Permit #2025110026
Permit Details
Status: INSPECT
| Parcel Id: 10-11-30-5115-00000-0032 |
| Subdivision: 1165 - PINE LAKES NORTH COMMERCE PARK |
| Job Phone: 727-483-9512 X126 |
| Location Address: 90 GRAND AVE |
| Type: CSD - COMMERCIAL SITE DEVELOPMENT |
| Issue Date: 01/13/2026 |
| NOC: Unknown |
| Applicant name: JEROME ANTHONY CILIENTO |
| Owner: MIRAL CORP |
|
Address 636 BROADWAY STE A SAN DIEGO, CA 92101 |
| Job Description: SITE WORK: HILLPOINTE SELF STORAGE |
| Type: CN |
Contractor
BAY TO BAY POPERTIES LLC
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
201 MAIN STREET SUITE 300 SAFETY HARBOR, FL 34695 |
CGC1508354 (Exp: 08/31/2026) | 727-483-9512 X126 | 727-797-1513 |
Inspection History
| Type | Request Date | Result | Inspector |
| UC-CONSTRUCTION ENTRANCE | 06/10/2026 | APPROVED - AS NOTED | LFITZGERALD |
| Note: 2/11/2026 - PREVIOUS INSPECTION NOTES this is an on going inspection-checked periodiaclly/USING TRUNCATED DOME MATS AND SWEEPER THRU OUT THE DAY AS NEEDED NOW WITH BASE ON SITE AND BASE IN ENTRANCE -NO SOILS TRACKING INTO ROADWAY | |||
| POTABLE WATERMAIN FLUSHED AND CHLORINATED | 05/27/2026 | CANCELLED BY APPLICANT | BWRIGHT |
| WATERMAIN FLUSH & PRESSURE TESTED | 05/26/2026 | CANCELLED BY APPLICANT | BHAINES |
| U-WATER METER INSTALLATION/VERIFICATION | 05/20/2026 | ||
| BLD- ADA VEHICULAR WAY | 05/18/2026 | CANCELLED BY INSPECTOR | CPISCITELLI |
| Note: 5/13/2026 - PREVIOUS INSPECTION NOTES | |||
| STABILIZATION | 05/18/2026 | APPROVED - AS NOTED | LFITZGERALD |
| Note: test road the roadway on site that is all base now along with Randy Homes-very good | |||
| BLD- ADA VEHICULAR WAY | 05/13/2026 | CANCELLED BY APPLICANT | KSANDOE |
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 05/13/2026 | PARTIALLY APPROVED | TPOLACEK |
| Note: THERE AREA FEW LOCATIONS WHERE SILT FENCE IS TORN CM WILL HAVE REPAIRS DONE TODAY OR TOMORROW. 2/17/2026 - PREVIOUS INSPECTION NOTES 2/17/26 EROSION CONTROL MEASURES INSTALLED PER SWPPP. FOLLOW UP INSPECTION NEXT MONTH. | |||
| U-PUMP STATION PRE-INSTALLATION | 05/07/2026 | PARTIALLY APPROVED | BHAINES |
| Note: Liner was applied, needs stainless steel plate with dates of application | |||
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | 04/28/2026 | PARTIALLY APPROVED | BHAINES |
| Note: Will need to be pressure tested | |||
| U-WATER SERVICE INSTALLATION | 04/23/2026 | PARTIALLY APPROVED | BHAINES |
| Note: Water service line to lift station. | |||
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | 04/22/2026 | CANCELLED BY APPLICANT | WEB |
| U-WATER SERVICE INSTALLATION | 04/22/2026 | CANCELLED BY APPLICANT | WEB |
| U-GRAVITY SEWER INSTALL/TESTING | 04/22/2026 | PARTIALLY APPROVED | BWRIGHT |
| UC-DRAINAGE STRUCT PLACMNT | 04/22/2026 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 4/10/2026 - PREVIOUS INSPECTION NOTES 4/9/2026 - PREVIOUS INSPECTION NOTES CS-1 AND MES D-20 SET HEADING TO D-21 everything now installed except entrance culvert with2 FES'S at each end | |||
| UC-DRAINAGE PIPE PLACEMENT/LAMPING | 04/22/2026 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 4/10/2026 - PREVIOUS INSPECTION NOTES 4/9/2026 - PREVIOUS INSPECTION NOTES RCP-12IN FROM cs-1 to mes in pinelakes ROW swale ADS FROM d-20 to d-21 everything now installed except entrance culvert with 2-FES'S | |||
| UC-DRAINAGE STRUCT PLACMNT | 04/10/2026 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 4/9/2026 - PREVIOUS INSPECTION NOTES CS-1 AND MES D-20 SET HEADING TO D-21 | |||
| UC-DRAINAGE PIPE PLACEMENT/LAMPING | 04/10/2026 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 4/9/2026 - PREVIOUS INSPECTION NOTES RCP-12IN FROM cs-1 to mes in pinelakes ROW swale ADS FROM d-20 to d-21 | |||
| U-SEWER FORCE MAIN INSTALL/TESTING | 04/10/2026 | CANCELLED BY APPLICANT | WEB |
| UC-DRAINAGE PIPE PLACEMENT/LAMPING | 04/09/2026 | PARTIALLY APPROVED | LFITZGERALD |
| Note: RCP-12IN FROM cs-1 to mes in pinelakes ROW swale | |||
| UC-DRAINAGE STRUCT PLACMNT | 04/09/2026 | PARTIALLY APPROVED | LFITZGERALD |
| Note: CS-1 AND MES | |||
| LDSC-TREE BARRICADE | 02/20/2026 | APPROVED | DRODRIGUEZ |
| Note: Tree Barricade in place according to plan. Small area has been downed but will be repaired. | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 02/17/2026 | PARTIALLY APPROVED | JMYERS |
| Note: 2/17/26 EROSION CONTROL MEASURES INSTALLED PER SWPPP. FOLLOW UP INSPECTION NEXT MONTH. | |||
| UC-CONSTRUCTION ENTRANCE | 02/11/2026 | PARTIALLY APPROVED | LFITZGERALD |
| Note: this is an on going inspection-checked periodiaclly | |||
| PLAN - PRE-CON 386-986-3750 | 01/16/2026 | APPROVED - AS NOTED | LFITZGERALD |
| Note: all city staff-GPS REP'S AND BAY TO BAY REP'S AND OWNER-all aspects of site work-scheduling inspections etc discussed | |||
| PROJECT CLOSE OUT MEETING (386-986-3750) | 01/16/2026 | CANCELLED BY APPLICANT | LFITZGERALD |
| Note: this is not a pre-con inspection | |||
| PROJECT CLOSE OUT MEETING (386-986-3750) | |||
| Note: 1/15/2026 - PREVIOUS INSPECTION NOTES this is not a pre-con inspection | |||
| UC-SUBSTANTIAL WALK-THRU | |||
| UC- PRELIMINARY AS-BUILTS | |||
| UC-FINAL SITE INSPECTION | |||
| UC-FINAL SITE STABILIZATION | |||
| U - UTILITY COMMERCIAL FINAL | |||
| UC-DRAINAGE STRUCT PLACMNT | |||
| Note: 4/22/2026 - PREVIOUS INSPECTION NOTES 4/10/2026 - PREVIOUS INSPECTION NOTES 4/9/2026 - PREVIOUS INSPECTION NOTES CS-1 AND MES D-20 SET HEADING TO D-21 everything now installed except entrance culvert with2 FES'S at each end | |||
| UC-DRAINAGE PIPE PLACEMENT/LAMPING | |||
| Note: 4/22/2026 - PREVIOUS INSPECTION NOTES 4/10/2026 - PREVIOUS INSPECTION NOTES 4/9/2026 - PREVIOUS INSPECTION NOTES RCP-12IN FROM cs-1 to mes in pinelakes ROW swale ADS FROM d-20 to d-21 everything now installed except entrance culvert with 2-FES'S | |||
| WATERMAIN FLUSH & PRESSURE TESTED | |||
| Note: 5/26/2026 - PREVIOUS INSPECTION NOTES | |||
| POTABLE WATERMAIN FLUSHED AND CHLORINATED | |||
| Note: 5/27/2026 - PREVIOUS INSPECTION NOTES | |||
| POTABLE WATERMAIN BACTERIOLOGICAL SAMPLING | |||
| TEMPORARY HYDRANT CONSTRUCTION METER | |||
| SIGNAGE - WATER AND SEWER | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | |||
| Note: 5/14/2026 - PREVIOUS INSPECTION NOTES THERE AREA FEW LOCATIONS WHERE SILT FENCE IS TORN CM WILL HAVE REPAIRS DONE TODAY OR TOMORROW. 2/17/2026 - PREVIOUS INSPECTION NOTES 2/17/26 EROSION CONTROL MEASURES INSTALLED PER SWPPP. FOLLOW UP INSPECTION NEXT MONTH. | |||
| UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) | |||
| UROW-RETENT/DETENT STABILI | |||
| UROW- CURBING & GUTTER | |||
| U-ROW FINAL | |||
| U - SEWER TIE IN | |||
| UC-TRAF - FINAL (SIGN/PAVEMENT MARKING) | |||
| PLANNING - OFFICE USE - FINAL AS-BUILT SURVEY | |||
| CLOSE OUT DOCUMENTS | |||
| IRRIGATION AFFIDAVIT | |||
| LDSC-IRRIGATION FINAL | |||
| LDSC- LANDSCAPE / IRRIGATION AS-BUILT | |||
| LDSC- LANDSCAPE FINAL | |||
| BLD - UNDERGROUND SITE LIGHTING CONDUITS | |||
| BLD - SITE LIGHTING-PLACEMENT/FOUNDATION | |||
| BLD - SITE LIGHTING-POLE SET/FIXTURE | |||
| MAINT BOND ACCEPTANCE (OFFICE) | |||
| GEOTECH-SITE PREP ENG CERTIFICATIO (OFFICE USE ONLY) | |||
| BLD - ADA RAMPS/SIDEWALKS/CROSSWALKS | |||
| BLD- ADA PARKING | |||
| BLD - ADA COMPLIANT | |||
| BLD- ADA SIGNAGECONTROL | |||
| U-PUMP STATION PRE-INSTALLATION | |||
| Note: 5/7/2026 - PREVIOUS INSPECTION NOTES Liner was applied, needs stainless steel plate with dates of application | |||
| U-PUMP STATION START-UP | |||
| U-GRAVITY SEWER INSTALL/TESTING | |||
| Note: 4/23/2026 - PREVIOUS INSPECTION NOTES | |||
| U-CROSS CONNECTION | |||
| U-WATER MAIN DISINFECTION | |||
| U-WATER MAIN DISINFECTION SAMPLING | |||
| U-SEWER FORCE MAIN INSTALL/TESTING | |||
| U-WATER SERVICE INSTALLATION | |||
| Note: 4/23/2026 - PREVIOUS INSPECTION NOTES Water service line to lift station. | |||
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | |||
| Note: 4/28/2026 - PREVIOUS INSPECTION NOTES Will need to be pressure tested |
Review History
| Department | Status | Date In | Date Out |
| DSD | COMPLETE | 01/13/2026 | 01/13/2026 |
| Note: Released By: DAMARIS RAMIREZ - (386)986-3750 - DRAMIREZ@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 11/03/2025 | 11/03/2025 |
| Note: Released By: PATRICK BUCKLEY - (386)986-3786 - PBUCKLEY@PALMCOASTGOV.COM | |||
| ELEC | COMPLETE | 11/03/2025 | 11/04/2025 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| PLENG | COMPLETE | 11/03/2025 | 11/03/2025 |
| Note: Released By: DENNIS R. LEAP, P.E. - (386)986-2482 - DLEAP@PALMCOASTGOV.COM | |||
| PLLA | COMPLETE | 11/03/2025 | 11/03/2025 |
| Note: Released By: DAMARIS RAMIREZ - (386)986-3750 - DRAMIREZ@PALMCOASTGOV.COM | |||
| UD1 | COMPLETE | 11/03/2025 | 11/04/2025 |
| Note: Released By: GREG DEGLER - (386)986-2384 - GDEGLER@PALMCOASTGOV.COM | |||
| DSD | HOLD | 11/03/2025 | 11/03/2025 |
| Note: Held By: DAMARIS RAMIREZ - (386)986-3750 - DRAMIREZ@PALMCOASTGOV.COM Need executed application returned to me. Need agreement to be executed Need utility receipt to show capacity fees being paid. Need DEP permits. |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| ADMINISTRATIVE- SITE DEVELOP | ¤125.00 | 01/13/2026 |
| INSPECTION - GENERAL | ¤320.00 | 01/13/2026 |
| SITE DEVELOPMENT ADMIN PLANNIN | ¤179.00 | 01/13/2026 |
| SITE INSPECTION | ¤798.00 | 01/13/2026 |
| SITE PLAN 29 | ¤29.00 | 01/13/2026 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤1,451.00 |