Permit #2025020797

Permit Details

Status: FINAL

Parcel Id: 07-11-31-7003-00170-0030
Block: 00170
Subdivision: 7003 -
Job Phone: 386-872-8025
Location Address: 5 CARDWELL CT
Type: SW - SEAWALL
Issue Date: 03/14/2025
NOC: RECORDED
Applicant name: STEPHEN SEAN LAWRENCE
Owner: MULLANEY JEFFREY THOMAS

Address

5 CARDWELL COURT

PALM COAST, FL 32137

Lot: 0030
Contracted Stated Job Value: ¤35,000.00
Job Description: SEAWALL
Type: CN

Contractor

ACANTHUS CONSTRUCTION LLC
Status Location Address State License Number Phone
ACTIVE

54 BURNELL DRIVE

PALM COAST, FL 32137

CGC1535903 (Exp: 08/31/2026) 386-318-1125

Inspection History

Type Request Date Result Inspector
SEAWALL FINAL 11/13/2025 FINAL APPROVED HCAMACHO
ROW - STORMWATER FINAL 11/12/2025 APPROVED PFLANAGAN
Note: CORRECTIONS MADE At the time of the inspection all minimum city requirements were met. It is the builders and the homowners responsibility to ensure that nothing changes after this Inspection is approved. It will not be on the city if any changes after this inspection. -------------------------------------------------------------------------------- New inspection due to canceled inspection 10/10/2025 - PREVIOUS INSPECTION NOTES ** 10/10/25 NEED TO REPAIR THE WASHOUTS BENEATH SOD OF BOTH RIGHT AND LEFT SIDES WASHOUTS ARE BENEATH THE NEW SOD ** WHERE NEW SOD JOINS WITH NEED TO INSTALL ANOTHER ROW OF SOD AND CUT IN TO MATCH THE EXISTING GRADE AND COVER THE EXPOSED BARE EARTH ** RIGHT SIDE BARE AREA BETWEEN #3 AND YOUR PROJECT SITE YOU NEED TO REPAIR WHERE AREA WAS DAMAGED DUE TO MACHINE TRACKING SOD REQUIRED TO MATCH WHAT WAS DAMAGED DURRING YOUR PROJECT SOD REQUIRED TO BE CUT IN TO MATCH GRADE THIS WAS DISCUSSED DURRING OUR SITE MEET FOR THE REQUIRED CORRECTIONS ** NEED TO REMOVE THE PIECE OF STEEL THAT WAS LEFT STICKING OUT OF NEWLY LAID SOD IT IS A SAFETY HAZZARD ** NOTE AREAS REQUIRING ATTENTION HIGH LIGHTED WITH PINK PAINT ** SEE ATTACHED PHOTOS FROM TODAYS INSPECTION _______________________________________________________________________________________________________________________ 8/11/2025 - PREVIOUS INSPECTION NOTES ** 08/11/25 NEED TO REPAIR AREA ON SIDE BETWEEN #3 AND #5 PROJECT SITE WHERE RUTS FROM MACHINE WERE CREATED ** NEED TO REMOVE SEDIMENT OUT OF CANAL ON LEFT SIDE OF DOCK THAT ERRODED IN DURING PROJECT AS WELL AS TO THE RIGHT OF BOAT DOCK AND PROPERTY LINE ** BUILDER NEEDS TO CREATE THE SWALE ACROSS THE ENTIRE SEAWALL AS INDICATED IN DRAWING 1100.J AS NOTED IN SECTION 1100.10 SEAWALLS/BULKHEAD/REVETMENT CONSTRUCTION PERMIT REQUIREMENTS ** SOD NEEDS TO BE CUT INTO PLACE TO MATCH EXISTING GRADE
ROW - FINAL INSPECTION 10/15/2025 APPROVED EMADISON
Note: AT THE TIME OF THE INSPECTION, ALL MINIMUM CITY REQUIREMENTS WERE MET. NIETHER THE INSPECTOR NOR THE CITY IS RESPONSIBLE IF, FOR WHATEVER REASON, SITE CONDITIONS CHANGE OVER TIME AFTER THE INSPECTION. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED
ROW - STORMWATER FINAL 10/15/2025 CANCELLED BY APPLICANT WEB
Note: 10/10/2025 - PREVIOUS INSPECTION NOTES ** 10/10/25 NEED TO REPAIR THE WASHOUTS BENEATH SOD OF BOTH RIGHT AND LEFT SIDES WASHOUTS ARE BENEATH THE NEW SOD ** WHERE NEW SOD JOINS WITH NEED TO INSTALL ANOTHER ROW OF SOD AND CUT IN TO MATCH THE EXISTING GRADE AND COVER THE EXPOSED BARE EARTH ** RIGHT SIDE BARE AREA BETWEEN #3 AND YOUR PROJECT SITE YOU NEED TO REPAIR WHERE AREA WAS DAMAGED DUE TO MACHINE TRACKING SOD REQUIRED TO MATCH WHAT WAS DAMAGED DURRING YOUR PROJECT SOD REQUIRED TO BE CUT IN TO MATCH GRADE THIS WAS DISCUSSED DURRING OUR SITE MEET FOR THE REQUIRED CORRECTIONS ** NEED TO REMOVE THE PIECE OF STEEL THAT WAS LEFT STICKING OUT OF NEWLY LAID SOD IT IS A SAFETY HAZZARD ** NOTE AREAS REQUIRING ATTENTION HIGH LIGHTED WITH PINK PAINT ** SEE ATTACHED PHOTOS FROM TODAYS INSPECTION _______________________________________________________________________________________________________________________ 8/11/2025 - PREVIOUS INSPECTION NOTES ** 08/11/25 NEED TO REPAIR AREA ON SIDE BETWEEN #3 AND #5 PROJECT SITE WHERE RUTS FROM MACHINE WERE CREATED ** NEED TO REMOVE SEDIMENT OUT OF CANAL ON LEFT SIDE OF DOCK THAT ERRODED IN DURING PROJECT AS WELL AS TO THE RIGHT OF BOAT DOCK AND PROPERTY LINE ** BUILDER NEEDS TO CREATE THE SWALE ACROSS THE ENTIRE SEAWALL AS INDICATED IN DRAWING 1100.J AS NOTED IN SECTION 1100.10 SEAWALLS/BULKHEAD/REVETMENT CONSTRUCTION PERMIT REQUIREMENTS ** SOD NEEDS TO BE CUT INTO PLACE TO MATCH EXISTING GRADE
ROW - STORMWATER FINAL 10/10/2025 Disapproved -FEE REQUIRED EMADISON
Note: ** 10/10/25 NEED TO REPAIR THE WASHOUTS BENEATH SOD OF BOTH RIGHT AND LEFT SIDES WASHOUTS ARE BENEATH THE NEW SOD ** WHERE NEW SOD JOINS WITH NEED TO INSTALL ANOTHER ROW OF SOD AND CUT IN TO MATCH THE EXISTING GRADE AND COVER THE EXPOSED BARE EARTH ** RIGHT SIDE BARE AREA BETWEEN #3 AND YOUR PROJECT SITE YOU NEED TO REPAIR WHERE AREA WAS DAMAGED DUE TO MACHINE TRACKING SOD REQUIRED TO MATCH WHAT WAS DAMAGED DURRING YOUR PROJECT SOD REQUIRED TO BE CUT IN TO MATCH GRADE THIS WAS DISCUSSED DURRING OUR SITE MEET FOR THE REQUIRED CORRECTIONS ** NEED TO REMOVE THE PIECE OF STEEL THAT WAS LEFT STICKING OUT OF NEWLY LAID SOD IT IS A SAFETY HAZZARD ** NOTE AREAS REQUIRING ATTENTION HIGH LIGHTED WITH PINK PAINT ** SEE ATTACHED PHOTOS FROM TODAYS INSPECTION _______________________________________________________________________________________________________________________ 8/11/2025 - PREVIOUS INSPECTION NOTES ** 08/11/25 NEED TO REPAIR AREA ON SIDE BETWEEN #3 AND #5 PROJECT SITE WHERE RUTS FROM MACHINE WERE CREATED ** NEED TO REMOVE SEDIMENT OUT OF CANAL ON LEFT SIDE OF DOCK THAT ERRODED IN DURING PROJECT AS WELL AS TO THE RIGHT OF BOAT DOCK AND PROPERTY LINE ** BUILDER NEEDS TO CREATE THE SWALE ACROSS THE ENTIRE SEAWALL AS INDICATED IN DRAWING 1100.J AS NOTED IN SECTION 1100.10 SEAWALLS/BULKHEAD/REVETMENT CONSTRUCTION PERMIT REQUIREMENTS ** SOD NEEDS TO BE CUT INTO PLACE TO MATCH EXISTING GRADE
ROW- PROJECT STATUS 08/25/2025 Status Check EMADISON
Note: ** 9:00 AM SITE MEET ** 08/25/25 met with contractor and site development to discuss proper grading required behind the seawall
ROW- PROJECT STATUS 08/22/2025 CANCELLED BY INSPECTOR EMADISON
Note: ** 08/18/25 9:00 AM SITE
ROW - STORMWATER FINAL 08/11/2025 Disapproved - NO FEE EMADISON
Note: ** 08/11/25 NEED TO REPAIR AREA ON SIDE BETWEEN #3 AND #5 PROJECT SITE WHERE RUTS FROM MACHINE WERE CREATED ** NEED TO REMOVE SEDIMENT OUT OF CANAL ON LEFT SIDE OF DOCK THAT ERRODED IN DURING PROJECT AS WELL AS TO THE RIGHT OF BOAT DOCK AND PROPERTY LINE ** BUILDER NEEDS TO CREATE THE SWALE ACROSS THE ENTIRE SEAWALL AS INDICATED IN DRAWING 1100.J AS NOTED IN SECTION 1100.10 SEAWALLS/BULKHEAD/REVETMENT CONSTRUCTION PERMIT REQUIREMENTS ** SOD NEEDS TO BE CUT INTO PLACE TO MATCH EXISTING GRADE
ROW - FINAL INSPECTION 08/11/2025 Disapproved -FEE REQUIRED EMADISON
Note: ** 08/11/25 NEED TO REPAIR AREA ON SIDE BETWEEN #3 AND #5 PROJECT SITE WHERE RUTS FROM MACHINE WERE CREATED ** NEED TO REMOVE SEDIMENT OUT OF CANAL ON LEFT SIDE OF DOCK THAT ERRODED IN DURING PROJECT AS WELL AS TO THE RIGHT OF BOAT DOCK AND PROPERTY LINE ** BUILDER NEEDS TO CREATE THE SWALE ACROSS THE ENTIRE SEAWALL AS INDICATED IN DRAWING 1100.J AS NOTED IN SECTION 1100.10 SEAWALLS/BULKHEAD/REVETMENT CONSTRUCTION PERMIT REQUIREMENTS ** SOD NEEDS TO BE CUT INTO PLACE TO MATCH EXISTING GRADE ** SEE ATTACHED PHOTO
SEAWALL DEADMAN CAP 06/17/2025 APPROVED HCAMACHO
ROW -TURBIDITY BARRER 04/28/2025 APPROVED FSLADISH
Note: 4/28/25 TURBITY BARRIER INSTALLED CORRECTLY AT THE TIME OF THIS INSPECION. YOU ARE REQUIRED TO KEEP BARRIER UP AND MAINTAINED THROUGHOUT THE CONSTRUCTION PROCESS.

Review History

Department Status Date In Date Out
ENGIN1 COMPLETE 03/14/2025 03/14/2025
Note: Released By: LEVI SALYERDS - (386)986-2575 - LSALYERDS@PALMCOASTGOV.COM
ZON COMPLETE 03/05/2025 03/05/2025
Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM
ENGIN1 HOLD 03/05/2025 03/10/2025
Note: Held By: LEVI SALYERDS - (386)986-2326 - LSALYERDS@PALMCOASTGOV.COM Please address previous comment: 1. On your site or engineering plan. please call out the connection type and/or sealing of joints at existing seawalls as necessary. Some sections of the engineering plan are difficult to read. The lineweight appears to be too high in some areas.
ENGIN1 HOLD 02/18/2025 03/04/2025
Note: Held By: LEVI SALYERDS - (386)986-2326 - LSALYERDS@PALMCOASTGOV.COM 1. On your site or engineering plan. please call out the connection type and/or sealing of joints at existing seawalls as necessary. Some sections of the engineering plan are difficult to read. The lineweight appears to be too high in some areas.
ZON HOLD 02/18/2025 02/18/2025
Note: Held By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM Please provide a note on the site plan that the seawall will be grey in color as is required by the Land Development Code.

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
RSI REINSPECTION 1 ¤35.00 11/12/2025
SW ENG REINSPECTION 20 ¤20.00 11/12/2025
SW ENG - REVIEW 20 ¤20.00 03/14/2025
SITE PLAN 15 ¤15.00 03/14/2025
SURCHARGE FS 533.721 ¤2.00 03/14/2025
SURCHARGE - FS 468.631 ¤2.14 03/14/2025
SW ENG REVIEW- 40 ¤40.00 03/14/2025
SW ENG - INSPECTION 20 ¤20.00 03/14/2025
ADJUSTMENT 10% (¤15.88) 03/14/2025
ADMINISTRATIVE RESIDENTIAL ¤30.00 03/14/2025
INSPECTION - RESIDENTIAL ¤96.25 03/14/2025
PLAN REVIEW - MISC 32.50 ¤32.50 03/14/2025
Fees Total Due: ¤0.00 Total Paid: ¤297.01