I want to search for...
Permit #2024110720
Permit Details
Status: FINAL
| Parcel Id: 06-12-31-5815-00000-06B0 |
| Block: 00000 |
| Subdivision: 5815 - |
| Job Phone: 904-305-7055 |
| Location Address: 15 MARKET AVE |
| Type: CSD - COMMERCIAL SITE DEVELOPMENT |
| Issue Date: 01/06/2025 |
| NOC: Unknown |
| Applicant name: TIMOTHY WAYNE YOUNG |
| Owner: GHM PROPERTY SOLUTIONS LLC |
|
Address 8411 SOUTHSIDE BLVD JACKSONVILLE, FL 32256 |
|
Address SUITE 100 JACKSONVILLE, FL 32256 |
| Lot: 06B0 |
| Job Description: SITE WORK: THE LEARNING EXPERIENCE DAY CARE FACILITY |
| Type: CN |
Contractor
TIM YOUNG CONSTRUCTION INC
| Status | Location Address | State License Number | Phone |
| ACTIVE |
9310 OLD KINGS RDS SUITE 1702 , |
CGC055192 (Exp: 08/31/2026) | 904-305-7055 |
Inspection History
| Type | Request Date | Result | Inspector |
| MAINT BOND ACCEPTANCE (OFFICE) | 04/23/2026 | APPROVED | DRAMIREZ |
| CLOSE OUT DOCUMENTS | 04/14/2026 | APPROVED | DRAMIREZ |
| U - UTILITY COMMERCIAL FINAL | 04/14/2026 | FINAL APPROVED | LFITZGERALD |
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 04/07/2026 | APPROVED - AS NOTED | LFITZGERALD |
| Note: 3/25/2026 2:02:55 PM- PREVIOUS INSPECTION NOTES 3/25/26 STRUCTURE A-4.1, A-5.1, A-5, AND THE EXISTING INLET THAT WAS CONNECTED TO NEED TO BE CLEANED. THE VACANT PROPERTY TO THE EAST NEEDS TO BE SEEDED AND THE ROW SODDED. PLEASE INFORM INSPECTOR WHEN THESE ITEMS HAVE BEEN COMPLETED. 2/17/2026 11:37:16 AM- PREVIOUS INSPECTION NOTES 2/17/26 EROSION CONTROL MEASURES HAVE BEEN RE-INSTALLED AND ROAD CLEANED. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO MAINTAIN THE SITE PER SWPPP. FOLLOW UP INSPECTION NEXT MONTH. 2/13/2026 - PREVIOUS INSPECTION NOTES 2/13/26 A STOP WORK ORDER HAS BEEN PLACED ON THIS PROPERTY UNTIL SILT FENCE IS RE-ESTABLISHED AND THE DIRT ON MARKET AVE HAS BEEN REMOVED. ONLY THE APPROVED ENTRACE SHALL BE UTILIZED. 2/12/2026 - PREVIOUS INSPECTION NOTES 2/12/26 SILT FENCE HAS NOT BEEN RE-INSTALLED PER SWPPP. SHALL BE RE-INSTALLED OR STOP WORK ORDER WILL BE PLACED ON SITE. FOLLOW UP INSPECTION FRIDAY 2/13/26. 2/10/2026 - PREVIOUS INSPECTION NOTES 2/10/26 SILT FENCE HAS NOT BEEN RE-INSTALLED PER SWPPP. FENCE SHALL BE RE-INSTALLED, FOLLOW UP INSPECTION WEDNESDAY 2/11/26. 2/4/2026 - PREVIOUS INSPECTION NOTES 2/4/26 SILT FENCE SHALL BE RE-INSTALLED PER SWPPP. FOLLOW UP INSPECTION FRIDAY 2/6/26. 11/13/2025 - PREVIOUS INSPECTION NOTES 11/13/25 SILT FENCE NEEDS TO BE RE-ESTABLISHED ON THE NORTH AND WEST PROPERTY LINES. 6/10/2025 - PREVIOUS INSPECTION NOTES 6/10/25 EROSION CONTROL MEASURES ARE IN PLACE AND FUNCTIONING. FOLLOW UP INSPECTION NEXT MONTH. all drainage structures that Jordan required now free of built up soils | |||
| FDEP WATERMAIN CLEARANCE | 04/07/2026 | FINAL APPROVED | BHAINES |
| Note: Inspector Notes from Inspection 9245 3/25/2026 - PREVIOUS INSPECTION NOTES required to sod ROW/SEED STRAW REMAINING AREAS IN VACANT LOT NEXT DOOR all completed now | |||
| IRRIGATION AFFIDAVIT | 04/07/2026 | APPROVED | RPICATAGI |
| Note: 3/25/2026 4:53:03 PM- PREVIOUS INSPECTION NOTES Irrigation Affidavit has not been received (uploaded to portal) | |||
| PLANNING - OFFICE USE - FINAL AS-BUILT SURVEY | 04/07/2026 | APPROVED | DRAMIREZ |
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | 04/07/2026 | FINAL APPROVED | BHAINES |
| Note: Inspector Notes from Inspection 9245 3/25/2026 - PREVIOUS INSPECTION NOTES required to sod ROW/SEED STRAW REMAINING AREAS IN VACANT LOT NEXT DOOR all completed now | |||
| U-ROW FINAL | 04/01/2026 | APPROVED - AS NOTED | LFITZGERALD |
| Note: 3/25/2026 - PREVIOUS INSPECTION NOTES required to sod ROW/SEED STRAW REMAINING AREAS IN VACANT LOT NEXT DOOR all completed now | |||
| U-ROW FINAL | 03/25/2026 | PARTIALLY APPROVED | LFITZGERALD |
| Note: required to sod ROW/SEED STRAW REMAINING AREAS IN VACANT LOT NEXT DOOR | |||
| UC-TRAF - FINAL (SIGN/PAVEMENT MARKING) | 03/25/2026 | FINAL APPROVED | LFITZGERALD |
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 03/25/2026 | PARTIALLY APPROVED | JMYERS |
| Note: 3/25/26 STRUCTURE A-4.1, A-5.1, A-5, AND THE EXISTING INLET THAT WAS CONNECTED TO NEED TO BE CLEANED. THE VACANT PROPERTY TO THE EAST NEEDS TO BE SEEDED AND THE ROW SODDED. PLEASE INFORM INSPECTOR WHEN THESE ITEMS HAVE BEEN COMPLETED. 2/17/2026 11:37:16 AM- PREVIOUS INSPECTION NOTES 2/17/26 EROSION CONTROL MEASURES HAVE BEEN RE-INSTALLED AND ROAD CLEANED. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO MAINTAIN THE SITE PER SWPPP. FOLLOW UP INSPECTION NEXT MONTH. 2/13/2026 - PREVIOUS INSPECTION NOTES 2/13/26 A STOP WORK ORDER HAS BEEN PLACED ON THIS PROPERTY UNTIL SILT FENCE IS RE-ESTABLISHED AND THE DIRT ON MARKET AVE HAS BEEN REMOVED. ONLY THE APPROVED ENTRACE SHALL BE UTILIZED. 2/12/2026 - PREVIOUS INSPECTION NOTES 2/12/26 SILT FENCE HAS NOT BEEN RE-INSTALLED PER SWPPP. SHALL BE RE-INSTALLED OR STOP WORK ORDER WILL BE PLACED ON SITE. FOLLOW UP INSPECTION FRIDAY 2/13/26. 2/10/2026 - PREVIOUS INSPECTION NOTES 2/10/26 SILT FENCE HAS NOT BEEN RE-INSTALLED PER SWPPP. FENCE SHALL BE RE-INSTALLED, FOLLOW UP INSPECTION WEDNESDAY 2/11/26. 2/4/2026 - PREVIOUS INSPECTION NOTES 2/4/26 SILT FENCE SHALL BE RE-INSTALLED PER SWPPP. FOLLOW UP INSPECTION FRIDAY 2/6/26. 11/13/2025 - PREVIOUS INSPECTION NOTES 11/13/25 SILT FENCE NEEDS TO BE RE-ESTABLISHED ON THE NORTH AND WEST PROPERTY LINES. 6/10/2025 - PREVIOUS INSPECTION NOTES 6/10/25 EROSION CONTROL MEASURES ARE IN PLACE AND FUNCTIONING. FOLLOW UP INSPECTION NEXT MONTH. | |||
| UC-SUBSTANTIAL WALK-THRU | 03/25/2026 | APPROVED - AS NOTED | LFITZGERALD |
| Note: Inspector Notes from Inspection 9235 2/19/2026 - PREVIOUS INSPECTION NOTES perma-curb-Bob now on site installing D curb thoughout parking area all curb including piece work on market where asphalt patch was constructed storm ,paving, drainage walk thru-some drainage issues to be corrected and reinspected by Jordan/1 8inx8in area where needs asphalt over the exposed base-jay informed/vacant lot that was heavily used needs sod along ROW and seed/straw remaining areas | |||
| UC-FINAL SITE INSPECTION | 03/25/2026 | FINAL APPROVED | LFITZGERALD |
| LANDSCAPE PRE-CONSTRUCTION MEETING | 03/25/2026 | APPROVED | RPICATAGI |
| IRRIGATION AFFIDAVIT | 03/25/2026 | Disapproved - NO FEE | RPICATAGI |
| Note: Irrigation Affidavit has not been received (uploaded to portal) | |||
| LDSC- LANDSCAPE FINAL | 03/25/2026 | FINAL APPROVED | RPICATAGI |
| UC- PRELIMINARY AS-BUILTS | 03/24/2026 | APPROVED - AS NOTED | LFITZGERALD |
| Note: Inspector Notes from Inspection 9235 2/19/2026 - PREVIOUS INSPECTION NOTES perma-curb-Bob now on site installing D curb thoughout parking area all curb including piece work on market where asphalt patch was constructed as -blts required to be on approved construction plans-red lined-this format to be submitted to city portal/need to call out existing storm drain that site drainage tied into | |||
| LDSC- LANDSCAPE / IRRIGATION AS-BUILT | 03/23/2026 | APPROVED | RPICATAGI |
| Note: 3/13/2026 9:06:42 AM- PREVIOUS INSPECTION NOTES UNDERSIZED PLANTS: --------------------------------------------- 77 Walters Viburnum at north buffer line, many are undersized - check size and replace with larger plants to meet specified size as required 5 Bottlebrush trees specified at 8 feet ht., None reach 8 feet ht. Remove and replace with 8 feet ht bottlebrush trees 10 Dahoon Holly specified at 10 feet ht. All are undersized, remove and replace with10' ht Dahoon Hollies 51 VO- Fragrant Viburnum specified at 48" ht. at East Buffer/Frontage (alternate viburnum species was requested and approved) However, 51 Podocarpus (species not approved) were planted with only a portion (40-60%) reaching full specified ht. Undersized plants (less than 48" ht.,) shall be removed and replaced with full size (48" ht) plants of same species - contractor shall coordinate possible alternate species with city landscape architect ,to find available appropriate available nursery stock. 5 East Paltka Holly @ 12 feet ht. shown on approved plan at rear of site. 5 Cedar trees below 8 feet ht are planted. Contractor shall remove and replace with specified species and size. Un-screened above-ground structure that require screening per LCD Sec 11.03.01 H ------------------------------------------------------------------------------------------------------------------------------------------- Rear of dumpster enclosure needs to be screened Backflow Preventer apparatus needs to be screened Freestanding electric meter See Table 11-4 for MEDIUM SCREEN/ shrub size (30" ht. space at 4 feet max. in 7 gallon containers) MULCH DEFICIENCY - Per approved plans, 3" thick layer of mulch is required in all planting areas. I inspection shows only 1" thick layer. Contractor to add mulch to meet spec requirement throughout project regardless of small plant size in parking islands DOCUMENTS REQUIRED -------------------------------------------------------- Landscape As Built plan signed and sealed by FLLORIDA RLA Irrigation As Built plan signed and sealed by FLORIDA RLA Irrigation Affidavit signed and sealed by FLORIDA RLA OR CERTIFIED IRRIGATION PROFESSIONAL | |||
| LDSC-IRRIGATION FINAL | 03/23/2026 | CANCELLED BY APPLICANT | WEB |
| LDSC-IRRIGATION FINAL | 03/23/2026 | APPROVED | RPICATAGI |
| LDSC- LANDSCAPE / IRRIGATION AS-BUILT | 03/12/2026 | Disapproved - NO FEE | RPICATAGI |
| Note: UNDERSIZED PLANTS: --------------------------------------------- 77 Walters Viburnum at north buffer line, many are undersized - check size and replace with larger plants to meet specified size as required 5 Bottlebrush trees specified at 8 feet ht., None reach 8 feet ht. Remove and replace with 8 feet ht bottlebrush trees 10 Dahoon Holly specified at 10 feet ht. All are undersized, remove and replace with10' ht Dahoon Hollies 51 VO- Fragrant Viburnum specified at 48" ht. at East Buffer/Frontage (alternate viburnum species was requested and approved) However, 51 Podocarpus (species not approved) were planted with only a portion (40-60%) reaching full specified ht. Undersized plants (less than 48" ht.,) shall be removed and replaced with full size (48" ht) plants of same species - contractor shall coordinate possible alternate species with city landscape architect ,to find available appropriate available nursery stock. 5 East Paltka Holly @ 12 feet ht. shown on approved plan at rear of site. 5 Cedar trees below 8 feet ht are planted. Contractor shall remove and replace with specified species and size. Un-screened above-ground structure that require screening per LCD Sec 11.03.01 H ------------------------------------------------------------------------------------------------------------------------------------------- Rear of dumpster enclosure needs to be screened Backflow Preventer apparatus needs to be screened Freestanding electric meter See Table 11-4 for MEDIUM SCREEN/ shrub size (30" ht. space at 4 feet max. in 7 gallon containers) MULCH DEFICIENCY - Per approved plans, 3" thick layer of mulch is required in all planting areas. I inspection shows only 1" thick layer. Contractor to add mulch to meet spec requirement throughout project regardless of small plant size in parking islands DOCUMENTS REQUIRED -------------------------------------------------------- Landscape As Built plan signed and sealed by FLLORIDA RLA Irrigation As Built plan signed and sealed by FLORIDA RLA Irrigation Affidavit signed and sealed by FLORIDA RLA OR CERTIFIED IRRIGATION PROFESSIONAL | |||
| UC-MOT MAINTENANCE OF TRAFFIC | 03/09/2026 | APPROVED - AS NOTED | LFITZGERALD |
| Note: Flaging for lane closures on Market for thermo striping the asphalt patch | |||
| UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) | 03/09/2026 | APPROVED | LFITZGERALD |
| Note: 1/8/2026 - PREVIOUS INSPECTION NOTES 1/7/2026 - PREVIOUS INSPECTION NOTES 12/1/2025 - PREVIOUS INSPECTION NOTES 11/18/2025 - PREVIOUS INSPECTION NOTES 11/12/2025 - PREVIOUS INSPECTION NOTES 11/7/2025 - PREVIOUS INSPECTION NOTES compact soils in front sidewalk and 4in required from edge to edge-correct/remove cold conrete left over in side bldg sidewalk-all conrete should be fresh and consistent left and right sides now poured-front sidewalk satisfactory for concrete but still awaiting final engineering for ADA ramps east side parking from building corner southward now front sidewalk poured Sidewalk in ROW along Market Ave-half way from west property line 5FT wide along Market ROW last section middle to east property line/6ft connection to already placed sidewalk | |||
| UROW- CURBING & GUTTER | 03/09/2026 | APPROVED - AS NOTED | LFITZGERALD |
| Note: 2/19/2026 - PREVIOUS INSPECTION NOTES perma-curb-Bob now on site installing D curb thoughout parking area all curb including piece work on market where asphalt patch was constructed | |||
| U - SEWER TIE IN | 03/09/2026 | APPROVED | BWRIGHT |
| BLD- ADA PARKING | 03/06/2026 | APPROVED | KSANDOE |
| BLD- ADA SIGNAGECONTROL | 03/06/2026 | APPROVED | KSANDOE |
| BLD - ADA SIGNAGE- INFOR/DIRECT | 03/06/2026 | APPROVED | KSANDOE |
| BLD - SITE LIGHTING-POLE SET/FIXTURE | 02/19/2026 | APPROVED | RMARTIN |
| UC-CONSTRUCTION ENTRANCE | 02/19/2026 | APPROVED - AS NOTED | LFITZGERALD |
| Note: 11/12/2025 - PREVIOUS INSPECTION NOTES 11/7/2025 - PREVIOUS INSPECTION NOTES entrance now not adequate-needs refershing so soils don't get in access roadway-needs to be done next couple of days or possible project shut down until rectified new rock now installed now all is paved | |||
| UC-MOT MAINTENANCE OF TRAFFIC | 02/19/2026 | APPROVED | LFITZGERALD |
| Note: flagging operation -Market -in order to repave 2 utility cuts | |||
| UC-ASPHALT PRE PLACEMENT | 02/19/2026 | APPROVED | LFITZGERALD |
| Note: flagging operation on Market in order to pave over 2 patches on Market from 2 utility tie ins-top layered milled,tac coat applied with thickened edge at each end | |||
| UROW- CURBING & GUTTER | 02/19/2026 | PARTIALLY APPROVED | LFITZGERALD |
| Note: perma-curb-Bob now on site installing D curb thoughout parking area | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 02/17/2026 | PARTIALLY APPROVED | JMYERS |
| Note: 2/17/26 EROSION CONTROL MEASURES HAVE BEEN RE-INSTALLED AND ROAD CLEANED. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO MAINTAIN THE SITE PER SWPPP. FOLLOW UP INSPECTION NEXT MONTH. 2/13/2026 - PREVIOUS INSPECTION NOTES 2/13/26 A STOP WORK ORDER HAS BEEN PLACED ON THIS PROPERTY UNTIL SILT FENCE IS RE-ESTABLISHED AND THE DIRT ON MARKET AVE HAS BEEN REMOVED. ONLY THE APPROVED ENTRACE SHALL BE UTILIZED. 2/12/2026 - PREVIOUS INSPECTION NOTES 2/12/26 SILT FENCE HAS NOT BEEN RE-INSTALLED PER SWPPP. SHALL BE RE-INSTALLED OR STOP WORK ORDER WILL BE PLACED ON SITE. FOLLOW UP INSPECTION FRIDAY 2/13/26. 2/10/2026 - PREVIOUS INSPECTION NOTES 2/10/26 SILT FENCE HAS NOT BEEN RE-INSTALLED PER SWPPP. FENCE SHALL BE RE-INSTALLED, FOLLOW UP INSPECTION WEDNESDAY 2/11/26. 2/4/2026 - PREVIOUS INSPECTION NOTES 2/4/26 SILT FENCE SHALL BE RE-INSTALLED PER SWPPP. FOLLOW UP INSPECTION FRIDAY 2/6/26. 11/13/2025 - PREVIOUS INSPECTION NOTES 11/13/25 SILT FENCE NEEDS TO BE RE-ESTABLISHED ON THE NORTH AND WEST PROPERTY LINES. 6/10/2025 - PREVIOUS INSPECTION NOTES 6/10/25 EROSION CONTROL MEASURES ARE IN PLACE AND FUNCTIONING. FOLLOW UP INSPECTION NEXT MONTH. | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 02/13/2026 | Disapproved -FEE REQUIRED | JMYERS |
| Note: 2/13/26 A STOP WORK ORDER HAS BEEN PLACED ON THIS PROPERTY UNTIL SILT FENCE IS RE-ESTABLISHED AND THE DIRT ON MARKET AVE HAS BEEN REMOVED. ONLY THE APPROVED ENTRACE SHALL BE UTILIZED. 2/12/2026 - PREVIOUS INSPECTION NOTES 2/12/26 SILT FENCE HAS NOT BEEN RE-INSTALLED PER SWPPP. SHALL BE RE-INSTALLED OR STOP WORK ORDER WILL BE PLACED ON SITE. FOLLOW UP INSPECTION FRIDAY 2/13/26. 2/10/2026 - PREVIOUS INSPECTION NOTES 2/10/26 SILT FENCE HAS NOT BEEN RE-INSTALLED PER SWPPP. FENCE SHALL BE RE-INSTALLED, FOLLOW UP INSPECTION WEDNESDAY 2/11/26. 2/4/2026 - PREVIOUS INSPECTION NOTES 2/4/26 SILT FENCE SHALL BE RE-INSTALLED PER SWPPP. FOLLOW UP INSPECTION FRIDAY 2/6/26. 11/13/2025 - PREVIOUS INSPECTION NOTES 11/13/25 SILT FENCE NEEDS TO BE RE-ESTABLISHED ON THE NORTH AND WEST PROPERTY LINES. 6/10/2025 - PREVIOUS INSPECTION NOTES 6/10/25 EROSION CONTROL MEASURES ARE IN PLACE AND FUNCTIONING. FOLLOW UP INSPECTION NEXT MONTH. | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 02/11/2026 | Disapproved -FEE REQUIRED | JMYERS |
| Note: 2/12/26 SILT FENCE HAS NOT BEEN RE-INSTALLED PER SWPPP. SHALL BE RE-INSTALLED OR STOP WORK ORDER WILL BE PLACED ON SITE. FOLLOW UP INSPECTION FRIDAY 2/13/26. 2/10/2026 - PREVIOUS INSPECTION NOTES 2/10/26 SILT FENCE HAS NOT BEEN RE-INSTALLED PER SWPPP. FENCE SHALL BE RE-INSTALLED, FOLLOW UP INSPECTION WEDNESDAY 2/11/26. 2/4/2026 - PREVIOUS INSPECTION NOTES 2/4/26 SILT FENCE SHALL BE RE-INSTALLED PER SWPPP. FOLLOW UP INSPECTION FRIDAY 2/6/26. 11/13/2025 - PREVIOUS INSPECTION NOTES 11/13/25 SILT FENCE NEEDS TO BE RE-ESTABLISHED ON THE NORTH AND WEST PROPERTY LINES. 6/10/2025 - PREVIOUS INSPECTION NOTES 6/10/25 EROSION CONTROL MEASURES ARE IN PLACE AND FUNCTIONING. FOLLOW UP INSPECTION NEXT MONTH. | |||
| UC-ASPHALT PRE PLACEMENT | 02/11/2026 | APPROVED | LFITZGERALD |
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 02/06/2026 | Disapproved -FEE REQUIRED | JMYERS |
| Note: 2/10/26 SILT FENCE HAS NOT BEEN RE-INSTALLED PER SWPPP. FENCE SHALL BE RE-INSTALLED, FOLLOW UP INSPECTION WEDNESDAY 2/11/26. 2/4/2026 - PREVIOUS INSPECTION NOTES 2/4/26 SILT FENCE SHALL BE RE-INSTALLED PER SWPPP. FOLLOW UP INSPECTION FRIDAY 2/6/26. 11/13/2025 - PREVIOUS INSPECTION NOTES 11/13/25 SILT FENCE NEEDS TO BE RE-ESTABLISHED ON THE NORTH AND WEST PROPERTY LINES. 6/10/2025 - PREVIOUS INSPECTION NOTES 6/10/25 EROSION CONTROL MEASURES ARE IN PLACE AND FUNCTIONING. FOLLOW UP INSPECTION NEXT MONTH. | |||
| UC-ASPHALT PRE PLACEMENT | 02/05/2026 | CANCELLED BY APPLICANT | WEB |
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 02/04/2026 | Disapproved - NO FEE | JMYERS |
| Note: 2/4/26 SILT FENCE SHALL BE RE-INSTALLED PER SWPPP. FOLLOW UP INSPECTION FRIDAY 2/6/26. 11/13/2025 - PREVIOUS INSPECTION NOTES 11/13/25 SILT FENCE NEEDS TO BE RE-ESTABLISHED ON THE NORTH AND WEST PROPERTY LINES. 6/10/2025 - PREVIOUS INSPECTION NOTES 6/10/25 EROSION CONTROL MEASURES ARE IN PLACE AND FUNCTIONING. FOLLOW UP INSPECTION NEXT MONTH. | |||
| BLD - SITE LIGHTING-PLACEMENT/FOUNDATION | 01/20/2026 | APPROVED | MKRASKI |
| BLD - SITE LIGHTING-PLACEMENT/FOUNDATION | 01/16/2026 | Disapproved - NO FEE | RMARTIN |
| Note: BONDING CONDUCTOR NOT INSTALLED 11/12/2025 - PREVIOUS INSPECTION NOTES Right side of entry to corner 11/7/2025 - PREVIOUS INSPECTION NOTES 5FT wide along Market ROW last section middle to east property line/6ft connection to already placed sidewalk | |||
| BLD - ADA RAMPS/SIDEWALKS/CROSSWALKS | 01/08/2026 | APPROVED - AS NOTED | LFITZGERALD |
| Note: 11/12/2025 - PREVIOUS INSPECTION NOTES Right side of entry to corner 11/7/2025 - PREVIOUS INSPECTION NOTES 5FT wide along Market ROW last section middle to east property line/6ft connection to already placed sidewalk | |||
| UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) | 01/08/2026 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 1/7/2026 - PREVIOUS INSPECTION NOTES 12/1/2025 - PREVIOUS INSPECTION NOTES 11/18/2025 - PREVIOUS INSPECTION NOTES 11/12/2025 - PREVIOUS INSPECTION NOTES 11/7/2025 - PREVIOUS INSPECTION NOTES compact soils in front sidewalk and 4in required from edge to edge-correct/remove cold conrete left over in side bldg sidewalk-all conrete should be fresh and consistent left and right sides now poured-front sidewalk satisfactory for concrete but still awaiting final engineering for ADA ramps east side parking from building corner southward now front sidewalk poured Sidewalk in ROW along Market Ave-half way from west property line 5FT wide along Market ROW last section middle to east property line/6ft connection to already placed sidewalk | |||
| UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) | 01/07/2026 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 12/1/2025 - PREVIOUS INSPECTION NOTES 11/18/2025 - PREVIOUS INSPECTION NOTES 11/12/2025 - PREVIOUS INSPECTION NOTES 11/7/2025 - PREVIOUS INSPECTION NOTES compact soils in front sidewalk and 4in required from edge to edge-correct/remove cold conrete left over in side bldg sidewalk-all conrete should be fresh and consistent left and right sides now poured-front sidewalk satisfactory for concrete but still awaiting final engineering for ADA ramps east side parking from building corner southward now front sidewalk poured Sidewalk in ROW along Market Ave-half way from west property line | |||
| WATERMAIN FLUSH & PRESSURE TESTED | 12/18/2025 | FINAL APPROVED | BWRIGHT |
| UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) | 12/01/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 11/18/2025 - PREVIOUS INSPECTION NOTES 11/12/2025 - PREVIOUS INSPECTION NOTES 11/7/2025 - PREVIOUS INSPECTION NOTES compact soils in front sidewalk and 4in required from edge to edge-correct/remove cold conrete left over in side bldg sidewalk-all conrete should be fresh and consistent left and right sides now poured-front sidewalk satisfactory for concrete but still awaiting final engineering for ADA ramps east side parking from building corner southward now front sidewalk poured | |||
| UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) | 11/18/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 11/12/2025 - PREVIOUS INSPECTION NOTES 11/7/2025 - PREVIOUS INSPECTION NOTES compact soils in front sidewalk and 4in required from edge to edge-correct/remove cold conrete left over in side bldg sidewalk-all conrete should be fresh and consistent left and right sides now poured-front sidewalk satisfactory for concrete but still awaiting final engineering for ADA ramps east side parking from building corner southward | |||
| UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) | 11/12/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 11/7/2025 - PREVIOUS INSPECTION NOTES compact soils in front sidewalk and 4in required from edge to edge-correct/remove cold conrete left over in side bldg sidewalk-all conrete should be fresh and consistent left and right sides now poured-front sidewalk satisfactory for concrete but still awaiting final engineering for ADA ramps | |||
| BLD - ADA RAMPS/SIDEWALKS/CROSSWALKS | 11/12/2025 | PARTIALLY APPROVED | KSANDOE |
| Note: Right side of entry to corner 11/7/2025 - PREVIOUS INSPECTION NOTES | |||
| UC-CONSTRUCTION ENTRANCE | 11/12/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 11/7/2025 - PREVIOUS INSPECTION NOTES entrance now not adequate-needs refershing so soils don't get in access roadway-needs to be done next couple of days or possible project shut down until rectified new rock now installed | |||
| UC-CONSTRUCTION ENTRANCE | 11/07/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: entrance now not adequate-needs refershing so soils don't get in access roadway-needs to be done next couple of days or possible project shut down until rectified | |||
| BLD - ADA RAMPS/SIDEWALKS/CROSSWALKS | 11/07/2025 | CANCELLED BY APPLICANT | KSANDOE |
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 11/07/2025 | Disapproved - NO FEE | JMYERS |
| Note: 11/13/25 SILT FENCE NEEDS TO BE RE-ESTABLISHED ON THE NORTH AND WEST PROPERTY LINES. 6/10/2025 - PREVIOUS INSPECTION NOTES 6/10/25 EROSION CONTROL MEASURES ARE IN PLACE AND FUNCTIONING. FOLLOW UP INSPECTION NEXT MONTH. | |||
| UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) | 11/07/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: compact soils in front sidewalk and 4in required from edge to edge-correct/remove cold conrete left over in side bldg sidewalk-all conrete should be fresh and consistent | |||
| BLD - UNDERGROUND SITE LIGHTING CONDUITS | 09/26/2025 | APPROVED | RMARTIN |
| U-GRAVITY SEWER INSTALL/TESTING | 08/18/2025 | APPROVED | LFITZGERALD |
| UC-DRAINAGE STRUCT PLACMNT | 08/18/2025 | APPROVED - AS NOTED | LFITZGERALD |
| UC-DRAINAGE PIPE PLACEMENT/LAMPING | 08/18/2025 | APPROVED | LFITZGERALD |
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | 08/05/2025 | PARTIALLY APPROVED | BWRIGHT |
| Note: 6 inch wet-tap done by Dave Jones. Joel Wirzman was onsite. | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 06/10/2025 | PARTIALLY APPROVED | JMYERS |
| Note: 6/10/25 EROSION CONTROL MEASURES ARE IN PLACE AND FUNCTIONING. FOLLOW UP INSPECTION NEXT MONTH. | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 06/03/2025 | CANCELLED BY INSPECTOR | JMYERS |
| Note: 5/6/2025 - PREVIOUS INSPECTION NOTES 5/6/25 SILT FENCE STILL FUNCTIONING. FOLLOW UP INSPECTION IN ONE MONTH 3/28/2025 - PREVIOUS INSPECTION NOTES 3/28/25 SILT FENCE INSTALLED ACCORDING TO SWPPP. FOLLOW UP INSPECTION EARLY MAY. | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 05/06/2025 | PARTIALLY APPROVED | JMYERS |
| Note: 5/6/25 SILT FENCE STILL FUNCTIONING. FOLLOW UP INSPECTION IN ONE MONTH 3/28/2025 - PREVIOUS INSPECTION NOTES 3/28/25 SILT FENCE INSTALLED ACCORDING TO SWPPP. FOLLOW UP INSPECTION EARLY MAY. | |||
| UC-CONSTRUCTION ENTRANCE | 04/24/2025 | APPROVED | BWRIGHT |
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 03/28/2025 | PARTIALLY APPROVED | JMYERS |
| Note: 3/28/25 SILT FENCE INSTALLED ACCORDING TO SWPPP. FOLLOW UP INSPECTION EARLY MAY. | |||
| PLAN - PRE-CON 386-986-3750 | 01/14/2025 | APPROVED - AS NOTED | LFITZGERALD |
| Note: *** NOTES ADDED BY LFITZGERALD 1/14/2025 9:43:09 AM *** cline-eric chuck, city-ken and gc on site discussed all particulars |
Review History
| Department | Status | Date In | Date Out |
| BADMIN | INFORMATION | 03/26/2026 | 03/26/2026 |
| Note: Marked INFORMATION By: BARBIE BEMBRY - (386)986-3780 - BUILDINGDIVISION@PALMCOASTGOV.COM These documents are to be submitted to the planning division. Please contact Damaris Ramirez to inquire about their process for submittal. dramirez@palmcoastgov.com | |||
| PLENG | COMPLETE | 12/09/2025 | 12/09/2025 |
| Note: Released By: DENNIS R. LEAP, P.E. - (386)986-2482 - DLEAP@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 11/14/2024 | 11/15/2024 |
| Note: Released By: PATRICK BUCKLEY - (386)986-3786 - PBUCKLEY@PALMCOASTGOV.COM | |||
| ELEC | COMPLETE | 11/14/2024 | 11/15/2024 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| PLENG | COMPLETE | 11/14/2024 | 11/15/2024 |
| Note: Released By: DENNIS R. LEAP, P.E. - (386)986-2482 - DLEAP@PALMCOASTGOV.COM | |||
| PLLA | COMPLETE | 11/14/2024 | 11/19/2024 |
| Note: Released By: DAMARIS RAMIREZ - (386)986-3750 - DRAMIREZ@PALMCOASTGOV.COM | |||
| UD1 | COMPLETE | 11/14/2024 | 11/15/2024 |
| Note: Released By: GREG DEGLER - (386)986-2384 - GDEGLER@PALMCOASTGOV.COM |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION- SITE INSPECTOR | ¤40.00 | 04/07/2026 |
| REINSPECTION- SITE INSPECTOR | ¤40.00 | 04/07/2026 |
| REINSPECTION- SITE INSPECTOR | ¤40.00 | 04/07/2026 |
| SITE PLAN 30 | ¤30.00 | 01/06/2025 |
| ADJUSTMENT 10% | (¤40.50) | 01/06/2025 |
| ADMINISTRATIVE- SITE DEVELOP | ¤125.00 | 01/06/2025 |
| SITE INSPECTION | ¤880.00 | 01/06/2025 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤1,114.50 |