I want to search for...
Permit #2025020941
Permit Details
Status: FINAL
| Parcel Id: 07-11-31-7034-00360-0110 |
| Block: 00360 |
| Subdivision: - |
| Job Phone: 386-627-1357 |
| Location Address: 6 EASTGATE LN |
| Type: DR - DRIVEWAY |
| Issue Date: 03/16/2025 |
| NOC: RECORDED |
| Applicant name: MITCHELL REED |
| Owner: DAY JOHN M & CAROLYN J H&W |
|
Address 6 EASTGATE LANE PALM COAST, FL 32164 |
| Lot: 0110 |
| Contracted Stated Job Value: ¤14,000.00 |
| Job Description: Paver driveway |
| Type: CN |
Contractor
ROYAL PAVING LLC
| Status | Location Address | Phone |
| ACTIVE |
4 LEWISTON COURT PALM COAST, FL 32137 |
386-237-7516 |
Inspection History
| Type | Request Date | Result | Inspector |
| ROW - FINAL INSPECTION | 04/23/2025 | APPROVED | EMADISON |
| Note: ** At the time of the inspection all minimum city requirements were met. It is the builder’s responsibility to ensure that nothing changes after this Inspection is approved. | |||
| ROW - FINAL INSPECTION | 04/14/2025 | Disapproved - NO FEE | EMADISON |
| Note: ** 04/14/25 BUILDER NEEDS TO ADHERE THE PAVERS TO THE MITERED ENDS WHEN INSPECTOR WAS WALKING ON MITERED ENDS THEY MOVED UNDER FOOT SAFETY HAZZARD ** NOTE WAS ABLE TO PULL OUT PAVERS ______________________________________________________________________________________________________________________ 4/9/2025 - PREVIOUS INSPECTION NOTES 04/09/25 TPOLACEK*** RIGHT SIDE OF DRIVEWAY FROM THE CULVERT TO THE WALKWAY. BUILDER MUST REMOVE SOD AND GRADE SO IT IS NOT A HAZARD TO ANYONE STEPPING OFF DRIVEWAY. SOD SHOULD MATCH GRADE AND HAVE A SMOOTH TRANSITION. ++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ 3/31/2025 - PREVIOUS INSPECTION NOTES 03/31 25 TPOLACEK**** ALL SOD MUST MATCH GRADE ALONG DRIVEWAY EDGE, CULVERT SHALL BE FREE AND CLEAR OF DEBRIS AND SEDIMENT THAT HAS WASHED IN. 5 Compacted dirt and sod must Drawing 300-G-12 Compacted dirt and sod must be placed around all edges of the poured concrete including around the miter ends and the driveway shoulders to prevent washout-ALL DISTURBED AREAS SHALL BE STABILIZED WITH SOD MATCHING EXISTING GRADE. | |||
| ROW - FINAL INSPECTION | 04/09/2025 | Disapproved -FEE REQUIRED | TPOLACEK |
| Note: 04/09/25 TPOLACEK*** RIGHT SIDE OF DRIVEWAY FROM THE CULVERT TO THE WALKWAY. BUILDER MUST REMOVE SOD AND GRADE SO IT IS NOT A HAZARD TO ANYONE STEPPING OFF DRIVEWAY. SOD SHOULD MATCH GRADE AND HAVE A SMOOTH TRANSITION. ++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ 3/31/2025 - PREVIOUS INSPECTION NOTES 03/31 25 TPOLACEK**** ALL SOD MUST MATCH GRADE ALONG DRIVEWAY EDGE, CULVERT SHALL BE FREE AND CLEAR OF DEBRIS AND SEDIMENT THAT HAS WASHED IN. 5 Compacted dirt and sod must Drawing 300-G-12 Compacted dirt and sod must be placed around all edges of the poured concrete including around the miter ends and the driveway shoulders to prevent washout-ALL DISTURBED AREAS SHALL BE STABILIZED WITH SOD MATCHING EXISTING GRADE. | |||
| U -UTILITY RESIDENTIAL FINAL | 03/31/2025 | FINAL APPROVED | LFITZGERALD |
| ROW - FINAL APRON (AFTER POUR) | 03/31/2025 | APPROVED | TPOLACEK |
| Note: PAVERS ARE SET AT THE TIME OF THE INSPECTION, ALL MINIMUM CITY REQUIREMENTS WERE MET. NIETHER THE INSPECTOR NOR THE CITY IS RESPONSIBLE IF, FOR WHATEVER REASON, SITE CONDITIONS CHANGE OVER TIME AFTER THE INSPECTION. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED | |||
| ROW - FINAL INSPECTION | 03/31/2025 | Disapproved -FEE REQUIRED | TPOLACEK |
| Note: 03/31 25 TPOLACEK**** ALL SOD MUST MATCH GRADE ALONG DRIVEWAY EDGE, CULVERT SHALL BE FREE AND CLEAR OF DEBRIS AND SEDIMENT THAT HAS WASHED IN. 5 Compacted dirt and sod must Drawing 300-G-12 Compacted dirt and sod must be placed around all edges of the poured concrete including around the miter ends and the driveway shoulders to prevent washout-ALL DISTURBED AREAS SHALL BE STABILIZED WITH SOD MATCHING EXISTING GRADE. | |||
| ROW- PRE-APRON (PRE-POUR) | 03/26/2025 | APPROVED | FSLADISH |
| Note: 3/26/25 YOU ARE APPREVED TO LAY PAVERS AT THE TIME OF THIS INSPECTION. BUILDER RESPONSIBLE IF, FOR WHATEVER REASON, SITE CONDITIONS CHANGE OVER TIME AFTER THE INSPECTION. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED. ___________________________________________________________________________________________________________________________ 3/19/2025 - PREVIOUS INSPECTION NOTES 3/19/25 AT THE TIME OF THIS INSPECTION YOU ARE PARTIALLY APPROVED TO POUR YOUR DRIVEWAY APRON, AND PAVER RESTRAINTS. **** DO NOT LAY ANY PAVERS UNTIL AFTER A SECONDARY SPREAD AND COMPACTION INSPECTION HAS BEEN SCHEDULED AND PASSED**** BUILDER SHOULD MAKE SURE IS 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE (FRC) DRAWING 300,E RESIDENTIAL CULVERT DETAIL BEFORE POURING. DOUBLE CHECK CULVERT ELEVATIONS | |||
| ROW- PAVER RESTRAINTS | 03/19/2025 | APPROVED | FSLADISH |
| Note: 3/19/25 AT THE TIME OF THIS INSPECTION YOU ARE APPROVED TO POUR YOUR PAVER RESTRAINTS. **** DO NOT LAY ANY PAVERS UNTIL AFTER A SECONDARY SPREAD AND COMPACTION INSPECTION HAS BEEN SCHEDULED AND PASSED**** BUILDER SHOULD MAKE SURE IS 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE (FRC) DRAWING 300,E RESIDENTIAL CULVERT DETAIL BEFORE POURING. DOUBLE CHECK CULVERT ELEVATIONS | |||
| ROW- PRE-APRON (PRE-POUR) | 03/19/2025 | PARTIALLY APPROVED | FSLADISH |
| Note: 3/19/25 AT THE TIME OF THIS INSPECTION YOU ARE PARTIALLY APPROVED TO POUR YOUR DRIVEWAY APRON, AND PAVER RESTRAINTS. **** DO NOT LAY ANY PAVERS UNTIL AFTER A SECONDARY SPREAD AND COMPACTION INSPECTION HAS BEEN SCHEDULED AND PASSED**** BUILDER SHOULD MAKE SURE IS 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE (FRC) DRAWING 300,E RESIDENTIAL CULVERT DETAIL BEFORE POURING. DOUBLE CHECK CULVERT ELEVATIONS |
Review History
| Department | Status | Date In | Date Out |
| ZON | COMPLETE | 03/06/2025 | 03/06/2025 |
| Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM | |||
| ZON | HOLD | 03/04/2025 | 03/04/2025 |
| Note: Held By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM Please submit original Right of Way Utilization Agreement for Paver Driveway | |||
| ZON | HOLD | 02/27/2025 | 02/28/2025 |
| Note: Held By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM REPEAT COMMENT: Please submit electronic copy of Right of Way Utilization Agreement for Paver Driveway for staff review. This document must be signed by all persons on deed to property and all signatures must be notarized. | |||
| ENGIN1 | COMPLETE | 02/27/2025 | 02/28/2025 |
| Note: Released By: LEVI SALYERDS - (386)986-2326 - LSALYERDS@PALMCOASTGOV.COM | |||
| SWALE | COMPLETE | 02/20/2025 | 02/27/2025 |
| Note: Released By: LEVI SALYERDS - (386)986-2326 - LSALYERDS@PALMCOASTGOV.COM | |||
| ENGIN1 | HOLD | 02/19/2025 | 02/20/2025 |
| Note: Held By: LEVI SALYERDS - (386)986-2326 - LSALYERDS@PALMCOASTGOV.COM Please include the type and size of the culvert on the site plan. 13"x17" CMP, 15" CMP, or 15" HDPE. | |||
| UTL | COMPLETE | 02/19/2025 | 02/24/2025 |
| Note: Released By: LARRY FITZGERALD - (386)286-2041 - LFITZGERALD@PALMCOASTGOV.COM | |||
| ZON | HOLD | 02/19/2025 | 02/20/2025 |
| Note: Held By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM Please submit electronic copy of Right of Way Utilization Agreement for Paver Driveway for staff review. This document must be signed by all persons on deed to property and all signatures must be notarized. |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| SW ENG REINSPECTION 20 | ¤20.00 | 04/13/2025 |
| SW ENG REINSPECTION 20 | ¤20.00 | 04/08/2025 |
| SW ENG RES REVIEW 200 | ¤200.00 | 03/16/2025 |
| SITE PLAN 15 | ¤15.00 | 03/16/2025 |
| ADJUSTMENT 10% | (¤3.00) | 03/16/2025 |
| ADMINISTRATIVE RESIDENTIAL | ¤30.00 | 03/16/2025 |
| RECORDING FEE REIMBURSE DOC | ¤44.00 | 03/16/2025 |
| SW ENG INSPECTION 40 | ¤40.00 | 03/16/2025 |
| SW ENG PRE APRON | ¤30.00 | 03/16/2025 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤396.00 |