAL CULVERT DETAIL BEFORE POURING. . IF FIBERGLASS OPTION IS USED, BUILDER REQUIRED TO USE 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED DOCUMENTATION OF THE ( FRC) CONTAINING THE FIBERGLASS MUST BE ATTACHED TO THE PERMIT PRIOR TO REQUESTING AN AFTER-POUR INSPECTION. 8.b. IF MESH OPTION IS USED, IT SHALL BE IN PLACE AT THE TIME OF THE PRE-POUR AT THE TIME OF THE INSPECTION READY TO POUR, IF RAIN PLEASE, BUILDER SHOULD DOUBLE CHECK SITE FOR ANY STANDING WATER. ALSO VERIFY PIPE ELEVATION HAS NOT CHANGED. NO EXPANSION JOINTS ALLOWED, AT THE TIME OF THIS INSPECTION ALL MINIMUM COPC REQUIREMENTS ARE MET. BUILDER TO BE HELD RESPONSIBLE IF, FOR WHATEVER REASON, SITE CONDITIONS CHANGE OVER TIME AFTER THE INSPECTION. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED. THIS INCLUDES BUT IS NOT LIMITED TO THE CULVERT PIPE ELEVATION APPROVAL FOR THE CONCRETE POUR 12/23/2025 - PREVIOUS INSPECTION NOTES 12-23-25 TPOLACEK** UPON CHECKING SWALE PLAN AND SURROUNDING CULVERT ELEVATION AS WELL AS THE VALLEY GUTTER ROAD CROSSING I DETERMINED THAT THE SWALE WOULD HOLD A SUBSTANTIAL AMOUNT OF WATER AND DRAIN TO OUTFALL. I CALLED THE SUPERVISOR FOR THE COPC SURVEYORS AND CONFIRMED WITH HIM ABOUT THE ELEVATIONS. THEY WILL BE SENDING OUT THE SURVEY CREW TO RE-CONFIRM THE SURROUNDING PIPE ELEVATIONS AS WELL AS THE VALLEY GUTTER TO POSSIBLY CHANGE THE SWALE PLAN DETAIL AND RAISE THE CULVERT ELEVATION SO DRAINAGE WILL FLOW. I AM CANCELING TODAYS INSPECTION DUE TO THE CIRCUMSTANCES INVOLVED. +++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ 12/22/2025 - PREVIOUS INSPECTION NOTES 12/22/25 YOU HAVE HIGH SPOTS AS WELL AS AN AREA THAT WAS DISTURBED/DUG UP AND NOT RECOMPACTED AND CORRECT DEPTH. YOU ALSO HAVE TWO BM IN THE POWER POLE. BENCHMARK EASILY IDENTIFIED Section 300.01 B(9) V-15 "9) An on-site, easily identifiable benchmark referenced to NAVD 1988 (e.g., fire hydrant, nail in power pole [1 nail per power pole], and manhole covers). Pavement nails will be accepted if the above locations are not available on site. (The benchmark must be maintained throughout the construction cycle and will be used in the swale plan and Final Survey). NAVD 1988 data sheets are available http://www.ngs.noaa.gov" SEE PHOTO FOR REFERENCE
ROW- PRE-APRON (PRE-POUR) 12/23/2025 CANCELLED BY APPLICANT TPOLACEK
Note: 12-23-25 TPOLACEK** UPON CHECKING SWALE PLAN AND SURROUNDING CULVERT ELEVATION AS WELL AS THE VALLEY GUTTER ROAD CROSSING I DETERMINED THAT THE SWALE WOULD HOLD A SUBSTANTIAL AMOUNT OF WATER AND DRAIN TO OUTFALL. I CALLED THE SUPERVISOR FOR THE COPC SURVEYORS AND CONFIRMED WITH HIM ABOUT THE ELEVATIONS. THEY WILL BE SENDING OUT THE SURVEY CREW TO RE-CONFIRM THE SURROUNDING PIPE ELEVATIONS AS WELL AS THE VALLEY GUTTER TO POSSIBLY CHANGE THE SWALE PLAN DETAIL AND RAISE THE CULVERT ELEVATION SO DRAINAGE WILL FLOW. I AM CANCELING TODAYS INSPECTION DUE TO THE CIRCUMSTANCES INVOLVED. +++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ 12/22/2025 - PREVIOUS INSPECTION NOTES 12/22/25 YOU HAVE HIGH SPOTS AS WELL AS AN AREA THAT WAS DISTURBED/DUG UP AND NOT RECOMPACTED AND CORRECT DEPTH. YOU ALSO HAVE TWO BM IN THE POWER POLE. BENCHMARK EASILY IDENTIFIED Section 300.01 B(9) V-15 "9) An on-site, easily identifiable benchmark referenced to NAVD 1988 (e.g., fire hydrant, nail in power pole [1 nail per power pole], and manhole covers). Pavement nails will be accepted if the above locations are not available on site. (The benchmark must be maintained throughout the construction cycle and will be used in the swale plan and Final Survey). NAVD 1988 data sheets are available http://www.ngs.noaa.gov" SEE PHOTO FOR REFERENCE
ROW- PRE-APRON (PRE-POUR) 12/22/2025 Disapproved -FEE REQUIRED FSLADISH
Note: 12/22/25 YOU HAVE HIGH SPOTS AS WELL AS AN AREA THAT WAS DISTURBED/DUG UP AND NOT RECOMPACTED AND CORRECT DEPTH. YOU ALSO HAVE TWO BM IN THE POWER POLE. BENCHMARK EASILY IDENTIFIED Section 300.01 B(9) V-15 "9) An on-site, easily identifiable benchmark referenced to NAVD 1988 (e.g., fire hydrant, nail in power pole [1 nail per power pole], and manhole covers). Pavement nails will be accepted if the above locations are not available on site. (The benchmark must be maintained throughout the construction cycle and will be used in the swale plan and Final Survey). NAVD 1988 data sheets are available http://www.ngs.noaa.gov" SEE PHOTO FOR REFERENCE
INSULATION 12/02/2025 APPROVED CVANSTRAHLEN
LATH/BRICK/ WATER BARRIER 12/02/2025 APPROVED CVANSTRAHLEN
ALL ROUGH 11/26/2025 APPROVED CVANSTRAHLEN
Note: *** NOTES ADDED BY CVANSTRAHLEN 11/26/2025 11:37:20 AM *** Please fix studs on laundry room wall 10/28/2025 - PREVIOUS INSPECTION NOTES Please fix previous items 10/24/2025 - PREVIOUS INSPECTION NOTES please fix items before next inspection #1-Dowel / down rods do not meet the minimum clearance (2" from face of block and/or 3/4: from inside of block) as required. (FBC-R606.3.4) ( all mark with orange spray paint ) #2-FBCR 606.3.1-HEAD AND BED JOINT LIMITS total 5 mark with pink market on page A-01 ( all mark with orange spry paint ) #3- window silt crack damage right side back window #4-FBC [A]107.3.1 -NEEDS APPROVED PLANS ON SITE ( need new set of plans
ROOF VALLEY & METAL 11/13/2025 APPROVED - AS NOTED CVANSTRAHLEN
Note: Please fix items before next inspection #1- Missing nails on hangers on trusses over garage area , please make sure nails are install on hangers ( garage trusses hangers ) 10/28/2025 - PREVIOUS INSPECTION NOTES Please fix previous items 10/24/2025 - PREVIOUS INSPECTION NOTES please fix items before next inspection #1-Dowel / down rods do not meet the minimum clearance (2" from face of block and/or 3/4: from inside of block) as required. (FBC-R606.3.4) ( all mark with orange spray paint ) #2-FBCR 606.3.1-HEAD AND BED JOINT LIMITS total 5 mark with pink market on page A-01 ( all mark with orange spry paint ) #3- window silt crack damage right side back window #4-FBC [A]107.3.1 -NEEDS APPROVED PLANS ON SITE ( need new set of plans
WALL SHEATHING 11/10/2025 CANCELLED BY INSPECTOR CVANSTRAHLEN
Note: Inspector Notes from Inspection 2340 10/29/25 Following items need to be fixed by next inspection to avoid failure and fees 1. Silt fence needs to be reapired and maintained FBC 3307.1 2. Swale needs to be cleared and kept cleared FBC 3303.5 3. Need a new set of plans on site FBC(A) 107.3.1 10/28/2025 - PREVIOUS INSPECTION NOTES Please fix previous items 10/24/2025 - PREVIOUS INSPECTION NOTES please fix items before next inspection #1-Dowel / down rods do not meet the minimum clearance (2" from face of block and/or 3/4: from inside of block) as required. (FBC-R606.3.4) ( all mark with orange spray paint ) #2-FBCR 606.3.1-HEAD AND BED JOINT LIMITS total 5 mark with pink market on page A-01 ( all mark with orange spry paint ) #3- window silt crack damage right side back window #4-FBC [A]107.3.1 -NEEDS APPROVED PLANS ON SITE ( need new set of plans
ROOF SHEATHING / BRACES/TIES/DOWN CELL 11/10/2025 APPROVED - AS NOTED CVANSTRAHLEN
Note: Please fix items before next inspection #1-Missing screws and nails on LGT3-SDS2.5 ,LGT2 w/Heta-16 and trusses T06 ,t07,t08,t09,t10 and t11 on straps #3-Please doble check hangers and straps for trusses , missing nails #2- Silt fence needs to be reapired and maintained FBC 3307.1 #4-Missing framing for master suite ceiling 10/28/2025 - PREVIOUS INSPECTION NOTES Please fix previous items 10/24/2025 - PREVIOUS INSPECTION NOTES please fix items before next inspection #1-Dowel / down rods do not meet the minimum clearance (2" from face of block and/or 3/4: from inside of block) as required. (FBC-R606.3.4) ( all mark with orange spray paint ) #2-FBCR 606.3.1-HEAD AND BED JOINT LIMITS total 5 mark with pink market on page A-01 ( all mark with orange spry paint ) #3- window silt crack damage right side back window #4-FBC [A]107.3.1 -NEEDS APPROVED PLANS ON SITE ( need new set of plans
ROOF VALLEY & METAL 11/10/2025 Disapproved -FEE REQUIRED CVANSTRAHLEN
Note: Job is not done Missing valleys , metal and underlayment 1. Silt fence needs to be reapired and maintained FBC 3307.1 10/28/2025 - PREVIOUS INSPECTION NOTES Please fix previous items 10/24/2025 - PREVIOUS INSPECTION NOTES please fix items before next inspection #1-Dowel / down rods do not meet the minimum clearance (2" from face of block and/or 3/4: from inside of block) as required. (FBC-R606.3.4) ( all mark with orange spray paint ) #2-FBCR 606.3.1-HEAD AND BED JOINT LIMITS total 5 mark with pink market on page A-01 ( all mark with orange spry paint ) #3- window silt crack damage right side back window #4-FBC [A]107.3.1 -NEEDS APPROVED PLANS ON SITE ( need new set of plans
ELECTRIC-TUG 10/31/2025 APPROVED CVANSTRAHLEN
TIE BEAM / LINTEL 10/29/2025 APPROVED - AS NOTED MCONTRYMAN
Note: 10/29/25 Following items need to be fixed by next inspection to avoid failure and fees 1. Silt fence needs to be reapired and maintained FBC 3307.1 2. Swale needs to be cleared and kept cleared FBC 3303.5 3. Need a new set of plans on site FBC(A) 107.3.1 10/28/2025 - PREVIOUS INSPECTION NOTES Please fix previous items 10/24/2025 - PREVIOUS INSPECTION NOTES please fix items before next inspection #1-Dowel / down rods do not meet the minimum clearance (2" from face of block and/or 3/4: from inside of block) as required. (FBC-R606.3.4) ( all mark with orange spray paint ) #2-FBCR 606.3.1-HEAD AND BED JOINT LIMITS total 5 mark with pink market on page A-01 ( all mark with orange spry paint ) #3- window silt crack damage right side back window #4-FBC [A]107.3.1 -NEEDS APPROVED PLANS ON SITE ( need new set of plans
TIE BEAM / LINTEL 10/28/2025 Disapproved -FEE REQUIRED CVANSTRAHLEN
Note: Please fix previous items 10/24/2025 - PREVIOUS INSPECTION NOTES please fix items before next inspection #1-Dowel / down rods do not meet the minimum clearance (2" from face of block and/or 3/4: from inside of block) as required. (FBC-R606.3.4) ( all mark with orange spray paint ) #2-FBCR 606.3.1-HEAD AND BED JOINT LIMITS total 5 mark with pink market on page A-01 ( all mark with orange spry paint ) #3- window silt crack damage right side back window #4-FBC [A]107.3.1 -NEEDS APPROVED PLANS ON SITE ( need new set of plans
GRAVITY SEWER TEST 10/27/2025 APPROVED - AS NOTED MGIBSON
Note: THIS WAS A VIRTUAL INSPECTION
SEWER TIE IN 10/27/2025 APPROVED - AS NOTED MGIBSON
Note: Inspector Notes from Inspection 2075 THIS WAS A VIRTUAL INSPECTION THIS WAS A VIRTUAL INSPECTION
TIE BEAM / LINTEL 10/24/2025 Disapproved -FEE REQUIRED CVANSTRAHLEN
Note: please fix items before next inspection #1-FBCR 606.3.4- rebar to closed to celinder block wall need 1" space min , total 3 mark with pink market on page A-01 #2-FBCR 606.3.1-HEAD AND BED JOINT LIMITS total 5 mark with pink market on page A-01 #3- window silt crack damage right side back window #4-FBC [A]107.3.1 -NEEDS APPROVED PLANS ON SITE ( need new set of plans
MONOLITHIC SLAB 10/14/2025 APPROVED CVANSTRAHLEN
FOUND SURVEY APPROVED (OFFICE) 10/08/2025 APPROVED RRICKS
PLUMBING 1ST ROUGH UNDERGROUND 10/08/2025 APPROVED MGIBSON
Note: 10/2/2025 - PREVIOUS INSPECTION NOTES FBCR-P-2503.7 NO PRESSURE ON WATER DISTRIBUTION LINES, FBCR-P-2503.5 NO HEAD TEST
WATER METER INSTALLATION REQUEST 10/03/2025 APPROVED CBOWERMASTER
PLUMBING 1ST ROUGH UNDERGROUND 10/02/2025 Disapproved -FEE REQUIRED MGIBSON
Note: FBCR-P-2503.7 NO PRESSURE ON WATER DISTRIBUTION LINES, FBCR-P-2503.5 NO HEAD TEST
GEOTECHNICAL REPORT APPROVAL (OFFICE USE) 09/15/2025 APPROVED PKNAPIK

Review History

Department Status Date In Date Out
MECH COMPLETE 03/11/2026 03/11/2026
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
MECH HOLD 03/09/2026 03/10/2026
Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Energy Calcs need to be signed by the owner/ owner agent below the preparer per R103.1.1.2 FBC Energy Conservation 2023 8Th edition
SW1 COMPLETE 10/07/2025 10/08/2025
Note: Released By: RODNEY RICKS - (386)986-4726 - RRICKS@PALMCOASTGOV.COM
BLD COMPLETE 10/07/2025 10/08/2025
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
ZON COMPLETE 10/07/2025 10/07/2025
Note: Released By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM
BLD COMPLETE 09/12/2025 09/15/2025
Note: Released By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM
SW1 HOLD 09/10/2025 09/11/2025
Note: Held By: PARREN FLANAGAN - (386)986-2392 - PFLANAGAN@PALMCOASTGOV.COM THE GEO TECH. REPORT NEEDS TO BE DONE BEFORE THIS INSPECTION OR REVIEW IS COMPLETED
ZON COMPLETE 09/10/2025 09/10/2025
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
BLD HOLD 08/28/2025 08/28/2025
Note: Held By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM Please upload geotech density report
MECH COMPLETE 06/27/2025 07/01/2025
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
BADMIN INFORMATION 06/02/2025 06/02/2025
Note: Marked INFORMATION By: LIBBY RAYBURN - - LRAYBURN@PALMCOASTGOV.COM extension request form incomplete. Must have all areas explains and details of why extension is needed 2nd request
BADMIN INFORMATION 05/30/2025 05/30/2025
Note: Marked INFORMATION By: LIBBY RAYBURN - - LRAYBURN@PALMCOASTGOV.COM extension request form incomplete. Must have all areas explains and details of why extension is needed
MECH COMPLETE 09/30/2024 10/01/2024
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
ELEC COMPLETE 09/24/2024 09/30/2024
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
BLD COMPLETE 09/24/2024 09/26/2024
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
MECH HOLD 09/24/2024 09/26/2024
Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Design location on Energy calcs needs to be Daytona Beach
ZON COMPLETE 09/24/2024 09/24/2024
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
BLD COMPLETE 08/07/2024 08/12/2024
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
ZON COMPLETE 07/18/2024 07/18/2024
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
ELEC COMPLETE 07/18/2024 07/25/2024
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
SW1 COMPLETE 07/09/2024 07/15/2024
Note: Released By: JOHN HOWARD - - JHOWARD@PALMCOASTGOV.COM SW1 completed review is contingent on stormwater inspector's approval of the final survey. A failed final survey inspection and/or a revised site plan indicating any significant change in drainage patterns and elevations negatively impacting neighboring lots, or the structure will result in a HOLD
ZON HOLD 07/09/2024 07/09/2024
Note: Held By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM Garage door color missing on color sheet
BLD COMPLETE 07/09/2024 07/11/2024
Note: Released By: JPI
MECH COMPLETE 07/09/2024 07/15/2024
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
ELEC HOLD 07/09/2024 07/15/2024
Note: Held By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM Need correct outlet spacing in bed 2 and living room.NEC 2020 210.52
ENGIN1 COMPLETE 07/09/2024 07/10/2024
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
BADMIN COMPLETE 05/14/2024 05/20/2024
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
BLD HOLD 05/14/2024 05/17/2024
Note: Held By: JPI 1. Per City Truss Submittal Requirements dated April 15, 2023, provide the truss plan packet signed and sealed by a licensed design professional including a completed shop drawing approval stamp on the truss cover sheet.
CUSVC COMPLETE 05/14/2024 05/21/2024
Note: Released By: HALEIGH HAND - - HHAND@PALMCOASTGOV.COM
ELEC HOLD 05/14/2024 05/20/2024
Note: Held By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM 1. Electrical riser diagram needs to include the surge protector. NEC 2020 230.67 2. Submit Electrical load calculations 3. Need correct outlet spacing in bed 2 and living room.NEC 2020 210.52 4. Range needs to be GFCI protected. NEC 2020 210.8
ENGIN1 COMPLETE 05/14/2024 05/14/2024
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
GAS CANCEL 05/14/2024 05/17/2024
LOCATE COMPLETE 05/14/2024 05/16/2024
Note: Released By: CANDACE BOWERMASTER - - CBOWERMASTER@PALMCOASTGOV.COM
MECH HOLD 05/14/2024 05/20/2024
Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Design location on Energy calcs needs to be Daytona Beach
SW1 HOLD 05/14/2024 05/15/2024
Note: Held By: JOHN HOWARD - - JHOWARD@PALMCOASTGOV.COM 1) Please include culvert pipe size and material to be used 2) Please include the garage FFE
ZON HOLD 05/14/2024 05/16/2024
Note: Held By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM Bathrooms labeled incorrectly AC pad location on site plan/survey doesn't match landscape and floor plans
SWALE COMPLETE 05/14/2024 09/10/2024
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
PLAN REVIEW - REVISION ¤32.50 03/12/2026
PLAN REVIEW - REVISION ¤32.50 03/10/2026
REINSPECTION RESIDENTIAL ¤40.00 03/10/2026
REINSPECTION RESIDENTIAL ¤40.00 03/10/2026
REINSPECTION RESIDENTIAL ¤40.00 03/10/2026
REINSPECTION RESIDENTIAL ¤40.00 03/10/2026
REINSPECTION RESIDENTIAL ¤40.00 03/10/2026
REINSPECTION RESIDENTIAL ¤40.00 03/10/2026
PLAN REVIEW - REVISION ¤32.50 03/10/2026
CONTRACTOR CHANGE ¤20.00 03/10/2026
CONTRACTOR CHANGE ¤20.00 03/10/2026
CONTRACTOR CHANGE ¤20.00 03/10/2026
ADMINISTRATIVE - EXTENSION ¤40.00 03/10/2026
ADMINISTRATIVE - EXTENSION ¤40.00 03/10/2026
EXTENSION ¤40.00 03/10/2026
RSI REINSPECTION 1 ¤35.00 03/10/2026
WATER -IRRIGATION INSPECTION ¤25.00 08/29/2024
IMPACT FEE PARKS ¤1,800.99 08/29/2024
IMPACT FEE TRANSPORTATION ¤1,862.00 08/29/2024
SURCHARGE - FS 468.631 ¤20.61 08/29/2024
SURCHARGE FS 533.721 ¤13.74 08/29/2024
SW ENG - FOUNDATION SURVEY ¤20.00 08/29/2024
CONNECTION FEES ¤21.00 08/29/2024
FC IMPACT FEE EMS ¤62.00 08/29/2024
IMPACT FEE FIRE ¤428.09 08/29/2024
FC IMPACT FEE LAW ENFORCEMENT ¤218.00 08/29/2024
FC IMPACT FEE LIBRARY ¤268.00 08/29/2024
IMPACT FEE SCHOOL ¤5,450.00 08/29/2024
INSPECTION - RESIDENTIAL ¤1,166.00 08/29/2024
ADMINISTRATIVE RESIDENTIAL ¤30.00 08/29/2024
WATER-METER ¤514.49 08/29/2024
WATER- TURN ON ¤25.00 08/29/2024
ADJUSTMENT 10% (¤152.67) 08/29/2024
PLAN REVIEW - RESIDENTIAL ¤330.72 08/29/2024
SW ENG INSPECTION 80 ¤80.00 08/29/2024
SW ENG - REVIEW 20 ¤20.00 08/29/2024
SW ENG PRE APRON ¤30.00 08/29/2024
SW ENG RES REVIEW 200 ¤200.00 08/29/2024
WATER CAPITAL FACILITY FEE ¤427.26 08/29/2024
SEWER CAPITAL FACILITY ¤775.70 08/29/2024
SITE PLAN 30 ¤30.00 08/29/2024
WATER CAPITAL FACILITY FEE (¤427.26) 08/07/2024
WATER CAPITAL FACILITY FEE ¤427.26 08/07/2024
SITE PLAN 30 ¤30.00 08/07/2024
SITE PLAN 30 (¤30.00) 08/07/2024
SEWER CAPITAL FACILITY ¤775.70 08/07/2024
SEWER CAPITAL FACILITY (¤775.70) 08/07/2024
SW ENG - REVIEW 20 (¤20.00) 08/07/2024
SW ENG - REVIEW 20 ¤20.00 08/07/2024
SW ENG RES REVIEW 200 ¤200.00 08/07/2024
SW ENG RES REVIEW 200 (¤200.00) 08/07/2024
SW ENG INSPECTION 80 ¤80.00 08/07/2024
SW ENG PRE APRON ¤30.00 08/07/2024
SW ENG PRE APRON (¤30.00) 08/07/2024
PLAN REVIEW - RESIDENTIAL ¤330.72 08/07/2024
FC IMPACT FEE EMS ¤62.00 08/07/2024
FC IMPACT FEE EMS (¤62.00) 08/07/2024
CONNECTION FEES (¤21.00) 08/07/2024
WATER- TURN ON ¤25.00 08/07/2024
ADJUSTMENT 10% (¤152.67) 08/07/2024
ADJUSTMENT 10% ¤152.67 08/07/2024
WATER- TURN ON (¤25.00) 08/07/2024
WATER-METER ¤514.49 08/07/2024
WATER-METER (¤514.49) 08/07/2024
ADMINISTRATIVE RESIDENTIAL ¤30.00 08/07/2024
ADMINISTRATIVE RESIDENTIAL (¤30.00) 08/07/2024
PLAN REVIEW - RESIDENTIAL (¤330.72) 08/07/2024
INSPECTION - RESIDENTIAL ¤1,166.00 08/07/2024
INSPECTION - RESIDENTIAL (¤1,166.00) 08/07/2024
IMPACT FEE SCHOOL ¤5,450.00 08/07/2024
IMPACT FEE TRANSPORTATION ¤1,862.00 08/07/2024
IMPACT FEE TRANSPORTATION (¤1,862.00) 08/07/2024
FC IMPACT FEE LIBRARY ¤268.00 08/07/2024
IMPACT FEE PARKS ¤1,800.99 08/07/2024
IMPACT FEE PARKS (¤1,800.99) 08/07/2024
FC IMPACT FEE LIBRARY (¤268.00) 08/07/2024
FC IMPACT FEE LAW ENFORCEMENT ¤218.00 08/07/2024
FC IMPACT FEE LAW ENFORCEMENT (¤218.00) 08/07/2024
IMPACT FEE FIRE ¤428.09 08/07/2024
IMPACT FEE FIRE (¤428.09) 08/07/2024
CONNECTION FEES ¤21.00 08/07/2024
SW ENG INSPECTION 80 (¤80.00) 08/07/2024
SURCHARGE - FS 468.631 (¤20.61) 08/07/2024
SURCHARGE - FS 468.631 ¤20.61 08/07/2024
SW ENG - FOUNDATION SURVEY ¤20.00 08/07/2024
SW ENG - FOUNDATION SURVEY (¤20.00) 08/07/2024
WATER -IRRIGATION INSPECTION (¤25.00) 08/07/2024
IMPACT FEE SCHOOL (¤5,450.00) 08/07/2024
WATER -IRRIGATION INSPECTION ¤25.00 08/07/2024
SURCHARGE FS 533.721 ¤13.74 08/07/2024
SURCHARGE FS 533.721 (¤13.74) 08/07/2024
Fees Total Due: ¤0.00 Total Paid: ¤14,218.43