I want to search for...
Permit #2025020494
Permit Details
Status: FINAL
| Parcel Id: 07-11-31-7009-00320-0030 |
| Block: 00320 |
| Subdivision: 7009 - |
| Job Phone: 904-384-1066 |
| Location Address: 93 FELLOWSHIP DR |
| Type: FU - FIRE UNDERGROUND |
| Issue Date: 04/07/2025 |
| NOC: RECORDED |
| Applicant name: JOSEPH R THOMAS |
| Owner: MARONDA HOMES LLC |
|
Address 5220 SHAD RD JACKSONVILLE, FL 32257 |
| Lot: 0030 |
| Contracted Stated Job Value: ¤15,000.00 |
| Job Description: FIRE SPRINKLER SYSTEM |
| Type: CN |
Contractor
STAR FIRE SPRINKLERS INC
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
533 STEVENS STREET JACKSONVILLE, FL 32254 |
19049400012010 (Exp: 06/30/2026) | 904-384-1066 | 904-302-9808 |
Inspection History
| Type | Request Date | Result | Inspector |
| FIRE FINAL | 04/29/2026 | FINAL APPROVED | RMARTIN |
| Note: 4/8/2026 - PREVIOUS INSPECTION NOTES 4/8/26 From last inspection .....Make sure the FDC and MAIN DRAIN sign are installed by final inspection Make sure the FDC and MAIN DRAIN sign are installed by final inspection | |||
| FIRE FINAL | 04/08/2026 | Disapproved - NO FEE | RMARTIN |
| Note: 4/8/26 From last inspection .....Make sure the FDC and MAIN DRAIN sign are installed by final inspection Make sure the FDC and MAIN DRAIN sign are installed by final inspection | |||
| FIRE MAIN HYDROSTATIC/BACKFLOW PREVENTOR | 03/25/2026 | APPROVED - AS NOTED | RMARTIN |
| Note: Make sure the FDC and MAIN DRAIN sign are installed by final inspection | |||
| FIRE SYSTEM FLUSH | 02/27/2026 | APPROVED | RMARTIN |
| FIRE MAIN PLACEMENT /SIZE/THRUST /BLOCKING | 02/27/2026 | APPROVED | RMARTIN |
| FIRE MAIN PLACEMENT /SIZE/THRUST /BLOCKING | 02/25/2026 | CANCELLED BY APPLICANT | WEB |
| FIRE FINAL | 02/17/2026 | Disapproved -FEE REQUIRED | JMUNSON |
| Note: 2/12/2026 - You have 3 other inspections on this permit you have not passed. You have to pass these before you can schedule your fire final. 2/10/2026 - PREVIOUS INSPECTION NOTES Need to schedule other inspections on this permit and pass prior to scheduling the Fire Final... Need to have FDC sign installed, need to have protection/plant bed aroound Fire line conduit (subject to physical damage) entering home, need to have main drain sign installed outside of home at main drain. | |||
| FIRE FINAL | 02/10/2026 | Disapproved - NO FEE | RMARTIN |
| Note: Need to schedule other inspections on this permit and pass prior to scheduling the Fire Final... Need to have FDC sign installed, need to have protection/plant bed aroound Fire line conduit (subject to physical damage) entering home, need to have main drain sign installed outside of home at main drain. |
Review History
| Department | Status | Date In | Date Out |
| FI1 | COMPLETE | 04/02/2025 | 04/07/2025 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| FI1 | HOLD | 03/20/2025 | 03/26/2025 |
| Note: Held By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM 1. Revise permit application to only installing FDC and Underground work. You will need separate permit for a sprinkler permit and underground permit. 3. Fire alarm permit will need to be applied for before sprinkler permit and underground permit can be released. 2nd REQUEST | |||
| FI1 | HOLD | 02/11/2025 | 02/25/2025 |
| Note: Held By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM 1. Revise permit application to only installing FDC and Underground work. You will need separate permit for a sprinkler permit and underground permit. 2. Owner will need to answer all hold comments on there occupancy permit before fire permits can be released. 3. Fire alarm permit will need to be applied for before sprinkler permit and underground permit can be released. 4. Upload manufacture specs of FDC locking caps. | |||
| UD1 | COMPLETE | 02/11/2025 | 02/25/2025 |
| Note: Released By: GREG DEGLER - (386)986-2384 - GDEGLER@PALMCOASTGOV.COM |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION - COMMERCIAL | ¤60.00 | 03/24/2026 |
| SURCHARGE FS 533.721 | ¤2.85 | 04/07/2025 |
| SURCHARGE - FS 468.631 | ¤4.27 | 04/07/2025 |
| SW ENG - INSPECTION 20 | ¤20.00 | 04/07/2025 |
| ADJUSTMENT 10% | (¤31.65) | 04/07/2025 |
| ADMINISTRATIVE - COMMERCIAL | ¤75.00 | 04/07/2025 |
| INSPECTION - FIRE COMMERCIAL | ¤69.00 | 04/07/2025 |
| PLAN REVIEW - COMMERCIAL | ¤172.50 | 04/07/2025 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤371.97 |