Permit #2024090371
Permit Details
Status: FINAL
| Total Square Footage: 35890 sqft |
| Block: 00000 |
| Subdivision: 2334 - EVOLVE PALM COAST - SANDLAKE SUBDIVISION LOT 4 |
| Job Phone: 304-694-7694 |
| Location Address: 82 EVOLVE PKWY |
| Type: BM - BUILDING MULTI - APARTMENT |
| Issue Date: 09/26/2024 |
| NOC: RECORDED |
| Applicant name: MATTHEW ADAM ROGERS |
| Owner: EVOLVE PALM COAST LLC |
|
Address 2918-A MARTINSVILLE ROAD GREENSBORO, NC 27408 |
| Lot: 0040 |
| Contracted Stated Job Value: ¤1,912,500.00 |
| Job Description: BLDG 1600 - (20 UNITS) |
| Type: CN |
| Original Permit #: 2024090226 |
Contractor
EVOLVE CONSTRUCTION OF FL LLC
| Status | Location Address | State License Number | Phone |
| INACTIVE |
2018A MARTINSVILLE RD GREENSBORO, NC 27408 |
CGC1532932 (Exp: 08/31/2026) | 304-694-7694 |
Sub Contractors
PAUL LEONARD RICHARDS
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
671 BUSINESS PARK BLVD WINTER GARDEN, FL 34787 |
CAC057235 (Exp: 08/31/2026) | 407-877-8090 | 407-877-8479 |
TRACEY LYNN HYMAN-MONTEE
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
75 STUMPFIELD ROAD PENSACOLA, FL 32503 |
CFC1430978 (Exp: 08/31/2026) | 850-477-0388 | 850-477-0381 |
MARK ASSELIN
| Status | Location Address | State License Number | Phone |
| ACTIVE |
3508 LENOX AVE JACKSONVILLE, FL 32254 |
EC13009251 (Exp: 08/31/2026) | 904-726-7966 |
JOSHUA DAVID CADILLAC
| Status | Location Address | State License Number | Phone |
| CANCEL |
3264 S UNIVERSITY DRIVE MIRMAR, FL 33025 |
CCC1333894 (Exp: 08/31/2026) | 954-333-8697 |
Inspection History
| Type | Request Date | Result | Inspector |
| HORIZONTAL ASSEMB PENETRATIONS | 03/06/2026 | APPROVED | KSANDOE |
| Note: 3/5/2026 12:57:34 PM- PREVIOUS INSPECTION NOTES | |||
| HORIZONTAL ASSEMB FINAL | 03/06/2026 | APPROVED | KSANDOE |
| Note: 3/5/2026 12:58:05 PM- PREVIOUS INSPECTION NOTES | |||
| BUILDING FINAL | 03/06/2026 | FINAL APPROVED | KSANDOE |
| FIRE FINAL | 03/06/2026 | APPROVED | RMARTIN |
| Note: 3/5/2026 - PREVIOUS INSPECTION NOTES | |||
| EXTERIOR ARCHITECTURAL FEATURES | 03/06/2026 | APPROVED | RPICATAGI |
| U - UTILITY COMMERCIAL FINAL | 03/06/2026 | FINAL APPROVED | BWRIGHT |
| FIRE FINAL | 03/05/2026 | CANCELLED BY APPLICANT | RMARTIN |
| HORIZONTAL ASSEMB FINAL | 03/05/2026 | CANCELLED BY APPLICANT | PKNAPIK |
| HORIZONTAL ASSEMB PENETRATIONS | 03/05/2026 | CANCELLED BY APPLICANT | PKNAPIK |
| PLUMBING FINAL | 02/19/2026 | FINAL APPROVED | HCAMACHO |
| U -UTILITY RESIDENTIAL FINAL | 02/17/2026 | FINAL APPROVED | BWRIGHT |
| FIREWALL FINAL | 02/06/2026 | APPROVED | KSANDOE |
| HVAC FINAL | 02/04/2026 | APPROVED | HCAMACHO |
| Note: 2/3/2026 - PREVIOUS INSPECTION NOTES All the CU's are missing locking caps on the ports. | |||
| HVAC FINAL | 02/03/2026 | Disapproved - NO FEE | HCAMACHO |
| Note: All the CU's are missing locking caps on the ports. | |||
| ELECTRIC FINAL | 01/29/2026 | FINAL APPROVED | MKRASKI |
| Note: | |||
| U - SEWER TIE IN | 01/28/2026 | APPROVED | RSIMS |
| Note: 1/28/26: Connection visually verified via scope camera. RS 1/20/2026 - PREVIOUS INSPECTION NOTES 1/20/26: Cancelled by Applicant in person. Waiting on RFI. | |||
| U - SEWER TIE IN | 01/20/2026 | CANCELLED BY APPLICANT | RSIMS |
| Note: 1/20/26: Cancelled by Applicant in person. Waiting on RFI. | |||
| U-CROSS CONNECTION | 01/20/2026 | APPROVED | BWRIGHT |
| ELECTRIC - EARLY POWER | 01/14/2026 | APPROVED - AS NOTED | MKRASKI |
| Note: Emailed FPL for power release @ 2pm | |||
| ELECTRIC FINAL | 01/12/2026 | CANCELLED BY APPLICANT | MKRASKI |
| Note: Requested a early power inspection, inspection added | |||
| ELECTRIC - EARLY POWER | 01/12/2026 | Disapproved - NO FEE | MKRASKI |
| Note: 1. No contractor onsite, Contractor must be on site for power release, need to open MDP anc check tourque specs | |||
| FIREWALL DRYWALL NAILING | 10/31/2025 | APPROVED | KSANDOE |
| FIREWALL DRYWALL NAILING | 10/30/2025 | APPROVED | FWILLIS |
| HORIZONTAL ASSEMB DRYWALL | 10/30/2025 | APPROVED | FWILLIS |
| FIREWALL FRAMING | 10/30/2025 | APPROVED | FWILLIS |
| HORIZONTAL ASSEMB FRAMING | 10/22/2025 | APPROVED | FWILLIS |
| INSULATION | 10/16/2025 | APPROVED | FWILLIS |
| Note: 8/12/2025 - PREVIOUS INSPECTION NOTES | |||
| ROOF SHEATHING / BRACE / TIE DOWN | 10/15/2025 | APPROVED | CPISCITELLI |
| Note: report submitted | |||
| LATH/BRICK/WATER BARRIER | 10/15/2025 | APPROVED | FWILLIS |
| LATH/BRICK/WATER BARRIER | 10/14/2025 | CANCELLED BY APPLICANT | WEB |
| FRAMING | 10/09/2025 | APPROVED | FWILLIS |
| Note: PERFORMED BY THIRD PARTY. THIS IS A FOLLOW UP INSPECTION. | |||
| PLUMBING 2ND ROUGH | 10/09/2025 | APPROVED | MGIBSON |
| FIREWALL PENETRATIONS | 09/24/2025 | APPROVED | FWILLIS |
| Note: 9/24/25 - INCLUDES ALL FLOORS. 7/25/2025 - PREVIOUS INSPECTION NOTES | |||
| ELECTRIC 2ND ROUGH | 08/29/2025 | APPROVED | MKRASKI |
| BLD - SEWER TIE IN | 08/28/2025 | APPROVED | MGIBSON |
| INSULATION | 08/12/2025 | PARTIALLY APPROVED | KSANDOE |
| HVAC ROUGH | 08/05/2025 | APPROVED | CPISCITELLI |
| Note: virtual inspection | |||
| STOREFRONT | 08/01/2025 | CANCELLED BY INSPECTOR | KSANDOE |
| HVAC ROUGH | 07/30/2025 | PARTIALLY APPROVED | CPISCITELLI |
| Note: inspected seams on fresh air to be able to wrap | |||
| WINDOW NAILING | 07/29/2025 | APPROVED | KSANDOE |
| Note: 7/7/2025 - PREVIOUS INSPECTION NOTES NOT COMPLETE. THIRD FLOOR NEEDS S.G.D DOORS INSTALLED. | |||
| FIREWALL PENETRATIONS | 07/25/2025 | PARTIALLY APPROVED | FWILLIS |
| WINDOW NAILING | 07/07/2025 | Disapproved - NO FEE | FWILLIS |
| Note: NOT COMPLETE. THIRD FLOOR NEEDS S.G.D DOORS INSTALLED. | |||
| LATH/BRICK/WATER BARRIER | 06/25/2025 | APPROVED | FWILLIS |
| Note: HOUSE WRAP Inspector Notes from Inspection 3444 BUILDING #1600. SECOND LAYER OF 5/8 SHEETROCK. TYPE 2 BUILDING | |||
| FIREWALL DRYWALL NAILING | 05/09/2025 | APPROVED - AS NOTED | FWILLIS |
| Note: BUILDING #1600. SECOND LAYER OF 5/8 SHEETROCK. TYPE 2 BUILDING | |||
| FIREWALL DRYWALL NAILING | 05/07/2025 | FINAL APPROVED | FWILLIS |
| Note: NOT FINALED....JUST APPROVED | |||
| FOUND SURVEY APPROVED (OFFICE) | 03/25/2025 | APPROVED | DLEAP |
Review History
| Department | Status | Date In | Date Out |
| BLD | COMPLETE | 10/03/2025 | 10/15/2025 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 06/05/2025 | 06/18/2025 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| PLENG | COMPLETE | 03/25/2025 | 03/25/2025 |
| Note: Released By: DENNIS R. LEAP, P.E. - (386)986-2482 - DLEAP@PALMCOASTGOV.COM | |||
| PLENG | HOLD | 03/12/2025 | 03/13/2025 |
| Note: Held By: DENNIS R. LEAP, P.E. - (386)986-2482 - DLEAP@PALMCOASTGOV.COM 1. Label plan "FOUNDATION SURVEY" and not SPECIFIC PURPOSE SURVEY. 2. Highlight foundation for specific foundation being permitted for in this permit application. | |||
| BLD | CANCEL | 09/26/2024 | 09/26/2024 |
| PLFM | INFORMATION | 09/13/2024 | 09/16/2024 |
| Note: Marked INFORMATION By: JORDAN MYERS, C.F.M - (386)986-4789 - JMYERS@PALMCOASTGOV.COM Vertical construction is not authorized until floodplain requirements have been met. | |||
| FI1 | COMPLETE | 09/10/2024 | 09/13/2024 |
| Note: Released By: LEE MILLER - (386)986-3783 - WMILLER@PALMCOASTGOV.COM | |||
| GAS | CANCEL | 09/10/2024 | 09/13/2024 |
| MECH | COMPLETE | 09/10/2024 | 09/13/2024 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| UD1 | COMPLETE | 09/10/2024 | 09/12/2024 |
| Note: Released By: GREG DEGLER - (386)986-2384 - GDEGLER@PALMCOASTGOV.COM | |||
| PLUM | COMPLETE | 09/10/2024 | 09/13/2024 |
| Note: Released By: PATRICK BUCKLEY - (386)986-3786 - PBUCKLEY@PALMCOASTGOV.COM | |||
| ARCHR | COMPLETE | 09/10/2024 | 09/16/2024 |
| Note: Released By: RICHARD PICATAGI - (386)986-3760 - RPICATAGI@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 09/10/2024 | 09/13/2024 |
| Note: Released By: PATRICK BUCKLEY - (386)986-3786 - PBUCKLEY@PALMCOASTGOV.COM | |||
| DSD | COMPLETE | 09/10/2024 | 09/12/2024 |
| Note: Released By: DAMARIS RAMIREZ - (386)986-3750 - DRAMIREZ@PALMCOASTGOV.COM | |||
| ELEC | COMPLETE | 09/10/2024 | 09/13/2024 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| IMPACT FEE PARKS | ¤36,019.80 | 11/25/2025 |
| IMPACT FEE TRANSPORTATION | ¤39,240.00 | 11/25/2025 |
| IMPACT FEE FIRE | ¤8,561.80 | 04/02/2025 |
| FC IMPACT FEE LAW ENFORCEMENT | ¤2,220.00 | 09/26/2024 |
| FC IMPACT FEE LIBRARY | ¤2,780.00 | 09/26/2024 |
| IMPACT FEE SCHOOL | ¤27,200.00 | 09/26/2024 |
| ADJUSTMENT 10% | (¤1,394.43) | 09/26/2024 |
| ADMINISTRATIVE - COMMERCIAL | ¤75.00 | 09/26/2024 |
| INSPECTION COMMERCIAL | ¤13,391.00 | 09/26/2024 |
| INSPECTION - FIRE COMMERCIAL | ¤478.25 | 09/26/2024 |
| FC IMPACT FEE EMS | ¤640.00 | 09/26/2024 |
| SURCHARGE FS 533.721 | ¤125.50 | 09/26/2024 |
| SURCHARGE - FS 468.631 | ¤188.25 | 09/26/2024 |
| SITE PLAN 30 | ¤30.00 | 09/26/2024 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤129,555.17 |