Permit #2025060361

Permit Details

Status: COED

Parcel Id: 07-11-31-7010-00010-0500
CONDITIONED SPACE: 2023 sqft
GARAGE: 724 sqft
OPENED PORCH (WITH ROOF) : 405 sqft
Total Square Footage: 3152 sqft
Block: 00010
Subdivision: 7010 -
Job Phone: 386-237-8427
Location Address: 36 FERNDALE LN
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 08/18/2025
NOC: RECORDED
Applicant name: JAY DARREN CURBOW
Owner: CHIAVELLI GEORGE & PATRICIA H&W

Address

12 FERNDALE LANE

PALM COAST, FL 32137

Lot: 0500
Contracted Stated Job Value: ¤365,000.00
Job Description: single family residence
Type: CN

Contractor

BLUE WATER HOMES INC
Status Location Address State License Number Phone
ACTIVE

4881 PALM COAST PARKWAY NW UNIT 1

PALM COAST, FL 32137

CBC1258679 (Exp: 08/31/2026) 386-445-3405

Sub Contractors

WILLIAM FRANK DUDLEY JR.
Status Location Address State License Number Phone
ACTIVE

P.O. BOX 978

Bunnell, FL 32110

EC0003177 (Exp: 08/31/2026) (386)437-3068
BRETT CHRISTIAN GIBSON
Status Location Address State License Number Phone
ACTIVE

250 SEGOVIA RD

ST AUGUSTINE, FL 32086

CAC1818423 (Exp: 08/31/2026) 904-229-8131
JEFFREY TROY SABAKA
Status Location Address State License Number Phone Fax
ACTIVE

2191 DEERWOOD ACRES DR

ST AUGUSTINE, FL 32084

CFC1427439 (Exp: 08/31/2026) 904-838-2218 904-819-0965
JACK DOUGLAS LANIER
Status Location Address State License Number Phone Fax
ACTIVE

485 COMMERCE WAY

LONGWOOD , FL 32750

CCC058022 (Exp: 08/31/2026) (321)441-2300 (321)441-2313

Inspection History

Type Request Date Result Inspector
ROW - FINAL APRON (AFTER POUR) 04/02/2026 APPROVED EMADISON
Note: ** AT THE TIME OF THE INSPECTION, ALL MINIMUM CITY REQUIREMENTS WERE MET. NIETHER THE INSPECTOR NOR THE CITY IS RESPONSIBLE IF, FOR WHATEVER REASON, SITE CONDITIONS CHANGE OVER TIME AFTER THE INSPECTION. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED
ROW - STORMWATER FINAL 04/02/2026 APPROVED EMADISON
Note: ** AT THE TIME OF THE INSPECTION, ALL MINIMUM CITY REQUIREMENTS WERE MET. NIETHER THE INSPECTOR NOR THE CITY IS RESPONSIBLE IF, FOR WHATEVER REASON, SITE CONDITIONS CHANGE OVER TIME AFTER THE INSPECTION. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED
U -UTILITY RESIDENTIAL FINAL 04/02/2026 APPROVED BVEIGA
Note: Inspector Notes from Inspection 9035 3/27/2026 - PREVIOUS INSPECTION NOTES Sewer clean-out need to be cut to grade. No CC. No IRR
ROW- FINAL SURVEY/GRADING CERTIFICATION 04/01/2026 APPROVED TPOLACEK
Note: Effective 03-25-26, the ROW Field Survey requirement is no longer in effect for Final Lot Grading and Drainage Certificates for new construction on subdivision and infill lots. All Final Lot Grading and Drainage Certificates for these projects will now be reviewed and approved only in the office. Field verification for the ROW-FIELD SURVEY will no longer be required as part of the standard approval process for these permit types 3/31/2026 - PREVIOUS INSPECTION NOTES 03-31-26 TPOLACEK*** THE LGDC AND THE FINAL SURVEY MUST BE UPLOADED AS ONE FILE/DOCUMENT.
ROW FIELD SURVEY /GRADING CERTIFICATION 04/01/2026 CANCELLED BY INSPECTOR TPOLACEK
Note: Effective 03-25-26, the ROW Field Survey requirement is no longer in effect for Final Lot Grading and Drainage Certificates for new construction on subdivision and infill lots. All Final Lot Grading and Drainage Certificates for these projects will now be reviewed and approved only in the office. Field verification for the ROW-FIELD SURVEY will no longer be required as part of the standard approval process for these permit types
ROW- FINAL SURVEY/GRADING CERTIFICATION 03/31/2026 Disapproved - NO FEE TPOLACEK
Note: 03-31-26 TPOLACEK*** THE LGDC AND THE FINAL SURVEY MUST BE UPLOADED AS ONE FILE/DOCUMENT.
U-CROSS CONNECTION 03/31/2026 APPROVED - AS NOTED BWRIGHT
Note: 3/27/2026 - PREVIOUS INSPECTION NOTES Sewer clean-out need to be cut to grade. No CC. No IRR
U-CROSS CONNECTION 03/27/2026 Disapproved - NO FEE BWRIGHT
Note: Sewer clean-out need to be cut to grade.
ROW FIELD SURVEY /GRADING CERTIFICATION 03/27/2026 CANCELLED BY INSPECTOR EMADISON
Note: ** Effective 03/25/26, the ROW Field Survey requirement is no longer in effect for Final Lot Grading and Drainage Certificates for new construction on subdivision and infill lots. All Final Lot Grading and Drainage Certificates for these projects will now be reviewed and approved only in the office. Field verification for the ROW-FIELD SURVEY will no longer be required as part of the standard approval process for these permit types. ** PER P. BUCKLEY CHIEF BUILDING Inspector. ________________________________________________________________________________________________________________________ 3/5/26 NOTE TO INSPECTOR: Met with contractor for cable box in the roadside swale and told them to sod yard and call AT&T to have it removed from swale. AT&T will be responsible to fix any damage when moved. Any question call Parren
BLD - BUILDING FINAL 03/27/2026 Approval - Private Provider PPROVIDER
ROW- FINAL SURVEY/GRADING CERTIFICATION 03/25/2026 APPROVED TPOLACEK
Note: Effective today, the ROW Field Survey requirement is no longer in effect for Final Lot Grading and Drainage Certificates for new construction on subdivision and infill lots. All Final Lot Grading and Drainage Certificates for these projects will now be reviewed and approved only in the office. Field verification for the ROW-FIELD SURVEY will no longer be required as part of the standard approval process for these permit types AT THE TIME OF THE INSPECTION, ALL MINIMUM CITY REQUIREMENTS WERE MET. NIETHER THE INSPECTOR NOR THE CITY IS RESPONSIBLE IF, FOR WHATEVER REASON, SITE CONDITIONS CHANGE OVER TIME AFTER THE INSPECTION. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED
ROW- PROJECT STATUS 03/05/2026 Status Check PFLANAGAN
Note: Met with contractor for cable box in the roadside swale and told them to sod yard and call AT&T to have it removed from swale. AT&T will be responsible to fix any damage when moved. ------------------------------------------------------------- Meeting a 9am
ROW - DRAINAGE 03/03/2026 APPROVED - AS NOTED EMADISON
Note: ** 03/03/26 SITE DEVELOPMMENT ON SITE WORKING ON FINAL GRADE AT THE TIME OF THIS INSPECTION __________________________________________________________________________________________________________________________ 3/2/2026 - PREVIOUS INSPECTION NOTES 03-02-26 TPOLACEK*** SITE CONDITIONS REMAIN THE SAME, BUILDER HAS NOT NOTIFIED THE INSPECTOR OF A FINAL GRADE DATE. BUILDER STILL NEEDS TO INSTALL ERSOSION CONTROL DEVICE SILT FENCE. INSPECTIONS WILL BE DAILY UNTIL CORRECTED. 2/27/2026 - PREVIOUS INSPECTION NOTES 02-27-26 TPOLACEK*** THERE IS STILL NO SILT FENCE INSTALLED. BUILDER WILL BE RESPONSIBLE TO REPAIR ANY AND ALL WASHOUTS INTO DRAINAGE DITCH AND ADJOIING PROPERTIES. IF BUILDER IS GOING TO FINAL GRADE IN LESS THAN 1 WEEK FROM TODAY BUILDER SHALL CALL INSPECTOR TO NOTIFY THEM OF THEIR INTENT. IF BUILDER FAILS TO CALL BUILDER WILL BE REQUIRED TO INSTALL SILT FENCE AS PREVIOUSLY NOTED IN PRIOR INSPECTIONS 2/24/2026 - PREVIOUS INSPECTION NOTES 02-24-26 TPOLACEK*** SILT FENCE IS STILL NOT IN PLACE AND MUST BE INSTALLED. BUILDER HAS 3 DAYS TO COMPLY 2/12/2026 - PREVIOUS INSPECTION NOTES 02-12-26 TPOLACEK**** BUILDER IS REQUIRED TO REESTABLISH SILT FENCE AROUND ENTIRE PROPERTY, CLEAN OUT TEMPORARY CULVERT AND REMOVE PORTA POTTY FROM THE ROW. 5 DAYS TO COMPLYALL EROSION CONTROL DEVICES MUST STAY IN WORKING ORDER THROUGHOUT THE ENTIRE BUILD PROCESS UNTIL ALL BARE GROUND IS COVERED WITH SOD TO STABILZE FROM WASHOUT.
ROW - DRAINAGE 03/02/2026 Disapproved -FEE REQUIRED TPOLACEK
Note: 03-02-26 TPOLACEK*** SITE CONDITIONS REMAIN THE SAME, BUILDER HAS NOT NOTIFIED THE INSPECTOR OF A FINAL GRADE DATE. BUILDER STILL NEEDS TO INSTALL ERSOSION CONTROL DEVICE SILT FENCE. INSPECTIONS WILL BE DAILY UNTIL CORRECTED. 2/27/2026 - PREVIOUS INSPECTION NOTES 02-27-26 TPOLACEK*** THERE IS STILL NO SILT FENCE INSTALLED. BUILDER WILL BE RESPONSIBLE TO REPAIR ANY AND ALL WASHOUTS INTO DRAINAGE DITCH AND ADJOIING PROPERTIES. IF BUILDER IS GOING TO FINAL GRADE IN LESS THAN 1 WEEK FROM TODAY BUILDER SHALL CALL INSPECTOR TO NOTIFY THEM OF THEIR INTENT. IF BUILDER FAILS TO CALL BUILDER WILL BE REQUIRED TO INSTALL SILT FENCE AS PREVIOUSLY NOTED IN PRIOR INSPECTIONS 2/24/2026 - PREVIOUS INSPECTION NOTES 02-24-26 TPOLACEK*** SILT FENCE IS STILL NOT IN PLACE AND MUST BE INSTALLED. BUILDER HAS 3 DAYS TO COMPLY 2/12/2026 - PREVIOUS INSPECTION NOTES 02-12-26 TPOLACEK**** BUILDER IS REQUIRED TO REESTABLISH SILT FENCE AROUND ENTIRE PROPERTY, CLEAN OUT TEMPORARY CULVERT AND REMOVE PORTA POTTY FROM THE ROW. 5 DAYS TO COMPLYALL EROSION CONTROL DEVICES MUST STAY IN WORKING ORDER THROUGHOUT THE ENTIRE BUILD PROCESS UNTIL ALL BARE GROUND IS COVERED WITH SOD TO STABILZE FROM WASHOUT.
ROW - DRAINAGE 02/27/2026 Disapproved -FEE REQUIRED TPOLACEK
Note: 02-27-26 TPOLACEK*** THERE IS STILL NO SILT FENCE INSTALLED. BUILDER WILL BE RESPONSIBLE TO REPAIR ANY AND ALL WASHOUTS INTO DRAINAGE DITCH AND ADJOIING PROPERTIES. IF BUILDER IS GOING TO FINAL GRADE IN LESS THAN 1 WEEK FROM TODAY BUILDER SHALL CALL INSPECTOR TO NOTIFY THEM OF THEIR INTENT. IF BUILDER FAILS TO CALL BUILDER WILL BE REQUIRED TO INSTALL SILT FENCE AS PREVIOUSLY NOTED IN PRIOR INSPECTIONS 2/24/2026 - PREVIOUS INSPECTION NOTES 02-24-26 TPOLACEK*** SILT FENCE IS STILL NOT IN PLACE AND MUST BE INSTALLED. BUILDER HAS 3 DAYS TO COMPLY 2/12/2026 - PREVIOUS INSPECTION NOTES 02-12-26 TPOLACEK**** BUILDER IS REQUIRED TO REESTABLISH SILT FENCE AROUND ENTIRE PROPERTY, CLEAN OUT TEMPORARY CULVERT AND REMOVE PORTA POTTY FROM THE ROW. 5 DAYS TO COMPLYALL EROSION CONTROL DEVICES MUST STAY IN WORKING ORDER THROUGHOUT THE ENTIRE BUILD PROCESS UNTIL ALL BARE GROUND IS COVERED WITH SOD TO STABILZE FROM WASHOUT.
ROW - DRAINAGE 02/24/2026 Disapproved -FEE REQUIRED TPOLACEK
Note: 02-24-26 TPOLACEK*** SILT FENCE IS STILL NOT IN PLACE AND MUST BE INSTALLED. BUILDER HAS 3 DAYS TO COMPLY 2/12/2026 - PREVIOUS INSPECTION NOTES 02-12-26 TPOLACEK**** BUILDER IS REQUIRED TO REESTABLISH SILT FENCE AROUND ENTIRE PROPERTY, CLEAN OUT TEMPORARY CULVERT AND REMOVE PORTA POTTY FROM THE ROW. 5 DAYS TO COMPLYALL EROSION CONTROL DEVICES MUST STAY IN WORKING ORDER THROUGHOUT THE ENTIRE BUILD PROCESS UNTIL ALL BARE GROUND IS COVERED WITH SOD TO STABILZE FROM WASHOUT.
ROW- PRE-APRON (PRE-POUR) 02/24/2026 APPROVED TPOLACEK
Note: AT THE TIME OF THE INSPECTION CULVERT PIPE IS GOOD IS READY TO POUR, IF RAIN PLEASE, BUILDER SHOULD DOUBLE CHECK CULVERT ELEVATIONS MAKE SURE TO USE 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE (FRC) DRAWING 300,E RESIDENTIAL CULVERT DETAIL BEFORE POURING. TICKET OF CONCRETE MIX DESIGN SHALL BE UPLOADED INTO PERMIT PORTAL. 8.a. IF FIBERGLASS OPTION IS USED, DOCUMENTATION OF THE ( FRC) CONTAINING THE FIBERGLASS MUST BE ATTACHED TO THE PERMIT PRIOR TO REQUESTING AN AFTER-POUR INSPECTION. 8.b. IF MESH OPTION IS USED, IT SHALL BE IN PLACE AT THE TIME OF THE PRE-POUR. WOOD CONTROL JOINTS ARE PROHIBITED IN THE RIGHT-OF-WAY. SAWCUT SHALL BE PROVIDED AT THE EDGE OF ROW AND EVERY 12' THEREAFTER, OR A MINIMUM OF 2 SAWCUTS WHICHEVER IS GREATER"
TUB SET 02/13/2026 Approval - Private Provider PPROVIDER
Note: Inspector Notes from Inspection 2095 1. Plumber called at 11:30 and we did a Virtual inspection. 1/9/2026 - PREVIOUS INSPECTION NOTES 1. At the time of inspection evrything was covered up. FBC P2503.2 UNCOVER WORK TO BE INSPECTED
ELECTRIC - EARLY POWER 02/13/2026 Approval - Private Provider PPROVIDER
ROW - DRAINAGE 02/12/2026 Disapproved -FEE REQUIRED TPOLACEK
Note: 02-12-26 TPOLACEK**** BUILDER IS REQUIRED TO REESTABLISH SILT FENCE AROUND ENTIRE PROPERTY, CLEAN OUT TEMPORARY CULVERT AND REMOVE PORTA POTTY FROM THE ROW. 5 DAYS TO COMPLYALL EROSION CONTROL DEVICES MUST STAY IN WORKING ORDER THROUGHOUT THE ENTIRE BUILD PROCESS UNTIL ALL BARE GROUND IS COVERED WITH SOD TO STABILZE FROM WASHOUT.
SEWER TIE IN 01/09/2026 Disapproved -FEE REQUIRED HCAMACHO
Note: 1. At the time of inspection evrything was covered up. FBC P2503.2 UNCOVER WORK TO BE INSPECTED
SEWER TIE IN 01/09/2026 APPROVED - AS NOTED HCAMACHO
Note: 1. Plumber called at 11:30 and we did a Virtual inspection. 1/9/2026 - PREVIOUS INSPECTION NOTES 1. At the time of inspection evrything was covered up. FBC P2503.2 UNCOVER WORK TO BE INSPECTED
INSULATION 12/18/2025 Approval - Private Provider PPROVIDER
LATH/BRICK/ WATER BARRIER 12/15/2025 Approval - Private Provider PPROVIDER
ALL ROUGH 12/15/2025 Approval - Private Provider PPROVIDER
ROOF VALLEY & METAL 12/01/2025 Approval - Private Provider PPROVIDER
Note: 11/25/2025 2:15:49 PM- PREVIOUS INSPECTION NOTES
ROOF VALLEY & METAL 11/25/2025 Disapproved- Private Provider PPROVIDER
WALL SHEATHING 11/24/2025 Approval - Private Provider PPROVIDER
ROOF SHEATHING / BRACES/TIES/DOWN CELL 11/24/2025 Approval - Private Provider PPROVIDER
TIE BEAM / LINTEL 10/28/2025 Approval - Private Provider PPROVIDER
MONOLITHIC SLAB 10/09/2025 Approval - Private Provider PPROVIDER
PLUMBING 1ST ROUGH UNDERGROUND 09/30/2025 Approval - Private Provider PPROVIDER
GRAVITY SEWER TEST 09/30/2025 Approval - Private Provider PPROVIDER
FORMBOARD SURVEY (OFFICE USE ONLY) 09/29/2025 APPROVED RRICKS
GEOTECHNICAL REPORT APPROVAL (OFFICE USE) 09/22/2025 APPROVED PKNAPIK
WATER METER INSTALLATION REQUEST 09/09/2025 APPROVED CBOWERMASTER
WILDLIFE CHECK - ENVIRONMENTAL 08/18/2025 APPROVED DRODRIGUEZ

Review History

Department Status Date In Date Out
BLD COMPLETE 11/17/2025 11/21/2025
Note: Released By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM
SW1 COMPLETE 10/28/2025 10/28/2025
Note: Released By: RODNEY RICKS - (386)986-4726 - RRICKS@PALMCOASTGOV.COM
ZON COMPLETE 10/28/2025 10/28/2025
Note: Released By: SCOTT THOMAS - (386)986-3780 - STHOMAS@PALMCOASTGOV.COM
BADMIN INFORMATION 10/08/2025 10/08/2025
Note: Marked INFORMATION By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM Can not process inspections need to be schedled
ZON COMPLETE 09/26/2025 09/26/2025
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
SW1 COMPLETE 09/26/2025 09/29/2025
Note: Released By: RODNEY RICKS - (386)986-4726 - RRICKS@PALMCOASTGOV.COM
BLD COMPLETE 09/18/2025 09/22/2025
Note: Released By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM
PLENV COMPLETE 08/13/2025 08/18/2025
Note: Released By: DYLAN RODRIGUEZ - - DRODRIGUEZ@PALMCOASTGOV.COM After action report was submitted and accepted by FWC meeting the requirements for 10.04.01 of the LDC. Staff suggests placing silt fence as soon as possible to prevent gopher tortoises from moving into the lot. If any gopher tortoises are located in the future further coordination may be necessary. In future submittals, acceptance email for after action report is required to be submitted.
BADMIN COMPLETE 06/09/2025 06/16/2025
Note: Released By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM
CUSVC COMPLETE 06/09/2025 06/12/2025
Note: Released By: HALEIGH HAND - - HHAND@PALMCOASTGOV.COM
ENGIN1 COMPLETE 06/09/2025 06/09/2025
Note: Released By: LEVI SALYERDS - (386)986-2575 - LSALYERDS@PALMCOASTGOV.COM
LOCATE COMPLETE 06/09/2025 06/09/2025
Note: Released By: CANDACE BOWERMASTER - - CBOWERMASTER@PALMCOASTGOV.COM
SW1 COMPLETE 06/09/2025 06/16/2025
Note: Released By: RODNEY RICKS - (386)986-4726 - RRICKS@PALMCOASTGOV.COM
ZON COMPLETE 06/09/2025 06/10/2025
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
SWALE COMPLETE 06/09/2025 06/25/2025
Note: Released By: LEVI SALYERDS - (386)986-2575 - LSALYERDS@PALMCOASTGOV.COM
PLENV HOLD 06/09/2025 06/12/2025
Note: Held By: DYLAN RODRIGUEZ - - DRODRIGUEZ@PALMCOASTGOV.COM Staff conducted a site visit on 06/12/25 and found potentially occupied Gopher Tortoise burrow. Please either provide a Gopher Tortoise survey by a QEP that shows the burrow is not within 25ft of construction activities or an approved After Action Report from FWC after relocation activities have been completed.

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
REINSPECTION FEE ¤40.00 03/26/2026
RSI GENERAL INSPECTION 32.50 ¤32.50 03/26/2026
RSI REINSPECTION 1 ¤35.00 03/26/2026
RSI REINSPECTION 1 ¤35.00 03/26/2026
RSI REINSPECTION 1 ¤35.00 03/26/2026
RSI REINSPECTION 1 ¤35.00 03/26/2026
RSI REINSPECTION 2 ¤75.00 03/26/2026
WASTEWATER MAIN EXTENSION IMPA ¤2,385.00 08/18/2025
SURCHARGE FS 533.721 ¤2.52 08/18/2025
SURCHARGE - FS 468.631 ¤3.78 08/18/2025
SW ENG - FOUNDATION SURVEY ¤20.00 08/18/2025
SW ENG INSPECTION 80 ¤80.00 08/18/2025
SW ENG PRE APRON ¤30.00 08/18/2025
SW ENG - REVIEW 20 ¤20.00 08/18/2025
SW ENG RES REVIEW 200 ¤200.00 08/18/2025
WATER METER W/ TAP ¤2,326.93 08/18/2025
SEWER CREDIT (¤1,147.00) 08/18/2025
WASTEWATER PERM INSPECTION ¤80.00 08/18/2025
WASTEWATER PERM REVIEW ¤25.00 08/18/2025
SEWER CAPITAL FACILITY ¤4,415.00 08/18/2025
WATER CAPITAL FACILITY FEE ¤3,790.49 08/18/2025
WATER PERMIT REVIEW ¤25.00 08/18/2025
WATER MAIN EXTENSION IMPACT ¤917.27 08/18/2025
SITE PLAN 30 ¤30.00 08/18/2025
WATER- TURN ON ¤50.00 08/18/2025
ADJUSTMENT 10% (¤3.00) 08/18/2025
ADMINISTRATIVE RESIDENTIAL ¤30.00 08/18/2025
ADMINISTRATIVE - RESID PP ¤225.00 08/18/2025
FC IMPACT FEE EMS ¤62.00 08/18/2025
IMPACT FEE FIRE ¤434.51 08/18/2025
FC IMPACT FEE LAW ENFORCEMENT ¤218.00 08/18/2025
FC IMPACT FEE LIBRARY ¤268.00 08/18/2025
IMPACT FEE PARKS ¤1,828.01 08/18/2025
IMPACT FEE SCHOOL ¤5,450.00 08/18/2025
IMPACT FEE TRANSPORTATION ¤1,916.00 08/18/2025
Fees Total Due: ¤0.00 Total Paid: ¤23,970.01