I want to search for...
Permit #2024090912
Permit Details
Status: EXPIRED
| Parcel Id: 07-11-31-7035-00050-0140 |
| Block: 00050 |
| Subdivision: - |
| Job Phone: 786-512-4421 |
| Location Address: 4 BIRD OF PARADISE DR |
| Type: DR - DRIVEWAY |
| Issue Date: 10/01/2024 |
| NOC: Unknown |
| Applicant name: ABEL MENENDEZ |
| Owner: LEON MANEUL A MATALLANA & DYANA MATALLANA JTWROS |
|
Address 4 BIRD OF PARADISE DRIVE PALM COAST, FL 32137 |
| Lot: 0140 |
| Contracted Stated Job Value: ¤4,500.00 |
| Job Description: 18x36 Concrete drive way extension |
| Type: CN |
Contractor
ROYAL TILE & PAVERS INC
| Status | Location Address | Phone |
| ACTIVE |
69 FLEETWOOD DR PALM COAST, FL 32137 |
786-512-4421 |
Inspection History
| Type | Request Date | Result | Inspector |
| ROW - FINAL INSPECTION | 09/29/2025 | Disapproved - NO FEE | EMADISON |
| Note: ** 09/29/25 nOT NOTED IN PREVIOUS INSPECTION THE BUILDER IS REQUIRED TO MAKE A HOT ASPHALT ROAD REPAIR ACROSS THE APRON OF THE DRIVEWAY ROAD REPAIR IS TO BE A MINIMUM OF 12 INCHES WIDE BY THE LENGTH OF THE APRON ** I AM NOT FEEING THIS INSPECTION DUE TO PREVIOUS INSPECTION NOT NOTING IT HOWEVER IF YOU HAVE NOT CORRECTED AT THE TIME OF THE NEXT SCHEDULED INSPECTION A FEE WILL BE IMPOSED ____________________________________________________________________________________________________________________ New inspection due to canceled inspection 4/8/2025 - PREVIOUS INSPECTION NOTES 1) NEED TO CLEAN ALL DIRT AND OVER POURED CONCRETE OUT OF CULVERT. 2) NEED TO REPAIR ALL BARE AREAS AND WASHOUTS WITH DIRT AND SOD . 3) NEED TO A SAW CUT IN CONCRETE OVER CULVERT PIPE. SEC 300,03 F4 V-21-The Stormwater Final Inspection will include visual inspection of the site and adjacent properties for debris, proper clean up and repair to damaged terrain. Bare earth on the site or surrounding properties must be sodded. SEE DRAWING 300.E | |||
| ROW - FINAL INSPECTION | 04/10/2025 | CANCELLED BY APPLICANT | WEB |
| Note: 4/8/2025 - PREVIOUS INSPECTION NOTES 1) NEED TO CLEAN ALL DIRT AND OVER POURED CONCRETE OUT OF CULVERT. 2) NEED TO REPAIR ALL BARE AREAS AND WASHOUTS WITH DIRT AND SOD . 3) NEED TO A SAW CUT IN CONCRETE OVER CULVERT PIPE. SEC 300,03 F4 V-21-The Stormwater Final Inspection will include visual inspection of the site and adjacent properties for debris, proper clean up and repair to damaged terrain. Bare earth on the site or surrounding properties must be sodded. SEE DRAWING 300.E | |||
| U -UTILITY RESIDENTIAL FINAL | 04/08/2025 | FINAL APPROVED | DHANEY |
| ROW - FINAL INSPECTION | 04/08/2025 | Disapproved -FEE REQUIRED | PFLANAGAN |
| Note: 1) NEED TO CLEAN ALL DIRT AND OVER POURED CONCRETE OUT OF CULVERT. 2) NEED TO REPAIR ALL BARE AREAS AND WASHOUTS WITH DIRT AND SOD . 3) NEED TO A SAW CUT IN CONCRETE OVER CULVERT PIPE. SEC 300,03 F4 V-21-The Stormwater Final Inspection will include visual inspection of the site and adjacent properties for debris, proper clean up and repair to damaged terrain. Bare earth on the site or surrounding properties must be sodded. SEE DRAWING 300.E | |||
| ROW- PRE-APRON (PRE-POUR) | 10/30/2024 | APPROVED | PFLANAGAN |
| Note: DO NOT CHANGE ANYTHING AFTER THIS INSPECTION IT'S YOUR RESPONSIBILITY TO CHECK THE CULVERT ELEVATIONS BEFORE POURING CONCRETE. ALL CONCRETE NEEDS TO BE A MINIMUM OF 3000PSI WITH FIBER OR WITH METAL MESH IN THE CONCRETE TO MEET ALL CITY'S STANDARDS. At the time of the inspection all minimum city requirements were met. It is the builders and the homowners responsibility to ensure that nothing changes after this Inspection is approved. It will not be on the city if any changes after this inspection. --------------------------------------------------------------------------------- 10/29/2024 - PREVIOUS INSPECTION NOTES DROVE BY AND SEEN THAT ROYAL TILE WAS FILLING IN THE ENTIRE DRIVEWAY WITH BASE AND NOW THE BASE IS NOT TO CITY'S STANDARDS DO TO NOT HAVE THE MINIMUM AMOUNT OF CONCRETE. NEED TO HAVE ANOTHER INSPECTION DONE BEFORE POURING. IF YOU POUR THE DRIVEWAY WITH OUT THIS INSPECTION YOU WILL BE PULLING THE DRIVEWAY PER GABE, PARREN, ED. | |||
| ROW- PRE-APRON (PRE-POUR) | 10/29/2024 | Disapproved - NO FEE | PFLANAGAN |
| Note: DROVE BY AND SEEN THAT ROYAL TILE WAS FILLING IN THE ENTIRE DRIVEWAY WITH BASE AND NOW THE BASE IS NOT TO CITY'S STANDARDS DO TO NOT HAVE THE MINIMUM AMOUNT OF CONCRETE. NEED TO HAVE ANOTHER INSPECTION DONE BEFORE POURING. IF YOU POUR THE DRIVEWAY WITH OUT THIS INSPECTION YOU WILL BE PULLING THE DRIVEWAY PER GABE, PARREN, ED. | |||
| ROW- PRE-APRON (PRE-POUR) | 10/25/2024 | APPROVED | PFLANAGAN |
| Note: IT'S YOUR RESPONSIBILITY TO CHECK THE CULVERT ELEVATIONS BEFORE POURING CONCRETE. ALL CONCRETE NEEDS TO BE A MINIMUM OF 3000PSI WITH FIBER OR WITH METAL MESH IN THE CONCRETE TO MEET ALL CITY'S STANDARDS. At the time of the inspection all minimum city requirements were met. It is the builders and the homowners responsibility to ensure that nothing changes after this Inspection is approved. It will not be on the city if any changes after this inspection. ----------------------------------------------------------------------------- 10/21/2024 - PREVIOUS INSPECTION NOTES 1) SOIL TO SOFT NEED TO COMPACT SOIL TO CITY STANDARDS. 2) THE CULVERT CAN ONLY BE BURIED HALF WAY. 3) THE SWALE PLAN DETAIL IS CHANGING THE INVERT NOE IS GOING TO BE AT A 26.80 SO PIPE IS NOT LOWER THEN CATCH BASIN TO THE RIGHT. | |||
| ROW- PRE-APRON (PRE-POUR) | 10/21/2024 | Disapproved - NO FEE | PFLANAGAN |
| Note: 1) SOIL TO SOFT NEED TO COMPACT SOIL TO CITY STANDARDS. 2) THE CULVERT CAN ONLY BE BURIED HALF WAY. 3) THE SWALE PLAN DETAIL IS CHANGING THE INVERT NOE IS GOING TO BE AT A 26.80 SO PIPE IS NOT LOWER THEN CATCH BASIN TO THE RIGHT. | |||
| ROW - FINAL APRON (AFTER POUR) | |||
| ROW - FINAL INSPECTION | |||
| Note: 9/29/2025 - PREVIOUS INSPECTION NOTES ** 09/29/25 nOT NOTED IN PREVIOUS INSPECTION THE BUILDER IS REQUIRED TO MAKE A HOT ASPHALT ROAD REPAIR ACROSS THE APRON OF THE DRIVEWAY ROAD REPAIR IS TO BE A MINIMUM OF 12 INCHES WIDE BY THE LENGTH OF THE APRON ** I AM NOT FEEING THIS INSPECTION DUE TO PREVIOUS INSPECTION NOT NOTING IT HOWEVER IF YOU HAVE NOT CORRECTED AT THE TIME OF THE NEXT SCHEDULED INSPECTION A FEE WILL BE IMPOSED ____________________________________________________________________________________________________________________ New inspection due to canceled inspection 4/8/2025 - PREVIOUS INSPECTION NOTES 1) NEED TO CLEAN ALL DIRT AND OVER POURED CONCRETE OUT OF CULVERT. 2) NEED TO REPAIR ALL BARE AREAS AND WASHOUTS WITH DIRT AND SOD . 3) NEED TO A SAW CUT IN CONCRETE OVER CULVERT PIPE. SEC 300,03 F4 V-21-The Stormwater Final Inspection will include visual inspection of the site and adjacent properties for debris, proper clean up and repair to damaged terrain. Bare earth on the site or surrounding properties must be sodded. SEE DRAWING 300.E |
Review History
| Department | Status | Date In | Date Out |
| ENGIN1 | COMPLETE | 10/03/2024 | 10/03/2024 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| UTL | COMPLETE | 10/03/2024 | 10/03/2024 |
| Note: Released By: LARRY FITZGERALD - (386)286-2041 - LFITZGERALD@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 10/03/2024 | 10/03/2024 |
| Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 10/01/2024 | 10/01/2024 |
| Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 10/01/2024 | 10/01/2024 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| UTL | COMPLETE | 10/01/2024 | 10/01/2024 |
| Note: Released By: LARRY FITZGERALD - (386)286-2041 - LFITZGERALD@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 09/24/2024 | 09/30/2024 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| UTL | COMPLETE | 09/24/2024 | 09/30/2024 |
| Note: Released By: LARRY FITZGERALD - (386)286-2041 - LFITZGERALD@PALMCOASTGOV.COM | |||
| ZON | HOLD | 09/24/2024 | 09/25/2024 |
| Note: Held By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM Because of the reduced clarity of the numbers on the site plan, please indicate the total width of the proposed driveway - noting that it can only be 36' wide. |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| ADJUSTMENT 10% | (¤3.00) | 10/01/2024 |
| ADMINISTRATIVE RESIDENTIAL | ¤30.00 | 10/01/2024 |
| SW ENG INSPECTION 40 | ¤40.00 | 10/01/2024 |
| SW ENG PRE APRON | ¤30.00 | 10/01/2024 |
| SW ENG RES REVIEW 200 | ¤200.00 | 10/01/2024 |
| SITE PLAN 15 | ¤15.00 | 10/01/2024 |
| SW ENG REINSPECTION 20 | ¤20.00 | |
| Fees | Total Due: ¤20.00 | Total Paid: ¤312.00 |