I want to search for...

Permit #2024100322

Permit Details

Status: COED

Parcel Id: 07-11-31-7010-00040-0030
GARAGE: 602 sqft
OPENED PORCH (WITH ROOF) : 237 sqft
CONDITIONED SPACE: 2336 sqft
Total Square Footage: 3175 sqft
Block: 00040
Subdivision: -
Job Phone: 844-885-8913
Location Address: 33 FERBER LN
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 10/28/2024
NOC: RECORDED
Applicant name: SIMON DALE VANWAGENEN
Owner: LGI HOMES - FLORIDA LLC

Address

1450 LAKE ROBBINS DRIVE

THE WOODLANDS, TX 77380

Address

STE 430

THE WOODLANDS, TX 77380

Lot: 0030
Contracted Stated Job Value: ¤225,243.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

LGI HOMES-FLORIDA LLC
Status Location Address State License Number Phone
ACTIVE

2304 SPRING HILL CT

TAMPA, FL 33602

CBC1257972 (Exp: 08/31/2026) 904-451-8258

Sub Contractors

TERRY BRICE DICKERSON
Status Location Address State License Number Phone
ACTIVE

4300 ST JOHN'S PARKWAY

ALPHARETTA, GA 30009

CCC1326209 (Exp: 08/31/2026) 407-548-6733
CHRISTOPHER DENNIS O'CONNER
Status Location Address State License Number Phone
ACTIVE

240 N LAKE CUNNINGHAM AVE

JACKSONVILLE, FL 32257

ER13015361 (Exp: 08/31/2026) 904-540-0858
BRETT CHRISTIAN GIBSON
Status Location Address State License Number Phone
ACTIVE

250 SEGOVIA RD

ST AUGUSTINE, FL 32086

CAC1818423 (Exp: 08/31/2026) 904-229-8131
PAUL ERIC FORSTER
Status Location Address State License Number Phone
ACTIVE

6114 GOODMAN RD

JACKSONVILLE, FL 32244

CFC1429261 (Exp: 08/31/2026) 904-647-1820

Inspection History

Type Request Date Result Inspector
BLD - BUILDING FINAL 03/31/2025 FINAL APPROVED HCAMACHO
BLD - BUILDING FINAL 03/27/2025 Disapproved - NO FEE CVANSTRAHLEN
Note: Please fix items before next inspection #1-6. Heat strips not marked for AH FBCR M1303.1 #2-refrigerator and microwave need a GFCI breaker
ROW - FINAL APRON (AFTER POUR) 03/25/2025 APPROVED PFLANAGAN
Note: At the time of the inspection, all minimum city requirements were met. The builder's responsible for ensuring that nothing changes after this Inspection is approved.
ROW - STORMWATER FINAL 03/25/2025 APPROVED PFLANAGAN
Note: CORRECTION MADE ---------------------------------------------------------------- THE SOD ON THE RIGHT NEEDS TO MATCH ADJACENT LOT GRADE TALKED WITH PHIL AND HE STATED IT WILL BE DONE BEFORE ROW FINAL INSPECTION
U -UTILITY RESIDENTIAL FINAL 03/24/2025 FINAL APPROVED LFITZGERALD
U-CROSS CONNECTION 03/24/2025 APPROVED - AS NOTED LFITZGERALD
Note: irr meter with PVB-no cc
ROW- FINAL SURVEY/GRADING CERTIFICATION 03/20/2025 APPROVED PFLANAGAN
Note: FINAL SURVEY MEETS CITYS STANDARDS
ROW FIELD SURVEY /GRADING CERTIFICATION 03/20/2025 APPROVED - AS NOTED PFLANAGAN
Note: THE SOD ON THE RIGHT NEEDS TO MATCH ADJACENT LOT GRADE TALKED WITH PHIL AND HE STATED IT WILL BE DONE BEFORE ROW FINAL INSPECTION
ELECTRIC - EARLY POWER 03/07/2025 APPROVED - AS NOTED JSTEWART
Note: *** NOTES ADDED BY JSTEWART 3/7/2025 10:25:45 AM *** Please relocate surge Protection to the service equipment (Main disconnect) prior to Final. NEC 230.67
ROW- PRE-APRON (PRE-POUR) 02/13/2025 APPROVED PFLANAGAN
Note: IT'S YOUR RESPONSIBILITY TO CHECK THE CULVERT ELEVATIONS BEFORE POURING CONCRETE. ALL CONCRETE NEEDS TO BE A MINIMUM OF 3000PSI WITH FIBER OR WITH METAL MESH IN THE CONCRETE TO MEET ALL CITY'S STANDARDS. At the time of the inspection all minimum city requirements were met. It is the builders and the homowners responsibility to ensure that nothing changes after this Inspection is approved. It will not be on the city if any changes after this inspection.
INSULATION 01/30/2025 APPROVED HCAMACHO
Note: 1/29/2025 - PREVIOUS INSPECTION NOTES A/C Registers missing seal.
GRAVITY SEWER TEST 01/29/2025 APPROVED - AS NOTED MGIBSON
Note: Inspector Notes from Inspection 2060 NEED REVISION FOR FLLORR PLAN. SHOWS GARAGE LEFT AND WHAT IS ON SITE IS GARAGE LEFT THIS WAS A VIRTUAL INSPECTION
SEWER TIE IN 01/29/2025 APPROVED - AS NOTED MGIBSON
Note: Inspector Notes from Inspection 2075 Inspector Notes from Inspection 2060 NEED REVISION FOR FLLORR PLAN. SHOWS GARAGE LEFT AND WHAT IS ON SITE IS GARAGE LEFT THIS WAS A VIRTUAL INSPECTION Inspector Notes from Inspection 2060 NEED REVISION FOR FLLORR PLAN. SHOWS GARAGE LEFT AND WHAT IS ON SITE IS GARAGE LEFT THIS WAS A VIRTUAL INSPECTION
INSULATION 01/29/2025 Disapproved - NO FEE HCAMACHO
Note: A/C Registers missing seal.
INSULATION 01/28/2025 CANCELLED BY APPLICANT WEB
LATH/BRICK/ WATER BARRIER 01/27/2025 APPROVED HCAMACHO
ALL ROUGH 01/24/2025 APPROVED - AS NOTED HCAMACHO
Note: 1. Bath fans need 2nd mechanical attacment. FBCR M1604.4.1 2. Swing door in the rear has more then 1/4" gap on top and missing screws. FBCR 609.1 3. A/C Registers missing seal.R402.4.1.1 4. Attic light/service outlet needs to be moved do to A/C being in the way. 5. Need new attic access location due to A/C being in the way.FBC [A]107.4 6. Revise Product approval sheet for windows and Slider. FBC [A]107.4 *Will check at Insualtion*
ELECTRIC-TUG 01/15/2025 APPROVED HCAMACHO
ROOF VALLEY & METAL 01/06/2025 APPROVED HCAMACHO
WALL SHEATHING 01/02/2025 APPROVED HCAMACHO
ROOF SHEATHING / BRACES/TIES/DOWN CELL 01/02/2025 APPROVED - AS NOTED HCAMACHO
Note: 1. Header beam in the rear porch is missing the straps for tied down. 2. Header in the front porch is missing straps for tie down and missing load path from knee wall to bearing posts.
ROOF VALLEY & METAL 01/02/2025 CANCELLED BY APPLICANT HCAMACHO
Note: Not ready
TIE BEAM / LINTEL 12/18/2024 CANCELLED BY INSPECTOR MCONTRYMAN
FOUND SURVEY APPROVED (OFFICE) 12/17/2024 APPROVED LSALYERDS
MONOLITHIC SLAB 12/09/2024 APPROVED HCAMACHO
PLUMBING 1ST ROUGH UNDERGROUND 12/06/2024 APPROVED - AS NOTED MGIBSON
Note: NEED REVISION FOR FLLORR PLAN. SHOWS GARAGE LEFT AND WHT IS ON SITE IS GARAGE LEFT
GEOTECHNICAL REPORT APPROVAL (OFFICE USE) 12/05/2024 APPROVED JMUNSON
WATER METER INSTALLATION REQUEST 11/01/2024 APPROVED CBOWERMASTER
WILDLIFE CHECK - ENVIRONMENTAL 10/08/2024 APPROVED DRODRIGUEZ

Review History

Department Status Date In Date Out
MECH COMPLETE 03/12/2025 03/13/2025
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
BLD COMPLETE 01/28/2025 01/29/2025
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
MECH COMPLETE 01/27/2025 01/28/2025
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
MECH HOLD 01/22/2025 01/27/2025
Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Energy Calcs need to be signed by the owner/ owner agent below the preparer per R103.1.1.2 FBC Energy Conservation 2023 8Th edition
ENGIN1 COMPLETE 12/13/2024 12/17/2024
Note: Released By: LEVI SALYERDS - - LSALYERDS@PALMCOASTGOV.COM After careful consideration, City Administration has waived the 0.2’ tolerance for this permit. No other requirements have been exceeded or waived.
ZON COMPLETE 12/13/2024 12/13/2024
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
BLD COMPLETE 12/06/2024 12/10/2024
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
ZON COMPLETE 12/06/2024 12/06/2024
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
BLD COMPLETE 12/02/2024 12/05/2024
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
ZON COMPLETE 10/23/2024 10/23/2024
Note: Released By: LIBBY RAYBURN - - LRAYBURN@PALMCOASTGOV.COM
SW1 COMPLETE 10/23/2024 10/23/2024
Note: Released By: JOHN HOWARD - - JHOWARD@PALMCOASTGOV.COM SW1 completed review is contingent on stormwater inspector's approval of the final survey. A failed final survey inspection and/or a revised site plan indicating any deviation from the approved site plan with significant change in drainage patterns and elevations negatively impacting neighboring lots, or the structure will result in a HOLD
ENGIN1 COMPLETE 10/23/2024 10/23/2024
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
SWALE COMPLETE 10/15/2024 12/04/2024
Note: Released By: LEVI SALYERDS - - LSALYERDS@PALMCOASTGOV.COM
BADMIN COMPLETE 10/08/2024 10/14/2024
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
BLD COMPLETE 10/08/2024 10/14/2024
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
CUSVC COMPLETE 10/08/2024 10/15/2024
Note: Released By: HALEIGH HAND - - HHAND@PALMCOASTGOV.COM
ELEC COMPLETE 10/08/2024 10/14/2024
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
ENGIN1 COMPLETE 10/08/2024 10/15/2024
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
GAS CANCEL 10/08/2024 10/09/2024
LOCATE COMPLETE 10/08/2024 10/09/2024
Note: Released By: CANDACE BOWERMASTER - - CBOWERMASTER@PALMCOASTGOV.COM
MECH COMPLETE 10/08/2024 10/09/2024
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
SW1 COMPLETE 10/08/2024 10/08/2024
Note: Released By: JOHN HOWARD - - JHOWARD@PALMCOASTGOV.COM SW1 completed review is contingent on stormwater inspector's approval of the final survey. A failed final survey inspection and/or a revised site plan indicating any deviation from the approved site plan with significant change in drainage patterns and elevations negatively impacting neighboring lots, or the structure will result in a HOLD
ZON HOLD 10/08/2024 10/09/2024
Note: Held By: MICHELLE RAMOS - (386)986-3780 - MRAMOS@PALMCOASTGOV.COM Site plan legal description missing map book #.
PLENV COMPLETE 10/08/2024 10/08/2024
Note: Released By: DYLAN RODRIGUEZ - - DRODRIGUEZ@PALMCOASTGOV.COM After action report was submitted and accepted by FWC meeting the requirements for 10.04.01 of the LDC. Staff suggests placing silt fence as soon as possible to prevent tortoise from moving into the lot. If any gopher tortoises are located in the future further coordination may be necessary. In future submittals, acceptance email for after action report is required to be submitted (GTT-24-01394).

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
PLAN REVIEW - REVISION ¤32.50 04/01/2025
CONNECTION FEES ¤1,187.26 10/28/2024
FC IMPACT FEE EMS ¤62.00 10/28/2024
IMPACT FEE FIRE ¤434.51 10/28/2024
FC IMPACT FEE LAW ENFORCEMENT ¤218.00 10/28/2024
FC IMPACT FEE LIBRARY ¤268.00 10/28/2024
IMPACT FEE PARKS ¤1,828.01 10/28/2024
IMPACT FEE SCHOOL ¤5,450.00 10/28/2024
IMPACT FEE TRANSPORTATION ¤1,862.00 10/28/2024
WATER -IRRIGATION INSPECTION ¤25.00 10/28/2024
WATER -IRRIGATION INSPECTION ¤25.00 10/28/2024
SURCHARGE FS 533.721 ¤14.28 10/28/2024
SURCHARGE - FS 468.631 ¤21.42 10/28/2024
SW ENG - FOUNDATION SURVEY ¤20.00 10/28/2024
SW ENG INSPECTION 80 ¤80.00 10/28/2024
SW ENG PRE APRON ¤30.00 10/28/2024
SW ENG - REVIEW 20 ¤20.00 10/28/2024
SW ENG RES REVIEW 200 ¤200.00 10/28/2024
SEWER INSPECTION ¤25.00 10/28/2024
SEWER CAPITAL FACILITY ¤6,120.52 10/28/2024
WATER CAPITAL FACILITY FEE ¤4,351.14 10/28/2024
SITE PLAN 30 ¤30.00 10/28/2024
WATER-METER ¤514.49 10/28/2024
WATER- TURN ON ¤25.00 10/28/2024
WATER- TURN ON ¤25.00 10/28/2024
ADJUSTMENT 10% (¤158.67) 10/28/2024
ADMINISTRATIVE RESIDENTIAL ¤30.00 10/28/2024
INSPECTION - RESIDENTIAL ¤1,212.75 10/28/2024
PLAN REVIEW - RESIDENTIAL ¤343.98 10/28/2024
Fees Total Due: ¤0.00 Total Paid: ¤24,297.19