Permit #2025041270

Permit Details

Status: COED

Parcel Id: 07-11-31-7013-00240-0060
CONDITIONED SPACE: 1809 sqft
GARAGE: 406 sqft
OPENED PORCH (WITH ROOF) : 33 sqft
Total Square Footage: 2248 sqft
Block: 00240
Subdivision: 7013 -
Job Phone: 239-571-5325
Location Address: 71 BROCKTON LN
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 05/02/2025
NOC: RECORDED
Applicant name: RYAN SCOTT DAVIS
Owner: SYNERGY HOMES LLC

Address

581 NW MERCANTILE PLACE

PORT SAINT LUCIE, FL 34986

Address

106

PORT SAINT LUCIE, FL 34986

Lot: 0060
Contracted Stated Job Value: ¤200,000.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

SYNERGY HOMES, LLC
Status Location Address State License Number
ACTIVE

1 HARGROVE GRADE, SUITE B1

PALM COAST, FL 32137

CBC1254289 (Exp: 08/31/2026)

Sub Contractors

MICHAEL FRANK MORELLO
Status Location Address State License Number Phone Fax
ACTIVE

2 HARGROVE GRADE

PALM COAST, FL 32164

CAC1819466 (Exp: 08/31/2026) 386-445-5023 386-446-4614
HEATH EDWARD SANFORD
Status Location Address State License Number Phone
ACTIVE

126 EAST END RD

SAN MATEO, FL 32187

CFC1429896 (Exp: 08/31/2026) 386-871-8823
WILLIAM FRANK DUDLEY JR.
Status Location Address State License Number Phone
ACTIVE

P.O. BOX 978

Bunnell, FL 32110

EC0003177 (Exp: 08/31/2026) (386)437-3068
TERRY BRICE DICKERSON
Status Location Address State License Number Phone
ACTIVE

4300 ST JOHN'S PARKWAY

ALPHARETTA, GA 30009

CCC1326209 (Exp: 08/31/2026) 407-548-6733

Inspection History

Type Request Date Result Inspector
BLD - BUILDING FINAL 11/20/2025 FINAL APPROVED JSTEWART
Note: 11/17/2025 - PREVIOUS INSPECTION NOTES 11/17/25 Via text at 11:22am 11/13/2025 - PREVIOUS INSPECTION NOTES via text
ROW - STORMWATER FINAL 11/20/2025 Disapproved -FEE REQUIRED PFLANAGAN
Note: STILL NEED TO REMOVE ALL OVER POURED CONCRETE AND SEDIMENT FROM THE CULVERT PIPE --------------------------------------------------------------------- 11/19/2025 - PREVIOUS INSPECTION NOTES 11-19-25 TPOLACEK*** BUILDER MUST REMOVE ALL OVER POUR CONCRETE AND SEDIMENT FROM CULVERT APPROVING THE AFTER POUR AND WILL HOLD IN FINAL ROW
ROW - STORMWATER FINAL 11/20/2025 APPROVED - AS NOTED PFLANAGAN
Note: DID VIRTUAL INSPECTION WITH GREYSON TO PASS FINAL STORMWATER FOR CORRECTIONS ON CLEANING CULVERT. -------------------------------------------------------------------- 11/20/2025 - PREVIOUS INSPECTION NOTES STILL NEED TO REMOVE ALL OVER POURED CONCRETE AND SEDIMENT FROM THE CULVERT PIPE --------------------------------------------------------------------- 11/19/2025 - PREVIOUS INSPECTION NOTES 11-19-25 TPOLACEK*** BUILDER MUST REMOVE ALL OVER POUR CONCRETE AND SEDIMENT FROM CULVERT APPROVING THE AFTER POUR AND WILL HOLD IN FINAL ROW
U -UTILITY RESIDENTIAL FINAL 11/19/2025 FINAL APPROVED BWRIGHT
ROW - STORMWATER FINAL 11/19/2025 Disapproved - NO FEE TPOLACEK
Note: 11-19-25 TPOLACEK*** BUILDER MUST REMOVE ALL OVER POUR CONCRETE AND SEDIMENT FROM CULVERT APPROVING THE AFTER POUR AND WILL HOLD IN FINAL ROW
ROW - FINAL APRON (AFTER POUR) 11/19/2025 APPROVED - AS NOTED TPOLACEK
Note: 11-19-25 TPOLACEK*** BUILDER MUST REMOVE ALL OVER POUR CONCRETE AND SEDIMENT FROM CULVERT APPROVING THE AFTER POUR AND WILL HOLD IN FINAL ROW
ROW- FINAL SURVEY/GRADING CERTIFICATION 11/18/2025 APPROVED TPOLACEK
ROW FIELD SURVEY /GRADING CERTIFICATION 11/18/2025 APPROVED TPOLACEK
Note: UPON WALKING PROPERTY DRAINAGE WILL WORK AS INDICATED ON FINAL SURVEY. AT THE TIME OF THE INSPECTION, ALL MINIMUM CITY REQUIREMENTS WERE MET. NIETHER THE INSPECTOR NOR THE CITY IS RESPONSIBLE IF, FOR WHATEVER REASON, SITE CONDITIONS CHANGE OVER TIME AFTER THE INSPECTION. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED
BLD - BUILDING FINAL 11/17/2025 CANCELLED BY APPLICANT MCONTRYMAN
Note: 11/17/25 Via text at 11:22am 11/13/2025 - PREVIOUS INSPECTION NOTES via text
BLD - BUILDING FINAL 11/13/2025 CANCELLED BY APPLICANT JSTEWART
Note: via text
ROW- PRE-APRON (PRE-POUR) 11/04/2025 APPROVED - AS NOTED TPOLACEK
Note: 11-04-25 TPOLACEK*** BUILDER NEEDS TO REPAIR LEFT SIDE MITER END BOARDS AND REESTABLISH FOOTERS BEFORE POURING. AT THE TIME OF THE INSPECTION CULVERT PIPE IS GOOD IS READY TO POUR, IF RAIN PLEASE, BUILDER SHOULD DOUBLE CHECK CULVERT ELEVATIONS MAKE SURE TO USE 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE (FRC) DRAWING 300,E RESIDENTIAL CULVERT DETAIL BEFORE POURING. CONTRACTORS WILL BE NOTIFIED WHEN TICKETS WILL BE REQUIRED WITH AN EMAIL BLAST.THE FOLLOWING IS CURRENTLY FOR INFORMATION ONLY: TICKET OF CONCRETE MIX DESIGN SHALL BE UPLOADED INTO PERMIT PORTAL. 8.a. IF FIBERGLASS OPTION IS USED, DOCUMENTATION OF THE ( FRC) CONTAINING THE FIBERGLASS MUST BE ATTACHED TO THE PERMIT PRIOR TO REQUESTING AN AFTER-POUR INSPECTION. 8.b. IF MESH OPTION IS USED, IT SHALL BE IN PLACE AT THE TIME OF THE PRE-POUR. + 10/31/2025 - PREVIOUS INSPECTION NOTES BUILDER REQUESTED I CANCEL INSPECTION
ROW- PRE-APRON (PRE-POUR) 10/31/2025 CANCELLED BY APPLICANT TPOLACEK
Note: BUILDER REQUESTED I CANCEL INSPECTION
ELECTRIC - EARLY POWER 09/26/2025 APPROVED - AS NOTED MCONTRYMAN
Note: 9/26/25 Email sent to FPL
SEWER TIE IN 09/24/2025 APPROVED - AS NOTED MGIBSON
Note: THIS WAS A VIRTUAL INSPECTION
INSULATION 09/05/2025 APPROVED FWILLIS
Note: Inspector Notes from Inspection 2420 Revised Plan for 24" OC has been submitted and approved. 9/2/2025 - PREVIOUS INSPECTION NOTES Previous Note not rectified.....1. All interior wall exceed 16'' o.c per detail on 9.0 DTL - "8" Interior walls (Non bearing) are framed 24" OC, Plan calls for 16" OC. please frame walls per plan or submit a revision to the city for approval indicationg 24" OC. 8/28/2025 - PREVIOUS INSPECTION NOTES 8/28/25 1. All interior wall exceed 16'' o.c per detail on 9.0 DTL - "8" 2. All goose necks and vent boots are missing FBC EC R402.4.1.1 3. Center bedroom #2 smoke detector romex sheathing has been strip back to far, sheathing must extend a min of 1/4'' into box NEC 314.17(B)(1)
ALL ROUGH 09/04/2025 APPROVED - AS NOTED JSTEWART
Note: Revised Plan for 24" OC has been submitted and approved. 9/2/2025 - PREVIOUS INSPECTION NOTES Previous Note not rectified.....1. All interior wall exceed 16'' o.c per detail on 9.0 DTL - "8" Interior walls (Non bearing) are framed 24" OC, Plan calls for 16" OC. please frame walls per plan or submit a revision to the city for approval indicationg 24" OC. 8/28/2025 - PREVIOUS INSPECTION NOTES 8/28/25 1. All interior wall exceed 16'' o.c per detail on 9.0 DTL - "8" 2. All goose necks and vent boots are missing FBC EC R402.4.1.1 3. Center bedroom #2 smoke detector romex sheathing has been strip back to far, sheathing must extend a min of 1/4'' into box NEC 314.17(B)(1)
ALL ROUGH 09/02/2025 Disapproved -FEE REQUIRED JSTEWART
Note: Previous Note not rectified.....1. All interior wall exceed 16'' o.c per detail on 9.0 DTL - "8" Interior walls (Non bearing) are framed 24" OC, Plan calls for 16" OC. please frame walls per plan or submit a revision to the city for approval indicationg 24" OC. 8/28/2025 - PREVIOUS INSPECTION NOTES 8/28/25 1. All interior wall exceed 16'' o.c per detail on 9.0 DTL - "8" 2. All goose necks and vent boots are missing FBC EC R402.4.1.1 3. Center bedroom #2 smoke detector romex sheathing has been strip back to far, sheathing must extend a min of 1/4'' into box NEC 314.17(B)(1)
ALL ROUGH 08/28/2025 Disapproved - NO FEE MKRASKI
Note: 8/28/25 1. All interior wall exceed 16'' o.c per detail on 9.0 DTL - "8" 2. All goose necks and vent boots are missing FBC EC R402.4.1.1 3. Center bedroom #2 smoke detector romex sheathing has been strip back to far, sheathing must extend a min of 1/4'' into box NEC 314.17(B)(1)
LATH/BRICK/ WATER BARRIER 08/28/2025 APPROVED FWILLIS
ALL ROUGH 08/27/2025 CANCELLED BY APPLICANT JSTEWART
Note: 8/26/2025 - PREVIOUS INSPECTION NOTES Previous Notes not rectified... All Rough Not Ready, Electricians are still installing. Please verify work is complete for Inspection, prior to scheduling. [A]110.6 Approval required. 8/25/2025 - PREVIOUS INSPECTION NOTES Previous notes not rectified. All Rough Not Ready, Electricians are still installing. Please verify work is complete for Inspection, prior to scheduling. [A]110.6 Approval required. Inspector Notes from Inspection 2460 *** NOTES ADDED BY JSTEWART 8/19/2025 2:00:29 PM *** please add stud or blocking at interior wall connections (wall buck) to fasten end stud 24"OC. FBC 2304.10.1 Fastener requirements. #8 in the fastening schedule. Please fasten end studs at garage walls where 2x connects to CMU wall. 2318.1.12 Studs joining masonry or reinforced concrete walls. will check at all rough Inspector Notes from Inspection 2340 *** NOTES ADDED BY JSTEWART 8/7/2025 2:28:09 PM *** Please remove Portable restroom from swale area, as to not impede the flow of storm water. FBC 3303.5 NOTE: Truss Package onsite, ground contact delivery, not covered.
ALL ROUGH 08/26/2025 Disapproved -FEE REQUIRED JSTEWART
Note: Previous Notes not rectified... All Rough Not Ready, Electricians are still installing. Please verify work is complete for Inspection, prior to scheduling. [A]110.6 Approval required. 8/25/2025 - PREVIOUS INSPECTION NOTES Previous notes not rectified. All Rough Not Ready, Electricians are still installing. Please verify work is complete for Inspection, prior to scheduling. [A]110.6 Approval required. Inspector Notes from Inspection 2460 *** NOTES ADDED BY JSTEWART 8/19/2025 2:00:29 PM *** please add stud or blocking at interior wall connections (wall buck) to fasten end stud 24"OC. FBC 2304.10.1 Fastener requirements. #8 in the fastening schedule. Please fasten end studs at garage walls where 2x connects to CMU wall. 2318.1.12 Studs joining masonry or reinforced concrete walls. will check at all rough Inspector Notes from Inspection 2340 *** NOTES ADDED BY JSTEWART 8/7/2025 2:28:09 PM *** Please remove Portable restroom from swale area, as to not impede the flow of storm water. FBC 3303.5 NOTE: Truss Package onsite, ground contact delivery, not covered.
ALL ROUGH 08/25/2025 Disapproved - NO FEE JSTEWART
Note: Previous notes not rectified. All Rough Not Ready, Electricians are still installing. Please verify work is complete for Inspection, prior to scheduling. [A]110.6 Approval required. Inspector Notes from Inspection 2460 *** NOTES ADDED BY JSTEWART 8/19/2025 2:00:29 PM *** please add stud or blocking at interior wall connections (wall buck) to fasten end stud 24"OC. FBC 2304.10.1 Fastener requirements. #8 in the fastening schedule. Please fasten end studs at garage walls where 2x connects to CMU wall. 2318.1.12 Studs joining masonry or reinforced concrete walls. will check at all rough Inspector Notes from Inspection 2340 *** NOTES ADDED BY JSTEWART 8/7/2025 2:28:09 PM *** Please remove Portable restroom from swale area, as to not impede the flow of storm water. FBC 3303.5 NOTE: Truss Package onsite, ground contact delivery, not covered.
WALL SHEATHING 08/19/2025 APPROVED JSTEWART
Note: Inspector Notes from Inspection 2340 *** NOTES ADDED BY JSTEWART 8/7/2025 2:28:09 PM *** Please remove Portable restroom from swale area, as to not impede the flow of storm water. FBC 3303.5 NOTE: Truss Package onsite, ground contact delivery, not covered.
ROOF SHEATHING / BRACES/TIES/DOWN CELL 08/19/2025 APPROVED - AS NOTED JSTEWART
Note: *** NOTES ADDED BY JSTEWART 8/19/2025 2:00:29 PM *** please add stud or blocking at interior wall connections (wall buck) to fasten end stud 24"OC. FBC 2304.10.1 Fastener requirements. #8 in the fastening schedule. Please fasten end studs at garage walls where 2x connects to CMU wall. 2318.1.12 Studs joining masonry or reinforced concrete walls. will check at all rough Inspector Notes from Inspection 2340 *** NOTES ADDED BY JSTEWART 8/7/2025 2:28:09 PM *** Please remove Portable restroom from swale area, as to not impede the flow of storm water. FBC 3303.5 NOTE: Truss Package onsite, ground contact delivery, not covered.
ROOF VALLEY & METAL 08/19/2025 APPROVED JSTEWART
Note: Inspector Notes from Inspection 2340 *** NOTES ADDED BY JSTEWART 8/7/2025 2:28:09 PM *** Please remove Portable restroom from swale area, as to not impede the flow of storm water. FBC 3303.5 NOTE: Truss Package onsite, ground contact delivery, not covered.
GRAVITY SEWER TEST 08/18/2025 APPROVED MGIBSON
TIE BEAM / LINTEL 08/07/2025 APPROVED - AS NOTED JSTEWART
Note: *** NOTES ADDED BY JSTEWART 8/7/2025 2:28:09 PM *** Please remove Portable restroom from swale area, as to not impede the flow of storm water. FBC 3303.5 NOTE: Truss Package onsite, ground contact delivery, not covered.
MONOLITHIC SLAB 07/31/2025 APPROVED JSTEWART
Note: 7/30/2025 - PREVIOUS INSPECTION NOTES 7/20/25 1. Missing 1 rebar on right side of garage wall (highlighted on plans)
MONOLITHIC SLAB 07/30/2025 Disapproved - NO FEE MCONTRYMAN
Note: 7/20/25 1. Missing 1 rebar on right side of garage wall (highlighted on plans)
U-CROSS CONNECTION 07/30/2025 APPROVED DHANEY
Note: *** NOTES ADDED BY DHANEY 7/30/2025 8:01:45 AM *** No Illegal hose CN's - no Cross CN. .
PLUMBING 1ST ROUGH UNDERGROUND 07/25/2025 APPROVED JSTEWART
FORMBOARD SURVEY (OFFICE USE ONLY) 07/21/2025 APPROVED - AS NOTED GBERTOLA
Note: Formboard approved.
GEOTECHNICAL REPORT APPROVAL (OFFICE USE) 07/17/2025 APPROVED JMUNSON
WATER METER INSTALLATION REQUEST 06/27/2025 APPROVED CBOWERMASTER

Review History

Department Status Date In Date Out
BLD COMPLETE 09/03/2025 09/03/2025
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
SW1 COMPLETE 07/21/2025 07/21/2025
Note: Released By: GABRIEL BERTOLA - (386)986-7660 - GBERTOLA@PALMCOASTGOV.COM
ZON COMPLETE 07/21/2025 07/21/2025
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
BADMIN COMPLETE 07/17/2025 07/17/2025
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
BADMIN COMPLETE 04/24/2025 04/29/2025
Note: Released By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM
BLD COMPLETE 04/24/2025 04/29/2025
Note: Released By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM
CUSVC COMPLETE 04/24/2025 04/30/2025
Note: Released By: HALEIGH HAND - - HHAND@PALMCOASTGOV.COM
ELEC COMPLETE 04/24/2025 04/28/2025
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
ENGIN1 COMPLETE 04/24/2025 04/24/2025
Note: Released By: LEVI SALYERDS - (386)986-2575 - LSALYERDS@PALMCOASTGOV.COM
GAS CANCEL 04/24/2025 04/25/2025
LOCATE COMPLETE 04/24/2025 04/24/2025
Note: Released By: TONI CHURCHILL - - TCHURCHILL@PALMCOASTGOV.COM
MECH COMPLETE 04/24/2025 04/28/2025
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
SW1 COMPLETE 04/24/2025 05/01/2025
Note: Released By: RODNEY RICKS - - RRICKS@PALMCOASTGOV.COM
ZON COMPLETE 04/24/2025 04/24/2025
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
SWALE COMPLETE 04/24/2025 05/12/2025
Note: Released By: LEVI SALYERDS - (386)986-2575 - LSALYERDS@PALMCOASTGOV.COM

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
RSI REINSPECTION 1 ¤35.00 11/20/2025
REINSPECTION RESIDENTIAL ¤40.00 11/20/2025
REINSPECTION RESIDENTIAL ¤40.00 11/20/2025
FC IMPACT FEE EMS ¤62.00 05/02/2025
IMPACT FEE FIRE ¤434.51 05/02/2025
FC IMPACT FEE LAW ENFORCEMENT ¤218.00 05/02/2025
FC IMPACT FEE LIBRARY ¤268.00 05/02/2025
IMPACT FEE PARKS ¤1,828.01 05/02/2025
IMPACT FEE SCHOOL ¤5,450.00 05/02/2025
IMPACT FEE TRANSPORTATION ¤1,916.00 05/02/2025
WATER- TURN ON ¤50.00 05/02/2025
ADJUSTMENT 10% (¤120.20) 05/02/2025
ADMINISTRATIVE RESIDENTIAL ¤30.00 05/02/2025
INSPECTION - RESIDENTIAL ¤913.00 05/02/2025
PLAN REVIEW - RESIDENTIAL ¤258.96 05/02/2025
WASTEWATER MAIN EXTENSION IMPA ¤2,189.82 05/02/2025
SURCHARGE FS 533.721 ¤10.82 05/02/2025
SURCHARGE - FS 468.631 ¤16.23 05/02/2025
SW ENG - FOUNDATION SURVEY ¤20.00 05/02/2025
SW ENG INSPECTION 80 ¤80.00 05/02/2025
SW ENG PRE APRON ¤30.00 05/02/2025
SW ENG - REVIEW 20 ¤20.00 05/02/2025
SW ENG RES REVIEW 200 ¤200.00 05/02/2025
WATER METER W/ TAP ¤2,326.93 05/02/2025
SEWER CREDIT (¤1,466.00) 05/02/2025
WASTEWATER PERM INSPECTION ¤80.00 05/02/2025
WASTEWATER PERM REVIEW ¤25.00 05/02/2025
SEWER CAPITAL FACILITY ¤3,930.70 05/02/2025
WATER CAPITAL FACILITY FEE ¤3,496.74 05/02/2025
WATER PERMIT REVIEW ¤25.00 05/02/2025
WATER MAIN EXTENSION IMPACT ¤854.40 05/02/2025
SITE PLAN 30 ¤30.00 05/02/2025
Fees Total Due: ¤0.00 Total Paid: ¤23,292.92