Permit #2025110891
Permit Details
Status: FINAL
| Parcel Id: 23-11-30-6060-00000-00G0 |
| Subdivision: 2333 - WHITEVIEW MULTI-FAMILY |
| Job Phone: 904-268-5515 |
| Location Address: 300 WISTERIA HILL DR |
| Type: CSD - COMMERCIAL SITE DEVELOPMENT |
| Issue Date: 12/19/2025 |
| NOC: Unknown |
| Applicant name: MICHAEL M PADGETT |
| Owner: MARBELLA APARTMENTS LLC |
|
Address 3060 PEACHTREE ROAD NW SUITE 970 ATLANTA, GA 30305 |
| Job Description: STAGING 3 SITE WORK: WHITEVIEW BLDGS 9 AND 10 |
| Type: CN |
Contractor
SUMMIT CONTRACTING GROUP INC
| Status | Location Address | State License Number | Phone |
| ACTIVE |
7595 BAYMEADOWS WAY SUITE 100 JACKSONVILLE, FL 32204 |
CGC1513073 (Exp: 08/31/2026) | 904-268-5515 |
Inspection History
| Type | Request Date | Result | Inspector |
| U - UTILITY COMMERCIAL FINAL | 02/02/2026 | FINAL APPROVED | LFITZGERALD |
| ROW - FINAL INSPECTION | 02/02/2026 | FINAL APPROVED | LFITZGERALD |
| LDSC- LANDSCAPE FINAL | 01/30/2026 | APPROVED - AS NOTED | RPICATAGI |
| Note: Two large green utility boxes at NE and SE corner or Bldg 300 need to be screened with 30" tall shrubs instead of low groundcover. Applicant shall make the changes. | |||
| CLOSE OUT DOCUMENTS | 01/29/2026 | APPROVED | DRAMIREZ |
| PLANNING - OFFICE USE - FINAL AS-BUILT SURVEY | 01/23/2026 | APPROVED | DRAMIREZ |
| IRRIGATION AFFIDAVIT | 01/23/2026 | APPROVED | RPICATAGI |
| Note: 1/21/2026 3:58:14 PM- PREVIOUS INSPECTION NOTES Provide signed and sealed affidavit | |||
| LDSC-IRRIGATION FINAL | 01/21/2026 | APPROVED | RPICATAGI |
| LDSC- LANDSCAPE / IRRIGATION AS-BUILT | 01/21/2026 | APPROVED | RPICATAGI |
| IRRIGATION AFFIDAVIT | 01/21/2026 | Disapproved - NO FEE | RPICATAGI |
| Note: Provide signed and sealed affidavit | |||
| UROW - FINAL DRAINAGE | 01/21/2026 | APPROVED | LFITZGERALD |
| Note: 12/23/2025 - PREVIOUS INSPECTION NOTES Inspector Notes from Inspection 9142 *** NOTES ADDED BY LFITZGERALD 12/22/2025 4:13:59 PM *** ALSO-JORDAN AND MYSELF TO VERIFY ALL PROPOSED WAS INSTALLED AND/OR IF CHANGES THAT THEY DID MAKE SENSE OR IS OK just recieved today-to be reviewed by Jordan and myself Phase 1-2=walk done with Jordan and Tom and couple corrections to make(just recieved as builts yesterday)/phase 3-4 also did walk withsome corrections to be made | |||
| UC-FINAL SITE INSPECTION | 01/21/2026 | APPROVED - AS NOTED | LFITZGERALD |
| Note: 12/22/2025 - PREVIOUS INSPECTION NOTES 2/13/2025 - PREVIOUS INSPECTION NOTES not close to being ready utility punch items refer to hydrants-see hydrants-hydrant valves need brass id tab/valve lid painted blue/and where it applies-if in asphalt -needs to be flush with asphalt grade and acessible AND JUST RECIEVED AS BUILTS FOR THESE 2 PHASES-NEEDS TO BE REVIEWED BY Jordan and myself any defiencies still outstanding will be covered by the site permit even though approved so that in order to CO the associated buildings | |||
| HYDRANT - PAINT / FLOW/VALVE/ RPM | 01/20/2026 | APPROVED - AS NOTED | LFITZGERALD |
| Note: 12/22/2025 - PREVIOUS INSPECTION NOTES 10/30/2025 - PREVIOUS INSPECTION NOTES 10/20/2025 - PREVIOUS INSPECTION NOTES Inspector Notes from Inspection 9114 installing storm culvert at South(Emergency)entrance 3/6/2025 - PREVIOUS INSPECTION NOTES All hydrants now flow tested-Tyler all hydrats now GPS now painted safty orange hydrant valves need brass id tab/valve lid painted blue/and where it applies-if in asphalt -needs to be flush with asphalt grade and acessible to help close out this stage ,hydrant issues-paintblue lid-brasss ID tabs-clean inside valve jacket so can get on the operating nut ok placed on Final Final and on stage 5-6 | |||
| UROW - FINAL DRAINAGE | 12/23/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: Inspector Notes from Inspection 9142 *** NOTES ADDED BY LFITZGERALD 12/22/2025 4:13:59 PM *** ALSO-JORDAN AND MYSELF TO VERIFY ALL PROPOSED WAS INSTALLED AND/OR IF CHANGES THAT THEY DID MAKE SENSE OR IS OK just recieved today-to be reviewed by Jordan and myself Phase 1-2=walk done with Jordan and Tom and couple corrections to make(just recieved as builts yesterday)/phase 3-4 also did walk withsome corrections to be made | |||
| UROW -FINAL GRADE PRIOR SOD | 12/22/2025 | APPROVED | LFITZGERALD |
| Note: 11/6/2025 - PREVIOUS INSPECTION NOTES Inspector Notes from Inspection 9240 turn lane on white mill-all sodded in on ROW next to widening/perimeter swale along existing homes where vinyl fence is,behind buildingds1,2 all sodded and slight positive grading so water makes its way to existing lake behind this project/swale alog whitemill next to asphalt path restored after slight diging while setting in power at power pole all satisfactory for PHASE 1 AND 2 | |||
| UC-TRAF - FINAL (SIGN/PAVEMENT MARKING) | 12/22/2025 | APPROVED | LFITZGERALD |
| Note: 10/28/2025 - PREVIOUS INSPECTION NOTES 10/27/2025 - PREVIOUS INSPECTION NOTES several directional arrows not yet installed/2nd lift asphalt up to divider roadway turn lane on white mill-good only ?is there yellow RPM's for the gore-roadway to be reconstructed by city future | |||
| HYDRANT - PAINT / FLOW/VALVE/ RPM | 12/22/2025 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 10/30/2025 - PREVIOUS INSPECTION NOTES 10/20/2025 - PREVIOUS INSPECTION NOTES Inspector Notes from Inspection 9114 installing storm culvert at South(Emergency)entrance 3/6/2025 - PREVIOUS INSPECTION NOTES All hydrants now flow tested-Tyler all hydrats now GPS now painted safty orange hydrant valves need brass id tab/valve lid painted blue/and where it applies-if in asphalt -needs to be flush with asphalt grade and acessible | |||
| UC-SUBSTANTIAL WALK-THRU | 12/22/2025 | APPROVED - AS NOTED | LFITZGERALD |
| Note: utility punch items refer to hydrants-see hydrants-hydrant valves need brass id tab/valve lid painted blue/and where it applies-if in asphalt -needs to be flush with asphalt grade and acessible AND JUST RECIEVED AS BUILTS FOR THESE 2 PHASES-NEEDS TO BE REVIEWED BY Jordan and myself | |||
| UC- PRELIMINARY AS-BUILTS | 12/22/2025 | APPROVED - AS NOTED | LFITZGERALD |
| Note: *** NOTES ADDED BY LFITZGERALD 12/22/2025 4:13:59 PM *** ALSO-JORDAN AND MYSELF TO VERIFY ALL PROPOSED WAS INSTALLED AND/OR IF CHANGES THAT THEY DID MAKE SENSE OR IS OK just recieved today-to be reviewed by Jordan and myself | |||
| UC-FINAL SITE INSPECTION | 12/22/2025 | Disapproved - NO FEE | LFITZGERALD |
| Note: 2/13/2025 - PREVIOUS INSPECTION NOTES not close to being ready utility punch items refer to hydrants-see hydrants-hydrant valves need brass id tab/valve lid painted blue/and where it applies-if in asphalt -needs to be flush with asphalt grade and acessible AND JUST RECIEVED AS BUILTS FOR THESE 2 PHASES-NEEDS TO BE REVIEWED BY Jordan and myself | |||
| BLD - ADA RAMPS/SIDEWALKS/CROSSWALKS | 12/22/2025 | APPROVED | KSANDOE |
| Note: 11/6/2025 - PREVIOUS INSPECTION NOTES | |||
| BLD- ADA PARKING | 12/22/2025 | APPROVED | KSANDOE |
| Note: 11/6/2025 - PREVIOUS INSPECTION NOTES | |||
| BLD - ADA COMPLIANT | 12/22/2025 | APPROVED | KSANDOE |
| Note: 11/6/2025 - PREVIOUS INSPECTION NOTES | |||
| BLD- ADA SIGNAGECONTROL | 12/22/2025 | APPROVED | KSANDOE |
| Note: 11/6/2025 - PREVIOUS INSPECTION NOTES | |||
| BLD- ADA VEHICULAR WAY | 12/22/2025 | APPROVED | KSANDOE |
| Note: 11/6/2025 - PREVIOUS INSPECTION NOTES | |||
| BLD - ADA SIGNAGE- INFOR/DIRECT | 12/22/2025 | APPROVED | KSANDOE |
| Note: 11/6/2025 - PREVIOUS INSPECTION NOTES | |||
| BLD - UNDERGROUND SITE LIGHTING CONDUITS | 12/22/2025 | APPROVED | RMARTIN |
| Note: 11/6/2025 - PREVIOUS INSPECTION NOTES | |||
| BLD - SITE LIGHTING-PLACEMENT/FOUNDATION | 12/22/2025 | APPROVED | RMARTIN |
| Note: 11/7/2025 - PREVIOUS INSPECTION NOTES Plans call for ground rods at each pole, have revision or make repair before next inspection, (phase 1, 2, and, 3) | |||
| BLD - SITE LIGHTING-POLE SET/FIXTURE | 12/22/2025 | APPROVED | RMARTIN |
| Note: 11/6/2025 - PREVIOUS INSPECTION NOTES |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| ADMINISTRATIVE- SITE DEVELOP | ¤125.00 | 12/19/2025 |
| INSPECTION - GENERAL | ¤360.00 | 12/19/2025 |
| SITE DEVELOPMENT ADMIN PLANNIN | ¤179.00 | 12/19/2025 |
| SITE INSPECTION | ¤399.00 | 12/19/2025 |
| SITE PLAN 29 | ¤29.00 | 12/19/2025 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤1,092.00 |