I want to search for...
Permit #2025061229
Permit Details
Status: COED
| Parcel Id: 07-11-31-7064-00100-0020 |
| Total Square Footage: 27 sqft |
| Block: 00100 |
| Subdivision: 7064 - |
| Job Phone: 386-956-9451 |
| Location Address: 17 LLACH CT |
| Type: RF - REROOF |
| Issue Date: 06/26/2025 |
| NOC: RECORDED |
| Applicant name: MATTHEW JAMES JOYCE |
| Owner: HARDESTY BRANDON C |
|
Address 17 LLACH COURT PALM COAST, FL 32164 |
| Lot: 0020 |
| Contracted Stated Job Value: ¤14,760.00 |
| Job Description: REROOF |
| Type: CN |
Contractor
ED SENEZ ROOFING SPECIALIST, LLC
| Status | Location Address | State License Number | Phone |
| INACTIVE |
1060 E INDUSTRIAL DRIVE ORANGE CITY, FL 32763 |
CCC1332645 (Exp: 08/31/2026) | 376-774-4950 |
Inspection History
| Type | Request Date | Result | Inspector |
| ROOF FINAL | 07/14/2025 | Approval - Private Provider | PPROVIDER |
| PROJECT STATUS (OFFICE USE) | 07/09/2025 | APPROVED | BBEMBRY |
| Note: The roof inspection was performed by city staff in error. Please disregard. Inspection performed by the private provider. | |||
| ROOF IN PROGRESS- MIDROOF | 07/09/2025 | Disapproved -FEE REQUIRED | JSTEWART |
| Note: Roof has been completed with No inspection. FBC [A] 110.1 Spoke with a representative of roofing contractor. Deconstruction as follows will be required for mid roof inspection. 1. Please have a installer remove ridge caps on front ridge by Power mast. 2. Please open small valley front left upper side. 3. Remove shingle on left and right sides at the eave aproximate 36" x 24". Note: please schedule the re inspection for Mid roof same day as deconstruction, and call Inspector with a aproximate time frame when above work is completed. | |||
| ROOF IN PROGRESS- MIDROOF | 07/09/2025 | Approval - Private Provider | PPROVIDER |
| Note: 7/9/2025 - PREVIOUS INSPECTION NOTES Roof has been completed with No inspection. FBC [A] 110.1 Spoke with a representative of roofing contractor. Deconstruction as follows will be required for mid roof inspection. 1. Please have a installer remove ridge caps on front ridge by Power mast. 2. Please open small valley front left upper side. 3. Remove shingle on left and right sides at the eave aproximate 36" x 24". Note: please schedule the re inspection for Mid roof same day as deconstruction, and call Inspector with a aproximate time frame when above work is completed. | |||
| ROOF AFFIDAVIT | 07/08/2025 | APPROVED | CGONCALVES |
Review History
| Department | Status | Date In | Date Out |
| BADMIN | INFORMATION | 07/10/2025 | 07/10/2025 |
| Note: Marked INFORMATION By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM use the portal to schedule the inspections | |||
| BADMIN | INFORMATION | 07/09/2025 | 07/09/2025 |
| Note: Marked INFORMATION By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM use the portal to schedule the inspections |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| ADJUSTMENT 10% | (¤9.00) | 06/26/2025 |
| ADMINISTRATIVE RESIDENTIAL | ¤30.00 | 06/26/2025 |
| INSPECTION - RESIDENTIAL | ¤60.00 | 06/26/2025 |
| SURCHARGE FS 533.721 | ¤2.00 | 06/26/2025 |
| SURCHARGE - FS 468.631 | ¤2.00 | 06/26/2025 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤85.00 |