I want to search for...

Permit #2025021258

Permit Details

Status: INSPECT

Parcel Id: 42-10-30-3210-00000-3000
CONDITIONED SPACE: 2258 sqft
GARAGE: 619 sqft
OPENED PORCH (WITH ROOF) : 216 sqft
Total Square Footage: 3093 sqft
Block: 00000
Subdivision: 3210 -
Job Phone: 386-236-4133
Location Address: 428 BOURGANVILLE DR
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 03/12/2025
NOC: RECORDED
Applicant name: LEONARDO CIRO SANCLEMENTE
Owner: MHK OF VOLUSIA COUNTY INC

Address

2379 BEVILLE ROAD

DAYTONA BEACH, FL 32119

Lot: 3000
Contracted Stated Job Value: ¤320,330.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

VOLUSIA RESIDENTIAL CONSTRUCTION, LLC
Status Location Address State License Number Phone
ACTIVE

2379 BEVILLE RD

DAYTONA BEACH, FL 32119

CBC1262114 (Exp: 08/31/2026) 386-236-4133

Sub Contractors

JONATHAN M PEARSON
Status Location Address State License Number Phone Fax
ACTIVE

209 N FORSYTH ST

BUNNELL, FL 32110

CFC1425941 (Exp: 08/31/2026) 386-597-0944 386-437-4996
HUGH MACDONALD
Status Location Address State License Number Phone
ACTIVE

10825 TOM FOLSOM ROAD, SUITE A

THONOTOSASSA, FL 33592

CCC1329562 (Exp: 08/31/2026) 813-986-4968
TIMUR ISPARYAN
Status Location Address State License Number Phone Fax
ACTIVE

3665 SPRINK PARK ROAD

JACKSONVILLE , FL 32207

CMC1249968 (Exp: 08/31/2026) 904-245-1818 904-337-1910
JAMES M GREENSLADE
Status Location Address State License Number Phone Fax
ACTIVE

311 S BAY ST

BUNNELL, FL 32110

EC13006083 (Exp: 08/31/2026) 386-263-2960 386-263-2980

Inspection History

Type Request Date Result Inspector
FOUND SURVEY APPROVED (OFFICE)
PLUMBING 1ST ROUGH UNDERGROUND
GRAVITY SEWER TEST
SEWER TIE IN
ELECTRIC - EARLY POWER
MONOLITHIC SLAB
LATH/BRICK/ WATER BARRIER
TIE BEAM / LINTEL
ALL ROUGH
WALL SHEATHING
ROOF SHEATHING / BRACES/TIES/DOWN CELL
ROOF VALLEY & METAL
INSULATION
BLD - BUILDING FINAL
WATER METER INSTALLATION REQUEST
U-CROSS CONNECTION
ROW- PRE-APRON (PRE-POUR)
ROW - FINAL APRON (AFTER POUR)
ROW- FINAL SURVEY/GRADING CERTIFICATION
ROW FIELD SURVEY /GRADING CERTIFICATION
ROW - STORMWATER FINAL
U -UTILITY RESIDENTIAL FINAL

Review History

Department Status Date In Date Out
SW1 CANCEL 12/09/2025 12/15/2025
ENGIN1 COMPLETE 12/09/2025 12/15/2025
Note: Released By: RODNEY RICKS - (386)986-4726 - RRICKS@PALMCOASTGOV.COM
SW1 COMPLETE 12/09/2025 12/15/2025
Note: Released By: RODNEY RICKS - (386)986-4726 - RRICKS@PALMCOASTGOV.COM
ZON COMPLETE 12/09/2025 12/09/2025
Note: Released By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM
BADMIN INFORMATION 12/05/2025 12/05/2025
Note: Marked INFORMATION By: JAZMIN ROSARIO - - JROSARIO@PALMCOASTGOV.COM FORM NOT COMPLETED. MISSING PRINTED NAME AND TITLE
ENGIN1 COMPLETE 10/14/2025 10/15/2025
Note: Released By: LEVI SALYERDS - (386)986-2575 - LSALYERDS@PALMCOASTGOV.COM
RSI CANCEL 10/14/2025 10/16/2025
SW1 HOLD 10/14/2025 10/16/2025
Note: Held By: RODNEY RICKS - (386)986-4726 - RRICKS@PALMCOASTGOV.COM Site Plan Comments: Revised site plan does not have proposed FFE. Please revise.
ZON COMPLETE 10/14/2025 10/15/2025
Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM
SW1 COMPLETE 09/30/2025 10/01/2025
Note: Released By: RODNEY RICKS - (386)986-4726 - RRICKS@PALMCOASTGOV.COM
ENGIN1 COMPLETE 09/30/2025 10/01/2025
Note: Released By: LEVI SALYERDS - (386)986-2575 - LSALYERDS@PALMCOASTGOV.COM
ZON COMPLETE 09/30/2025 09/30/2025
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
SW1 HOLD 09/22/2025 09/26/2025
Note: Held By: RODNEY RICKS - (386)986-4726 - RRICKS@PALMCOASTGOV.COM Grading comments: There shall be no slopes more than 4:1. On the fright side of this property there are slopes greater than 4:1. in 3.3' the maximum drop shall be no more than 0.825'. Please revise ensuring that there are no slopes greater than 4:1.
ENGIN1 COMPLETE 09/22/2025 09/23/2025
Note: Released By: LEVI SALYERDS - (386)986-2575 - LSALYERDS@PALMCOASTGOV.COM
ZON COMPLETE 09/22/2025 09/23/2025
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
SW1 HOLD 09/19/2025 09/19/2025
Note: Held By: EDWARD MADISON - (386)986-4770 - EMADISON@PALMCOASTGOV.COM ** 09/19/25 site plan shows an existing elevation shot in cormer at lanai and structure of (31.8) which will hold water need to show positive flow away from the structure
ENGIN1 COMPLETE 09/19/2025 09/22/2025
Note: Released By: LEVI SALYERDS - (386)986-2575 - LSALYERDS@PALMCOASTGOV.COM
ZON COMPLETE 09/19/2025 09/19/2025
Note: Released By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM
BLD COMPLETE 08/25/2025 08/29/2025
Note: Released By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM
ELEC COMPLETE 08/25/2025 08/27/2025
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
ENGIN1 COMPLETE 08/25/2025 08/26/2025
Note: Released By: LEVI SALYERDS - (386)986-2575 - LSALYERDS@PALMCOASTGOV.COM
MECH COMPLETE 08/25/2025 08/26/2025
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
SW1 HOLD 08/25/2025 09/02/2025
Note: Held By: RODNEY RICKS - (386)986-4726 - RRICKS@PALMCOASTGOV.COM Grading comments: Revised site plan has no proposed elevations. Please revise.
ZON COMPLETE 08/25/2025 08/25/2025
Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM
MECH COMPLETE 06/05/2025 06/06/2025
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
MECH HOLD 06/03/2025 06/05/2025
Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Energy Calcs need to be signed by the owner/ owner agent below the preparer per R103.1.1.2 FBC Energy Conservation 2023 8Th edition
MECH HOLD 05/30/2025 06/02/2025
Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM 1. Plans call out R4.1 insulation on walls. Energy Calcs say R5.8. Revise 2. Plans show wood adjacent wall with R19. Energy Calcs say CMU with R5.8. Revise (Second Request)
BLD CANCEL 05/30/2025 06/02/2025
MECH HOLD 05/23/2025 05/27/2025
Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM 1. Plans call out R4.1 insulation on walls. Energy Calcs say R5.8. Revise 2. Plans show wood adjacent wall with R19. Energy Calcs say CMU with R5.8. Revise 3. Energy Calcs need to be signed by the owner/ owner agent below the preparer per R103.1.1.2 FBC Energy Conservation 2023 8Th edition
SW1 COMPLETE 05/15/2025 05/20/2025
Note: Released By: RODNEY RICKS - (386)986-2001 - RRICKS@PALMCOASTGOV.COM
ENGIN1 COMPLETE 05/15/2025 05/20/2025
Note: Released By: RODNEY RICKS - (386)986-2001 - RRICKS@PALMCOASTGOV.COM
ZON COMPLETE 05/15/2025 05/15/2025
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
SW1 HOLD 05/07/2025 05/12/2025
Note: Held By: RODNEY RICKS - (386)986-2001 - RRICKS@PALMCOASTGOV.COM Verified that the proposed Finished Floor Elevation was increased to align with the FFEs of Lots 301 (under construction) and 298 (improved), ensuring no future grading or drainage issues for Lot 299. Also confirmed that the proposed common swale elevations between Lots 301 and 300 are consistent across both site plans Correction needed: Missing proposed elevation in the back yard on the right side for the drainage swale.
ENGIN1 COMPLETE 05/07/2025 05/08/2025
Note: Released By: LEVI SALYERDS - (386)986-2575 - LSALYERDS@PALMCOASTGOV.COM
ZON COMPLETE 05/07/2025 05/07/2025
Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM
ENGIN1 COMPLETE 04/30/2025 05/02/2025
Note: Released By: LEVI SALYERDS - (386)986-2575 - LSALYERDS@PALMCOASTGOV.COM
SW1 HOLD 04/30/2025 05/05/2025
Note: Held By: PARREN FLANAGAN - (386)986-2392 - PFLANAGAN@PALMCOASTGOV.COM NEED TO EXPLAIN WHY YOU ARE RAISING FFE OF THE STURCTURE 1.5' FROM THE LAST SITE PLAN. NEED TO HAVE PROPOSED ELEVATIONS OF THE DRAINAGE PATTERN BETWEEN THE BACK PROPERTY LINE AND THE STURCTURE TO SO IF DRAINAGE WILL FLOW PROPERLY
ZON COMPLETE 04/30/2025 05/01/2025
Note: Released By: MICHELLE RAMOS - (386)986-3780 - MRAMOS@PALMCOASTGOV.COM
ZON COMPLETE 03/05/2025 03/05/2025
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
URB COMPLETE 02/26/2025 03/05/2025
Note: Released By: JOHN BEAUDET - (386)986-2456 - JBEAUDET@PALMCOASTGOV.COM
BADMIN COMPLETE 02/25/2025 03/04/2025
Note: Released By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM
BLD COMPLETE 02/25/2025 03/04/2025
Note: Released By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM
CUSVC COMPLETE 02/25/2025 02/25/2025
Note: Released By: REBECCA SANDERS - - RSANDERS@PALMCOASTGOV.COM UTILITY FEES PAID ON PREVIOUS PERMIT
ELEC COMPLETE 02/25/2025 03/03/2025
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
ENGIN1 COMPLETE 02/25/2025 02/26/2025
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
GAS CANCEL 02/25/2025 02/27/2025
LOCATE COMPLETE 02/25/2025 03/03/2025
Note: Released By: CANDACE BOWERMASTER - - CBOWERMASTER@PALMCOASTGOV.COM
MECH COMPLETE 02/25/2025 02/28/2025
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
SW1 COMPLETE 02/25/2025 02/26/2025
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
ZON HOLD 02/25/2025 02/26/2025
Note: Held By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM Landscape plan missing sod type and if irrigation will be installed

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
ADJUSTMENT 10% (¤155.85) 03/12/2025
ADMINISTRATIVE RESIDENTIAL ¤30.00 03/12/2025
INSPECTION - RESIDENTIAL ¤1,190.75 03/12/2025
PLAN REVIEW - RESIDENTIAL ¤337.74 03/12/2025
FC IMPACT FEE EMS ¤62.00 03/12/2025
IMPACT FEE FIRE ¤434.51 03/12/2025
FC IMPACT FEE LAW ENFORCEMENT ¤218.00 03/12/2025
FC IMPACT FEE LIBRARY ¤268.00 03/12/2025
IMPACT FEE PARKS ¤1,828.01 03/12/2025
IMPACT FEE SCHOOL ¤5,450.00 03/12/2025
IMPACT FEE TRANSPORTATION ¤3,404.00 03/12/2025
SURCHARGE FS 533.721 ¤14.03 03/12/2025
SURCHARGE - FS 468.631 ¤21.04 03/12/2025
SW ENG - FOUNDATION SURVEY ¤20.00 03/12/2025
SW ENG INSPECTION 80 ¤80.00 03/12/2025
SW ENG PRE APRON ¤30.00 03/12/2025
SW ENG - REVIEW 20 ¤20.00 03/12/2025
SW ENG RES REVIEW 200 ¤200.00 03/12/2025
SITE PLAN 30 ¤30.00 03/12/2025
CONTRACTOR CHANGE ¤20.00
CONTRACTOR CHANGE ¤20.00
EXTENSION ¤40.00
EXTENSION ¤40.00
Fees Total Due: ¤120.00 Total Paid: ¤13,482.23