I want to search for...

Permit #2025040212

Permit Details

Status: FINAL

Parcel Id: 07-11-31-7003-00070-0130
Block: 00070
Subdivision: -
Job Phone: 386-566-6359
Location Address: 26 CLINTON CT S
Type: SW - SEAWALL
Issue Date: 04/24/2025
NOC: RECORDED
Applicant name: THAD RAYMOND ADAMEK
Owner: BOWMAN GILBERT & BARBARA C/O JULIAN ANDERSON BOWMA

Address

43 WARRINER GARDENS

LONDON SW11 4EA UK, 0

Address

WEYBRIDGE SURREY

LONDON SW11 4EA UK, 0

Lot: 0130
Contracted Stated Job Value: ¤35,000.00
Job Description: REPLACE SEAWALL
Type: CN

Contractor

HALIFAX MARINE CONSTRUCTION, INC
Status Location Address State License Number Phone
ACTIVE

945 DUNCAN ROAD

SOUTH DAYTONA, FL 32119

CRC1330178 (Exp: 08/31/2026) 386-767-4972

Inspection History

Type Request Date Result Inspector
SEAWALL FINAL 07/08/2025 FINAL APPROVED HCAMACHO
SEAWALL FINAL 07/07/2025 Disapproved - NO FEE HCAMACHO
Note: Please remove turbity barrier before we can Final.
ROW - STORMWATER FINAL 07/02/2025 APPROVED - AS NOTED PFLANAGAN
Note: PLEASE REMOVE TURIBITY BARRIER
ROW - FINAL INSPECTION 07/02/2025 APPROVED PFLANAGAN
Note: At the time of the inspection all minimum city requirements were met. It is the builders and the homowners responsibility to ensure that nothing changes after this Inspection is approved. It will not be on the city if any changes after this inspection.
SEAWALL DEADMAN CAP 04/28/2025 FINAL APPROVED HCAMACHO
ROW -TURBIDITY BARRER 04/25/2025 APPROVED - AS NOTED FSLADISH
Note: 4/25/25 The permittee shall be responsible for the maintaining the barrier for the duration of the project to ensure continuous protection of the waterbody. Repairs to the barrier will be performed in accordance with the manufacturer’s specifications. C. Once operations below the mean high water line are completed, the collected sediment will be removed and the original depth or plan elevation shall be restored. Any spoils from the operation must be removed to an upland area and stabilized. Suspended sediment will be allowed to settle before removing the barrier. Floating turbidity barriers shall be removed in such a manner as to minimize turbidity.

Review History

Department Status Date In Date Out
BLD COMPLETE 04/24/2025 04/24/2025
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
BLD HOLD 04/03/2025 04/08/2025
Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM COMMENTS BELOW PER THE 2023 FLORIDA BUILDING CODE-BUILDING (FBCB), CITY OF PALM COAST LAND DEVELOPMENT CODE, CITY OF PALM COAST TECHNICAL MANUAL (COPCTM), FLORIDA STATUTES (FS), FLORIDA ADMINISTRATIVE CODE (FAC), AND AUTHORITY HAVING JURISDICTION (AHJ). Add General Note (or similarly titled) section titled “City of Palm Coast Seawalls, Bulkheads and Revetments Construction Standards” conspicuously displayed on the plans and add the following general notes: 1. Seawall and revetment construction shall conform to the City of Palm Coast Technical Manual Engineering Design Standards Section 1100.09 Seawalls / Bulkheads and Revetments and the City of Palm Coast Unified Land Development Code Chapter 4, Section 4.01.06. In the event of conflict between seawall and revetment design plans and The City of Palm Coast Technical Manual Engineering Design Standards Section 1100.09, the City of Palm Coast Technical Manual Engineering Design Standards Section 1100.09 and the Unified Land Development Code Chapter 4, Section 4.01.06 shall be controlling. 2. Turbidity barriers shall be installed and maintained in accordance with the City of Palm Coast Technical Manual Engineering Design Standards Section 1200 Erosion Control, Section 1200.01 and Drawing # 1200 B Floating Turbidity Barrier Example. 3. Turbidity barriers shall be installed prior to construction, removal of turf and landscaping and disturbance and removal of any part of the seawall. 4. Turbidity barriers shall be installed and maintained and shall remain in place for the duration of construction and shall not be removed until collected sediment and debris have been removed to the original canal depth or approved plan elevation. 5. Turbidity barriers shall remain in place until all upland areas have been restored and all landscaping and final lot improvements have been completed and the ROW Final Inspection is approved by the City. 6. Turbidity barriers shall not be anchored or otherwise attached to any seawall. 7. Existing seawall panels, bulkhead cap, restraints / deadman, seawall panels shall be completely removed from the City of Palm Coast Right-of-Way and lawfully disposed of in accordance with Florida Statutes and Department of Environmental Protection regulations. Exceptions for partial seawall reconstruction projects may be accepted by the City of Palm Coast at its discretion and with prior coordination and approval before commencement of seawall removal / deconstruction. 8. The new seawall shall be installed entirely within private property and in vertical and horizontal alignment with existing, adjacent seawalls. If no adjacent seawalls exist then seawall panels are to be installed within private property. Not more than one-half of the bulkhead cap may project into the City Right-of-Way provided no part of the seawall panels project into the Right of Way. 9. The top of the seawall bulkhead cap shall be a maximum of elevation of 2.5 feet based on the NAVD 88. 10. The top of the seawall bulkhead cap may be increased in elevation when connection to an existing bulkhead at the end of the canal is necessary but in no case can the new seawall cap be at a higher elevation than the bulkhead at the end of the canal. The maximum allowed transition in elevation is the width of one (1) seawall panel. PLAN COMMENTS 1. PROVIDE SEAWALL GRADING PLAN PREPARED BY A FLORIDA LICENSED PROFESSIONAL ENGINEER. GRADING PLAN IS TO PROVIDE SUFFICIENT DESIGN INFORMATIONINCLUDING FINISHED GRADE ELEVATIONS, DIRECTIONAL INDICATORS OF STORMWATER FLOWS THAT INDICATE STORMWATER IS DIRECTED INTO THE CANALWITHOUT TOPPING OR CIRCUMVENTING SEAWALL RETURNS. lENGHTH AND ELEVATION OF SEAWALL RETURNS MUST BE SHOWN INCLUDING ANY STEPPING NECESSARY TO ENSURE STORMWATER IS MAINTAINED ON THE LOT UNTIL IT REACHES THE CANAL. GRADING PLAN TO SHOW REQUIRED SWALE AND SWALE SLOPES FOR SWALE ADJACENT TO SEAWALL. COPCTM SECTION 1100.10. SECTION A ABD B 2. ENGINEERED PLANS NEED TO DESIGNATE THE ELEVATION OF THE SEAWALL BULKHEAD CAP NO MORE THAN 2.5 FEET NAVD. LDC CHAPTER 4, SECTION 4.01.06 E.1. 3. ENGINEER NEEDS TO PROVIDE THE STRUCTURAL CONNECTION OF BULKHEAD CAP TO ADJACENT SEAWALL. SEAWALL PANELS ARE LAPPED OR ABUTTED USING ½ INCH EXPANSION JOINT MATERIAL AND DETAIL PROVIDED ON PLANS. 4. PROVIDE STRUCTURAL CONNECTION OF SEAWALL CAP AND PANELS TO ADJACENT SEAWALL CAP AND PANELS OR PROVIDE A SEWALL RETURN . SEAWALL RETURN TO EXTEND A MINIMUM OF 10 FEET INTO THE PROPERTY AND CONSTRUCTED IN THE SAME MANNER AS OTHER PARTS OF THE SEAWALL. SEAWALL RETURN MUST EXTEND FURTHER INTO THE LOT A SUFFICIENT DISTANCE TO ENSURE THE COMPLETED POST-CONSTRUCTION GRADING CAN BE COMPLETED IN A MANNER SO THAT LOT STORMWATER DRAINAGE REMAINS ON THE LOT UNTIL IT FLOWS OVER THE SEAWALL AND DOES NOT TOP OR CIRCUMVENT THE RETURN AND IMPACT ADJACENT LOT OWNER. SEE APPROVED GRADING AND DRAINAGE PLAN TO VERIFY LENGTHS AND ELEVATIONS OF RETURNS MATCH WHAT IS SHOWN ON THE ENGINEERED PLANS. COPCTM SECTION 1100.09, DRAWING #1100.G. 5. ENGINEERED PLANS NEED TO DESIGNATE THE NEW SEAWALL BULKHEAD CAP TO BE AT SAME ELEVATION AS ADJACENT SEAWALLS.
ENGIN1 COMPLETE 04/03/2025 04/11/2025
Note: Released By: CARMELO MORALES - (386)986-4758 - CMORALES@PALMCOASTGOV.COM
ZON COMPLETE 04/03/2025 04/03/2025
Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
ADJUSTMENT 10% (¤15.88) 04/24/2025
ADMINISTRATIVE RESIDENTIAL ¤30.00 04/24/2025
INSPECTION - RESIDENTIAL ¤96.25 04/24/2025
PLAN REVIEW - MISC 32.50 ¤32.50 04/24/2025
SURCHARGE FS 533.721 ¤2.00 04/24/2025
SURCHARGE - FS 468.631 ¤2.14 04/24/2025
SW ENG REVIEW- 40 ¤40.00 04/24/2025
SW ENG - INSPECTION 20 ¤20.00 04/24/2025
SW ENG - REVIEW 20 ¤20.00 04/24/2025
SITE PLAN 15 ¤15.00 04/24/2025
Fees Total Due: ¤0.00 Total Paid: ¤242.01