Permit #2025110892
Permit Details
Status: FINAL
| Parcel Id: 23-11-30-6060-00000-00G0 |
| Subdivision: 2333 - WHITEVIEW MULTI-FAMILY |
| Job Phone: 904-268-5515 |
| Location Address: 300 WISTERIA HILL DR |
| Type: CSD - COMMERCIAL SITE DEVELOPMENT |
| Issue Date: 02/06/2026 |
| NOC: Unknown |
| Applicant name: MICHAEL M PADGETT |
| Owner: MARBELLA APARTMENTS LLC |
|
Address 3060 PEACHTREE ROAD NW SUITE 970 ATLANTA, GA 30305 |
| Job Description: STAGING 5 SITE WORK: WHITEVIEW BLDGS 7, 8, 12 AND 14 |
| Type: CN |
Contractor
SUMMIT CONTRACTING GROUP INC
| Status | Location Address | State License Number | Phone |
| ACTIVE |
7595 BAYMEADOWS WAY SUITE 100 JACKSONVILLE, FL 32204 |
CGC1513073 (Exp: 08/31/2026) | 904-268-5515 |
Inspection History
| Type | Request Date | Result | Inspector |
| CLOSE OUT DOCUMENTS | 04/16/2026 | APPROVED | DRAMIREZ |
| PLANNING - OFFICE USE - FINAL AS-BUILT SURVEY | 04/16/2026 | APPROVED | DRAMIREZ |
| IRRIGATION AFFIDAVIT | 04/16/2026 | APPROVED | RPICATAGI |
| LDSC-IRRIGATION FINAL | 04/16/2026 | APPROVED | RPICATAGI |
| LDSC- LANDSCAPE FINAL | 04/16/2026 | APPROVED | RPICATAGI |
| UROW - FINAL DRAINAGE | 04/08/2026 | FINAL APPROVED | LFITZGERALD |
| Note: 2/18/2026 - PREVIOUS INSPECTION NOTES some storm grates with fabric-misc asphalt and as agreed with GC-vac /clean all drainage vac-con all drainage structures-most with light amount of soils | |||
| ROW - FINAL INSPECTION | 04/08/2026 | APPROVED | LFITZGERALD |
| UC- PRELIMINARY AS-BUILTS | 04/08/2026 | APPROVED | LFITZGERALD |
| UC-FINAL SITE INSPECTION | 04/08/2026 | FINAL APPROVED | LFITZGERALD |
| Note: 2/13/2025 - PREVIOUS INSPECTION NOTES not close to being ready | |||
| U - UTILITY COMMERCIAL FINAL | 04/08/2026 | APPROVED | LFITZGERALD |
| LDSC- LANDSCAPE / IRRIGATION AS-BUILT | 03/17/2026 | APPROVED | RPICATAGI |
| UC-TRAF - FINAL (SIGN/PAVEMENT MARKING) | 03/04/2026 | APPROVED | LFITZGERALD |
| Note: 10/28/2025 - PREVIOUS INSPECTION NOTES 10/27/2025 - PREVIOUS INSPECTION NOTES several directional arrows not yet installed/2nd lift asphalt up to divider roadway turn lane on white mill-good only ?is there yellow RPM's for the gore-roadway to be reconstructed by city future | |||
| BLD - ADA RAMPS/SIDEWALKS/CROSSWALKS | 03/03/2026 | APPROVED | KSANDOE |
| Note: 11/6/2025 - PREVIOUS INSPECTION NOTES | |||
| BLD- ADA PARKING | 03/03/2026 | APPROVED | KSANDOE |
| Note: 11/6/2025 - PREVIOUS INSPECTION NOTES | |||
| BLD - ADA COMPLIANT | 03/03/2026 | APPROVED | KSANDOE |
| Note: 11/6/2025 - PREVIOUS INSPECTION NOTES | |||
| BLD- ADA SIGNAGECONTROL | 03/03/2026 | APPROVED | KSANDOE |
| Note: 11/6/2025 - PREVIOUS INSPECTION NOTES | |||
| BLD- ADA VEHICULAR WAY | 03/03/2026 | APPROVED | KSANDOE |
| Note: 11/6/2025 - PREVIOUS INSPECTION NOTES | |||
| BLD - ADA SIGNAGE- INFOR/DIRECT | 03/03/2026 | APPROVED | KSANDOE |
| Note: 11/6/2025 - PREVIOUS INSPECTION NOTES | |||
| HYDRANT - PAINT / FLOW/VALVE/ RPM | 02/17/2026 | APPROVED | LFITZGERALD |
| Note: 10/30/2025 - PREVIOUS INSPECTION NOTES 10/20/2025 - PREVIOUS INSPECTION NOTES Inspector Notes from Inspection 9114 installing storm culvert at South(Emergency)entrance 3/6/2025 - PREVIOUS INSPECTION NOTES All hydrants now flow tested-Tyler all hydrats now GPS now painted safty orange | |||
| UC-SUBSTANTIAL WALK-THRU | 02/17/2026 | APPROVED - AS NOTED | LFITZGERALD |
| Note: still missing some brass ID tabs for valves-on order /some storm catch basins still with fabic-asphalt covering-Bill informed and will remove and will catch it on final for overall site inspection by Jordan and myself | |||
| UROW - FINAL DRAINAGE | 02/17/2026 | PARTIALLY APPROVED | LFITZGERALD |
| Note: some storm grates with fabric-misc asphalt and as agreed with GC-vac /clean all drainage | |||
| UROW -FINAL GRADE PRIOR SOD | 02/13/2026 | APPROVED | LFITZGERALD |
| Note: 11/6/2025 - PREVIOUS INSPECTION NOTES Inspector Notes from Inspection 9240 turn lane on white mill-all sodded in on ROW next to widening/perimeter swale along existing homes where vinyl fence is,behind buildingds1,2 all sodded and slight positive grading so water makes its way to existing lake behind this project/swale alog whitemill next to asphalt path restored after slight diging while setting in power at power pole all satisfactory for PHASE 1 AND 2 | |||
| BLD - SITE LIGHTING-POLE SET/FIXTURE | 02/12/2026 | APPROVED | JMUNSON |
| Note: 2/9/2026 - PREVIOUS INSPECTION NOTES 2/9/26 1. No revision and can not see ground rod at each pole per previous inspection 11/7/25 1. Plans call for ground rods at each pole, have revision or make repair before next inspection | |||
| BLD - UNDERGROUND SITE LIGHTING CONDUITS | 02/09/2026 | APPROVED | MKRASKI |
| BLD - SITE LIGHTING-PLACEMENT/FOUNDATION | 02/09/2026 | APPROVED | MKRASKI |
| BLD - SITE LIGHTING-POLE SET/FIXTURE | 02/09/2026 | Disapproved - NO FEE | MKRASKI |
| Note: 2/9/26 1. No revision and can not see ground rod at each pole per previous inspection 11/7/25 1. Plans call for ground rods at each pole, have revision or make repair before next inspection |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| ADMINISTRATIVE- SITE DEVELOP | ¤125.00 | 02/06/2026 |
| INSPECTION - GENERAL | ¤360.00 | 02/06/2026 |
| SITE DEVELOPMENT ADMIN PLANNIN | ¤179.00 | 02/06/2026 |
| SITE INSPECTION | ¤399.00 | 02/06/2026 |
| SITE PLAN 29 | ¤29.00 | 02/06/2026 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤1,092.00 |