Permit #2025070331

Permit Details

Status: FINAL

Block: 01010
Subdivision: -
Job Phone: 386-322-8700
Location Address: 1255 SEMINOLE WOODS BLVD
Type: SDD - SUBDIVISION SITE DEVELOPMENT
Issue Date: 08/11/2025
NOC: Unknown
Applicant name: CHAD HAZEN
Owner: BYRNDOG PCP, LLC

Address

180 BROOKHAVEN CT S

PALM COAST, FL 32164

Lot: 0021
Job Description: SITE WORK: SEMINOLE TRACE PHASE 1A
Type: CN

Contractor

HAZEN CONSTRUCTION LLC
Status Location Address State License Number Phone
ACTIVE

1599 TIONIA RD

NEW SMYRNA BEACH, FL 32168

CGC061991 (Exp: 08/31/2026) 386-322-8700

Inspection History

Type Request Date Result Inspector
LDSC- LANDSCAPE / IRRIGATION AS-BUILT 05/19/2026 APPROVED - AS NOTED DRAMIREZ
Note: Bond was submitted.
LDSC- LANDSCAPE FINAL 05/18/2026 APPROVED - AS NOTED DRAMIREZ
Note: BOND SUBMITTED
MAINT BOND ACCEPTANCE (OFFICE) 05/18/2026 APPROVED DRAMIREZ
LDSC-IRRIGATION FINAL 05/18/2026 APPROVED - AS NOTED DRAMIREZ
Note: BOND SUBMITTED.
PERFORMANCE BOND ACCEPTANCE 05/15/2026 APPROVED DRAMIREZ
Note: LANDSCAPE BOND
ROW - EROSION CONTROL / INLET PROTE/SILT FENCE 05/06/2026 APPROVED JMYERS
Note: 4/28/2026 - PREVIOUS INSPECTION NOTES 4/28/26 PER ENVIRONMENTAL PLANNER, 10 THREE-GALLON SAW PALMETTOS SHALL BE PLANTED IN THE WASHOUT AREA BEHIND THE POND TO PROVIDE STABILIZATION. 1/30/2026 - PREVIOUS INSPECTION NOTES 1/30/26 ALL STORM INFRASTRUCTURE IS CLEARED AND APPROVED. WASHOUT BEHIND POND HAS NOT BEEN ADDRESSED, ALL SILT SHALL BE REMOVED FROM WETLANDS BY HAND. 1/28/2026 - PREVIOUS INSPECTION NOTES FINAL WALK SCHEDULED FOR 1/30/26
ROW - EROSION CONTROL / INLET PROTE/SILT FENCE 04/22/2026 Disapproved - NO FEE JMYERS
Note: 4/28/26 PER ENVIRONMENTAL PLANNER, 10 THREE-GALLON SAW PALMETTOS SHALL BE PLANTED IN THE WASHOUT AREA BEHIND THE POND TO PROVIDE STABILIZATION. 1/30/2026 - PREVIOUS INSPECTION NOTES 1/30/26 ALL STORM INFRASTRUCTURE IS CLEARED AND APPROVED. WASHOUT BEHIND POND HAS NOT BEEN ADDRESSED, ALL SILT SHALL BE REMOVED FROM WETLANDS BY HAND. 1/28/2026 - PREVIOUS INSPECTION NOTES FINAL WALK SCHEDULED FOR 1/30/26
CLOSE OUT DOCUMENTS 02/03/2026 APPROVED DRAMIREZ
U-GRAVITY SEWER INSTALL/TESTING 01/30/2026 APPROVED LFITZGERALD
Note: Inspector Notes from Inspection 9220 10/21/2025 - PREVIOUS INSPECTION NOTES sidewalk at east lift station to intersection/also at entrance at Seminole -north side to 4 lane center median sidewalk landings at entrance now installed (ada mats as well)/misc landings thru out site 1/26/2026 - PREVIOUS INSPECTION NOTES 9/10/2025 - PREVIOUS INSPECTION NOTES continuing phase A and B sewer video/mandrel at early start area
ROW - EROSION CONTROL / INLET PROTE/SILT FENCE 01/30/2026 PARTIALLY APPROVED JMYERS
Note: 1/30/26 ALL STORM INFRASTRUCTURE IS CLEARED AND APPROVED. WASHOUT BEHIND POND HAS NOT BEEN ADDRESSED, ALL SILT SHALL BE REMOVED FROM WETLANDS BY HAND. 1/28/2026 - PREVIOUS INSPECTION NOTES FINAL WALK SCHEDULED FOR 1/30/26
UC-FINAL SITE INSPECTION 01/30/2026 FINAL APPROVED LFITZGERALD
Note: 1/26/2026 - PREVIOUS INSPECTION NOTES FINAL WALK SCHEDULED FOR 1/29=THURSDAY
U-ROW FINAL 01/30/2026 FINAL APPROVED LFITZGERALD
Note: 1/26/2026 - PREVIOUS INSPECTION NOTES FINAL WLK SCHEDULED FOR 1/29-THURSDAY
U - UTILITY COMMERCIAL FINAL 01/29/2026 APPROVED LFITZGERALD
ROW - EROSION CONTROL / INLET PROTE/SILT FENCE 01/26/2026 PARTIALLY APPROVED JMYERS
Note: FINAL WALK SCHEDULED FOR 1/30/26
UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) 01/26/2026 APPROVED - AS NOTED LFITZGERALD
Note: 10/21/2025 - PREVIOUS INSPECTION NOTES sidewalk at east lift station to intersection/also at entrance at Seminole -north side to 4 lane center median sidewalk landings at entrance now installed (ada mats as well)/misc landings thru out site
U-ROW FINAL 01/26/2026 CANCELLED BY APPLICANT LFITZGERALD
Note: FINAL WLK SCHEDULED FOR 1/29-THURSDAY
WIRE TEST 01/26/2026 APPROVED BHAINES
U-GRAVITY SEWER INSTALL/TESTING 01/26/2026 CANCELLED BY APPLICANT BHAINES
Note: 9/10/2025 - PREVIOUS INSPECTION NOTES continuing phase A and B sewer video/mandrel at early start area
U-SEWER FORCE MAIN INSTALL/TESTING 01/26/2026 APPROVED BHAINES
Note: 8/28/2025 - PREVIOUS INSPECTION NOTES 6in fm to 2nd lift station along Cascades from lot 118 down silvering street
U-WATER SERVICE INSTALLATION 01/26/2026 APPROVED BHAINES
Note: 9/19/2025 - PREVIOUS INSPECTION NOTES all servce whips accounted for in early start area-Cascades to station 28+20/Sea Myrtle/copper leaf to station10+00 to 12+00,nextr is to flow them all
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR 01/26/2026 APPROVED BHAINES
Note: 8/28/2025 - PREVIOUS INSPECTION NOTES 8/14/2025 - PREVIOUS INSPECTION NOTES now satisfactory at: to lots 181/129 copper leaf to,lots 377/353 copper leaf drive,all river birch to 117/118 cascades remainder of main to end of Cascades
U-REUSE MAIN INSTALL/TESTING 01/26/2026 APPROVED BHAINES
Note: 9/19/2025 - PREVIOUS INSPECTION NOTES 8/14/2025 - PREVIOUS INSPECTION NOTES pressure tested from lots 181/129 to 377/353 on Copper Leaf drive and all river birch lane up to lots cascage 118/117 all service whips accounted for -early start area=Cascades to station 28+50/Sea Myrtle Dr/Copper Leaf 10+00 to12+00
UC-FINAL SITE INSPECTION 01/26/2026 CANCELLED BY APPLICANT LFITZGERALD
Note: FINAL WALK SCHEDULED FOR 1/29=THURSDAY
FDEP WATERMAIN CLEARANCE 01/23/2026 APPROVED BWRIGHT
Note: 9/19/2025 - PREVIOUS INSPECTION NOTES Inspector Notes from Inspection 9235 9/10/2025 - PREVIOUS INSPECTION NOTES miami curb continuing miami curb installed early start area-Cascades to 28+50/Sea Myrtle Dr./Copper Leaf 10+00 to 12+00
POTABLE WATERMAIN FLUSHED AND CHLORINATED 01/23/2026 APPROVED BWRIGHT
Note: 9/30/2025 - PREVIOUS INSPECTION NOTES 9/19/2025 - PREVIOUS INSPECTION NOTES early start areas as already indicated on other inspections next areas chlorinated
POTABLE WATERMAIN BACTERIOLOGICAL SAMPLING 01/23/2026 APPROVED BWRIGHT
Note: 10/2/2025 - PREVIOUS INSPECTION NOTES 10/1/2025 - PREVIOUS INSPECTION NOTES 9/19/2025 - PREVIOUS INSPECTION NOTES early start areas indicated on other inpections Kyle with Hazen finished chlorinating,will obtain samples tomorow and friday DAY 1 samples
HYDRANT - PAINT / FLOW/VALVE/ RPM 01/23/2026 APPROVED BWRIGHT
SIGNAGE - WATER AND SEWER 01/23/2026 APPROVED BWRIGHT
WATERMAIN FLUSH & PRESSURE TESTED 01/23/2026 APPROVED BWRIGHT
Note: 9/19/2025 - PREVIOUS INSPECTION NOTES early start area as indicated on other inspections
PLANNING - OFFICE USE - FINAL AS-BUILT SURVEY 01/20/2026 APPROVED DRAMIREZ
FIRE FINAL (STABILIZED ROADWAY TEST) 01/13/2026 APPROVED LFITZGERALD
U-PUMP STATION START-UP 01/09/2026 APPROVED BHAINES
Note: Inspector Notes from Inspection 9111 Inspector Notes from Inspection 9147 Inspector Notes from Inspection 9602 Inspector Notes from Inspection 9720 all roads now with first lift asphalt temp paint on first lift asphalt-as noted on punch list from walk thru-install painted cross walks between 2 ada landings-john with ETM agreed to get Hazen to take care of all bare areas now with seed and fertilizer-some areas slow going with grass-recommended watering with truck since it's the dry time of year 11/5/2025 - PREVIOUS INSPECTION NOTES 10/1/2025 - PREVIOUS INSPECTION NOTES continuing along Copper Leaf and Cascades from last placement(FDEP Clearence line) 1a now complete with first lift-now redoing patch on Seminole blvd. al areas now paved-waiting on all compaction reports
UC-ASPHALT PRE PLACEMENT 12/18/2025 APPROVED - AS NOTED LFITZGERALD
Note: Inspector Notes from Inspection 9147 Inspector Notes from Inspection 9602 Inspector Notes from Inspection 9720 all roads now with first lift asphalt temp paint on first lift asphalt-as noted on punch list from walk thru-install painted cross walks between 2 ada landings-john with ETM agreed to get Hazen to take care of all bare areas now with seed and fertilizer-some areas slow going with grass-recommended watering with truck since it's the dry time of year 11/5/2025 - PREVIOUS INSPECTION NOTES 10/1/2025 - PREVIOUS INSPECTION NOTES continuing along Copper Leaf and Cascades from last placement(FDEP Clearence line) 1a now complete with first lift-now redoing patch on Seminole blvd. al areas now paved-waiting on all compaction reports
STABLIZED ROAD & ACCESS / TURNAROUNDS 12/18/2025 APPROVED - AS NOTED LFITZGERALD
Note: all roads now with first lift asphalt
UC-TRAF - FINAL (SIGN/PAVEMENT MARKING) 12/18/2025 APPROVED - AS NOTED LFITZGERALD
Note: Inspector Notes from Inspection 9720 all roads now with first lift asphalt temp paint on first lift asphalt-as noted on punch list from walk thru-install painted cross walks between 2 ada landings-john with ETM agreed to get Hazen to take care of
UC-FINAL SITE STABILIZATION 12/18/2025 APPROVED - AS NOTED LFITZGERALD
Note: *** NOTES ADDED BY LFITZGERALD 1/23/2026 3:51:57 PM *** install sidewalk landings at entrance/re pave asphalt patch-Sweminole blvd(open cut area/place back asphalt at ares where sewr services were corrected Inspector Notes from Inspection 9602 Inspector Notes from Inspection 9720 all roads now with first lift asphalt temp paint on first lift asphalt-as noted on punch list from walk thru-install painted cross walks between 2 ada landings-john with ETM agreed to get Hazen to take care of all bare areas now with seed and fertilizer-some areas slow going with grass-recommended watering with truck since it's the dry time of year
UC-SUBSTANTIAL WALK-THRU 12/12/2025 APPROVED - AS NOTED LFITZGERALD
Note: Inspector Notes from Inspection 9108 utilized in order to redo patch on Seminole blvd(wet tap area) 1A was walked with John Goodman-ETM,Mike Oakley-Hazen-JordaMeyers and punch lis for my inspections e-mailed to these parties
UC- PRELIMINARY AS-BUILTS 12/12/2025 APPROVED LFITZGERALD
Note: Inspector Notes from Inspection 9140 Inspector Notes from Inspection 9108 utilized in order to redo patch on Seminole blvd(wet tap area) 1A was walked with John Goodman-ETM,Mike Oakley-Hazen-JordaMeyers and punch lis for my inspections e-mailed to these parties
UC-MOT MAINTENANCE OF TRAFFIC 11/05/2025 APPROVED - AS NOTED LFITZGERALD
Note: utilized in order to redo patch on Seminole blvd(wet tap area)
UC-ASPHALT PRE PLACEMENT 11/05/2025 PARTIALLY APPROVED LFITZGERALD
Note: 10/1/2025 - PREVIOUS INSPECTION NOTES continuing along Copper Leaf and Cascades from last placement(FDEP Clearence line) 1a now complete with first lift-now redoing patch on Seminole blvd.
UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) 10/21/2025 PARTIALLY APPROVED LFITZGERALD
Note: sidewalk at east lift station to intersection/also at entrance at Seminole -north side to 4 lane center median
POTABLE WATERMAIN BACTERIOLOGICAL SAMPLING 10/02/2025 PARTIALLY APPROVED BHAINES
Note: 10/1/2025 - PREVIOUS INSPECTION NOTES 9/19/2025 - PREVIOUS INSPECTION Insepction done with Kyle of Hazen. Will get B-T reports for inspection tomorrow and Friday.
POTABLE WATERMAIN BACTERIOLOGICAL SAMPLING 10/01/2025 PARTIALLY APPROVED LFITZGERALD
Note: 9/19/2025 - PREVIOUS INSPECTION NOTES early start areas indicated on other inpections Kyle with Hazen finished chlorinating,will obtain samples tomorow and friday
UC-ASPHALT PRE PLACEMENT 10/01/2025 PARTIALLY APPROVED LFITZGERALD
Note: continuing along Copper Leaf and Cascades from last placement(FDEP Clearence line)
POTABLE WATERMAIN FLUSHED AND CHLORINATED 09/30/2025 PARTIALLY APPROVED LFITZGERALD
Note: 9/19/2025 - PREVIOUS INSPECTION NOTES early start areas as already indicated on other inspections next areas chlorinated
POTABLE WATERMAIN BACTERIOLOGICAL SAMPLING 09/19/2025 PARTIALLY APPROVED LFITZGERALD
Note: early start areas indicated on other inpections
POTABLE WATERMAIN FLUSHED AND CHLORINATED 09/19/2025 PARTIALLY APPROVED LFITZGERALD
Note: early start areas as already indicated on other inspections
WATERMAIN FLUSH & PRESSURE TESTED 09/19/2025 PARTIALLY APPROVED LFITZGERALD
Note: early start area as indicated on other inspections
FDEP WATERMAIN CLEARANCE 09/19/2025 PARTIALLY APPROVED LFITZGERALD
Note: Inspector Notes from Inspection 9235 9/10/2025 - PREVIOUS INSPECTION NOTES miami curb continuing miami curb installed early start area-Cascades to 28+50/Sea Myrtle Dr./Copper Leaf 10+00 to 12+00
UROW- CURBING & GUTTER 09/19/2025 APPROVED - AS NOTED LFITZGERALD
Note: 9/10/2025 - PREVIOUS INSPECTION NOTES miami curb continuing miami curb installed
UROW-RETENT/DETENT STABILI 09/19/2025 APPROVED LFITZGERALD
U-REUSE MAIN INSTALL/TESTING 09/19/2025 PARTIALLY APPROVED LFITZGERALD
Note: 8/14/2025 - PREVIOUS INSPECTION NOTES pressure tested from lots 181/129 to 377/353 on Copper Leaf drive and all river birch lane up to lots cascage 118/117 all service whips accounted for -early start area=Cascades to station 28+50/Sea Myrtle Dr/Copper Leaf 10+00 to12+00
U-PUMP STATION PRE-INSTALLATION 09/19/2025 APPROVED LFITZGERALD
Note: also noted on original site permit
UC-DRAINAGE PIPE PLACEMENT/LAMPING 09/19/2025 APPROVED LFITZGERALD
Note: 9/10/2025 - PREVIOUS INSPECTION NOTES CONTINUING PHASE a/b
UC-DRAINAGE STRUCT PLACMNT 09/19/2025 APPROVED LFITZGERALD
Note: 9/10/2025 - PREVIOUS INSPECTION NOTES continuing phase A/B
U-WATER SERVICE INSTALLATION 09/19/2025 PARTIALLY APPROVED LFITZGERALD
Note: all servce whips accounted for in early start area-Cascades to station 28+20/Sea Myrtle/copper leaf to station10+00 to 12+00,nextr is to flow them all
U-GRAVITY SEWER INSTALL/TESTING 09/10/2025 PARTIALLY APPROVED LFITZGERALD
Note: continuing phase A and B sewer video/mandrel at early start area
UC-DRAINAGE PIPE PLACEMENT/LAMPING 09/10/2025 PARTIALLY APPROVED LFITZGERALD
Note: CONTINUING PHASE a/b
UC-DRAINAGE STRUCT PLACMNT 09/10/2025 PARTIALLY APPROVED LFITZGERALD
Note: continuing phase A/B
UROW- CURBING & GUTTER 09/10/2025 PARTIALLY APPROVED LFITZGERALD
Note: miami curb continuing
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR 08/28/2025 PARTIALLY APPROVED LFITZGERALD
Note: *** NOTES ADDED BY LFITZGERALD 8/28/2025 12:09:36 PM *** pressure test along Cascades 8/14/2025 - PREVIOUS INSPECTION NOTES now satisfactory at: to lots 181/129 copper leaf to,lots 377/353 copper leaf drive,all river birch to 117/118 cascades remainder of main to end of Cascades
U-SEWER FORCE MAIN INSTALL/TESTING 08/28/2025 PARTIALLY APPROVED LFITZGERALD
Note: 6in fm to 2nd lift station along Cascades from lot 118
U-REUSE MAIN INSTALL/TESTING 08/14/2025 PARTIALLY APPROVED LFITZGERALD
Note: *** NOTES ADDED BY LFITZGERALD 8/14/2025 1:26:39 PM *** pig flush end of cascades,end of penny cress end of copper leaf and end river birch pressure tested from lots 181/129 to 377/353 on Copper Leaf drive and all river birch lane up to lots cascage 118/117
UC-CONSTRUCTION ENTRANCE 08/14/2025 APPROVED - AS NOTED LFITZGERALD
Note: no need since 1st phase now mostly asphalted es. at seminole woods parkway and at also at west end leading into grand landings 5
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR 08/13/2025 PARTIALLY APPROVED LFITZGERALD
Note: *** NOTES ADDED BY LFITZGERALD 8/14/2025 1:28:33 PM *** satisfactory for pressure test *** NOTES ADDED BY LFITZGERALD 8/14/2025 1:27:38 PM *** pig flush end cascades,end copper leaf,end penny dress ,end river birch now satisfactory at: to lots 181/129 copper leaf to,lots 377/353 copper leaf drive,all river birch to 117/118 cascades

Review History

Department Status Date In Date Out
PLENG COMPLETE 07/10/2025 07/10/2025
Note: Released By: DAMARIS RAMIREZ - (386)986-3750 - DRAMIREZ@PALMCOASTGOV.COM
PLLA COMPLETE 07/10/2025 07/10/2025
Note: Released By: DAMARIS RAMIREZ - (386)986-3750 - DRAMIREZ@PALMCOASTGOV.COM
UD1 COMPLETE 07/10/2025 07/10/2025
Note: Released By: DAMARIS RAMIREZ - (386)986-3750 - DRAMIREZ@PALMCOASTGOV.COM

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
ADJUSTMENT 10% (¤25.00) 08/11/2025
ADMINISTRATIVE- SITE DEVELOP ¤250.00 08/11/2025
SITE DEVELOPMENT ADMIN PLANNIN ¤179.00 08/11/2025
SITE INSPECTION ¤855.00 08/11/2025
SITE PLAN 29 ¤29.00 08/11/2025
Fees Total Due: ¤0.00 Total Paid: ¤1,288.00