Permit #2025090404
Permit Details
Status: INSPECT
| Parcel Id: 04-12-31-0000-04030-0000 |
| Block: 01010 |
| Subdivision: 2370 - COQUINA SHORES |
| Job Phone: (386)931-7331 |
| Location Address: 6150 STATE HWY 100 E |
| Type: CSD - COMMERCIAL SITE DEVELOPMENT |
| Issue Date: 09/23/2025 |
| NOC: Unknown |
| Applicant name: SCOTT DALE SOWERS |
| Owner: PULTE HOME COMPANY LLC |
|
Address 12724 GRAN BAY PARKEAY WEST JACKSONVILLE, FL 32258 |
|
Address SUITE 200 JACKSONVILLE, FL 32258 |
| Lot: 0050 |
| Job Description: OFF-SITE IMPROVMENTS: COQUINA SHORES |
| Type: CN |
Contractor
S E CLINE CONSTRUCTION, INC
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
PO BOX 354425 PALM COAST, FL 32137 |
CGC061947 (Exp: 08/31/2028) | (386)446-6426 | (386)446-6481 |
Inspection History
| Type | Request Date | Result | Inspector |
| UC-MOT MAINTENANCE OF TRAFFIC | 04/15/2026 | APPROVED | LFITZGERALD |
| UC-ASPHALT PRE PLACEMENT | 04/15/2026 | APPROVED | LFITZGERALD |
| Note: 3/30/2026 - PREVIOUS INSPECTION NOTES right turn lane-west bound now paved and striped | |||
| UC-DRAINAGE STRUCT PLACMNT | 04/15/2026 | APPROVED | LFITZGERALD |
| UC-DRAINAGE PIPE PLACEMENT/LAMPING | 04/15/2026 | APPROVED | LFITZGERALD |
| UC- PRELIMINARY AS-BUILTS | 04/15/2026 | APPROVED | LFITZGERALD |
| UC-FINAL SITE INSPECTION | 04/15/2026 | FINAL APPROVED | LFITZGERALD |
| UC-FINAL SITE STABILIZATION | 04/15/2026 | CANCELLED BY INSPECTOR | LFITZGERALD |
| Note: not applicable | |||
| UC-SUBSTANTIAL WALK-THRU | 04/15/2026 | APPROVED | LFITZGERALD |
| Note: 4/10/2026 - PREVIOUS INSPECTION NOTES Clean out the 2" Corp at the end of the reuse line just before the blow off, also swap lid to show reuse. Bring existing water valves to grade and pour new concrete pads | |||
| UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) | 04/15/2026 | APPROVED | LFITZGERALD |
| Note: 4/1/2026 - PREVIOUS INSPECTION NOTES 4/1/2026 - PREVIOUS INSPECTION NOTES 3/2/2026 - PREVIOUS INSPECTION NOTES 2/26/2026 - PREVIOUS INSPECTION NOTES 2/24/2026 - PREVIOUS INSPECTION NOTES waiting on compaction test reports section 1=entrance to about half way to Popeye's-requested compaction reports-still waiting-last week TODAY-section 2=from last pour to Popeye's driveway-still waiting on compaction reports-spoke with Marty Bacon-Cline-he was told all was satisfactory from ECS/sub-contractor BUT I STILL NEED REPORTS sidewalk connection to east entrance-both sides duplicate | |||
| UROW- CURBING & GUTTER | 04/15/2026 | CANCELLED BY INSPECTOR | LFITZGERALD |
| Note: not applicable | |||
| U-ROW FINAL | 04/15/2026 | APPROVED - AS NOTED | LFITZGERALD |
| Note: sod now being placed all along ROW where needed | |||
| UC-TRAF - FINAL (SIGN/PAVEMENT MARKING) | 04/10/2026 | FINAL APPROVED | LFITZGERALD |
| UC- PRELIMINARY AS-BUILTS | 04/10/2026 | APPROVED - AS NOTED | BHAINES |
| Note: ARV'S need to be called out | |||
| UC-SUBSTANTIAL WALK-THRU | 04/10/2026 | PARTIALLY APPROVED | BHAINES |
| Note: Clean out the 2" Corp at the end of the reuse line just before the blow off, also swap lid to show reuse. Bring existing water valves to grade and pour new concrete pads | |||
| UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) | 04/01/2026 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 3/2/2026 - PREVIOUS INSPECTION NOTES 2/26/2026 - PREVIOUS INSPECTION NOTES 2/24/2026 - PREVIOUS INSPECTION NOTES waiting on compaction test reports section 1=entrance to about half way to Popeye's-requested compaction reports-still waiting-last week TODAY-section 2=from last pour to Popeye's driveway-still waiting on compaction reports-spoke with Marty Bacon-Cline-he was told all was satisfactory from ECS/sub-contractor BUT I STILL NEED REPORTS sidewalk connection to east entrance-both sides | |||
| UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) | 04/01/2026 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 4/1/2026 - PREVIOUS INSPECTION NOTES 3/2/2026 - PREVIOUS INSPECTION NOTES 2/26/2026 - PREVIOUS INSPECTION NOTES 2/24/2026 - PREVIOUS INSPECTION NOTES waiting on compaction test reports section 1=entrance to about half way to Popeye's-requested compaction reports-still waiting-last week TODAY-section 2=from last pour to Popeye's driveway-still waiting on compaction reports-spoke with Marty Bacon-Cline-he was told all was satisfactory from ECS/sub-contractor BUT I STILL NEED REPORTS sidewalk connection to east entrance-both sides duplicate | |||
| UC-ASPHALT PRE PLACEMENT | 03/30/2026 | PARTIALLY APPROVED | LFITZGERALD |
| Note: right turn lane-west bound now paved and striped | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 03/03/2026 | CANCELLED BY APPLICANT | JMYERS |
| Note: 2/24/2026 - PREVIOUS INSPECTION NOTES 2/24/26 SILT FENCE INSTALLED BUT SOME JOINTS NEED TO BE RE-WRAPPED AND SOME SECTIONS TRENCHED IN. FOLLOW UP INSPECTION TUESDAY 3/3/26. | |||
| UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) | 03/02/2026 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 2/26/2026 - PREVIOUS INSPECTION NOTES 2/24/2026 - PREVIOUS INSPECTION NOTES waiting on compaction test reports section 1=entrance to about half way to Popeye's-requested compaction reports-still waiting-last week TODAY-section 2=from last pour to Popeye's driveway-still waiting on compaction reports-spoke with Marty Bacon-Cline-he was told all was satisfactory from ECS/sub-contractor BUT I STILL NEED REPORTS | |||
| UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) | 02/25/2026 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 2/24/2026 - PREVIOUS INSPECTION NOTES waiting on compaction test reports | |||
| U-WATER MAIN DISINFECTION | 02/25/2026 | APPROVED | BWRIGHT |
| U-WATER MAIN DISINFECTION SAMPLING | 02/25/2026 | APPROVED | BWRIGHT |
| U-SEWER FORCE MAIN INSTALL/TESTING | 02/25/2026 | APPROVED | BWRIGHT |
| UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) | 02/24/2026 | PARTIALLY APPROVED | LFITZGERALD |
| Note: waiting on compaction test reports | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 02/23/2026 | Disapproved - NO FEE | JMYERS |
| Note: 2/24/26 SILT FENCE INSTALLED BUT SOME JOINTS NEED TO BE RE-WRAPPED AND SOME SECTIONS TRENCHED IN. FOLLOW UP INSPECTION TUESDAY 3/3/26. | |||
| ROW- PROJECT STATUS | 11/13/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: From Subject Received Size Categories Ms. Jordan Myers, CFM Coquina Shores Off-Site Utilities 11:37 AM 25 MB Myself, Brice, Brandon, and Larry were out at the Pre-Con for offsite utilities for Coquina Shores this morning. We were shown the location of the proposed off-site utilities and were extremely concerned with their location inside the wetlands; please see attached photos. There is a very large cypress tree in close proximity as well as a substantial amount of standing water from the swamp. Brice brought up that maintenance of the utilities at this location and the ability to identify a leak with the amount of existing standing water would be extremely problematic. The impacts to the wetlands associated with the Conservation FLUM in the area is also a concern. They are supposed to start work on this tomorrow, however with these issues brought to light I think it is necessary to delay and regroup to discuss possible other locations for these utilities. | |||
| PLAN - PRE-CON 386-986-3750 | 11/13/2025 | APPROVED - AS NOTED | LFITZGERALD |
| Note: meeting on site to discuss and resolve proposed construction(install reuse and forcemain )in a wet land/conservation area(appox.500ft west of project entrance | |||
| PLAN - PRE-CON 386-986-3750 | 09/26/2025 | APPROVED | BWRIGHT |
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | |||
| Note: 3/3/2026 - PREVIOUS INSPECTION NOTES 2/24/2026 - PREVIOUS INSPECTION NOTES 2/24/26 SILT FENCE INSTALLED BUT SOME JOINTS NEED TO BE RE-WRAPPED AND SOME SECTIONS TRENCHED IN. FOLLOW UP INSPECTION TUESDAY 3/3/26. | |||
| ROW- PROJECT STATUS | |||
| Note: 11/13/2025 - PREVIOUS INSPECTION NOTES From Subject Received Size Categories Ms. Jordan Myers, CFM Coquina Shores Off-Site Utilities 11:37 AM 25 MB Myself, Brice, Brandon, and Larry were out at the Pre-Con for offsite utilities for Coquina Shores this morning. We were shown the location of the proposed off-site utilities and were extremely concerned with their location inside the wetlands; please see attached photos. There is a very large cypress tree in close proximity as well as a substantial amount of standing water from the swamp. Brice brought up that maintenance of the utilities at this location and the ability to identify a leak with the amount of existing standing water would be extremely problematic. The impacts to the wetlands associated with the Conservation FLUM in the area is also a concern. They are supposed to start work on this tomorrow, however with these issues brought to light I think it is necessary to delay and regroup to discuss possible other locations for these utilities. | |||
| U - UTILITY COMMERCIAL FINAL | |||
| PLANNING - OFFICE USE - FINAL AS-BUILT SURVEY | |||
| LANDSCAPE PRE-CONSTRUCTION MEETING | |||
| IRRIGATION AFFIDAVIT | |||
| LDSC-IRRIGATION FINAL | |||
| LDSC- LANDSCAPE / IRRIGATION AS-BUILT | |||
| LDSC- LANDSCAPE FINAL | |||
| U-REUSE MAIN INSTALL/TESTING | |||
| MAINT BOND ACCEPTANCE (OFFICE) | |||
| CLOSE OUT DOCUMENTS | |||
| POTABLE WATERMAIN FLUSHED AND CHLORINATED | |||
| POTABLE WATERMAIN BACTERIOLOGICAL SAMPLING |
Review History
| Department | Status | Date In | Date Out |
| BLD | COMPLETE | 09/16/2025 | 09/16/2025 |
| Note: Released By: PATRICK BUCKLEY - (386)986-3786 - PBUCKLEY@PALMCOASTGOV.COM | |||
| ELEC | COMPLETE | 09/16/2025 | 09/16/2025 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| PLENG | COMPLETE | 09/16/2025 | 09/16/2025 |
| Note: Released By: DENNIS R. LEAP, P.E. - (386)986-2482 - DLEAP@PALMCOASTGOV.COM | |||
| PLLA | COMPLETE | 09/16/2025 | 09/16/2025 |
| Note: Released By: DAMARIS RAMIREZ - (386)986-3750 - DRAMIREZ@PALMCOASTGOV.COM | |||
| UD1 | COMPLETE | 09/16/2025 | 09/18/2025 |
| Note: Released By: ALEXANDER BLAKE - - ABLAKE@PALMCOASTGOV.COM |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| ADJUSTMENT 10% | (¤12.50) | 09/23/2025 |
| ADMINISTRATIVE- SITE DEVELOP | ¤125.00 | 09/23/2025 |
| SITE DEVELOPMENT ADMIN PLANNIN | ¤179.00 | 09/23/2025 |
| SITE INSPECTION | ¤627.00 | 09/23/2025 |
| SITE PLAN 29 | ¤29.00 | 09/23/2025 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤947.50 |