Permit #2025020155

Permit Details

Status: FINAL

Parcel Id: 06-12-31-0650-000B0-0011
Block: 000B0
Subdivision: -
Job Phone: 386-547-6093
Location Address: 101 HAVEN BLVD
Type: CSD - COMMERCIAL SITE DEVELOPMENT
Issue Date: 03/03/2025
NOC: Unknown
Applicant name: JOSEPH D WEBER
Owner: TEG THE HAVEN AT PALM COAST LLC

Address

SUITE 110

AIRMONT, NY 10952

Address

365 ROUTE 59

AIRMONT, NY 10952

Lot: 0011
Job Description: SITE WORK: THE HAVEN STAGE 2 - MULTI-FAMILY, 2 UNIT TH AND SFR UNITS
Type: CN

Contractor

JD WEBER CONSTRUCTION CO.
Status Location Address State License Number Phone Fax
ACTIVE

150 BUSINESS CENTER DRIVE

ORMOND BEACH, FL 32174

CUC1224075 (Exp: 08/31/2026) (386)671-2727 (386)671-2471

Inspection History

Type Request Date Result Inspector
LDSC-IRRIGATION FINAL 01/09/2026 APPROVED RPICATAGI
CLOSE OUT DOCUMENTS 01/05/2026 APPROVED DRAMIREZ
U - UTILITY COMMERCIAL FINAL 12/10/2025 FINAL APPROVED LFITZGERALD
UROW - FINAL DRAINAGE 11/20/2025 APPROVED - AS NOTED JMYERS
Note: 11/20/25 DEVELOPER IN PROCESS OF HAVING SYSTEM CLEANED. WILL BE COMPLETED WITHIN 2 WEEKS TIME. 10/15/2025 1:47:10 PM- PREVIOUS INSPECTION NOTES 10/15/25 DRAINAGE WALKTHROUGH NOT COMPLETED TOO MANY INLETS HAD SILT, DEBRIS, AND FILTER FABRIC STILL IN PLACE. ALL STRUCTURES NEED TO BE CLEANED OF ALL SILT AND DEBRIS. RE-SCHEDULE WHEN COMPLETED.
LDSC- LANDSCAPE FINAL 10/31/2025 APPROVED RPICATAGI
PLANNING - OFFICE USE - FINAL AS-BUILT SURVEY 10/27/2025 APPROVED DRAMIREZ
LDSC-IRRIGATION FINAL 10/27/2025 APPROVED WEB
U-WATER METER INSTALLATION/VERIFICATION 10/23/2025 APPROVED BWRIGHT
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR 10/23/2025 APPROVED BWRIGHT
Note: 10/10/2025 - PREVIOUS INSPECTION NOTES
U-SEWER FORCE MAIN INSTALL/TESTING 10/23/2025 APPROVED BWRIGHT
U-WATER SERVICE INSTALLATION 10/23/2025 APPROVED BWRIGHT
U-GRAVITY SEWER INSTALL/TESTING 10/23/2025 APPROVED BWRIGHT
Note: 3/28/2023 - PREVIOUS INSPECTION NOTES Not ready
U-REUSE MAIN INSTALL/TESTING 10/23/2025 APPROVED BWRIGHT
U-WATER MAIN DISINFECTION 10/23/2025 APPROVED BWRIGHT
U-WATER MAIN DISINFECTION SAMPLING 10/23/2025 APPROVED BWRIGHT
U-PUMP STATION START-UP 10/23/2025 APPROVED BWRIGHT
LDSC- LANDSCAPE / IRRIGATION AS-BUILT 10/22/2025 APPROVED RPICATAGI
UC-TRAF - FINAL (SIGN/PAVEMENT MARKING) 10/15/2025 APPROVED - AS NOTED LFITZGERALD
Note: 3 -20 mph speed limit signs missing-Roger informed
UC-FINAL SITE INSPECTION 10/15/2025 APPROVED LFITZGERALD
UROW - FINAL DRAINAGE 10/15/2025 Disapproved -FEE REQUIRED JMYERS
Note: 10/15/25 DRAINAGE WALKTHROUGH NOT COMPLETED TOO MANY INLETS HAD SILT, DEBRIS, AND FILTER FABRIC STILL IN PLACE. ALL STRUCTURES NEED TO BE CLEANED OF ALL SILT AND DEBRIS. RE-SCHEDULE WHEN COMPLETED.
UROW-RETENT/DETENT STABILI 10/15/2025 APPROVED LFITZGERALD
UROW -FINAL GRADE PRIOR SOD 10/15/2025 APPROVED LFITZGERALD
Note: Inspector Notes from Inspection 9602 3 -20 mph speed limit signs missing-Roger informed
UC-SUBSTANTIAL WALK-THRU 10/14/2025 APPROVED - AS NOTED LFITZGERALD
Note: Roger on site and informed :3 -20 mph speed limit signs missing,/sprinkler head undermining part of sidewalk landing for apt 4001/all stop signs for garage driveways installed per plan but that location has the signs being blocked by garage wall-unable to see upon leaving garages
UC- PRELIMINARY AS-BUILTS 10/14/2025 APPROVED - AS NOTED LFITZGERALD
Note: drainage as blts received-handed to Jordan for her inspection
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR 10/10/2025 CANCELLED BY APPLICANT LFITZGERALD
UROW- CURBING & GUTTER 10/10/2025 APPROVED - AS NOTED LFITZGERALD
Note: Inspector Notes from Inspection 9114 Inspector Notes from Inspection 9113 no notes entered by past inspector indicating all approved-i need to result in order to close out permit-i did visit the site and as best as possible,verify al is satisfactory
UC-CONSTRUCTION ENTRANCE 10/10/2025 APPROVED LFITZGERALD
UC-MOT MAINTENANCE OF TRAFFIC 10/10/2025 APPROVED LFITZGERALD
UC-ASPHALT PRE PLACEMENT 10/10/2025 APPROVED LFITZGERALD
UC-DRAINAGE STRUCT PLACMNT 10/10/2025 APPROVED - AS NOTED LFITZGERALD
Note: no notes entered by past inspector indicating all approved-i need to result in order to close out permit-i did visit the site and as best as possible,verify al is satisfactory
UC-DRAINAGE PIPE PLACEMENT/LAMPING 10/10/2025 APPROVED - AS NOTED LFITZGERALD
Note: Inspector Notes from Inspection 9113 no notes entered by past inspector indicating all approved-i need to result in order to close out permit-i did visit the site and as best as possible,verify al is satisfactory
BLD - ADA RAMPS/SIDEWALKS/CROSSWALKS 08/14/2025 APPROVED KSANDOE
BLD- ADA PARKING 08/14/2025 APPROVED KSANDOE
BLD - ADA COMPLIANT 08/14/2025 APPROVED KSANDOE
BLD- ADA SIGNAGECONTROL 08/14/2025 APPROVED KSANDOE
BLD- ADA VEHICULAR WAY 08/14/2025 APPROVED KSANDOE
BLD - ADA SIGNAGE- INFOR/DIRECT 08/14/2025 APPROVED KSANDOE
BLD - UNDERGROUND SITE LIGHTING CONDUITS 03/14/2025 APPROVED RMARTIN
BLD - SITE LIGHTING-PLACEMENT/FOUNDATION 03/14/2025 APPROVED RMARTIN
BLD - SITE LIGHTING-POLE SET/FIXTURE 03/14/2025 APPROVED RMARTIN

Review History

Department Status Date In Date Out
DSD COMPLETE 02/27/2025 02/27/2025
Note: Released By: DAMARIS RAMIREZ - (386)986-3750 - DRAMIREZ@PALMCOASTGOV.COM
BLD CANCEL 02/04/2025 02/04/2025
ELEC CANCEL 02/04/2025 02/04/2025
PLENG CANCEL 02/04/2025 02/04/2025
PLLA CANCEL 02/04/2025 02/04/2025
UD1 CANCEL 02/04/2025 02/04/2025

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
ADJUSTMENT 10% (¤48.50) 03/03/2025
ADMINISTRATIVE- SITE DEVELOP ¤125.00 03/03/2025
SITE INSPECTION ¤920.00 03/03/2025
SITE PLAN 30 ¤30.00 03/03/2025
Fees Total Due: ¤0.00 Total Paid: ¤1,026.50