I want to search for...

Permit #2024101006

Permit Details

Status: COED

Parcel Id: 07-11-31-7026-00630-0180
CONDITIONED SPACE: 1800 sqft
GARAGE: 410 sqft
OPENED PORCH (WITH ROOF) : 36 sqft
Total Square Footage: 2246 sqft
Block: 00630
Subdivision: 7026 -
Job Phone: 689-250-2429
Location Address: 3 PINTO LN
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 11/13/2024
NOC: RECORDED
Applicant name: RYAN M COURECH
Owner: A AND R-MERIDIAN REAL ESTATE DEVELOPMENT LLC

Address

688 N ORLANDO AVENUE

MAITLAND, FL 32751

Address

207

MAITLAND, FL 32751

Lot: 0180
Contracted Stated Job Value: ¤208,000.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN
Original Permit #: 2024010999

Contractor

MCH CONSTRUCTION LLC
Status Location Address State License Number Phone
INACTIVE

668 N ORLANDO AVE, STE 207

MAITLAND, FL 32751

CBC1262898 (Exp: 08/31/2026) 407-602-8257

Sub Contractors

JONATHAN M PEARSON
Status Location Address State License Number Phone Fax
ACTIVE

209 N FORSYTH ST

BUNNELL, FL 32110

CFC1425941 (Exp: 08/31/2026) 386-597-0944 386-437-4996
DANA SUE COOLEY
Status Location Address State License Number Phone
INACTIVE

PO BOX 1718

FLAGLER BEACH, FL 32136

CCC1333449 (Exp: 08/31/2026) 904-535-1680
JOSEPH C WRIGHT
Status Location Address Mailing Address State License Number Phone Fax
ACTIVE

15 HARGROVE LANE

PALM COAST, FL 32137

UNIT 3 D

PALM COAST, FL 32137

EC13003278 (Exp: 08/31/2026) 386-447-9644 386-447-9633
DUSTIN ARCHER
Status Location Address State License Number Phone
ACTIVE

2785 WRIGHTS ROAD SUITE 1133

OVIEDO, FL 32765

CMC1251099 (Exp: 08/31/2026) 407-391-1145

Inspection History

Type Request Date Result Inspector
ROW - STORMWATER FINAL 09/02/2025 APPROVED TPOLACEK
Note: AT THE TIME OF THE INSPECTION, ALL MINIMUM CITY REQUIREMENTS WERE MET. NIETHER THE INSPECTOR NOR THE CITY IS RESPONSIBLE IF, FOR WHATEVER REASON, SITE CONDITIONS CHANGE OVER TIME AFTER THE INSPECTION. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED Inspector Notes from Inspection 9272 08/28/25 TPOLACEK**** HOT PATCH IS NOT COMPLETED AT THIS TIME. BUILDER HAS NOT REQUESTED THE FINAL ROW SO I WILL APPROVE THE AFTER POUR AS NOTED AND WAIT FOR FINAL ROW FOR HOT PATCH. CULVERT IS FILLED WITH WATER AT THIS TIME AS WELL SO AT THE TIME OF FINAL ROW INSPECTOR SHALL CHECK CULVERT IS CLEAR OF DEBRIS AND OVER POUR CONCRETE.
ROW - FINAL APRON (AFTER POUR) 08/28/2025 APPROVED - AS NOTED TPOLACEK
Note: 08/28/25 TPOLACEK**** HOT PATCH IS NOT COMPLETED AT THIS TIME. BUILDER HAS NOT REQUESTED THE FINAL ROW SO I WILL APPROVE THE AFTER POUR AS NOTED AND WAIT FOR FINAL ROW FOR HOT PATCH. CULVERT IS FILLED WITH WATER AT THIS TIME AS WELL SO AT THE TIME OF FINAL ROW INSPECTOR SHALL CHECK CULVERT IS CLEAR OF DEBRIS AND OVER POUR CONCRETE.
ROW- FINAL SURVEY/GRADING CERTIFICATION 08/27/2025 APPROVED TPOLACEK
ROW FIELD SURVEY /GRADING CERTIFICATION 08/27/2025 APPROVED TPOLACEK
Note: AT THE TIME OF THE INSPECTION, ALL MINIMUM CITY REQUIREMENTS WERE MET. NIETHER THE INSPECTOR NOR THE CITY IS RESPONSIBLE IF, FOR WHATEVER REASON, SITE CONDITIONS CHANGE OVER TIME AFTER THE INSPECTION. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED
BLD - BUILDING FINAL 08/25/2025 Approval - Private Provider PPROVIDER
ROW- PRE-APRON (PRE-POUR) 07/30/2025 APPROVED TPOLACEK
Note: AT THE TIME OF THE INSPECTION CULVERT PIPE IS GOOD IS READY TO POUR, IF RAIN PLEASE, BUILDER SHOULD DOUBLE CHECK CULVERT ELEVATIONS MAKE SURE TO USE 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE (FRC) DRAWING 300,E RESIDENTIAL CULVERT DETAIL BEFORE POURING. CONTRACTORS WILL BE NOTIFIED WHEN TICKETS WILL BE REQUIRED WITH AN EMAIL BLAST.THE FOLLOWING IS CURRENTLY FOR INFORMATION ONLY: TICKET OF CONCRETE MIX DESIGN SHALL BE UPLOADED INTO PERMIT PORTAL. 8.a. IF FIBERGLASS OPTION IS USED, DOCUMENTATION OF THE ( FRC) CONTAINING THE FIBERGLASS MUST BE ATTACHED TO THE PERMIT PRIOR TO REQUESTING AN AFTER-POUR INSPECTION. 8.b. IF MESH OPTION IS USED, IT SHALL BE IN PLACE AT THE TIME OF THE PRE-POUR.
U - SEWER TIE IN 07/15/2025 APPROVED MGIBSON
U-CROSS CONNECTION 07/15/2025 APPROVED - AS NOTED LFITZGERALD
Note: noirr-no cc
GRAVITY SEWER TEST 07/15/2025 Approval - Private Provider PPROVIDER
PEP TANK INSTALLATION REQUEST 06/13/2025 APPROVED CBOWERMASTER
WALL SHEATHING 05/30/2025 Approval - Private Provider PPROVIDER
ROOF SHEATHING / BRACES/TIES/DOWN CELL 05/30/2025 Approval - Private Provider PPROVIDER
ROOF VALLEY & METAL 05/28/2025 Approval - Private Provider PPROVIDER
INSULATION 05/28/2025 Approval - Private Provider PPROVIDER
ALL ROUGH 05/28/2025 Approval - Private Provider PPROVIDER
ELECTRIC - EARLY POWER 05/13/2025 Approval - Private Provider PPROVIDER
GRAVITY SEWER TEST 04/29/2025 CANCELLED BY APPLICANT WEB
U-CROSS CONNECTION 04/29/2025 CANCELLED BY APPLICANT WEB
U - SEWER TIE IN 04/29/2025 CANCELLED BY APPLICANT WEB
TIE BEAM / LINTEL 04/23/2025 Approval - Private Provider PPROVIDER
LATH/BRICK/ WATER BARRIER 04/22/2025 Approval - Private Provider PPROVIDER
MONOLITHIC SLAB 04/21/2025 Approval - Private Provider PPROVIDER
MONOLITHIC SLAB 04/21/2025 Approval - Private Provider PPROVIDER
FOUND SURVEY APPROVED (OFFICE) 02/06/2025 APPROVED TBAKER
MONOLITHIC SLAB 01/21/2025 CANCELLED BY APPLICANT WEB
PLUMBING 1ST ROUGH UNDERGROUND 01/08/2025 Approval - Private Provider PPROVIDER
GEOTECHNICAL REPORT APPROVAL (OFFICE USE) 01/06/2025 APPROVED JMUNSON
WATER METER INSTALLATION REQUEST 11/27/2024 APPROVED CBOWERMASTER

Review History

Department Status Date In Date Out
BADMIN INFORMATION 08/28/2025 08/28/2025
Note: Marked INFORMATION By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM
BADMIN HOLD 08/27/2025 08/27/2025
Note: Held By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM No inspection codes provided
MECH COMPLETE 08/06/2025 08/06/2025
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
MECH COMPLETE 06/13/2025 06/17/2025
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
BADMIN INFORMATION 05/28/2025 05/28/2025
Note: Marked INFORMATION By: LIBBY RAYBURN - - LRAYBURN@PALMCOASTGOV.COM wrong code on the inspecton report for a lintel
BADMIN INFORMATION 04/21/2025 04/21/2025
Note: Marked INFORMATION By: LIBBY RAYBURN - - LRAYBURN@PALMCOASTGOV.COM Wrong File Name Uploaded file name was not correct - Example: Site plan=site plan (do not add anything to the file names like numbers.)
ENGIN1 COMPLETE 02/06/2025 02/06/2025
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
ZON COMPLETE 02/06/2025 02/06/2025
Note: Released By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM
BLD COMPLETE 12/30/2024 01/06/2025
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
MECH COMPLETE 12/20/2024 12/23/2024
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
BLD HOLD 12/16/2024 12/19/2024
Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM This was deferred submittal of geotech. Submit preliminary report
BLD HOLD 12/09/2024 12/13/2024
Note: Held By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM 1. Submit certification letter and density reports. Must be digitally signed and sealed.
BLD COMPLETE 11/05/2024 11/13/2024
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
BADMIN COMPLETE 10/29/2024 11/05/2024
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
BLD HOLD 10/29/2024 11/05/2024
Note: Held By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM 2. product approval sheet is not filled out completely. 3. Need to update revision numbers.
LOCATE COMPLETE 10/23/2024 10/29/2024
Note: Released By: CANDACE BOWERMASTER - - CBOWERMASTER@PALMCOASTGOV.COM
SW1 COMPLETE 10/23/2024 10/23/2024
Note: Released By: JOHN HOWARD - - JHOWARD@PALMCOASTGOV.COM SW1 completed review is contingent on stormwater inspector's approval of the final survey. A failed final survey inspection and/or a revised site plan indicating any deviation from the approved site plan with significant change in drainage patterns and elevations negatively impacting neighboring lots, or the structure will result in a HOLD
ZON COMPLETE 10/23/2024 10/25/2024
Note: Released By: LIBBY RAYBURN - - LRAYBURN@PALMCOASTGOV.COM
MECH COMPLETE 10/23/2024 10/29/2024
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
BADMIN HOLD 10/23/2024 10/29/2024
Note: Held By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM 1. Need shop drawing approval stamp on truss packet or truss layout. 2. product approval sheet is not filled out completely. 3. Need to update revision numbers. 4. Submit truss layout
CUSVC COMPLETE 10/23/2024 10/24/2024
Note: Released By: HALEIGH HAND - - HHAND@PALMCOASTGOV.COM
ENGIN1 COMPLETE 10/23/2024 10/23/2024
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
BADMIN INFORMATION 10/23/2024 10/23/2024
Note: Marked INFORMATION By: BARBIE BEMBRY - (386)986-3780 - BUILDINGDIVISION@PALMCOASTGOV.COM For future private provider submittals. The owner name on the priviate provider forms need to match the legal owners name in every area where the owner is identified. Example, A and R Meridian .... is the owner. Not MCH or other names that were entered in as owners in the 'fee owner' name area and signature owner name area. The certificate of insurance from the private provider should have the City of Palm Coast lsited as the certificate holder. Certificates holders are notified if there is a lapse in insurance.
SWALE COMPLETE 10/23/2024 12/06/2024
Note: Released By: LEVI SALYERDS - - LSALYERDS@PALMCOASTGOV.COM

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
PLAN REVIEW - REVISION ¤32.50 09/02/2025
CONNECTION FEES ¤1,187.26 11/13/2024
FC IMPACT FEE EMS ¤62.00 11/13/2024
IMPACT FEE FIRE ¤434.51 11/13/2024
FC IMPACT FEE LAW ENFORCEMENT ¤218.00 11/13/2024
FC IMPACT FEE LIBRARY ¤268.00 11/13/2024
IMPACT FEE PARKS ¤1,828.01 11/13/2024
IMPACT FEE SCHOOL ¤5,450.00 11/13/2024
IMPACT FEE TRANSPORTATION ¤1,862.00 11/13/2024
WATER -IRRIGATION INSPECTION ¤25.00 11/13/2024
SURCHARGE FS 533.721 ¤3.43 11/13/2024
SURCHARGE - FS 468.631 ¤5.14 11/13/2024
SW ENG - FOUNDATION SURVEY ¤20.00 11/13/2024
SW ENG INSPECTION 80 ¤80.00 11/13/2024
SW ENG PRE APRON ¤30.00 11/13/2024
SW ENG - REVIEW 20 ¤20.00 11/13/2024
SW ENG RES REVIEW 200 ¤200.00 11/13/2024
SEWER CREDIT (¤2,089.25) 11/13/2024
SEWER INSPECTION ¤25.00 11/13/2024
SEWER CAPITAL FACILITY ¤6,120.52 11/13/2024
WATER CREDIT (¤620.28) 11/13/2024
WATER CAPITAL FACILITY FEE ¤4,351.14 11/13/2024
SITE PLAN 30 ¤30.00 11/13/2024
WATER- TURN ON ¤25.00 11/13/2024
ADJUSTMENT 50% (¤342.60) 11/13/2024
ADMINISTRATIVE RESIDENTIAL ¤30.00 11/13/2024
INSPECTION - RESIDENTIAL ¤572.00 11/13/2024
PLAN REVIEW - APPROVED MASTER ¤83.20 11/13/2024
Fees Total Due: ¤0.00 Total Paid: ¤19,910.58