Permit #2025090043
Permit Details
Status: FINAL
| Parcel Id: 07-11-31-7059-00180-0210 |
| Block: 00180 |
| Subdivision: 7059 - |
| Job Phone: 386-547-2994 |
| Location Address: 41 SEATTLE TRL |
| Type: AL - ALUMINUM SCREEN STRUCTURE |
| Issue Date: 09/08/2025 |
| NOC: RECORDED |
| Applicant name: JOSEPH DEREK CARTWRIGHT |
| Owner: LYNCH MICHAEL W & JENNIFER A LYNCH H&W |
|
Address 41 SEATTLE TRAIL PALM COAST, FL 32164 |
| Lot: 0210 |
| Contracted Stated Job Value: ¤21,628.00 |
| Job Description: Pool enclosure extension on new concrete |
| Type: CN |
Contractor
EAST COAST ALUMINUM OF VOLUSIA INC
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
151 RODEO ROAD ORMOND BEACH, FL 32174 |
SCC131150000 (Exp: 08/31/2026) | 386-310-7962 | (386)615-3713 |
Inspection History
| Type | Request Date | Result | Inspector |
| FINAL - BUILDING MISC | 12/04/2025 | FINAL APPROVED | BTAYLOR |
| ROW- FINAL SURVEY/GRADING CERTIFICATION | 12/02/2025 | APPROVED | FSLADISH |
| Note: 11/19/2025 - PREVIOUS INSPECTION NOTES 11/19/25 YOU HAVE UPLOADED A BOUNDARY SURVEY. COPC REQUIRES A TOPOGRAPHICAL SURVEY THAT MEETS OUR FINAL SURVEY STANDARDS. SURVEY UNCLEAR OR UNREADABLE Section 300.01 F(1) V-17 "Final Survey. The Final Survey is used to verify compliance with the Topographic Survey, Lot Grading Plan and Swale Plan. (1) A Final Survey must be submitted in person or uploaded online. If the survey is incomplete, unclear, does not adequately show the drainage patterns, or if the constructed drainage is incorrect, it will be disapproved until corrections are made and resubmitted for review and approval. Once any required field changes have been made and the survey has been revised, the contractor shall submit one (1) signed and sealed revised survey for review. If the field changes and/or the revised survey is accepted, a final inspection may be scheduled by the contractor." | |||
| ROW FIELD SURVEY /GRADING CERTIFICATION | 12/02/2025 | APPROVED | FSLADISH |
| Note: 12/2/25 AT THE TIME OF THE INSPECTION, ALL MINIMUM CITY REQUIREMENTS WERE MET. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED. | |||
| ROW - FINAL INSPECTION | 12/02/2025 | APPROVED | FSLADISH |
| Note: 12/2/25 AT THE TIME OF THE INSPECTION, ALL MINIMUM CITY REQUIREMENTS WERE MET. IT IS THE BUILDER'S RESPONSIBILITY TO ENSURE THAT NOTHING CHANGES AFTER THIS INSPECTION IS APPROVED. | |||
| ROW- FINAL SURVEY/GRADING CERTIFICATION | 11/19/2025 | Disapproved - NO FEE | FSLADISH |
| Note: 11/19/25 YOU HAVE UPLOADED A BOUNDARY SURVEY. COPC REQUIRES A TOPOGRAPHICAL SURVEY THAT MEETS OUR FINAL SURVEY STANDARDS. SURVEY UNCLEAR OR UNREADABLE Section 300.01 F(1) V-17 "Final Survey. The Final Survey is used to verify compliance with the Topographic Survey, Lot Grading Plan and Swale Plan. (1) A Final Survey must be submitted in person or uploaded online. If the survey is incomplete, unclear, does not adequately show the drainage patterns, or if the constructed drainage is incorrect, it will be disapproved until corrections are made and resubmitted for review and approval. Once any required field changes have been made and the survey has been revised, the contractor shall submit one (1) signed and sealed revised survey for review. If the field changes and/or the revised survey is accepted, a final inspection may be scheduled by the contractor." | |||
| MONOLITHIC SLAB | 09/16/2025 | APPROVED | BTAYLOR |
Review History
| Department | Status | Date In | Date Out |
| RSI | COMPLETE | 09/05/2025 | 09/05/2025 |
| Note: Released By: PARREN FLANAGAN - (386)986-2392 - PFLANAGAN@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 09/05/2025 | 09/05/2025 |
| Note: Released By: MICHELLE RAMOS - (386)986-3780 - MRAMOS@PALMCOASTGOV.COM | |||
| BFLOOD | CANCEL | 09/02/2025 | 09/02/2025 |
| BLD | COMPLETE | 09/02/2025 | 09/02/2025 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| RSI | HOLD | 09/02/2025 | 09/03/2025 |
| Note: Held By: PARREN FLANAGAN - (386)986-2392 - PFLANAGAN@PALMCOASTGOV.COM THE SITE PLAN MUST HAVE THE DIMENSION OF THE NEW CONCRETE PAD | |||
| ZON | COMPLETE | 09/02/2025 | 09/03/2025 |
| Note: Released By: MICHELLE RAMOS - (386)986-3780 - MRAMOS@PALMCOASTGOV.COM |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| ADJUSTMENT 10% | (¤12.25) | 09/08/2025 |
| ADMINISTRATIVE RESIDENTIAL | ¤30.00 | 09/08/2025 |
| INSPECTION - ALUMINUM ENCLOSU | ¤60.00 | 09/08/2025 |
| PLAN REVIEW - MISC 32.50 | ¤32.50 | 09/08/2025 |
| SURCHARGE FS 533.721 | ¤2.00 | 09/08/2025 |
| SURCHARGE - FS 468.631 | ¤2.00 | 09/08/2025 |
| SITE PLAN 15 | ¤15.00 | 09/08/2025 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤129.25 |