I want to search for...
Permit #2024121088
Permit Details
Status: FINAL
| Parcel Id: 07-11-31-7021-00010-0340 |
| Block: 00010 |
| Subdivision: 7021 - |
| Job Phone: 386-586-9144 |
| Location Address: 83 WELLWOOD LN |
| Type: GEN - GENERATOR |
| Issue Date: 01/06/2025 |
| NOC: Unknown |
| Applicant name: JOHN EDWARD GAMBONE |
| Owner: DELORENZO EUGENE TRUSTEE |
|
Address 118 WESTLEE LANE PALM COAST, FL 32164 |
| Lot: 0340 |
| Contracted Stated Job Value: ¤3,200.00 |
| Job Description: install 18kw generator |
| Type: CN |
Contractor
BREAKERS ELECTRICAL CONSTRUCTION, INC
| Status | Location Address | Mailing Address | State License Number | Phone |
| ACTIVE |
15 HARGROVE LN PALM COAST, FL 32137 |
1G PALM COAST, FL 32137 |
EC13006037 (Exp: 08/31/2026) | 386-586-9144 |
Inspection History
| Type | Request Date | Result | Inspector |
| ELECTRIC FINAL | 07/31/2025 | FINAL APPROVED | RMARTIN |
| Note: 6/18/2025 - PREVIOUS INSPECTION NOTES 6/18/25 Generator needs work so they are calling in the inspection when the work is complete 6/11/2025 - PREVIOUS INSPECTION NOTES 6/11/25 1. No contractor on site, must be onsite to open ATS and panel and do generator start up. 3/11/25 Via text canceled 3/6/25 1. No contractor on site, must be onsite to open ATS and panel and do generator start up. | |||
| ELECTRIC FINAL | 06/18/2025 | CANCELLED BY APPLICANT | MCONTRYMAN |
| Note: 6/18/25 Generator needs work so they are calling in the inspection when the work is complete 6/11/2025 - PREVIOUS INSPECTION NOTES 6/11/25 1. No contractor on site, must be onsite to open ATS and panel and do generator start up. 3/11/25 Via text canceled 3/6/25 1. No contractor on site, must be onsite to open ATS and panel and do generator start up. | |||
| ELECTRIC FINAL | 06/11/2025 | Disapproved - NO FEE | MKRASKI |
| Note: 6/11/25 1. No contractor on site, must be onsite to open ATS and panel and do generator start up. 3/11/25 Via text canceled 3/6/25 1. No contractor on site, must be onsite to open ATS and panel and do generator start up. | |||
| ELECTRIC FINAL | 03/11/2025 | CANCELLED BY APPLICANT | MKRASKI |
| Note: 3/11/25 Via text 3/6/2025 - PREVIOUS INSPECTION NOTES No contractor on site, must be onsite to open ATS and panel and do generator start up. | |||
| ELECTRIC FINAL | 03/06/2025 | Disapproved - NO FEE | MKRASKI |
| Note: No contractor on site, must be onsite to open ATS and panel and do generator start up. | |||
| ELECTRIC FINAL | 01/10/2025 | CANCELLED BY APPLICANT | WEB |
Review History
| Department | Status | Date In | Date Out |
| ELEC | COMPLETE | 12/30/2024 | 01/03/2025 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 12/30/2024 | 12/30/2024 |
| Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| ADMINISTRATIVE - EXTENSION | ¤40.00 | 07/30/2025 |
| ADMINISTRATIVE RESIDENTIAL | ¤30.00 | 01/06/2025 |
| INSPECTION - RESIDENTIAL | ¤60.00 | 01/06/2025 |
| PLAN REVIEW - MISC 32.50 | ¤32.50 | 01/06/2025 |
| SURCHARGE FS 533.721 | ¤2.00 | 01/06/2025 |
| SURCHARGE - FS 468.631 | ¤2.00 | 01/06/2025 |
| SITE PLAN 15 | ¤15.00 | 01/06/2025 |
| ADJUSTMENT 10% | (¤12.25) | 01/06/2025 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤169.25 |