Permit #2024071057
Permit Details
Status: INSPECT
| Parcel Id: 29-12-31-0000-01010-0021 |
| Block: 01010 |
| Subdivision: - |
| Job Phone: 386-322-8700 |
| Location Address: 1255 SEMINOLE WOODS BLVD |
| Type: SDD - SUBDIVISION SITE DEVELOPMENT |
| Issue Date: 02/04/2025 |
| NOC: Unknown |
| Applicant name: CHAD HAZEN |
| Owner: BYRNDOG PCP, LLC |
|
Address 180 BROOKHAVEN CT S PALM COAST, FL 32164 |
| Lot: 0021 |
| Job Description: SITE WORK-SEMINOLE TRACE |
| Type: CN |
Contractor
HAZEN CONSTRUCTION LLC
| Status | Location Address | State License Number | Phone |
| ACTIVE |
1599 TIONIA RD NEW SMYRNA BEACH, FL 32168 |
CGC061991 (Exp: 08/31/2026) | 386-322-8700 |
Inspection History
| Type | Request Date | Result | Inspector |
| WIRE TEST | 12/01/2025 | PARTIALLY APPROVED | BHAINES |
| Note: 10/22/2025 - PREVIOUS INSPECTION NOTES 7/23/2025 - PREVIOUS INSPECTION NOTES 2 hazen reps performing tone testing on FM-OFF/ON SITE,RECLAIM AND WATER UP TO EARLY START BOUNDARIES | |||
| UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) | 11/21/2025 | APPROVED | LFITZGERALD |
| Note: Inspector Notes from Inspection 9140 this is over all site permit where the project is divided into 1A AND 1B-so closing out inspections for this permit 5/15/2025 - PREVIOUS INSPECTION NOTES sidewalks along seminole south-north sides of entrance-with 95% compaction achieved 4/25/2025 - PREVIOUS INSPECTION NOTES replaced/poured new sidewalk along Seminole from entrance -Grand Landings southward for several hundred feet | |||
| UROW-RETENT/DETENT STABILI | 11/21/2025 | APPROVED | LFITZGERALD |
| Note: 4/25/2025 - PREVIOUS INSPECTION NOTES pond up front(next Seminole blvd) now sodded slopes | |||
| UROW- CURBING & GUTTER | 11/21/2025 | APPROVED | LFITZGERALD |
| Note: 5/29/2025 - PREVIOUS INSPECTION NOTES now starting F curb near entrance moving thru interior | |||
| UC-CONSTRUCTION ENTRANCE | 11/21/2025 | APPROVED | LFITZGERALD |
| Note: 3/6/2025 - PREVIOUS INSPECTION NOTES 3 dimple mats and fresh rock now installed 2/27/2025 - PREVIOUS INSPECTION NOTES entranvce initially installed by Smith trucking-needs refreshin-spokewith Mike-Hazen-planning on using the dimple pads and will refresh with more rock | |||
| UC-MOT MAINTENANCE OF TRAFFIC | 11/21/2025 | APPROVED | LFITZGERALD |
| Note: 4/25/2025 - PREVIOUS INSPECTION NOTES Flagging operations still on going while proposed road widening continues to be constructed-MOT in compliance 4/15/2025 - PREVIOUS INSPECTION NOTES flagging operations now employed-better barricades on site-signage is adequeate-need to install cone tapper for south end at flagger-mike informed 4/14/2025 - PREVIOUS INSPECTION NOTES just only striping grass in proposed new pavement(west ROW)-start flagging tomorrow-YMB Boaerd up since 3/4 indicating road work proposed | |||
| UC-ASPHALT PRE PLACEMENT | 11/21/2025 | APPROVED | LFITZGERALD |
| Note: 5/13/2025 - PREVIOUS INSPECTION NOTES open cut now patched and after first ride thru needs work smoothing out-mike informed and working on correcting/turn lane getting final lift 4/28/2025 - PREVIOUS INSPECTION NOTES compaction test for stab-subgrade and limerock based verified and satisfactory for proposed road widening | |||
| UC-DRAINAGE STRUCT PLACMNT | 11/21/2025 | APPROVED | LFITZGERALD |
| Note: 5/29/2025 - PREVIOUS INSPECTION NOTES continuing at ponds and various locations 5/7/2025 - PREVIOUS INSPECTION NOTES structures through out site ie 104/103/2101/2100/309/310/311 4/14/2025 - PREVIOUS INSPECTION NOTES str. 302-301-104(pond MES) installed | |||
| UC-DRAINAGE PIPE PLACEMENT/LAMPING | 11/21/2025 | APPROVED | LFITZGERALD |
| Note: 5/29/2025 - PREVIOUS INSPECTION NOTES continuing at ponds and various locations 5/7/2025 - PREVIOUS INSPECTION NOTES all runs for structures 104/309/2100 4/14/2025 - PREVIOUS INSPECTION NOTES pipe runs for 104-301-302 installed | |||
| UC-SUBSTANTIAL WALK-THRU | 11/21/2025 | APPROVED - AS NOTED | LFITZGERALD |
| Note: this is over all site permit where the project is divided into 1A AND 1B-so closing out inspections for this permit | |||
| WIRE TEST | 10/22/2025 | PARTIALLY APPROVED | BHAINES |
| Note: 7/23/2025 - PREVIOUS INSPECTION NOTES 2 hazen reps performing tone testing on FM-OFF/ON SITE,RECLAIM AND WATER UP TO EARLY START BOUNDARIES | |||
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | 08/28/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: Inspector Notes from Inspection 9030 5/29/2025 - PREVIOUS INSPECTION NOTES main now pig flushed-pressure tested 11+00 to phase line at copper leaf and sea myrtle 5/7/2025 - PREVIOUS INSPECTION NOTES at copper leaf intersection area 4/25/2025 - PREVIOUS INSPECTION NOTES inspections now noted on 1A site permit 4/15/2025 - PREVIOUS INSPECTION NOTES installed from station 13-18 on Cascades way stat 18 to lift ststaion receive mh 5/29/2025 - PREVIOUS INSPECTION NOTES now pig flushed to phase lines copper leaf/sea myrtle and cascades/all pressure tested from POC -phase lines at cascades/copper leaf/sea myrtle 5/15/2025 - PREVIOUS INSPECTION NOTES 5-14 barrel flush from POC to 12in stub to 16 stub to 12in station 11+75/5-15 pig flush 12in from 11)75 to copper leaf intersection 5/7/2025 - PREVIOUS INSPECTION NOTES continue with 16 to 12in at entrance and at copperleaf-myrtle areas 4/30/2025 - PREVIOUS INSPECTION NOTES wm installed to copper leaf /cascade interection 4/15/2025 - PREVIOUS INSPECTION NOTES installed from station 13-18 on Cascades way now-10x10 wet tap on class wm at Sloganer along with 2in poly jumper line that will go under roadway to other side for a water source-to be shut down at end at corp/install 10-16 in tie in connecting =pipe from gate valve at tap see 1a permit for continued notes | |||
| U-REUSE MAIN INSTALL/TESTING | 08/14/2025 | APPROVED - AS NOTED | LFITZGERALD |
| Note: 5/29/2025 - PREVIOUS INSPECTION NOTES main now pig flushed-pressure tested 11+00 to phase line at copper leaf and sea myrtle 5/7/2025 - PREVIOUS INSPECTION NOTES at copper leaf intersection area 4/25/2025 - PREVIOUS INSPECTION NOTES inspections now noted on 1A site permit 4/15/2025 - PREVIOUS INSPECTION NOTES installed from station 13-18 on Cascades way stat 18 to lift ststaion receive mh | |||
| HYDRANT - PAINT / FLOW/VALVE/ RPM | 07/23/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 7/10/2025 - PREVIOUS INSPECTION NOTES with Kyle-flowed 7 hydrants for early start area(5 on Cascade,1 on sea myrtle,1 on copper leaf) all at 1130-1160gpm/Randy also pesent GPS now completed for 7 hydrants | |||
| WIRE TEST | 07/23/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 2 hazen reps performing tone testing on FM-OFF/ON SITE,RECLAIM AND WATER UP TO EARLY START BOUNDARIES | |||
| U-GRAVITY SEWER INSTALL/TESTING | 07/16/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 3/26/2025 - PREVIOUS INSPECTION NOTES mh132,mh131 and 133 set with accompaning 8in runs 3/19/2025 - PREVIOUS INSPECTION NOTES mh134 set and installing 6in to mh132 Early start/model home area:all manholes installed,mud work at inverts and collars for rims-now air already done-ok and now tv/madrel | |||
| UC - PROJECT STATUS | 07/14/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: sewer laterals/re-claim service whips/potable service whips now all accounted for vesuscplan counts-EARLY START/MODEL HOME AREA | |||
| WATERMAIN FLUSH & PRESSURE TESTED | 07/14/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: see water install insprction for early start testing-will use this inspection now thatim aware | |||
| FDEP WATERMAIN CLEARANCE | 07/14/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: now satisfactory for-EARLy START/MODEL HOMES AREA | |||
| HYDRANT - PAINT / FLOW/VALVE/ RPM | 07/10/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: with Kyle-flowed 7 hydrants for early start area(5 on Cascade,1 on sea myrtle,1 on copper leaf) all at 1130-1160gpm/Randy also pesent | |||
| U-WATER MAIN DISINFECTION SAMPLING | 07/10/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: all bacti samples for early start area-cascade lots 38/118,Copper leaf 182/128 and all sea murtle way passed both days | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 06/11/2025 | PARTIALLY APPROVED | JMYERS |
| Note: 6/11/25 EROSION CONTROL MEASURES IN PLACE AND FUNCTIONING. FOLLOW UP INSPECTION IN ONE MONTH. | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 06/04/2025 | CANCELLED BY INSPECTOR | JMYERS |
| Note: 5/8/2025 - PREVIOUS INSPECTION NOTES 5/8/25 EROSION CONTROL MEASURES ARE IN PLACE AND FUNCTIONING. FOLLOW UP INSPECTION NEXT MONTH 4/9/2025 - PREVIOUS INSPECTION NOTES 4/9/25 SILT FENCE REPAIRS HAVE BEEN MADE. FOLLOW UP INSPECTION NEXT MONTH 4/3/2025 - PREVIOUS INSPECTION NOTES 4/3/25 WEST PROPERTY LINE SILT FENCE HAS MULTIPLE FAILURES. SILT FENCE SHALL BE RE-INSTALLED. FOLLOW UP INSPECTION 4/9/25 3/6/2025 - PREVIOUS INSPECTION NOTES 3/6/25 SILT FENCE ALONG SEMINOLE WOODS FUNCTIONING, STILL CLEARING SITE. FOLLOW UP INSPECTION IN ONE MONTH | |||
| U-WATER MAIN DISINFECTION | 06/02/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: *** NOTES ADDED BY LFITZGERALD 7/10/2025 12:42:31 PM *** phase lines are lots38/118 on Cascades way,lots 182/128 on Copper Leaf and all Sea Myrtle way first phase-early start areas-Kyle now heating it ip to called out phase lines(stationing) | |||
| U-SEWER FORCE MAIN INSTALL/TESTING | 05/29/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: now pig flushed-pressure tested 6in/4in to Cascades 28+50/1st lift station 4/25/2025 - PREVIOUS INSPECTION NOTES OFF SITE INSTALATION: 4/2/2025 - PREVIOUS INSPECTION NOTES Hydrstatic pressure test now completed station 15+00-95+00=12in pvc and 14in bore/10+00-11+00=6in pvc(total9500ft) 4/1/2025 - PREVIOUS INSPECTION NOTES 2nd3rd pig flush on 12in/bores completed as well as 6in stub at entrance/now tap at Grand Landings on C900 pvc completed 3/26/2025 - PREVIOUS INSPECTION NOTES 1st pig flush along Seminole from 1st drill pipe-including drill pipe northward upto 100ft south of Sasame 3/18/2025 - PREVIOUS INSPECTION NOTES about half c900 along Seminole is installed with 3 drill pipe locations connected 3/6/2025 - PREVIOUS INSPECTION NOTES 3rd drill pipe installed and starting to install 12in-DR18 2/27/2025 - PREVIOUS INSPECTION NOTES start 12pvc(16hdpe) in directional drill at 1st canal crossing heading south ON SITE INSTALL:Cascades way near entrance several hundred feet to pig launch at lift station MH | |||
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | 05/29/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: now pig flushed to phase lines copper leaf/sea myrtle and cascades/all pressure tested from POC -phase lines at cascades/copper leaf/sea myrtle 5/15/2025 - PREVIOUS INSPECTION NOTES 5-14 barrel flush from POC to 12in stub to 16 stub to 12in station 11+75/5-15 pig flush 12in from 11)75 to copper leaf intersection 5/7/2025 - PREVIOUS INSPECTION NOTES continue with 16 to 12in at entrance and at copperleaf-myrtle areas 4/30/2025 - PREVIOUS INSPECTION NOTES wm installed to copper leaf /cascade interection 4/15/2025 - PREVIOUS INSPECTION NOTES installed from station 13-18 on Cascades way now-10x10 wet tap on class wm at Sloganer along with 2in poly jumper line that will go under roadway to other side for a water source-to be shut down at end at corp/install 10-16 in tie in connecting =pipe from gate valve at tap | |||
| UC-DRAINAGE PIPE PLACEMENT/LAMPING | 05/29/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: continuing at ponds and various locations 5/7/2025 - PREVIOUS INSPECTION NOTES all runs for structures 104/309/2100 4/14/2025 - PREVIOUS INSPECTION NOTES pipe runs for 104-301-302 installed | |||
| U-REUSE MAIN INSTALL/TESTING | 05/29/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: main now pig flushed-pressure tested 11+00 to phase line at copper leaf and sea myrtle 5/7/2025 - PREVIOUS INSPECTION NOTES at copper leaf intersection area 4/25/2025 - PREVIOUS INSPECTION NOTES 4/15/2025 - PREVIOUS INSPECTION NOTES installed from station 13-18 on Cascades way stat 18 to lift ststaion receive mh | |||
| UC-DRAINAGE STRUCT PLACMNT | 05/29/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: continuing at ponds and various locations 5/7/2025 - PREVIOUS INSPECTION NOTES structures through out site ie 104/103/2101/2100/309/310/311 4/14/2025 - PREVIOUS INSPECTION NOTES str. 302-301-104(pond MES) installed | |||
| UROW- CURBING & GUTTER | 05/29/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: now starting F curb near entrance moving thru interior | |||
| UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) | 05/15/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: sidewalks along seminole south-north sides of entrance-with 95% compaction achieved 4/25/2025 - PREVIOUS INSPECTION NOTES replaced/poured new sidewalk along Seminole from entrance -Grand Landings southward for several hundred feet | |||
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | 05/15/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 5-14 barrel flush from POC to 12in stub to 16 stub to 12in station 11+75/5-15 pig flush 12in from 11)75 to copper leaf intersection 5/7/2025 - PREVIOUS INSPECTION NOTES continue with 16 to 12in at entrance and at copperleaf-myrtle areas 4/30/2025 - PREVIOUS INSPECTION NOTES wm installed to copper leaf /cascade interection 4/15/2025 - PREVIOUS INSPECTION NOTES installed from station 13-18 on Cascades way now-10x10 wet tap on class wm at Sloganer along with 2in poly jumper line that will go under roadway to other side for a water source-to be shut down at end at corp/install 10-16 in tie in connecting =pipe from gate valve at tap | |||
| UC-ASPHALT PRE PLACEMENT | 05/13/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: open cut now patched and after first ride thru needs work smoothing out-mike informed and working on correcting/turn lane getting final lift 4/28/2025 - PREVIOUS INSPECTION NOTES compaction test for stab-subgrade and limerock based verified and satisfactory for proposed road widening | |||
| UC-DRAINAGE STRUCT PLACMNT | 05/07/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: structures through out site ie 104/103/2101/2100/309/310/311 4/14/2025 - PREVIOUS INSPECTION NOTES str. 302-301-104(pond MES) installed | |||
| UC-DRAINAGE PIPE PLACEMENT/LAMPING | 05/07/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: all runs for structures 104/309/2100 4/14/2025 - PREVIOUS INSPECTION NOTES pipe runs for 104-301-302 installed | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 05/07/2025 | PARTIALLY APPROVED | JMYERS |
| Note: 5/8/25 EROSION CONTROL MEASURES ARE IN PLACE AND FUNCTIONING. FOLLOW UP INSPECTION NEXT MONTH 4/9/2025 - PREVIOUS INSPECTION NOTES 4/9/25 SILT FENCE REPAIRS HAVE BEEN MADE. FOLLOW UP INSPECTION NEXT MONTH 4/3/2025 - PREVIOUS INSPECTION NOTES 4/3/25 WEST PROPERTY LINE SILT FENCE HAS MULTIPLE FAILURES. SILT FENCE SHALL BE RE-INSTALLED. FOLLOW UP INSPECTION 4/9/25 3/6/2025 - PREVIOUS INSPECTION NOTES 3/6/25 SILT FENCE ALONG SEMINOLE WOODS FUNCTIONING, STILL CLEARING SITE. FOLLOW UP INSPECTION IN ONE MONTH | |||
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | 05/07/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: continue with 16 to 12in at entrance and at copperleaf-myrtle areas 4/30/2025 - PREVIOUS INSPECTION NOTES wm installed to copper leaf /cascade interection 4/15/2025 - PREVIOUS INSPECTION NOTES installed from station 13-18 on Cascades way now-10x10 wet tap on class wm at Sloganer along with 2in poly jumper line that will go under roadway to other side for a water source-to be shut down at end at corp/install 10-16 in tie in connecting =pipe from gate valve at tap | |||
| U-REUSE MAIN INSTALL/TESTING | 05/07/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: at copper leaf intersection area 4/25/2025 - PREVIOUS INSPECTION NOTES 4/15/2025 - PREVIOUS INSPECTION NOTES installed from station 13-18 on Cascades way stat 18 to lift ststaion receive mh | |||
| ROW- PROJECT STATUS | 05/01/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 4/30-open cut to install new WM- half(east side) opened and backfilled with soils and 12in base with asphalt overlay-Roberta -Bechtol eng. performing compaction testing-5/1 now continuing to install 16in WM open cut west side and backfill accordingly 4/25/2025 - PREVIOUS INSPECTION NOTES road widening for proposed turn lane-existing soils meet LBR 40 for stab-subgradeand compacted to 98%/limerock base meets lbr100 AND COMPACTED TO 98% AND NOW PRIMED IN PREPERATION FOR ASPHALT | |||
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | 04/30/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: wm installed to copper leaf /cascade interection 4/15/2025 - PREVIOUS INSPECTION NOTES installed from station 13-18 on Cascades way now-10x10 wet tap on class wm at Sloganer along with 2in poly jumper line that will go under roadway to other side for a water source-to be shut down at end at corp/install 10-16 in tie in connecting =pipe from gate valve at tap | |||
| UC-ASPHALT PRE PLACEMENT | 04/29/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: compaction test for stab-subgrade and limerock based verified and satisfactory for proposed road widening | |||
| UC-MOT MAINTENANCE OF TRAFFIC | 04/25/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: Flagging operations still on going while proposed road widening continues to be constructed-MOT in compliance 4/15/2025 - PREVIOUS INSPECTION NOTES flagging operations now employed-better barricades on site-signage is adequeate-need to install cone tapper for south end at flagger-mike informed 4/14/2025 - PREVIOUS INSPECTION NOTES just only striping grass in proposed new pavement(west ROW)-start flagging tomorrow-YMB Boaerd up since 3/4 indicating road work proposed | |||
| ROW- PROJECT STATUS | 04/25/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: road widening for proposed turn lane-existing soils meet LBR 40 for stab-subgradeand compacted to 98%/limerock base meets lbr100 AND COMPACTED TO 98% AND NOW PRIMED IN PREPERATION FOR ASPHALT | |||
| U-REUSE MAIN INSTALL/TESTING | 04/25/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 4/15/2025 - PREVIOUS INSPECTION NOTES installed from station 13-18 on Cascades way stat 18 to lift ststaion receive mh | |||
| U-SEWER FORCE MAIN INSTALL/TESTING | 04/25/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: OFF SITE INSTALATION: 4/2/2025 - PREVIOUS INSPECTION NOTES Hydrstatic pressure test now completed station 15+00-95+00=12in pvc and 14in bore/10+00-11+00=6in pvc(total9500ft) 4/1/2025 - PREVIOUS INSPECTION NOTES 2nd3rd pig flush on 12in/bores completed as well as 6in stub at entrance/now tap at Grand Landings on C900 pvc completed 3/26/2025 - PREVIOUS INSPECTION NOTES 1st pig flush along Seminole from 1st drill pipe-including drill pipe northward upto 100ft south of Sasame 3/18/2025 - PREVIOUS INSPECTION NOTES about half c900 along Seminole is installed with 3 drill pipe locations connected 3/6/2025 - PREVIOUS INSPECTION NOTES 3rd drill pipe installed and starting to install 12in-DR18 2/27/2025 - PREVIOUS INSPECTION NOTES start 12pvc(16hdpe) in directional drill at 1st canal crossing heading south ON SITE INSTALL:Cascades way near entrance several hundred feet to pig launch at lift station MH | |||
| UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) | 04/25/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: replaced/poured new sidewalk along Seminole from entrance -Grand Landings southward for several hundred feet | |||
| UROW-RETENT/DETENT STABILI | 04/25/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: pond up front(next Seminole blvd) now sodded slopes | |||
| U-REUSE MAIN INSTALL/TESTING | 04/15/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: installed from station 13-18 on Cascades way | |||
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | 04/15/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: installed from station 13-18 on Cascades way | |||
| UC-MOT MAINTENANCE OF TRAFFIC | 04/15/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: flagging operations now employed-better barricades on site-signage is adequeate-need to install cone tapper for south end at flagger-mike informed 4/14/2025 - PREVIOUS INSPECTION NOTES just only striping grass in proposed new pavement(west ROW)-start flagging tomorrow-YMB Boaerd up since 3/4 indicating road work proposed | |||
| UC-MOT MAINTENANCE OF TRAFFIC | 04/14/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: just only striping grass in proposed new pavement(west ROW)-start flagging tomorrow-YMB Boaerd up since 3/4 indicating road work proposed | |||
| UC-DRAINAGE STRUCT PLACMNT | 04/14/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: str. 302-301-104(pond MES) installed | |||
| UC-DRAINAGE PIPE PLACEMENT/LAMPING | 04/14/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: pipe runs for 104-301-302 installed | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 04/09/2025 | PARTIALLY APPROVED | JMYERS |
| Note: 4/9/25 SILT FENCE REPAIRS HAVE BEEN MADE. FOLLOW UP INSPECTION NEXT MONTH 4/3/2025 - PREVIOUS INSPECTION NOTES 4/3/25 WEST PROPERTY LINE SILT FENCE HAS MULTIPLE FAILURES. SILT FENCE SHALL BE RE-INSTALLED. FOLLOW UP INSPECTION 4/9/25 3/6/2025 - PREVIOUS INSPECTION NOTES 3/6/25 SILT FENCE ALONG SEMINOLE WOODS FUNCTIONING, STILL CLEARING SITE. FOLLOW UP INSPECTION IN ONE MONTH | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 04/02/2025 | Disapproved - NO FEE | JMYERS |
| Note: 4/3/25 WEST PROPERTY LINE SILT FENCE HAS MULTIPLE FAILURES. SILT FENCE SHALL BE RE-INSTALLED. FOLLOW UP INSPECTION 4/9/25 3/6/2025 - PREVIOUS INSPECTION NOTES 3/6/25 SILT FENCE ALONG SEMINOLE WOODS FUNCTIONING, STILL CLEARING SITE. FOLLOW UP INSPECTION IN ONE MONTH | |||
| U-SEWER FORCE MAIN INSTALL/TESTING | 04/02/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: Hydrstatic pressure test now completed station 15+00-95+00=12in pvc and 14in bore/10+00-11+00=6in pvc(total9500ft) 4/1/2025 - PREVIOUS INSPECTION NOTES 2nd3rd pig flush on 12in/bores completed as well as 6in stub at entrance/now tap at Grand Landings on C900 pvc completed 3/26/2025 - PREVIOUS INSPECTION NOTES 1st pig flush along Seminole from 1st drill pipe-including drill pipe northward upto 100ft south of Sasame 3/18/2025 - PREVIOUS INSPECTION NOTES about half c900 along Seminole is installed with 3 drill pipe locations connected 3/6/2025 - PREVIOUS INSPECTION NOTES 3rd drill pipe installed and starting to install 12in-DR18 2/27/2025 - PREVIOUS INSPECTION NOTES start 12(14) in directional drill at 1st canal crossing | |||
| U-SEWER FORCE MAIN INSTALL/TESTING | 04/01/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 2nd3rd pig flush on 12in/bores completed as well as 6in stub at entrance/now tap at Grand Landings on C900 pvc completed 3/26/2025 - PREVIOUS INSPECTION NOTES 1st pig flush along Seminole from 1st drill pipe-including drill pipe northward upto 100ft south of Sasame 3/18/2025 - PREVIOUS INSPECTION NOTES about half c900 along Seminole is installed with 3 drill pipe locations connected 3/6/2025 - PREVIOUS INSPECTION NOTES 3rd drill pipe installed and starting to install 12in-DR18 2/27/2025 - PREVIOUS INSPECTION NOTES start 12(14) in directional drill at 1st canal crossing | |||
| U-GRAVITY SEWER INSTALL/TESTING | 03/26/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: mh132,mh131 and 133 set with accompaning 8in runs 3/19/2025 - PREVIOUS INSPECTION NOTES mh134 set and installing 6in to mh132 | |||
| U-SEWER FORCE MAIN INSTALL/TESTING | 03/26/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 1st pig flush along Seminole from 1st drill pipe-including drill pipe northward upto 100ft south of Sasame 3/18/2025 - PREVIOUS INSPECTION NOTES about half c900 along Seminole is installed with 3 drill pipe locations connected 3/6/2025 - PREVIOUS INSPECTION NOTES 3rd drill pipe installed and starting to install 12in-DR18 2/27/2025 - PREVIOUS INSPECTION NOTES start 12(14) in directional drill at 1st canal crossing | |||
| U-GRAVITY SEWER INSTALL/TESTING | 03/19/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: *** NOTES ADDED BY LFITZGERALD 3/19/2025 10:44:38 AM *** 8in mh134 set and installing 6in to mh132 | |||
| U-SEWER FORCE MAIN INSTALL/TESTING | 03/18/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: about half c900 along Seminole is installed with 3 drill pipe locations connected 3/6/2025 - PREVIOUS INSPECTION NOTES 3rd drill pipe installed and starting to install 12in-DR18 2/27/2025 - PREVIOUS INSPECTION NOTES start 12(14) in directional drill at 1st canal crossing | |||
| U-SEWER FORCE MAIN INSTALL/TESTING | 03/06/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 3rd drill pipe installed and starting to install 12in-DR18 2/27/2025 - PREVIOUS INSPECTION NOTES start 12(14) in directional drill at 1st canal crossing | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 03/06/2025 | PARTIALLY APPROVED | JMYERS |
| Note: 3/6/25 SILT FENCE ALONG SEMINOLE WOODS FUNCTIONING, STILL CLEARING SITE. FOLLOW UP INSPECTION IN ONE MONTH | |||
| UC-CONSTRUCTION ENTRANCE | 03/06/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 3 dimple mats and fresh rock now installed 2/27/2025 - PREVIOUS INSPECTION NOTES entranvce initially installed by Smith trucking-needs refreshin-spokewith Mike-Hazen-planning on using the dimple pads and will refresh with more rock | |||
| UC-CONSTRUCTION ENTRANCE | 02/27/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: entranvce initially installed by Smith trucking-needs refreshin-spokewith Mike-Hazen-planning on using the dimple pads and will refresh with more rock | |||
| U-SEWER FORCE MAIN INSTALL/TESTING | 02/27/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: start 12(14) in directional drill at 1st canal crossing | |||
| PLAN - PRE-CON 386-986-3750 | 02/06/2025 | APPROVED | LFITZGERALD |
| PLANNING - OFFICE USE - FINAL AS-BUILT SURVEY | |||
| LDSC-IRRIGATION FINAL | |||
| LDSC- LANDSCAPE / IRRIGATION AS-BUILT | |||
| LDSC- LANDSCAPE FINAL | |||
| CLOSE OUT DOCUMENTS | |||
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | |||
| Note: 8/28/2025 - PREVIOUS INSPECTION NOTES Inspector Notes from Inspection 9030 5/29/2025 - PREVIOUS INSPECTION NOTES main now pig flushed-pressure tested 11+00 to phase line at copper leaf and sea myrtle 5/7/2025 - PREVIOUS INSPECTION NOTES at copper leaf intersection area 4/25/2025 - PREVIOUS INSPECTION NOTES inspections now noted on 1A site permit 4/15/2025 - PREVIOUS INSPECTION NOTES installed from station 13-18 on Cascades way stat 18 to lift ststaion receive mh 5/29/2025 - PREVIOUS INSPECTION NOTES now pig flushed to phase lines copper leaf/sea myrtle and cascades/all pressure tested from POC -phase lines at cascades/copper leaf/sea myrtle 5/15/2025 - PREVIOUS INSPECTION NOTES 5-14 barrel flush from POC to 12in stub to 16 stub to 12in station 11+75/5-15 pig flush 12in from 11)75 to copper leaf intersection 5/7/2025 - PREVIOUS INSPECTION NOTES continue with 16 to 12in at entrance and at copperleaf-myrtle areas 4/30/2025 - PREVIOUS INSPECTION NOTES wm installed to copper leaf /cascade interection 4/15/2025 - PREVIOUS INSPECTION NOTES installed from station 13-18 on Cascades way now-10x10 wet tap on class wm at Sloganer along with 2in poly jumper line that will go under roadway to other side for a water source-to be shut down at end at corp/install 10-16 in tie in connecting =pipe from gate valve at tap see 1a permit for continued notes | |||
| U-GRAVITY SEWER INSTALL/TESTING | |||
| Note: 7/16/2025 - PREVIOUS INSPECTION NOTES 3/26/2025 - PREVIOUS INSPECTION NOTES mh132,mh131 and 133 set with accompaning 8in runs 3/19/2025 - PREVIOUS INSPECTION NOTES mh134 set and installing 6in to mh132 Early start/model home area:all manholes installed,mud work at inverts and collars for rims-now air already done-ok and now tv/madrel | |||
| U-SEWER FORCE MAIN INSTALL/TESTING | |||
| Note: 5/29/2025 - PREVIOUS INSPECTION NOTES now pig flushed-pressure tested 6in/4in to Cascades 28+50/1st lift station 4/25/2025 - PREVIOUS INSPECTION NOTES OFF SITE INSTALATION: 4/2/2025 - PREVIOUS INSPECTION NOTES Hydrstatic pressure test now completed station 15+00-95+00=12in pvc and 14in bore/10+00-11+00=6in pvc(total9500ft) 4/1/2025 - PREVIOUS INSPECTION NOTES 2nd3rd pig flush on 12in/bores completed as well as 6in stub at entrance/now tap at Grand Landings on C900 pvc completed 3/26/2025 - PREVIOUS INSPECTION NOTES 1st pig flush along Seminole from 1st drill pipe-including drill pipe northward upto 100ft south of Sasame 3/18/2025 - PREVIOUS INSPECTION NOTES about half c900 along Seminole is installed with 3 drill pipe locations connected 3/6/2025 - PREVIOUS INSPECTION NOTES 3rd drill pipe installed and starting to install 12in-DR18 2/27/2025 - PREVIOUS INSPECTION NOTES start 12pvc(16hdpe) in directional drill at 1st canal crossing heading south ON SITE INSTALL:Cascades way near entrance several hundred feet to pig launch at lift station MH | |||
| U-WATER SERVICE INSTALLATION | |||
| U-WATER MAIN DISINFECTION | |||
| Note: 6/2/2025 - PREVIOUS INSPECTION NOTES first phase-early start areas-Kyle now heating it ip to called out phase lines(stationing) | |||
| U-WATER MAIN DISINFECTION SAMPLING | |||
| Note: 7/10/2025 - PREVIOUS INSPECTION NOTES all bacti samples for early start area-cascade lots 38/118,Copper leaf 182/128 and all sea murtle way passed both days | |||
| UC - PROJECT STATUS | |||
| Note: 7/14/2025 - PREVIOUS INSPECTION NOTES sewer laterals/re-claim service whips/potable service whips now all accounted for vesuscplan counts-EARLY START/MODEL HOME AREA | |||
| ROW- PROJECT STATUS | |||
| Note: 5/1/2025 - PREVIOUS INSPECTION NOTES 4/30-open cut to install new WM- half(east side) opened and backfilled with soils and 12in base with asphalt overlay-Roberta -Bechtol eng. performing compaction testing-5/1 now continuing to install 16in WM open cut west side and backfill accordingly 4/25/2025 - PREVIOUS INSPECTION NOTES road widening for proposed turn lane-existing soils meet LBR 40 for stab-subgradeand compacted to 98%/limerock base meets lbr100 AND COMPACTED TO 98% AND NOW PRIMED IN PREPERATION FOR ASPHALT | |||
| UC-FINAL SITE INSPECTION | |||
| U - UTILITY COMMERCIAL FINAL | |||
| PROJECT CLOSE OUT MEETING (386-986-3750) | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | |||
| Note: 6/11/2025 - PREVIOUS INSPECTION NOTES 6/11/25 EROSION CONTROL MEASURES IN PLACE AND FUNCTIONING. FOLLOW UP INSPECTION IN ONE MONTH. | |||
| FDEP WATERMAIN CLEARANCE | |||
| Note: 7/14/2025 - PREVIOUS INSPECTION NOTES now satisfactory for-EARLy START/MODEL HOMES AREA-water only | |||
| WATERMAIN FLUSH & PRESSURE TESTED | |||
| Note: 7/14/2025 - PREVIOUS INSPECTION NOTES see water install insprction for early start testing-will use this inspection now thatim aware | |||
| UROW - FINAL DRAINAGE | |||
| U-ROW FINAL | |||
| UC-TRAF - FINAL (SIGN/PAVEMENT MARKING) | |||
| HYDRANT - PAINT / FLOW/VALVE/ RPM | |||
| Note: 7/23/2025 - PREVIOUS INSPECTION NOTES 7/10/2025 - PREVIOUS INSPECTION NOTES with Kyle-flowed 7 hydrants for early start area(5 on Cascade,1 on sea myrtle,1 on copper leaf) all at 1130-1160gpm/Randy also pesent GPS now completed for 7 hydrants | |||
| WIRE TEST | |||
| Note: 12/1/2025 - PREVIOUS INSPECTION NOTES 10/22/2025 - PREVIOUS INSPECTION NOTES 7/23/2025 - PREVIOUS INSPECTION NOTES 2 hazen reps performing tone testing on FM-OFF/ON SITE,RECLAIM AND WATER UP TO EARLY START BOUNDARIES |
Review History
| Department | Status | Date In | Date Out |
| PLENG | COMPLETE | 06/13/2025 | 06/16/2025 |
| Note: Released By: DENNIS R. LEAP, P.E. - (386)986-2482 - DLEAP@PALMCOASTGOV.COM | |||
| PLLA | COMPLETE | 06/13/2025 | 06/30/2025 |
| Note: Released By: RICHARD PICATAGI - (386)986-3760 - RPICATAGI@PALMCOASTGOV.COM | |||
| UD1 | COMPLETE | 06/13/2025 | 06/23/2025 |
| Note: Released By: GREG DEGLER - (386)986-2384 - GDEGLER@PALMCOASTGOV.COM | |||
| PLENG | COMPLETE | 07/22/2024 | 07/22/2024 |
| Note: Released By: DENNIS R. LEAP, P.E. - (386)986-2482 - DLEAP@PALMCOASTGOV.COM | |||
| PLLA | COMPLETE | 07/22/2024 | 07/22/2024 |
| Note: Released By: DAMARIS RAMIREZ - (386)986-3750 - DRAMIREZ@PALMCOASTGOV.COM | |||
| UD1 | COMPLETE | 07/22/2024 | 07/31/2024 |
| Note: Released By: GREG DEGLER - (386)986-2384 - GDEGLER@PALMCOASTGOV.COM |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| ADJUSTMENT 10% | (¤12.50) | 02/04/2025 |
| ADMINISTRATIVE- SITE DEVELOP | ¤125.00 | 02/04/2025 |
| SITE INSPECTION | ¤1,000.00 | 02/04/2025 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤1,112.50 |