Permit #2025120540
Permit Details
Status: INSPECT
| Parcel Id: 07-11-31-7028-00300-0200 |
| CONDITIONED SPACE: 1654 sqft |
| GARAGE: 396 sqft |
| OPENED PORCH (WITH ROOF) : 19 sqft |
| OPENED PORCH (WITH ROOF) : 100 sqft |
| Total Square Footage: 2169 sqft |
| Block: 00300 |
| Subdivision: 2302 - SECTION 28-PINE GROVE |
| Job Phone: 407-476-8195 |
| Location Address: 14 POWDER LN |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 12/26/2025 |
| NOC: RECORDED |
| Applicant name: CARLETTE RENE WITTE |
| Owner: INB BFS LAND LLC |
|
Address 7380 WEST SAND LAKE ROAD ORLANDO, FL 32819 |
|
Address SUITE 600 ORLANDO, FL 32819 |
| Lot: 0200 |
| Contracted Stated Job Value: ¤250,000.00 |
| Job Description: Construction of New SFR |
| Type: CN |
Contractor
INNOVATIVE NATIONWIDE BUILDERS INC
| Status | Location Address | State License Number | Phone |
| ACTIVE |
3670 MAGUIRE BLVD #220 , |
CRC1330026 (Exp: 08/31/2026) | 855-694-6634 |
Sub Contractors
JASON LEE JAMES
| Status | Location Address | State License Number | Phone |
| ACTIVE |
217 N WESTMONTE DR SUITE 1007 ALTAMONTE SPRINGS, FL 32714 |
CAC1820196 (Exp: 08/31/2026) | 407-404-4000 |
ANTHONY OKEITH FENNELL
| Status | Location Address | State License Number | Phone |
| ACTIVE |
217 N. WESTMONTE DR, SUITE 1007 ALTAMONTE SPRINGS, FL 32714 |
EC13011194 (Exp: 08/31/2026) | 407-404-4000 |
HEATH EDWARD SANFORD
| Status | Location Address | State License Number | Phone |
| ACTIVE |
126 EAST END RD SAN MATEO, FL 32187 |
CFC1429896 (Exp: 08/31/2026) | 386-871-8823 |
TERRY BRICE DICKERSON
| Status | Location Address | State License Number | Phone |
| ACTIVE |
4300 ST JOHN'S PARKWAY ALPHARETTA, GA 30009 |
CCC1326209 (Exp: 08/31/2026) | 407-548-6733 |
Inspection History
| Type | Request Date | Result | Inspector |
| ROW- PRE-APRON (PRE-POUR) | 06/08/2026 | APPROVED - AS NOTED | TPOLACEK |
| Note: 06-08-26 TPOLACEK*** BUILDER MUST DIG OUT FOOTERS BEFORE POURING CONCRETE, ALL FORM BOARDS MUST BE BACKFILLED OR EXTENDED DOWN TO PREVENT OVER POUR. APPROVING AS NOTED AT THE TIME OF THE INSPECTION CULVERT PIPE IS GOOD IS READY TO POUR, IF RAIN PLEASE, BUILDER SHOULD DOUBLE CHECK CULVERT ELEVATIONS MAKE SURE TO USE 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE (FRC) DRAWING 300,E RESIDENTIAL CULVERT DETAIL BEFORE POURING. TICKET OF CONCRETE MIX DESIGN SHALL BE UPLOADED INTO PERMIT PORTAL. 8.a. IF FIBERGLASS OPTION IS USED, DOCUMENTATION OF THE ( FRC) CONTAINING THE FIBERGLASS MUST BE ATTACHED TO THE PERMIT PRIOR TO REQUESTING AN AFTER-POUR INSPECTION. 8.b. IF MESH OPTION IS USED, IT SHALL BE IN PLACE AT THE TIME OF THE PRE-POUR. WOOD CONTROL JOINTS ARE PROHIBITED IN THE RIGHT-OF-WAY. SAWCUT SHALL BE PROVIDED AT THE EDGE OF ROW AND EVERY 12' THEREAFTER, OR A MINIMUM OF 2 SAWCUTS WHICHEVER IS GREATER" ____________________________________________________________________________________________________________________________ New inspection due to canceled inspection 5/27/2026 - PREVIOUS INSPECTION NOTES 5/27/26 Culvert pipe needs to be buried to spring line (1/2 way). the pouring area around pipe is to soft to pour at the time of this inspection. You have area at mitered end without the copc minimum 6" x 6" depth. See photo for reference. | |||
| ROW- PRE-APRON (PRE-POUR) | 05/29/2026 | CANCELLED BY APPLICANT | WEB |
| Note: 5/27/2026 - PREVIOUS INSPECTION NOTES 5/27/26 Culvert pipe needs to be buried to spring line (1/2 way). the pouring area around pipe is to soft to pour at the time of this inspection. You have area at mitered end without the copc minimum 6" x 6" depth. See photo for reference. | |||
| ROW- PRE-APRON (PRE-POUR) | 05/27/2026 | Disapproved -FEE REQUIRED | FSLADISH |
| Note: 5/27/26 Culvert pipe needs to be buried to spring line (1/2 way). the pouring area around pipe is to soft to pour at the time of this inspection. You have area at mitered end without the copc minimum 6" x 6" depth. See photo for reference. | |||
| SEWER TIE IN | 05/22/2026 | APPROVED | RSIMS |
| Note: *** NOTES ADDED BY RSIMS 5/22/2026 1:11:44 PM *** Approved 5/21/2026 - PREVIOUS INSPECTION NOTES 5/21/26: 5/20/26: NO CHANGE. CONNECTION COVERED WITH DIRT AND WATER. FBC-[A]110.3 - Plumbing (1) Underground inspection. To be made after trenches or ditches are excavated, piping installed, and before any backfill is put in place. /// FBCR-P2503.2 - Concealment. A plumbing or drainage system, or part thereof, shall not be covered, concealed or put into use until it has been tested, inspected and approved by the building official ***** BUILDER TO PLEASE VISUALLY VERIFY THAT THE CONNECTION IS CLEARED FOR INSPECTION TO AVOID WASTING CITY TIME AND RESOURCES. THANK YOU. 5/20/2026 - PREVIOUS INSPECTION NOTES 5/20/26: NO CHANGE. CONNECTION COVERED WITH DIRT AND WATER. FBC-[A]110.3 - Plumbing (1) Underground inspection. To be made after trenches or ditches are excavated, piping installed, and before any backfill is put in place. /// FBCR-P2503.2 - Concealment. A plumbing or drainage system, or part thereof, shall not be covered, concealed or put into use until it has been tested, inspected and approved by the building official 5/15/2026 - PREVIOUS INSPECTION NOTES Excessive dirt wash-in from rain storm has covered connection to sewer. Please expose sewer tie-in connection for inspection. FBC [A]110.1 | |||
| SEWER TIE IN | 05/21/2026 | Disapproved -FEE REQUIRED | RSIMS |
| Note: *** NOTES ADDED BY RSIMS 5/21/2026 12:29:25 PM *** 5/21/26: 5/20/26: NO CHANGE. CONNECTION COVERED WITH DIRT AND WATER. FBC-[A]110.3 - Plumbing (1) Underground inspection. To be made after trenches or ditches are excavated, piping installed, and before any backfill is put in place. /// FBCR-P2503.2 - Concealment. A plumbing or drainage system, or part thereof, shall not be covered, concealed or put into use until it has been tested, inspected and approved by the building official ***** BUILDER TO PLEASE VISUALLY VERIFY THAT THE CONNECTION IS CLEARED FOR INSPECTION TO AVOID WASTING CITY TIME AND RESOURCES. THANK YOU. 5/20/2026 - PREVIOUS INSPECTION NOTES 5/20/26: NO CHANGE. CONNECTION COVERED WITH DIRT AND WATER. FBC-[A]110.3 - Plumbing (1) Underground inspection. To be made after trenches or ditches are excavated, piping installed, and before any backfill is put in place. /// FBCR-P2503.2 - Concealment. A plumbing or drainage system, or part thereof, shall not be covered, concealed or put into use until it has been tested, inspected and approved by the building official 5/15/2026 - PREVIOUS INSPECTION NOTES Excessive dirt wash-in from rain storm has covered connection to sewer. Please expose sewer tie-in connection for inspection. FBC [A]110.1 | |||
| ELECTRIC - EARLY POWER | 05/20/2026 | APPROVED | RSIMS |
| Note: *** NOTES ADDED BY RSIMS 5/20/2026 10:05:34 AM *** 5/20/26: fpl EMAILED TO RELEASE POWER. Inspector Notes from Inspection 2200 *** NOTES ADDED BY RSIMS 4/8/2026 1:44:33 PM *** 4/8/26: FPL emailed > Approved for TUG | |||
| SEWER TIE IN | 05/20/2026 | Disapproved -FEE REQUIRED | RSIMS |
| Note: *** NOTES ADDED BY RSIMS 5/20/2026 10:06:37 AM *** Date correction to date marked below. This should be 5/20/26 not 5/18/26. *** NOTES ADDED BY RSIMS 5/20/2026 10:04:44 AM *** 5/18/26: NO CHANGE. CONNECTION COVERED WITH DIRT AND WATER. FBC-[A]110.3 - Plumbing (1) Underground inspection. To be made after trenches or ditches are excavated, piping installed, and before any backfill is put in place. /// FBCR-P2503.2 - Concealment. A plumbing or drainage system, or part thereof, shall not be covered, concealed or put into use until it has been tested, inspected and approved by the building official 5/15/2026 - PREVIOUS INSPECTION NOTES Excessive dirt wash-in from rain storm has covered connection to sewer. Please expose sewer tie-in connection for inspection. FBC [A]110.1 | |||
| GRAVITY SEWER TEST | 05/15/2026 | APPROVED | KSANDOE |
| Note: 4/30/2026 - PREVIOUS INSPECTION NOTES 4/30/26: 1). Building drain is not run fully to the pep tank location or second cleanout. FBC-P3005.2.3 Building drain and building sewer junction. / FBC-P2503.4 Building sewer testing. 2). Pipe directly after the second 45* elbow is not pitched at the required minimum (1/4" per FT > 2%). (pipe is level). FBC-P3005.3 Horizontal drainage piping slope. | |||
| SEWER TIE IN | 05/15/2026 | Disapproved - NO FEE | KSANDOE |
| Note: Excessive dirt wash-in from rain storm has covered connection to sewer. Please expose sewer tie-in connection for inspection. FBC [A]110.1 | |||
| GRAVITY SEWER TEST | 04/30/2026 | Disapproved -FEE REQUIRED | RSIMS |
| Note: *** NOTES ADDED BY RSIMS 4/30/2026 1:35:57 PM *** Correction on slope is 1% or 1/8" per foot. *** NOTES ADDED BY RSIMS 4/30/2026 12:54:02 PM *** 4/30/26: 1). Building drain is not run fully to the pep tank location or second cleanout. FBC-P3005.2.3 Building drain and building sewer junction. / FBC-P2503.4 Building sewer testing. 2). Pipe directly after the second 45* elbow is not pitched at the required minimum (1/4" per FT > 2%). (pipe is level). FBC-P3005.3 Horizontal drainage piping slope. | |||
| PEP TANK INSTALLATION REQUEST | 04/29/2026 | APPROVED | ISANDERSON |
| DRYWALL NAILING | 04/27/2026 | APPROVED | RSIMS |
| Note: *** NOTES ADDED BY RSIMS 4/27/2026 12:44:28 PM *** Approved | |||
| INSULATION | 04/21/2026 | APPROVED | RSIMS |
| Note: *** NOTES ADDED BY RSIMS 4/21/2026 1:31:11 PM *** 4/16/2026 - PREVIOUS INSPECTION NOTES 4/16/26: 1). Numerous cardboard baffles do not meet the 1" minimum clearance from the roof sheathing as required. FBC-R806.3 | |||
| INSULATION | 04/16/2026 | Disapproved - NO FEE | RSIMS |
| Note: *** NOTES ADDED BY RSIMS 4/16/2026 12:00:31 PM *** 4/16/26: 1). Numerous cardboard baffles do not meet the 1" minimum clearance from the roof sheathing as required. FBC-R806.3 | |||
| LATH/BRICK/ WATER BARRIER | 04/15/2026 | APPROVED | RSIMS |
| Note: *** NOTES ADDED BY RSIMS 4/15/2026 12:27:27 PM *** Approved | |||
| INSULATION | 04/14/2026 | CANCELLED BY APPLICANT | WEB |
| ALL ROUGH | 04/10/2026 | APPROVED | RSIMS |
| Note: *** NOTES ADDED BY RSIMS 4/10/2026 12:52:09 PM *** Approved Inspector Notes from Inspection 2460 *** NOTES ADDED BY RSIMS 4/8/2026 1:49:04 PM *** 4/8/26: Approved as noted pending approval of engineer's letter which is only accepted at the time of inspection. As previously noted the plan page states screws into top plate but there is a header not a top plate. Ask engineer to clarify into header. 4/1/2026 - PREVIOUS INSPECTION NOTES 4/1/26: PREVIOUSLY LISTED ITEMS 1, 2 AND 3 REMAIN UNRESOLVED. PLEASE HAVE SUPERINTENDENT VISUALLY VERIFY COMPLETION PRIOR TO SCHEDULING RE-INSPECTION TO AVOID WASTING CITY TIME AND RESOURCES. 3/25/2026 - PREVIOUS INSPECTION NOTES 3/25/26: 1). Right side entry knee wall does not match plan requirements WF95 shown on plan page S4.0. FBC [A]107.4 2). Plan page S4.0 has detail SC that needs clarification because it calls for SDWC15600 screws into top plate but there is a porch beam there which has straps from beam to truss installed. Revision required. FBC [A]107.4 3). Front gable is missing cross bracing as required in detail GE01/D2. Correction or plan revision required. FBC [A]107.4 4). 2-ply Truss T01 needs nails fully embedded as required. FBC [A]107.4 | |||
| ELECTRIC-TUG | 04/08/2026 | APPROVED - AS NOTED | RSIMS |
| Note: *** NOTES ADDED BY RSIMS 4/8/2026 1:44:33 PM *** 4/8/26: FPL emailed > Approved for TUG | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 04/08/2026 | APPROVED - AS NOTED | RSIMS |
| Note: *** NOTES ADDED BY RSIMS 4/8/2026 1:49:04 PM *** 4/8/26: Approved as noted pending approval of engineer's letter which is only accepted at the time of inspection. As previously noted the plan page states screws into top plate but there is a header not a top plate. Ask engineer to clarify into header. 4/1/2026 - PREVIOUS INSPECTION NOTES 4/1/26: PREVIOUSLY LISTED ITEMS 1, 2 AND 3 REMAIN UNRESOLVED. PLEASE HAVE SUPERINTENDENT VISUALLY VERIFY COMPLETION PRIOR TO SCHEDULING RE-INSPECTION TO AVOID WASTING CITY TIME AND RESOURCES. 3/25/2026 - PREVIOUS INSPECTION NOTES 3/25/26: 1). Right side entry knee wall does not match plan requirements WF95 shown on plan page S4.0. FBC [A]107.4 2). Plan page S4.0 has detail SC that needs clarification because it calls for SDWC15600 screws into top plate but there is a porch beam there which has straps from beam to truss installed. Revision required. FBC [A]107.4 3). Front gable is missing cross bracing as required in detail GE01/D2. Correction or plan revision required. FBC [A]107.4 4). 2-ply Truss T01 needs nails fully embedded as required. FBC [A]107.4 | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 04/01/2026 | Disapproved -FEE REQUIRED | RSIMS |
| Note: *** NOTES ADDED BY RSIMS 4/1/2026 9:30:22 AM *** 4/1/26: PREVIOUSLY LISTED ITEMS 1, 2 AND 3 REMAIN UNRESOLVED. PLEASE HAVE SUPERINTENDENT VISUALLY VERIFY COMPLETION PRIOR TO SCHEDULING RE-INSPECTION TO AVOID WASTING CITY TIME AND RESOURCES. 3/25/2026 - PREVIOUS INSPECTION NOTES 3/25/26: 1). Right side entry knee wall does not match plan requirements WF95 shown on plan page S4.0. FBC [A]107.4 2). Plan page S4.0 has detail SC that needs clarification because it calls for SDWC15600 screws into top plate but there is a porch beam there which has straps from beam to truss installed. Revision required. FBC [A]107.4 3). Front gable is missing cross bracing as required in detail GE01/D2. Correction or plan revision required. FBC [A]107.4 4). 2-ply Truss T01 needs nails fully embedded as required. FBC [A]107.4 | |||
| ROOF VALLEY & METAL | 03/27/2026 | APPROVED | RSIMS |
| Note: *** NOTES ADDED BY RSIMS 3/27/2026 10:54:11 AM *** Approved | |||
| WALL SHEATHING | 03/25/2026 | APPROVED | RSIMS |
| Note: *** NOTES ADDED BY RSIMS 3/25/2026 1:02:56 PM *** Approved | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 03/25/2026 | Disapproved - NO FEE | RSIMS |
| Note: *** NOTES ADDED BY RSIMS 3/25/2026 1:16:13 PM *** 3/25/26: 1). Right side entry knee wall does not match plan requirements WF95 shown on plan page S4.0. FBC [A]107.4 2). Plan page S4.0 has detail SC that needs clarification because it calls for SDWC15600 screws into top plate but there is a porch beam there which has straps from beam to truss installed. Revision required. FBC [A]107.4 3). Front gable is missing cross bracing as required in detail GE01/D2. Correction or plan revision required. FBC [A]107.4 4). 2-ply Truss T01 needs nails fully embedded as required. FBC [A]107.4 | |||
| TIE BEAM / LINTEL | 03/13/2026 | APPROVED | RSIMS |
| Note: *** NOTES ADDED BY RSIMS 3/13/2026 9:02:46 AM *** Inspector Notes from Inspection 2250 *** NOTES ADDED BY RSIMS 3/4/2026 1:27:49 PM *** 3/4/26: 1). Need termite certificate or intent to treat on site prior to next inspection. FBCR 318 | |||
| MONOLITHIC SLAB | 03/04/2026 | APPROVED - AS NOTED | RSIMS |
| Note: *** NOTES ADDED BY RSIMS 3/4/2026 1:27:49 PM *** 3/4/26: 1). Need termite certificate or intent to treat on site prior to next inspection. FBCR 318 | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 02/27/2026 | APPROVED | RSIMS |
| Note: *** NOTES ADDED BY RSIMS 2/27/2026 1:11:03 PM *** 2/24/2026 - PREVIOUS INSPECTION NOTES 2/24/26: 1). Pex water piping does not match Manufacturer's installation instructions for bundling. "FBC-P2906.10 Cross-linked polyethylene plastic (PEX). Joints between cross-linked polyethylene plastic tubing or fittings shall comply with Section P2906.10.1 or Section P2906.10.2. Bundling: Parallel runs of Uponor PEX may be bundled together, when approved by local code, given the following: • Bundle hot and cold water pipes separately at least 6"" apart (15.2cm), unless piping is insulated. • Support the bundle at the required on-center distance. • Use cable ties to group a bundle.* *Cable ties are not approved for supporting pipe. PEX Piping Systems Installation Guide | 45" | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 02/24/2026 | Disapproved - NO FEE | RSIMS |
| Note: *** NOTES ADDED BY RSIMS 2/24/2026 11:40:46 AM *** 2/24/26: 1). Pex water piping does not match Manufacturer's installation instructions for bundling. "FBC-P2906.10 Cross-linked polyethylene plastic (PEX). Joints between cross-linked polyethylene plastic tubing or fittings shall comply with Section P2906.10.1 or Section P2906.10.2. Bundling: Parallel runs of Uponor PEX may be bundled together, when approved by local code, given the following: • Bundle hot and cold water pipes separately at least 6"" apart (15.2cm), unless piping is insulated. • Support the bundle at the required on-center distance. • Use cable ties to group a bundle.* *Cable ties are not approved for supporting pipe. PEX Piping Systems Installation Guide | 45" | |||
| GEOTECHNICAL REPORT APPROVAL (OFFICE USE) | 02/23/2026 | APPROVED | PKNAPIK |
| FORMBOARD SURVEY (OFFICE USE ONLY) | 02/17/2026 | APPROVED | RRICKS |
| WATER METER INSTALLATION REQUEST | 02/06/2026 | APPROVED | CBOWERMASTER |
| U-CROSS CONNECTION | |||
| ROW - FINAL APRON (AFTER POUR) | |||
| ROW - FINAL INSPECTION | |||
| U -UTILITY RESIDENTIAL FINAL | |||
| BLD - BUILDING FINAL |
Review History
| Department | Status | Date In | Date Out |
| BLD | COMPLETE | 04/13/2026 | 04/14/2026 |
| Note: Released By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 04/06/2026 | 04/10/2026 |
| Note: Released By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 02/17/2026 | 02/23/2026 |
| Note: Released By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM | |||
| SW1 | COMPLETE | 02/17/2026 | 02/17/2026 |
| Note: Released By: RODNEY RICKS - (386)986-4726 - RRICKS@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 02/17/2026 | 02/17/2026 |
| Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 12/22/2025 | 12/22/2025 |
| Note: Released By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM | |||
| SWALE | COMPLETE | 12/18/2025 | 12/31/2025 |
| Note: Released By: LEVI SALYERDS - (386)986-2575 - LSALYERDS@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 12/16/2025 | 12/22/2025 |
| Note: Released By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM | |||
| CUSVC | COMPLETE | 12/16/2025 | 12/19/2025 |
| Note: Released By: HALEIGH HAND - - HHAND@PALMCOASTGOV.COM | |||
| ELEC | COMPLETE | 12/16/2025 | 12/17/2025 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 12/16/2025 | 12/18/2025 |
| Note: Released By: LEVI SALYERDS - (386)986-2575 - LSALYERDS@PALMCOASTGOV.COM | |||
| GAS | CANCEL | 12/16/2025 | 12/17/2025 |
| LOCATE | COMPLETE | 12/16/2025 | 12/22/2025 |
| Note: Released By: TONI CHURCHILL - - TCHURCHILL@PALMCOASTGOV.COM | |||
| MECH | COMPLETE | 12/16/2025 | 12/18/2025 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| SW1 | COMPLETE | 12/16/2025 | 12/16/2025 |
| Note: Released By: PARREN FLANAGAN - (386)986-2392 - PFLANAGAN@PALMCOASTGOV.COM | |||
| ZON | HOLD | 12/16/2025 | 12/17/2025 |
| Note: Held By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM Street name at top of site plan/survey spelled incorrectly |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION RESIDENTIAL | ¤40.00 | 06/05/2026 |
| REINSPECTION RESIDENTIAL | ¤40.00 | 06/05/2026 |
| REINSPECTION FEE | ¤40.00 | 06/05/2026 |
| REINSPECTION FEE | ¤40.00 | 06/05/2026 |
| RSI REINSPECTION 1 | ¤35.00 | 06/05/2026 |
| RSI ROW FINAL INSPECTION | ¤16.25 | 12/26/2025 |
| SCHOOL BOARD IMPACT FEE RES | ¤5,450.00 | 12/26/2025 |
| WASTEWATER MAIN EXTENSION IMPA | ¤2,385.00 | 12/26/2025 |
| SURCHARGE FS 533.721 | ¤11.56 | 12/26/2025 |
| SURCHARGE - FS 468.631 | ¤17.34 | 12/26/2025 |
| SW ENG RES REVIEW 240 | ¤240.00 | 12/26/2025 |
| WATER METER W/ TAP | ¤2,326.93 | 12/26/2025 |
| TRANSP RES IMPACT FEE 10-25 | ¤6,235.58 | 12/26/2025 |
| SEWER CREDIT | (¤650.00) | 12/26/2025 |
| WASTEWATER PERM INSPECTION | ¤80.00 | 12/26/2025 |
| WASTEWATER PERM REVIEW | ¤25.00 | 12/26/2025 |
| SEWER CAPITAL FACILITY | ¤4,415.00 | 12/26/2025 |
| WATER CAPITAL FACILITY FEE | ¤3,790.49 | 12/26/2025 |
| WATER PERMIT REVIEW | ¤25.00 | 12/26/2025 |
| WATER MAIN EXTENSION IMPACT | ¤917.27 | 12/26/2025 |
| SITE PLAN 30 | ¤30.00 | 12/26/2025 |
| RSI DRIVEWAY AFTER POUR | ¤16.25 | 12/26/2025 |
| RSE DRIVE PRE POUR INSPECTION | ¤32.50 | 12/26/2025 |
| RSI FIELD SURVEY INSPECTION | ¤48.75 | 12/26/2025 |
| RSI FORMBOARD REVIEW | ¤16.25 | 12/26/2025 |
| RSI PLAN REVIEW NEW | ¤48.75 | 12/26/2025 |
| RSI FNL SURVEY/GRADING CERT | ¤48.75 | 12/26/2025 |
| FC IMPACT FEE EMS | ¤62.00 | 12/26/2025 |
| FC IMPACT FEE LAW ENFORCEMENT | ¤218.00 | 12/26/2025 |
| FC IMPACT FEE LIBRARY | ¤268.00 | 12/26/2025 |
| FIRE RES IMPACT FEE 10-25 | ¤942.00 | 12/26/2025 |
| PEP TANK INSTALL | ¤756.74 | 12/26/2025 |
| PARKS IMPACT FEE 10-25 | ¤3,164.00 | 12/26/2025 |
| WATER- TURN ON | ¤50.00 | 12/26/2025 |
| ADMINISTRATIVE RESIDENTIAL | ¤30.00 | 12/26/2025 |
| INSPECTION - RESIDENTIAL | ¤877.25 | 12/26/2025 |
| PLAN REVIEW - RESIDENTIAL | ¤248.82 | 12/26/2025 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤32,338.48 |