I want to search for...
Permit #2024081002
Permit Details
Status: COED
| Parcel Id: 07-11-31-7059-00690-0070 |
| CONDITIONED SPACE: 2400 sqft |
| GARAGE: 566 sqft |
| OPENED PORCH (WITH ROOF) : 350 sqft |
| Total Square Footage: 3316 sqft |
| Block: 00690 |
| Subdivision: 7059 - |
| Job Phone: 386-283-2035 |
| Location Address: 4 SLEIGH BELL PL |
| Type: DU - DUPLEX |
| Issue Date: 09/16/2024 |
| NOC: RECORDED |
| Applicant name: OLEG BELINSKIY |
| Owner: TARASOVA ANNA & ALEXANDER SHPERLING H&W |
|
Address 2 CREEKSIDE COURT PALM COAST, FL 32137 |
| Lot: 0070 |
| Contracted Stated Job Value: ¤350,000.00 |
| Job Description: DUPLEX |
| Type: CN |
Contractor
FLORIDAS BEST BUILDERS INC
| Status | Location Address | State License Number | Phone |
| ACTIVE |
19 PINE CIRCLE DRIVE PALM COAST, FL 32164 |
CBC1264760 (Exp: 08/31/2026) | 386-283-2035 |
Sub Contractors
OLEG BELINSKIY
| Status | Location Address | State License Number | Phone |
| ACTIVE |
19 PINE CIRCLE DRIVE19 PALM COAST, FL 32167 |
CCC1325974 (Exp: 08/31/2026) | 386-263-7906 |
JUAN CARLOS GONZALEZ
| Status | Location Address | State License Number |
| ACTIVE |
1328 COUNTY ROAD 308 CRESCENT CITY, FL 32112 |
RF11067806 (Exp: 08/31/2027) |
FERNANDO MEZA SR
| Status | Location Address | State License Number | Phone |
| ACTIVE |
457 CHELSEA PLACE AVE ORMOND BEACH, FL 32174 |
EC13003906 (Exp: 08/31/2026) | 386-241-5211 |
TIMUR ISPARYAN
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
3665 SPRINK PARK ROAD JACKSONVILLE , FL 32207 |
CMC1249968 (Exp: 08/31/2026) | 904-245-1818 | 904-337-1910 |
Inspection History
| Type | Request Date | Result | Inspector |
| U-CROSS CONNECTION | 07/18/2025 | APPROVED | BWRIGHT |
| Note: 7/15/2025 - PREVIOUS INSPECTION NOTES No IRR. No CC | |||
| ROW - FINAL APRON (AFTER POUR) | 07/15/2025 | APPROVED | FSLADISH |
| Note: 7/15/25 AT THE TIME OF THIS INSPECTIONS ALL COPC REQUIREMENTS WERE MET, NEITHER THE INSPECTOR NOR THE CITY IS RESPONSIBLE IF, FOR WHATEVER REASON, SITE CONDITIONS CHANGE OVER TIME AFTER THE INSPECTION. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED. | |||
| BLD - BUILDING FINAL | 07/15/2025 | FINAL APPROVED | BTAYLOR |
| U-CROSS CONNECTION | 07/15/2025 | Disapproved - NO FEE | BWRIGHT |
| Note: No IRR. No CC | |||
| ROW - FINAL INSPECTION | 07/15/2025 | APPROVED | FSLADISH |
| Note: 7/15/25 AT THE TIME OF THIS INSPECTIONS ALL COPC REQUIREMENTS WERE MET, NEITHER THE INSPECTOR NOR THE CITY IS RESPONSIBLE IF, FOR WHATEVER REASON, SITE CONDITIONS CHANGE OVER TIME AFTER THE INSPECTION. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED. *** INSPECTORS NOTE. YOU WILL BE REQUIRED TO REMOVE THE CONCRETE DEBRIS AND SOD TO GRADE THE RIGHT SIDE VACANT SWALE OUTLINED IN PINK PAINT BEFORE ROW FINAL PASSAGE.*** | |||
| U -UTILITY RESIDENTIAL FINAL | 07/15/2025 | FINAL APPROVED | BWRIGHT |
| ROW- FINAL SURVEY/GRADING CERTIFICATION | 06/11/2025 | APPROVED - AS NOTED | FSLADISH |
| Note: 6/11/95 WALKED PROPERTY AND DETERMINED DRAINAGE IN FIELD WILL WORK AT THE TIME OF THIS INSPECTION. APPROVING THIS SURVEY AS NOTED. 6/3/2025 - PREVIOUS INSPECTION NOTES NOTE TO INSPECTOR 5/15/2025 MET WITH JASON FROM ROSS FOR GRADING OF THE LEFT SIDE OF PROPERTY. THERE WILL BE A COMMON SWALE DUE TO NEW CONSTRUCTION THE THE LEFT OF THIS PROPERTY. COMMON SWALE WILL NEED TO HAVE POSITIVE FLOW. 6/3/25 BASED ON THIS NOTE AND PRIOR CONVERSATION WITH GRADER, YOUR SURVEY IS INCORRECT PER THIS DISCUSSION. IT MATCHES YOUR SITE PLAN BUT A COMMON SWALE WAS DETERMINED TO BE NECCESSARY. YOUR SURVEY SHOWS AN INSIDE SWALE THIS IS SURVEY DOES NOT REFLECT THIS. PLEASE SEE PHOTO FOR REFERENCE. | |||
| ROW FIELD SURVEY /GRADING CERTIFICATION | 06/11/2025 | APPROVED | FSLADISH |
| Note: 6/11/95 WALKED PROPERTY AND DETERMINED DRAINAGE IN FIELD WILL WORK AT THE TIME OF THIS INSPECTION. *** INSPECTORS NOTE. YOU WILL BE REQUIRED TO REMOVE THE COCRETE DEBRIS AND SOD TO GRADE THE RIGHT SIDE VACANT SWALE OUTLINED IN PINK PAINT BEFORE ROW FINAL PASSAGE.*** Inspector Notes from Inspection 9463 6/11/95 WALKED PROPERTY AND DETERMINED DRAINAGE IN FIELD WILL WORK AT THE TIME OF THIS INSPECTION. APPROVING THIS SURVEY AS NOTED. 6/3/2025 - PREVIOUS INSPECTION NOTES NOTE TO INSPECTOR 5/15/2025 MET WITH JASON FROM ROSS FOR GRADING OF THE LEFT SIDE OF PROPERTY. THERE WILL BE A COMMON SWALE DUE TO NEW CONSTRUCTION THE THE LEFT OF THIS PROPERTY. COMMON SWALE WILL NEED TO HAVE POSITIVE FLOW. 6/3/25 BASED ON THIS NOTE AND PRIOR CONVERSATION WITH GRADER, YOUR SURVEY IS INCORRECT PER THIS DISCUSSION. IT MATCHES YOUR SITE PLAN BUT A COMMON SWALE WAS DETERMINED TO BE NECCESSARY. YOUR SURVEY SHOWS AN INSIDE SWALE THIS IS SURVEY DOES NOT REFLECT THIS. PLEASE SEE PHOTO FOR REFERENCE. | |||
| ROW- FINAL SURVEY/GRADING CERTIFICATION | 06/03/2025 | Disapproved - NO FEE | FSLADISH |
| Note: NOTE TO INSPECTOR 5/15/2025 MET WITH JASON FROM ROSS FOR GRADING OF THE LEFT SIDE OF PROPERTY. THERE WILL BE A COMMON SWALE DUE TO NEW CONSTRUCTION THE THE LEFT OF THIS PROPERTY. COMMON SWALE WILL NEED TO HAVE POSITIVE FLOW. 6/3/25 BASED ON THIS NOTE AND PRIOR CONVERSATION WITH GRADER, YOUR SURVEY IS INCORRECT PER THIS DISCUSSION. IT MATCHES YOUR SITE PLAN BUT A COMMON SWALE WAS DETERMINED TO BE NECCESSARY. YOUR SURVEY SHOWS AN INSIDE SWALE THIS IS SURVEY DOES NOT REFLECT THIS. PLEASE SEE PHOTO FOR REFERENCE. | |||
| ROW- PROJECT STATUS | 05/15/2025 | Status Check | PFLANAGAN |
| Note: MET WITH JASON FROM ROSS FOR GRADING OF THE LEFT SIDE OF PROPERTY. THERE WILL BE A COMMON SWALE DUE TO NEW CONSTRUCTION THE THE LEFT OF THIS PROPERTY. COMMON SWALE WILL NEED TO HAVE POSITIVE FLOW. | |||
| ROW- PRE-APRON (PRE-POUR) | 04/21/2025 | APPROVED | PFLANAGAN |
| Note: READY FOR PAVERS ------------------------------------------------------------------------------- 4/14/2025 - PREVIOUS INSPECTION NOTES ** 04/14/25 APRON READY TO POUR WITH PAVER RESTRAINT ** At the time of the inspection all minimum city requirements were met. It is the builders responsibility to ensure that nothing changes after this Inspection is approved. This includes but is not limited to, the Culvert Pipe Elevation from the time of the inspection approval to the concrete pour. **MAKE SURE THERE IS 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE (FRC) DRAWING 300,E RESIDENTIAL CULVERT DETAIL ** SCHEDULE NEXT PRE-POUR ONCE PAVER BASE HAS BEEN SPREAD AND COMPACTED ** DO NOT SET PAVERS UNTIL NEXT PRE-POUR HAS BEEN APPROVED | |||
| ELECTRIC - EARLY POWER | 04/17/2025 | APPROVED - AS NOTED | BTAYLOR |
| Note: 4-17-25 1. Emailed FPL at 2:17. | |||
| ROW- PAVER RESTRAINTS | 04/14/2025 | APPROVED | EMADISON |
| Note: ** 04/14//25 READY TO POUR PAVER RESTRAINTS AND APRON ** At the time of the inspection all minimum city requirements were met. It is the builders responsibility to ensure that nothing changes after this Inspection is approved. **MAKE SURE THERE IS 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE | |||
| ROW- PRE-APRON (PRE-POUR) | 04/14/2025 | PARTIALLY APPROVED | EMADISON |
| Note: ** 04/14/25 APRON READY TO POUR WITH PAVER RESTRAINT ** At the time of the inspection all minimum city requirements were met. It is the builders responsibility to ensure that nothing changes after this Inspection is approved. This includes but is not limited to, the Culvert Pipe Elevation from the time of the inspection approval to the concrete pour. **MAKE SURE THERE IS 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE (FRC) DRAWING 300,E RESIDENTIAL CULVERT DETAIL ** SCHEDULE NEXT PRE-POUR ONCE PAVER BASE HAS BEEN SPREAD AND COMPACTED ** DO NOT SET PAVERS UNTIL NEXT PRE-POUR HAS BEEN APPROVED | |||
| GRAVITY SEWER TEST | 03/18/2025 | APPROVED | MGIBSON |
| Note: Inspector Notes from Inspection 2060 11/19/2024 - PREVIOUS INSPECTION NOTES MISSED INSPECTION,UNCOVER ALL WASTE AND VENT FBC[A] 110.1 PLUMBING CONCEALED. WATERSERVICE NOT RAN YET | |||
| SEWER TIE IN | 03/18/2025 | APPROVED | MGIBSON |
| Note: Inspector Notes from Inspection 2060 11/19/2024 - PREVIOUS INSPECTION NOTES MISSED INSPECTION,UNCOVER ALL WASTE AND VENT FBC[A] 110.1 PLUMBING CONCEALED. WATERSERVICE NOT RAN YET | |||
| PEP TANK INSTALLATION REQUEST | 02/25/2025 | APPROVED | CBOWERMASTER |
| INSULATION | 02/20/2025 | APPROVED | BTAYLOR |
| Note: Inspector Notes from Inspection 2420 2-14-25 1. Outlets on island need to be moved to the edges due to counter top over hang. Both units. 1/14/2025 - PREVIOUS INSPECTION NOTES 1-14-25 1. Missing garage door. 2. Bearing wall has been cut more than 60% in different locations. Repair will need to be done before moving forward. 3. Bearing wall studs have been cut more than 60% in different locations. Repair will need to be done before moving forward. 4. Electrical panel is not fire blocked at the top. | |||
| ALL ROUGH | 02/14/2025 | APPROVED - AS NOTED | BTAYLOR |
| Note: 2-14-25 1. Outlets on island need to be moved to the edges due to counter top over hang. Both units. 1/14/2025 - PREVIOUS INSPECTION NOTES 1-14-25 1. Missing garage door. 2. Bearing wall has been cut more than 60% in different locations. Repair will need to be done before moving forward. 3. Bearing wall studs have been cut more than 60% in different locations. Repair will need to be done before moving forward. 4. Electrical panel is not fire blocked at the top. | |||
| LATH/BRICK/ WATER BARRIER | 01/14/2025 | APPROVED | BTAYLOR |
| ALL ROUGH | 01/14/2025 | Disapproved - NO FEE | BTAYLOR |
| Note: 1-14-25 1. Missing garage door. 2. Bearing wall has been cut more than 60% in different locations. Repair will need to be done before moving forward. 3. Bearing wall studs have been cut more than 60% in different locations. Repair will need to be done before moving forward. 4. Electrical panel is not fire blocked at the top. | |||
| FIREWALL FINAL | 12/31/2024 | APPROVED | PKNAPIK |
| FIREWALL DRYWALL NAILING | 12/27/2024 | APPROVED | FWILLIS |
| ROOF VALLEY & METAL | 12/20/2024 | APPROVED | BTAYLOR |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 12/18/2024 | APPROVED | BTAYLOR |
| Note: 12/17/2024 - PREVIOUS INSPECTION NOTES 12/17/24 Approved to keep work going. Will check at next inspection 1. Missing fasteners for wall to block. Required tapcons for load bearing walls per plan | |||
| WALL SHEATHING | 12/17/2024 | APPROVED | MCONTRYMAN |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 12/17/2024 | Disapproved - NO FEE | MCONTRYMAN |
| Note: 12/17/24 Approved to keep work going. Will check at next inspection 1. Missing fasteners for wall to block. Required tapcons for load bearing walls per plan | |||
| FIREWALL FRAMING | 12/17/2024 | APPROVED | MCONTRYMAN |
| FOUND SURVEY APPROVED (OFFICE) | 12/16/2024 | APPROVED | LSALYERDS |
| TIE BEAM / LINTEL | 12/05/2024 | APPROVED | BTAYLOR |
| MONOLITHIC SLAB | 11/25/2024 | APPROVED | PKNAPIK |
| Note: 11/22/2024 - PREVIOUS INSPECTION NOTES 11-22-24 1. Need to have complete set of readable plans on site. | |||
| MONOLITHIC SLAB | 11/22/2024 | Disapproved -FEE REQUIRED | BTAYLOR |
| Note: 11-22-24 1. Need to have complete set of readable plans on site. | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 11/20/2024 | APPROVED - AS NOTED | MGIBSON |
| Note: 11/19/2024 - PREVIOUS INSPECTION NOTES MISSED INSPECTION,UNCOVER ALL WASTE AND VENT FBC[A] 110.1 PLUMBING CONCEALED. WATERSERVICE NOT RAN YET | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 11/19/2024 | Disapproved - NO FEE | MGIBSON |
| Note: MISSED INSPECTION,UNCOVER ALL WASTE AND VENT FBC[A] 110.1 PLUMBING CONCEALED | |||
| GEOTECHNICAL REPORT APPROVAL (OFFICE USE) | 11/18/2024 | APPROVED | JMUNSON |
| WATER METER INSTALLATION REQUEST | 10/23/2024 | APPROVED | CBOWERMASTER |
Review History
| Department | Status | Date In | Date Out |
| BLD | COMPLETE | 01/21/2025 | 01/27/2025 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 01/14/2025 | 01/15/2025 |
| Note: Released By: LEVI SALYERDS - (386)986-2326 - LSALYERDS@PALMCOASTGOV.COM | |||
| SW1 | COMPLETE | 01/14/2025 | 01/15/2025 |
| Note: Released By: LEVI SALYERDS - (386)986-2326 - LSALYERDS@PALMCOASTGOV.COM | |||
| ZON | HOLD | 01/14/2025 | 01/14/2025 |
| Note: Held By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM Please bring in originals for processing | |||
| ZON | COMPLETE | 01/14/2025 | 01/14/2025 |
| Note: Released By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 12/13/2024 | 12/16/2024 |
| Note: Released By: LEVI SALYERDS - - LSALYERDS@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 12/13/2024 | 12/13/2024 |
| Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 11/19/2024 | 11/21/2024 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| BLD | HOLD | 11/12/2024 | 11/18/2024 |
| Note: Held By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM 1. Truss packet or truss layout need shop drawing approval stamp by EOR | |||
| BLD | COMPLETE | 09/16/2024 | 09/17/2024 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 09/05/2024 | 09/07/2024 |
| Note: Released By: JPI | |||
| SWALE | COMPLETE | 08/23/2024 | 10/24/2024 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| BADMIN | COMPLETE | 08/22/2024 | 08/29/2024 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| BLD | HOLD | 08/22/2024 | 08/29/2024 |
| Note: Held By: JPI 1. Based on an internet inquiry, the following product approval numbers appear to have recently expired, please cure. 10852 (Structural - Stud Plate Tie), 15638 (Structural - Truss Plates), 15228 (Composite Lumber). 107.2.4 | |||
| CUSVC | COMPLETE | 08/22/2024 | 08/26/2024 |
| Note: Released By: LUCY NABICO - - | |||
| ELEC | COMPLETE | 08/22/2024 | 08/29/2024 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 08/22/2024 | 08/23/2024 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| GAS | CANCEL | 08/22/2024 | 08/27/2024 |
| LOCATE | COMPLETE | 08/22/2024 | 08/26/2024 |
| Note: Released By: CANDACE BOWERMASTER - - CBOWERMASTER@PALMCOASTGOV.COM | |||
| MECH | COMPLETE | 08/22/2024 | 08/28/2024 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| SW1 | COMPLETE | 08/22/2024 | 08/23/2024 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 08/22/2024 | 08/23/2024 |
| Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION RESIDENTIAL | ¤40.00 | 02/11/2025 |
| RECORDING FEE REIMBURSE DOC | ¤44.00 | 02/11/2025 |
| IMPACT FEE TRANSPORTATION | ¤2,890.00 | 09/16/2024 |
| WATER -IRRIGATION INSPECTION | ¤50.00 | 09/16/2024 |
| SURCHARGE FS 533.721 | ¤14.79 | 09/16/2024 |
| SURCHARGE - FS 468.631 | ¤22.18 | 09/16/2024 |
| SW ENG - FOUNDATION SURVEY | ¤20.00 | 09/16/2024 |
| SW ENG INSPECTION 80 | ¤80.00 | 09/16/2024 |
| SW ENG PRE APRON | ¤30.00 | 09/16/2024 |
| SW ENG - REVIEW 20 | ¤20.00 | 09/16/2024 |
| SW ENG RES REVIEW 200 | ¤200.00 | 09/16/2024 |
| SEWER CREDIT | (¤2,932.00) | 09/16/2024 |
| SEWER INSPECTION | ¤25.00 | 09/16/2024 |
| SEWER CAPITAL FACILITY | ¤12,241.04 | 09/16/2024 |
| WATER CAPITAL FACILITY FEE | ¤8,702.28 | 09/16/2024 |
| SITE PLAN 30 | ¤30.00 | 09/16/2024 |
| CONNECTION FEES | ¤2,374.52 | 09/16/2024 |
| FC IMPACT FEE EMS | ¤124.00 | 09/16/2024 |
| IMPACT FEE FIRE | ¤856.18 | 09/16/2024 |
| FC IMPACT FEE LAW ENFORCEMENT | ¤436.00 | 09/16/2024 |
| FC IMPACT FEE LIBRARY | ¤536.00 | 09/16/2024 |
| IMPACT FEE PARKS | ¤3,600.18 | 09/16/2024 |
| IMPACT FEE SCHOOL | ¤10,900.00 | 09/16/2024 |
| WATER- TURN ON | ¤50.00 | 09/16/2024 |
| ADJUSTMENT 10% | (¤164.32) | 09/16/2024 |
| ADMINISTRATIVE RESIDENTIAL | ¤30.00 | 09/16/2024 |
| INSPECTION - RESIDENTIAL | ¤1,256.75 | 09/16/2024 |
| PLAN REVIEW - RESIDENTIAL | ¤356.46 | 09/16/2024 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤41,833.06 |