I want to search for...

Permit #2026010932

Permit Details

Status: INSPECT

Parcel Id: 07-11-31-7012-00090-0060
GARAGE: 508 sqft
OPENED PORCH (WITH ROOF) : 259 sqft
CONDITIONED SPACE: 2332 sqft
Total Square Footage: 3099 sqft
Block: 00090
Subdivision: 2187 - SECTION 12-BELLE TERRE
Job Phone: 352-433-8382
Location Address: 117 BAYSIDE DR
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 03/02/2026
NOC: RECORDED
Applicant name: ALFREDO E SCHEER
Owner: ESTELA SPECS 6 LLC

Address

2601 S BAYSHORE DRIVE 18TH FLOOR

COCONUT GROVE, FL 33133

Lot: 0060
Contracted Stated Job Value: ¤165,000.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

ESTELA LIVING LLC
Status Location Address State License Number Phone
ACTIVE

237 S. DIXIE HWY, 4TH FLOOR

CORAL GABLES, FL 33133

CGC1534535 (Exp: 08/31/2026) 352-433-8382

Sub Contractors

JUAN CARLOS GONZALEZ
Status Location Address State License Number
ACTIVE

1328 COUNTY ROAD 308

CRESCENT CITY, FL 32112

RF11067806 (Exp: 08/31/2027)
DUSTIN L ESTEP
Status Location Address State License Number Phone Fax
ACTIVE

2041 N HIAWASSEE RD

APOPKA, FL 32703

CCC1330971 (Exp: 08/31/2026) 407-702-0206 352-988-6629
JOSEPH HORATIO STRADA JR
Status Location Address State License Number Phone
ACTIVE

3400 ST JOHNS PARKWAY

SANFORD, FL 32771

EC13003715 (Exp: 08/31/2026) 877-906-1113
JOSEPH H STRADA JR
Status Location Address State License Number Phone
ACTIVE

3400 ST JOHNS PKWY

SANFORD, FL 32771

CAC043953 (Exp: 08/31/2026) 877-906-1113

Inspection History

Type Request Date Result Inspector
LATH/BRICK/ WATER BARRIER 06/10/2026 APPROVED JSTEWART
Note: Inspector Notes from Inspection 2420 1. Spare bath vanity receptacle (closest to toilet), needs to be landed into a Holding Box outlet, and ensure min distance from shower/tub is 36". NEC 314.23(B) / NEC 406.9(C) 2. Sub panel is sharing concealed space with Plumbing, Sub panel is required to have no other MEP's in a shared space. (A.) Relocate sub panel from Plumbing. (B.) Re route Plumbing (vent) from current location to a adjascent cavity, and then fire block below the sub panel to seperate the Plumbing from slab and the sub panel cavity. NEC Article 110.26 Inspector Notes from Inspection 2450 Inspector Notes from Inspection 2460 1. The 1st Truss A10 at Lanai wall has several webs, top cord and bottom that have been broken, altered and are missing. There are 3 locations in this truss that scabs have been added. Marked in Orange 2. The 2nd Truss A10 at Lanai wall is missing a chunk of web that has been cut. Marked in Orange *Need Truss Engineering showing proper repair of both trusses.*
INSULATION 06/10/2026 APPROVED JSTEWART
Note: Inspector Notes from Inspection 2420 1. Spare bath vanity receptacle (closest to toilet), needs to be landed into a Holding Box outlet, and ensure min distance from shower/tub is 36". NEC 314.23(B) / NEC 406.9(C) 2. Sub panel is sharing concealed space with Plumbing, Sub panel is required to have no other MEP's in a shared space. (A.) Relocate sub panel from Plumbing. (B.) Re route Plumbing (vent) from current location to a adjascent cavity, and then fire block below the sub panel to seperate the Plumbing from slab and the sub panel cavity. NEC Article 110.26 Inspector Notes from Inspection 2450 Inspector Notes from Inspection 2460 1. The 1st Truss A10 at Lanai wall has several webs, top cord and bottom that have been broken, altered and are missing. There are 3 locations in this truss that scabs have been added. Marked in Orange 2. The 2nd Truss A10 at Lanai wall is missing a chunk of web that has been cut. Marked in Orange *Need Truss Engineering showing proper repair of both trusses.*
ALL ROUGH 06/05/2026 APPROVED - AS NOTED JSTEWART
Note: 1. Spare bath vanity receptacle (closest to toilet), needs to be landed into a Holding Box outlet, and ensure min distance from shower/tub is 36". NEC 314.23(B) / NEC 406.9(C) 2. Sub panel is sharing concealed space with Plumbing, Sub panel is required to have no other MEP's in a shared space. (A.) Relocate sub panel from Plumbing. (B.) Re route Plumbing (vent) from current location to a adjascent cavity, and then fire block below the sub panel to seperate the Plumbing from slab and the sub panel cavity. NEC Article 110.26 Inspector Notes from Inspection 2450 Inspector Notes from Inspection 2460 1. The 1st Truss A10 at Lanai wall has several webs, top cord and bottom that have been broken, altered and are missing. There are 3 locations in this truss that scabs have been added. Marked in Orange 2. The 2nd Truss A10 at Lanai wall is missing a chunk of web that has been cut. Marked in Orange *Need Truss Engineering showing proper repair of both trusses.*
WALL SHEATHING 06/01/2026 APPROVED - AS NOTED JSTEWART
Note: Inspector Notes from Inspection 2460 1. The 1st Truss A10 at Lanai wall has several webs, top cord and bottom that have been broken, altered and are missing. There are 3 locations in this truss that scabs have been added. Marked in Orange 2. The 2nd Truss A10 at Lanai wall is missing a chunk of web that has been cut. Marked in Orange *Need Truss Engineering showing proper repair of both trusses.*
ROOF SHEATHING / BRACES/TIES/DOWN CELL 05/21/2026 APPROVED - AS NOTED HCAMACHO
Note: 1. The 1st Truss A10 at Lanai wall has several webs, top cord and bottom that have been broken, altered and are missing. There are 3 locations in this truss that scabs have been added. Marked in Orange 2. The 2nd Truss A10 at Lanai wall is missing a chunk of web that has been cut. Marked in Orange *Need Truss Engineering showing proper repair of both trusses.*
ROOF VALLEY & METAL 05/21/2026 APPROVED HCAMACHO
ROOF SHEATHING 05/15/2026 APPROVED JSTEWART
Note: 5/14/2026 - PREVIOUS INSPECTION NOTES Not ready, loose sheets, installer is onsite still nailing roof deck. 5/13/2026 - PREVIOUS INSPECTION NOTES
ROOF SHEATHING 05/14/2026 Disapproved - NO FEE JSTEWART
Note: Not ready, loose sheets, installer is onsite still nailing roof deck. 5/13/2026 - PREVIOUS INSPECTION NOTES
ROOF SHEATHING 05/13/2026 CANCELLED BY APPLICANT JSTEWART
TIE BEAM / LINTEL 05/04/2026 APPROVED KSANDOE
MONOLITHIC SLAB 04/24/2026 APPROVED KSANDOE
Note: 4/23/2026 - PREVIOUS INSPECTION NOTES 1. Missing steel on the shower right side see plans & detail Q/SD2. 2. Missing recess for the shower and the steel see plans & detail Q/SD2.
MONOLITHIC SLAB 04/23/2026 Disapproved - NO FEE HCAMACHO
Note: 1. Missing steel on the shower right side see plans & detail Q/SD2. 2. Missing recess for the shower and the steel see plans & detail Q/SD2.
PLUMBING 1ST ROUGH UNDERGROUND 04/20/2026 APPROVED - AS NOTED KSANDOE
Note: Supply line not connected
GEOTECHNICAL REPORT APPROVAL (OFFICE USE) 04/16/2026 APPROVED PKNAPIK
FORMBOARD SURVEY (OFFICE USE ONLY) 04/07/2026 APPROVED PFLANAGAN
WATER METER INSTALLATION REQUEST 03/17/2026 APPROVED ISANDERSON
U-CROSS CONNECTION
ROW- PRE-APRON (PRE-POUR)
ROW - FINAL APRON (AFTER POUR)
ROW - FINAL INSPECTION
U -UTILITY RESIDENTIAL FINAL
DRYWALL NAILING
BLD - BUILDING FINAL
GRAVITY SEWER TEST
SEWER TIE IN
ELECTRIC - EARLY POWER

Review History

Department Status Date In Date Out
BLD COMPLETE 06/01/2026 06/02/2026
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
BLD COMPLETE 04/16/2026 04/16/2026
Note: Released By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM
BLD COMPLETE 04/15/2026 04/15/2026
Note: Released By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM
BLD COMPLETE 04/10/2026 04/14/2026
Note: Released By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM
SW1 COMPLETE 04/07/2026 04/07/2026
Note: Released By: PARREN FLANAGAN - (386)986-2392 - PFLANAGAN@PALMCOASTGOV.COM
ZON COMPLETE 04/07/2026 04/07/2026
Note: Released By: SCOTT THOMAS - (386)986-3780 - STHOMAS@PALMCOASTGOV.COM
BLD COMPLETE 03/05/2026 03/05/2026
Note: Released By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM
ZON COMPLETE 02/24/2026 02/24/2026
Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM
SW1 COMPLETE 02/24/2026 03/02/2026
Note: Released By: PARREN FLANAGAN - (386)986-2392 - PFLANAGAN@PALMCOASTGOV.COM
BADMIN HOLD 02/24/2026 02/24/2026
Note: Held By: SCOTT THOMAS - (386)986-3780 - STHOMAS@PALMCOASTGOV.COM RENAME TO LOT GRADING.PDF & SITE PLAN.PDF
BADMIN COMPLETE 02/24/2026 02/26/2026
Note: Released By: SCOTT THOMAS - (386)986-3780 - STHOMAS@PALMCOASTGOV.COM
ZON HOLD 02/13/2026 02/13/2026
Note: Held By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM Provide a clearly visible site plan on it own Site plan : please provide the setbacks clearly in the front left side and right rear
SW1 HOLD 02/13/2026 02/19/2026
Note: Held By: PARREN FLANAGAN - (386)986-2392 - PFLANAGAN@PALMCOASTGOV.COM BERM IN THE BACK YARD NEEDS TO BE ON THE 5' EASMENT SO NO MORE THEN THE 5' WILL IMPACT THE ADJACENT LOT BEHIND THIS PROPOSED LOT.
SW1 HOLD 02/05/2026 02/12/2026
Note: Held By: RODNEY RICKS - (386)986-4726 - RRICKS@PALMCOASTGOV.COM Berm on the right side creates a slope greater than 4:1 in some areas. Please provide the legnth from the back property line to the berm to clearly depict if the 4:1 slope requirements are being made.
ELEC COMPLETE 02/05/2026 02/09/2026
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
ZON HOLD 02/05/2026 02/05/2026
Note: Held By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM Elevation for the sides are missing uploaded same plans twice Site plan : please provide the setbacks clearly in the front left side and right rear
BLD COMPLETE 02/05/2026 02/10/2026
Note: Released By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM
SWALE COMPLETE 01/29/2026 02/05/2026
Note: Released By: LEVI SALYERDS - (386)986-2575 - LSALYERDS@PALMCOASTGOV.COM
BLD COMPLETE 01/28/2026 02/02/2026
Note: Released By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM
CUSVC COMPLETE 01/28/2026 02/04/2026
Note: Released By: HALEIGH HAND - - HHAND@PALMCOASTGOV.COM
ELEC HOLD 01/28/2026 02/03/2026
Note: Held By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM 1. Submit electrical plan
ENGIN1 COMPLETE 01/28/2026 01/29/2026
Note: Released By: LEVI SALYERDS - (386)986-2575 - LSALYERDS@PALMCOASTGOV.COM
GAS CANCEL 01/28/2026 01/29/2026
LOCATE COMPLETE 01/28/2026 02/02/2026
Note: Released By: CANDACE BOWERMASTER - - CBOWERMASTER@PALMCOASTGOV.COM
MECH COMPLETE 01/28/2026 01/30/2026
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
ZON HOLD 01/28/2026 02/03/2026
Note: Held By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM Plans are missing: I could not complete the review as these plans were not provided. Provide elevations plan Provide a floor plan
SW1 HOLD 01/28/2026 02/02/2026
Note: Held By: RODNEY RICKS - (386)986-4726 - RRICKS@PALMCOASTGOV.COM Based on the information provide there are inconsistent elevations on the 10' shots beyond the property line that does not agree with surrounding elevations. Please confirm all elevations to reflect proper existing grades. - On the left side the are locations where the proposed berm is lowered than the property line allowing water to negatively impact this lot. - Please ensure that there are no slopes greater than 4:1 when revisions are made.

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
FC IMPACT FEE EMS ¤62.00 03/02/2026
FC IMPACT FEE LAW ENFORCEMENT ¤218.00 03/02/2026
FC IMPACT FEE LIBRARY ¤268.00 03/02/2026
FIRE RES IMPACT FEE 10-25 ¤942.00 03/02/2026
PARKS IMPACT FEE 10-25 ¤3,164.00 03/02/2026
RSI DRIVEWAY AFTER POUR ¤16.25 03/02/2026
RSE DRIVE PRE POUR INSPECTION ¤32.50 03/02/2026
RSI FIELD SURVEY INSPECTION ¤48.75 03/02/2026
RSI FORMBOARD REVIEW ¤16.25 03/02/2026
RSI PLAN REVIEW NEW ¤48.75 03/02/2026
RSI FNL SURVEY/GRADING CERT ¤48.75 03/02/2026
RSI ROW FINAL INSPECTION ¤16.25 03/02/2026
SCHOOL BOARD IMPACT FEE RES ¤5,450.00 03/02/2026
WASTEWATER MAIN EXTENSION IMPA ¤2,385.00 03/02/2026
SURCHARGE FS 533.721 ¤16.26 03/02/2026
SURCHARGE - FS 468.631 ¤24.38 03/02/2026
SW ENG RES REVIEW 240 ¤240.00 03/02/2026
WATER METER W/ TAP ¤2,326.93 03/02/2026
TRANSP RES IMPACT FEE 10-25 ¤8,791.64 03/02/2026
SEWER CREDIT (¤1,147.00) 03/02/2026
WASTEWATER PERM INSPECTION ¤80.00 03/02/2026
WASTEWATER PERM REVIEW ¤25.00 03/02/2026
SEWER CAPITAL FACILITY ¤4,415.00 03/02/2026
WATER CAPITAL FACILITY FEE ¤3,790.49 03/02/2026
WATER PERMIT REVIEW ¤25.00 03/02/2026
WATER MAIN EXTENSION IMPACT ¤917.27 03/02/2026
SITE PLAN 30 ¤30.00 03/02/2026
WATER- TURN ON ¤50.00 03/02/2026
ADMINISTRATIVE RESIDENTIAL ¤30.00 03/02/2026
INSPECTION - RESIDENTIAL ¤1,243.00 03/02/2026
PLAN REVIEW - RESIDENTIAL ¤352.56 03/02/2026
PLAN REVIEW - REVISION ¤32.50
Fees Total Due: ¤32.50 Total Paid: ¤33,927.03